Joel Manfredo, Chief Technology Officer of the County Executive Office Information Technology for the County of Orange, gave this presentation at Pepperdine University’s free conference, “From Information Systems to Innovation Systems: Establishing the Next Generation Information Systems Department,” on Wednesday, October 12, 2011. The conference was sponsored by the Center for Applied Research at Pepperdine's Graziadio School of Business and Management
Citation preview
Joel A. ManfredoChief Technology Officer
October 12, 2011
1
Accelerating IT Mojo in the Face of Financial Distress
Background
Timeline
Phases 1 - 5
Results
Next Steps
Conclusions and Lessons Learned
Agenda
County of Orange
$5.6 Billion Budget
7 Programs
32 Agencies / Departments
CEO IT ServicesServices are delivered through an Internal Service Fund
“Running a Service Delivery Business”
Pricing a ServiceWhat does internet access cost?
Hardware:•Redundant Firewalls•Redundant Routers•Redundant Core Switches•IPS / IDS Hardware•Monitoring (Orion) Servers•Content Filtering Appliances•Content Filtering Report Servers•DNS Servers
Software:•Firewall Security Software licensing•Content Filtering Software licensing & Report Services•Orion Monitoring Software licensing•DNS Software (Unix and Wintel)
Data Center FacilitiesContracts:•Redundant Internet Service Providers:
1. TW Telecom2. VPLS (this is a fail-over service)
•IPS / IDS monitoring Service•Redundant WAN Circuit Contracts•Redundant Firewall Maintenance Contract (HW and SW)•Redundant Routers Maintenance Contract HW and SW)
•Redundant Core Switches Maintenance Contract HW and SW)•Content Filtering Maintenance Contract•County ARIN IP and BGP AS Services
Depreciation:•Firewalls - Hardware and software Depreciation associated •Routers - Hardware and software Depreciation associated •Core Switches - Hardware and software Depreciation associated •Monitoring - Hardware and software Depreciation associated •Content Filtering - Hardware and software Depreciation associated
Other CEOIT Services:•Contracts & Procurement Management•Resource Management•Financial and Cost, Budget Analysis •Billing Processing
Labor:•Network Engineering Labor•Security Engineering Labor•Availability Management Analysis•Capacity Management Analysis•Incident Management (Service Desk)•Change Management•Management
The Story…Operational Transformation in the Face of Financial Distress
Environment:
Organization: 1. A culture built on Heroics 2. Siloed organization 3. Assigning blame 4. Resistance to change 5. No priorities
Financial:
1. 27% budget reduction (2 years) 2. Expiring staff augmentation contract
Results:
1. Moved to top 10% against benchmark 2. Increased customer satisfaction 16% 3. Reduced SLA exceptions by 77%
How:
Combination: 1. Leadership 2. Soft skills introduction 3. Sustained “drumbeat” 4. The persuader 5. ITSM principles
Method: 1. Plan 2. Implement 3. Absorb 4. Measure
“Be transparent, or be gone”
Phases of the JourneyMethod - Plan, Implement, Absorb, Measure
Phase 1: ITSM Training April 2009DISC (Soft Skills) Training May 2009
Capacity Management May 2009Availability Management June 2009Resource Planning June 2009Project Prioritization June 2009
Phase 2: Network & Platform Services Reorganization October 2009 Service Design Package November 2009Monthly MAP meetings March 2010
Phase 4: Network Operations Center January 2011ITSM Full Suite (BMC – “AMP”) March 2011
Phase 3: Marketing Brochure (Mini Service Catalog) October 2010 Service Desk re-implementation December 2010
Phase 5: Re-benchmark AIMM July 2011 Service Catalog October 2011
ITSM Reorganization FutureService Level Management Future
Further Automate Capacity & Availability Future
Today
20092010
2010
Chaos
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
NPS Reorganized:-Plan & Design-Build & Transition-Operate & Maintain
ACS Program Executive hired
Availability Reporting
Capacity Reporting
(DISC)
Resource Planning
Project Prioritization
AIMM (HP) Report 46-Technology & Architecture-Mgt Tools & Process Maturity-Culture & IT Staff Maturity-Demand, Supply & IT Governance
“One Team”
Training
Ticket Aging Process
Service request turnaround improvements (100%)
Incidents – from over 5 days to 1
Not a single failed non-standard RFC
Not a single Service Level Breach
CTO Portal
Incident Mgt Process
Customer Survey (Jul – Dec 09)
Customer Survey (Jan – Jun 10)
Communication Team Formed
ITSM Integrated Suite Service Desk
County Connection: OCDC
Data Center Tour Tech Fest
Marketing Brochure “Agency Success is Our Mission”
IT Service Management Path to Maturity
AIMM (HP) Report 34
SDP Process
Certifications: 95
Driving Continuous Improvements
Performance Audit Report
“A journey of a thousand miles begins with a single step”
Phase 1
Phase 2
Phase 3
2011Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
IT Service Management Path to Maturity
Network Operations Center Launched
ITSM Integrated Suite Launch – FULL SUITE (CMDB, Change, Release…)
MSB Planning Success
Virtual Server Farm Replacement
Method
Application Monitoring
Driving Continuous Improvements
Service Catalog
Service Level Management
ITSM based Reorganization
Customer Survey (Jul – Dec 10)
AIMM (HP) Report 10
Plan
Implement
Absorb
Measure
Phase 4 Phase 5
Phase 1
DISC AssessmentPhase 1: Dominance, Influence, Steadiness, Compliance
Nov Mar April May June Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jul Aug Sep0
50
100
150
200
250
300
350
400
Cumulative Monthly Accomplishments
Management Action PlanResults through Present
2010 2011
Capacity Report Availability Report
Capacity & Availability ReportingPhase 1
Capacity Report
Capacity & Availability ReportingPhase 1
Values
Row Labels ETC Hours 3 Week FTE
Enterprise Infrastructure Srvcs 13.92 0.12
Networks and Platform Services 523.87 4.37
Security & Bus Continuity Oper 15.50 0.13
Grand Total 553.28 4.61
Resource PlanningKey Metrics
3 Week Summary (by organization unit):
Resource PlanningKey Metrics
3 Week Summary (by project):
Projects with late tasks:
Row Labels Sum of ETC
Disaster Recovery Implementation (FY11-12) 336.00
Enterprise Secure File Transfer Migration 33.20
ePages Replacement 22.00
Exchange 2010 Production Build out 112.00
HR & FS Access Definition Project Schedule 1.50
Secure FTP Infrastructure Upgrade 48.58
Grand Total 553.28
Sum of ETC
Row Labels Grand Total
ePages Replacement 10.00
Grand Total 10.00
Phase 2
20092010
2010
Chaos
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
NPS Reorganized:-Plan & Design-Build & Transition-Operate & Maintain
ACS Program Executive hired
Availability Reporting
Capacity Reporting
(DISC)
Resource Planning
Project Prioritization
AIMM (HP) Report 46-Technology & Architecture-Mgt Tools & Process Maturity-Culture & IT Staff Maturity-Demand, Supply & IT Governance
“One Team”
Training
Ticket Aging Process
Service request turnaround improvements (100%)
Incidents – from over 5 days to 1
Not a single failed non-standard RFC
Not a single Service Level Breach
CTO Portal
Incident Mgt Process
Customer Survey (Jul – Dec 09)
Customer Survey (Jan – Jun 10)
Communication Team Formed
ITSM Integrated Suite Service Desk
County Connection: OCDC
Data Center Tour Tech Fest
Marketing Brochure “Agency Success is Our Mission”
IT Service Management Path to Maturity
AIMM (HP) Report 34
SDP Process
Certifications: 95
Driving Continuous Improvements
Performance Audit Report
“A journey of a thousand miles begins with a single step”
Phase 2
ASG IRM Process Security NPS OPS TSD PMO BA
Plan & Design
Build & Transition
Operate & Maintain
ITSM Organizational DesignPhase 2: Reorganization of NPS
Pla
n an
d D
esig
n
Overall Architecture and Technologies / Standards*
Capacity Requirements
Availability Requirements
Training Requirements
POC requirements
Design Diagrams and Requirements
MOUs/SLRs
Success Criteria
TCO Calculations
Alternatives
Backup requirements
Process / Procedure requirements
Monitoring requirements
Access Requirements
Standard Requests
Engineering and Ops review and acceptance
Continuous improvement or scalability plans
Approval of the Design from Peer Groups
Approval of the design from Chief Architect
Approval of the design from Customer
Bui
ld a
nd T
rans
ition Design Validation / Review and
Acceptance
Procurements
Configuration and Installation
Update and Audit of Asset Lists/CMDB
RFC Execution and Coordination/Communication
Rollout Plan
Backout Plan
Risk Assessment for RFC
Ops Training and Handoff
QA and Validation of Systems
Feedback to Design Team
Approval of Rollout from Ops
Approval of Rollout from customer
Approval of Rollout from Design group
Support and monitoring during cool down/warranty period O
pe
rate
an
d M
ain
tain
System acceptance
Registering application in ops (contact information, service levels, monitoring
and backup information, new or changed procedures, Access levels)
Update procedures
System lockdown
QA and Validation of Monitoring, Backups and Access
Assist in Negotiating SLRs/SLAs
Freeze and Warranty Period Management
ITSM Organizational Design
SDR SDP – Issues identified through the process
Phase 3
20092010
2010
Chaos
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
NPS Reorganized:-Plan & Design-Build & Transition-Operate & Maintain
ACS Program Executive hired
Availability Reporting
Capacity Reporting
(DISC)
Resource Planning
Project Prioritization
AIMM (HP) Report 46-Technology & Architecture-Mgt Tools & Process Maturity-Culture & IT Staff Maturity-Demand, Supply & IT Governance
“One Team”
Training
Ticket Aging Process
Service request turnaround improvements (100%)
Incidents – from over 5 days to 1
Not a single failed non-standard RFC
Not a single Service Level Breach
CTO Portal
Incident Mgt Process
Customer Survey (Jul – Dec 09)
Customer Survey (Jan – Jun 10)
Communication Team Formed
ITSM Integrated Suite – Service Desk
County Connection: OCDC
Data Center Tour Tech Fest
Marketing Brochure “Agency Success is Our Mission”
IT Service Management Path to Maturity
AIMM (HP) Report 34
SDP Process
Certifications: 95
Driving Continuous Improvements
Performance Audit Report
“A journey of a thousand miles begins with a single step”
Phase 3
It’s working...Phase 3: “Mojo”
November 2009 Not a single Service Level Breech Incidents – from over 5 days to 1 Not a single failed non-standard RFC Service request turnaround improvements
(100%)
- Marshall Goldsmith
Marketing BrochurePhase 3: “Mini Service Catalog”
Marketing BrochurePhase 3: “Mini Service Catalog”
Phase 4
2011Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
IT Service Management Path to Maturity
Network Operations Center Launched
ITSM Integrated Suite Launch – FULL SUITE (CMDB, Change, Release…)
MSB Planning Success
Virtual Server Farm Replacement
Method
Application Monitoring
Driving Continuous Improvements
Service Catalog
Service Level Management
ITSM based Reorganization
Customer Survey (Jul – Dec 10)
AIMM (HP) Report 10
Plan
Implement
Absorb
Measure
Phase 4
Phase 4
Network Operations Center
Network Monitoring
Handoff/Review Logs
Orion Network Dashboard
Daily Walkthrough AM/PM
IP Monitor Int/Ext/DR
INMON
Server Monitoring
Handoff/Review Logs
Orion Server Dashboard
VM Console
IP Monitor Probation/Int
HP SIM
ResultsCustomWritten
Phase 4: BMC Suite through the Cloud
Integrated ITSM Suite
More Results
Results
Evidence of Improvements
Incident Tickets
Percent Resolved
0
100
200
300
400
500
600
700
800
Jan-09
Feb-09
Mar-09
Apr-09
May-09
Jun-09Jul-0
9
Aug-09
Sep-09
Oct-09
Nov-09
Dec-09
Jan-10
Feb-10
Mar-10
Apr-10
May-10
Jun-10Jul-1
0
Aug-10
Sep-10
Oct-10
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11Jul-1
1
Aug-11
Sep-11
50%55%60%65%70%75%80%85%90%95%
100%
Results
Evidence of Improvements
CY2009 CY20100
100
200
300
400
500
SLA Exceptions Reduced by 77%
Results
Evidence of Improvements
CY2009 CY20100
2
4
6
8
10
12
14
Average Days to Resolve Tickets Reduced 75%
Results: HP’s Converged Infrastructure Maturity Model
Evidence of Improvements
Results: HP’s Converged Infrastructure Maturity Model
Evidence of Improvements
Evidence of Improvements
Technology & Architecture Tools & Processes Culture & IT Staff Maturity Demand, Supply & IT Governance
1.00
1.50
2.00
2.50
3.00
3.50
4.00
Orange CountyUS Public Sector
Orange County versus US Public Sector BenchmarkJuly 2011
Results: HP’s Converged Infrastructure Maturity Model
Evidence of ImprovementsResults: HP’s Converged Infrastructure Maturity Model
Dec-09 Jul-10 Jul-110
10
20
30
40
50
60
70
80
90
100
BetterEqual
Orange County Percent of Characteristics "At or Better"July 2011
Headcount
- 27%
Top 10%
Customer Survey Scale: 1 = worst; 4 = best
Evidence of Improvements
Phase 5
2011Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
IT Service Management Path to Maturity
Network Operations Center Launched
ITSM Integrated Suite Launch – FULL SUITE (CMDB, Change, Release…)
MSB Planning Success
Virtual Server Farm Replacement
Method
Application Monitoring
Driving Continuous Improvements
Service Catalog
Service Level Management
ITSM based Reorganization
Customer Survey (Jul – Dec 10)
AIMM (HP) Report 10
Plan
Implement
Absorb
Measure
Phase 5
Service CatalogInternet Service Provider
SERVICE DESCRIPTIONCEO/IT is the ISP for the County and its agencies. This service includes reasonable and equitable Internet bandwidth and access capability to and from the County backbone to the Internet.
WHAT IS INCLUDED This includes the installation, configuration, ongoing
maintenance and security of the core routers that are outward facing to the Internet
Provides redundant Internet providers configured in failover configuration
64 Class C Networks that are available and managed by CEO/IT for existing outward facing applications
Availability of an Enterprise Class, Tier 2 Data Center Network Operations Center (NOC) (staffed hours: Mon-Fri,
8am-5pm) Monitoring of Enterprise Components and Hosts on a 24x7x365
basis Command Center staffed on a 24x7x365 basis Enterprise Software Licensing and Contracts Management
associated with this service Enterprise Services
HOW WE CHARGEThis service is included in the County Network Services Rate. CEO/IT utilizes the total email address count from each agency’s Active Directory (AD) as a divisor to calculate the cost distribution for CEO/IT Security Services, Enterprise Shared Services, and County Network Connectivity.
SERVICE TIPS Limit Internet usage to business related activities
ADDITIONAL INFORMATIONFor those who wish to filter their Internet browsing, we offer a secure web filtering solution. See Secure Web Filtering Services.
Extend ITSM Based OrganizationMove the Plan & Design Group and the Build & Transition Group “up”
Conclusions and Lessons Learned
Conclusions & Lessons Learned
1. Financial distress clouds have their silver linings in IT environments.a. Working together in the face of a single galvanizing eventb. Speak with “one voice”
2. It Takes an IT mojo-driven strategy to implement sustained continued improvements in financial distress.
a. Courage and consistency; buy-inb. Incremental changes (process, organizational), planning and soft skills provided results
3. New leadership can ignite IT Mojo. a. Common goalsb. Common messages
4. Establish a drumbeat to pace the changes and measure visibly and consistently.a. Messaging consistencyb. Allow the organization to digest changes
5. Establish key measurements of the categories shown in the customer surveys.a. Report on themb. Make sure everyone knows what’s being measured
6. Establish a consistent program of accountability .a. Report on themb. Make sure everyone knows what’s being measured
7. Benchmark the organization before commencing the journey.