Upload
gmasiuk
View
1.179
Download
1
Embed Size (px)
DESCRIPTION
G Masiuk Presentation May 21, 2012 WCQI Anaheim
Citation preview
World Conference on Quality and Improvement
May 21-23, 2012
Anaheim, California
Case Studies In
Continuous Quality Improvement
Gordon Masiuk, President
Masiuk Consulting Services Ltd. www.business-performance-excellence.ca
MCS
Implementing Quality Improvement
• What has worked well in your organization?
• What are some of your challenges?
• I wish I could….
MCS
“If you think you can, or, if you think
you can’t, you’re right!”
Henry Ford
MCS
Presentation Overview
• Case Study 1: Reducing Downtime and Improving Production in an Oil Field Operation
• Case Study 2: Plant Maintenance Initiative to Reduce Downtime and Improve Production in the First Half Hour of Start-Up
• Case Study 3: Reducing Corporate Wide Rig Release to On-Stream Cycle Time and Increasing Production and Cash Flow For an Oil & Gas Operation
MCS
Focus of the Presentation
• What Was Needed to get the Initiative Started?
• How The Initiative was Identified
• Improvement Methodology Used
• Quality Management Analytical Tools Used
• Implementing and Measuring the Improvements
• Bottom Line Impacts
• During the case studies ask yourself how you might be able to apply the quality concepts, tools and measurements in your organization!
MCS
Improving Production and Reducing
Downtime in an Oil Field Operation
Case Study 1
MCS
What Was Needed to get the Initiative Started?
• This initiative was part of an overall Continuous Quality Improvement (CQI) pilot process – acquired sponsorship of executive and senior management
• Focus was to generate bottom line results: improving production, reducing costs, eliminating waste and downtime
• “Engagement and commitment” of the production supervisor and his operators vs. their “compliance”
• Formal and just-in-time training and coaching of supervisors, operators, engineers and others in practical application of CQI tools and methods, teamwork and leadership effectiveness was critical
• Full time on-site consultant to guide the initiative
• “Diplomatic Immunity” to allow the area to challenge the status quo
MCS
Key Opportunities
• Operations supervisor wanted to involve his
teams in the improvement of production and
reduction of downtime. This would be the first
exposure of the operations crews to a Continuous
Improvement initiative.
• Operations supervisor was very open to learning
and applying performance management and
continuous improvement techniques. His
engagement and leadership was critical to
success.
MCS
Continuous Improvement Approach
• Plan-Do-Check-Act continuous
improvement model
Plan
Act Do
Check
Continuous
Improvement
Model
MCS
Continuous Improvement Approach
• Used the Plan-Do-Check-Act (PDCA) approach to design and implement the improvement.
• Started the process by conducting operations/ engineering team brainstorming sessions to understand their operational issues.
• Identified potential improvement opportunities focused on reducing downtime or improving production (including the “vice on the back of the truck”).
• Reviewed one year of production accounting data to identify specific causes of downtime and lost production (Pareto Analysis) and to establish a baseline of performance.
• Engaged operations staff and other disciplines in problem solving exercises (Root Cause analysis).
• Further fine tuned the accounting data, identified primary improvement opportunity.
MCS
“The best way to get a good idea, is to
get a lot of ideas”
Linus Pauling
Nobel Winning Chemist
MCS
Downtime
Top 12/57 Vital Few
Shortage/Lost Production
Top 12/56 Vital Few
Reason Hours Reason Barrels
Quota Produced 12900 Quota Produced 20337
BH Pump Failure 5330 BH Pump Failure 15848
Pumped Off 2900 Turnaround 10502
Engine Failure 2809 Recover Load Oil 4189
SI (Flared Gas) 2374 Pumped Off 3310
Recover Load Oil 2326 Engine Failure 3069
Turnaround 1982 Pump Change 2656
Line Break 1821 WCT Request 2336
Road Conditions 1080 Line Break 2142
Pump Change 1043 SI (Flared Gas) 2045
WCT Request 1032 Rods Parted 1384
Shut In 864 Gear Box 1054
Vital Few (Top 20%)
MCS
1 Year Baseline Lost Production/Shortage - Pareto Chart
0
5000
10000
15000
20000
25000
Quo
ta P
rodu
ced
BH P
ump
Failu
re
Turna
roun
d
Rec
over
Loa
d Oil
Pumpe
d Off
Engine
Failu
re
Pump
Cha
nge
WCT R
eque
st
Line
Bre
ak
SI (Flar
ed G
as)
Rod
s Par
ted
Gea
r Box
Press
ure
Surve
y
High
Line
Pre
ssur
e
Power
Failure
Fuel G
as
Com
pres
sor D
own
Polishe
d Rod
Pig S
tuck
Shut I
n
Wor
kove
r
Test O
ther
Well
Equipm
ent F
ailure
Wat
er D
ispo
sal P
roblem
Mec
hanica
l Failure
Saddle
Brg
Roa
d Con
ditio
ns
Bent P
olishe
d Rod
SEF
Flow Line
Wax
ed O
ff
DEF
Gen
erat
or F
ailure
Low IG
Spark
Plug
Tank Roo
m W
ater
Prasc
o Fa
ilure
Plug
Upg
rade
Line
Fro
zen
Off
Wat
er S
witc
h
Rod
Hun
g Up
(DEF)
Wat
er In
jection Pro
blem
Tank Sw
itch
Ignitio
n
High
Tank
Lev
el
Clutch
Weigh
ts M
oved
Well H
ead
Hole
in T
ubing
Oil Sw
itch
High
Disch
arge
Pre
ssur
e
Coo
ler F
roze
n
High
Press
ure
Batte
ry D
own
Low O
il
Reasons for Lost Production/Shortage
Ba
rre
ls o
f O
il
BHP failures accounted for 20.1% of annual lost production out of the 56 categories
of downtime
Production Accounting Pareto Analysis
MCS
1 Year Baseline Downtime Hours - Pareto Chart
0
2000
4000
6000
8000
10000
12000
14000
Quo
ta P
rodu
ced
BH P
ump
Failu
re
Pumpe
d Off
Engine
Failu
re
SI (Flar
ed G
as)
Rec
over
Loa
d Oil
Turna
roun
d
Line
Bre
ak
Roa
d Con
ditio
ns
Pump
Cha
nge
WCT R
eque
st
Shut I
n
Gea
r Box
Mec
hanica
l Failure
Upg
rade
Rod
s Par
ted
SEF
Test O
ther
Well
Tank Roo
m W
ater
Press
ure
Surve
y
Fuel G
as
Com
pres
sor D
own
Equipm
ent F
ailure
Rod
Hun
g Up
(DEF)
High
Line
Pre
ssur
e
No
Nom
inat
ion
High
Tank
Lev
el
Wor
kove
r
Pig S
tuck
Spark
Plug
Power
Failure
DEF
Saddle
Brg
High
Press
ure
Polishe
d Rod
Well H
ead
Flow Line
Wax
ed O
ff
Low IG
Hole
in T
ubing
Ignitio
nPlu
g
Wat
er D
ispo
sal P
roblem
Clutch
Bent P
olishe
d Rod
Weigh
ts M
oved
Gen
erat
or F
ailure
Line
Fro
zen
Off
Wat
er S
witc
h
Oil Sw
itch
Prasc
o Fa
ilure
High
Disch
arge
Pre
ssur
e
Wat
er In
jection Pro
blem
Coo
ler F
roze
n
Batte
ry D
own
Low O
il
Tank Sw
itch
Reason for Downtime
Ho
urs
of
Do
wn
tim
e
BHP Failures accounted for 11.7% of the total downtime out of the 57
categories, about 222 - 24 hour days
Production Accounting Pareto Analysis
MCS
Depth: 1300 – 1500 meters
(4200 – 4900 feet)
Bottom Hole Pump
Oil Producing Formation
Bottom Hole Pump
Oil Producing Formation
Pump Jack
MCS
Bottom Hole
Pump Failures
Operators Methods
Machines Environment
Operators don ’ t know optimum production level
Equipment at wrong speed/temp
Different Shifts operate differently
Wrong start up/shut down
Wrong strokes/minute
Poor Training
“ Wait till it breaks ”
Inadequate maintenance
Lack of Procedure Budget cuts
Materials
Improper
Chemicals
Improper
Dewaxers
Failures in specific wells
Formation
Corrosion Plugs Pump
Temperature
Pressure
Seats/balls failures
Pump specs not to acid level
Rod impacts damage pump
Rod Stretch
Low cost/low quality pumps
Inadequate pump for application
Inadequate orientation/on - the job training
Engineers provide inaccurate data
Inadequate orientation/on - the job training
Engineers provide inaccurate data
Lack of Procedure
Poor
Training
Poor
Training
Bottom Hole Pump Failure – Root Cause Analysis
Bottom Hole
Pump Failures
Operators Methods
Machines Environment
’
Different Shifts operate differently
Wrong start up/shut down
Wrong strokes/minute
Poor Training
“ Wait till it breaks ”
Inadequate maintenance
Lack of Procedure Budget cuts
Materials
Improper
Chemicals
Improper
Dewaxers
Failures in specific wells
Formation
Corrosion Plugs Pump
Temperature
Pressure
Seats/balls failures
Pump specs not to acid level
Rod impacts damage pump
Rod Stretch
Low cost/low quality pumps
Inadequate pump for application
-
-
Lack of Procedure
Poor
Training
Poor
Training
Bottom Hole Pump Failure – Root Cause Analysis
MCS
Bottom Hole
Pump Failures
OperatorsMethods
MachinesEnvironment
Operators don’t know optimum production level
Equipment at wrong speed/temp
Different Shifts operate differently
Operators not fully trained
Wrong start up/shut down
Wrong strokes/minute
Poor Training
“Wait till it breaks”
Inadequate maintenance
Lack of Procedure Budget cuts
Materials
Improper
Chemicals
Improper
Dewaxers
Failures in specific wells
Formation
Acid
Gas
Corrosion
Sand
Plugs Pump
Temperature
Pressure
Seats/balls failures
Pump specs not to acid level
Rod impacts damage pump
Pump jack speed
Rod Stretch
Low cost/low quality pumps
Low Bid Policy
High failure rate
Inadequate pump for application
Inadequate orientation/on-the job training
Engineers provide inaccurate data
Operators not fully trained
Inadequate orientation/on-the job training
Engineers provide inaccurate data
Lack of Procedure
Poor
Training
Poor
Training
Bottom Hole Pump Failure – Root Cause Analysis
Bottom Hole
Pump Failures
OperatorsMethods
MachinesEnvironment
Operators don’t know optimum production level
Equipment at wrong speed/temp
Different Shifts operate differently
Operators not fully trained
Wrong start up/shut down
Wrong strokes/minute
Poor Training
“Wait till it breaks”
Inadequate maintenance
Lack of Procedure Budget cuts
Materials
Improper
Chemicals
Improper
Dewaxers
Failures in specific wells
Formation
Acid
Gas
Corrosion
Sand
Plugs Pump
Temperature
Pressure
Seats/balls failures
Pump specs not to acid level
Rod impacts damage pump
Pump jack speed
Rod Stretch
Low cost/low quality pumps
Low Bid Policy
High failure rate
Inadequate pump for application
Inadequate orientation/on-the job training
Engineers provide inaccurate data
Operators not fully trained
Inadequate orientation/on-the job training
Engineers provide inaccurate data
Lack of Procedure
Poor
Training
Poor
Training
Bottom Hole Pump Failure – Root Cause Analysis
MCS
Improvement: Discovery
• Upon determining that the root cause of BHP failures was the physical design limitations of the pump, we needed to determine which wells had the problem.
• 89 wells had bottom hole pumps – to replace them all may not have been the right solution.
• As the field operators would rotate through the area, no one really knew the extent of the problem, or where it really was.
• A second Pareto Analysis was done to pinpoint the actual BHP failures and impacts by well.
MCS
Second Pareto to Pinpoint the Opportunities
Bottom Hole Pump Failure - Affected Wells:
Impact on Lost Production
86
6 3.6 2.3 1.1 0.3 0.3 0.2 0.1 0.090
10
20
30
40
50
60
70
80
90
100
D4 B57 D80 B63 D59 D82 D6 D85 D99 B74
Affected Wells
Perc
en
tag
e o
f L
ost
Pro
du
cti
on
Out of the 89 wells with BHPs, 10 had BHP failures in the past year and
one of those wells had 86% of the lost production!
MCS
Second Pareto to Pinpoint the Opportunities
D4 accounted for 25% of the 5330 hours of downtime: 1332.5 hours,
or 55.5 – 24 hour days
Bottom Hole Pump Failure - Affected Wells:
Impact on Downtime
25
7
28
5
10
15
5
3.3
1 0.7
0
5
10
15
20
25
30
D4 B57 D80 B63 D59 D82 D6 D85 D99 B74
Affected Wells
Perc
en
tag
e o
f D
ow
n T
ime H
ou
rs
MCS
“A problem well defined,
is a problem half solved!”
Peter Scholtes
MCS
Improvement: PLAN
• D4 was targeted to have its current BHP replaced with the highest quality 100HP BHP, the next time a failure occurred.
• D4 was down for an average of almost 5 days per month due to BHP failures in the past year.
• After installation of the high quality BHP, the team would monitor the failure rate, downtime hours, production impacts and related costs.
• A determination would be made after a 90 day test period what impacts the new BHP might have.
• The cost of replacing the BHP was $10,000/day charged by service rig contractors – usually required about 3.5 to 4 days per incident. If the BHP failures could be reduced, it would save service rig costs as well.
MCS
Improvement: DO
• Within one month, the BHP failed at D4. The old
BHP was replaced with the new 100HP BHP.
• A few weeks thereafter, another BHP failed in a
different well, B57 which had the second highest
rate of lost production due to BHP failures at 6%.
• The team decided to install and test another high
quality 100HP BHP in B57 as well.
MCS
Improvement: CHECK
• Over the next three months, no downtime occurred in D4 or B57 since installation of the new BHPs.
• However, an unexpected bonus was realized. The higher quality pump was also performing more efficiently than the low quality BHP. The result was an incremental increase in production from 339 BOE/day to 433 BOE/day, an increase of 94 BOE per day (28%) in D4.
• As with the production increase with D4, B57 also experienced a production increase, but in this case the increase was from 81.6 BOE/day to 157 BOE/day, an increase of 75.4 BOE/day, a 92% increase.
MCS
Lost Production/Shortage After Improvement - Pareto Analysis
0
5000
10000
15000
20000
25000
Quo
ta P
rodu
ced
BH P
ump Fa
ilure
Turna
roun
d
Rec
over Loa
d Oil
Pum
ped Off
Eng
ine Fa
ilure
Pum
p Cha
nge
WCT R
eque
st
Line
Break
SI (
Flar
ed G
as)
Rod
s Parted
Gea
r Box
Pre
ssure Sur
vey
High Line
Press
ure
Pow
er Failure
Fue
l Gas
Com
pres
sor D
own
Polishe
d Rod
Pig S
tuck
Shu
t In
Wor
kove
r
Tes
t Other W
ell
Equ
ipmen
t Failure
Water D
ispo
sal P
roblem
Mec
hanica
l Failure
Sad
dle Brg
Roa
d Con
ditio
ns
Ben
t Polishe
d Rod
SEF
Flow Line W
axed
Off
DEF
Gen
erator F
ailure
Low IG
Spa
rk P
lug
Tan
k Roo
m W
ater
Pra
sco Fa
ilure
Plug
Upg
rade
Line
Fro
zen Off
Water S
witc
h
Rod
Hun
g Up (D
EF)
Water In
jection Problem
Tan
k Switc
h
Ignitio
n
High Ta
nk Lev
el
Clutch
Weigh
ts M
oved
Well H
ead
Hole in Tub
ing
Oil Switc
h
High Disch
arge
Pre
ssure
Coo
ler F
roze
n
High Pre
ssure
Battery D
own
Low O
il
Reasons for Lost Production/Shortage
Barrels
of
Oil
The reduced downtime generated a 92% reduction in lost production
In this category
Pareto After Improvement Implemented
MCS
Bottom Hole Pump Failure - Affected Wells:
Impact on Production After Improvement
0 03.6 2.3 1.1 0.3 0.3 0.2 0.1 0.09
0
10
20
30
40
50
60
70
80
90
100
D4 B57 D80 B63 D59 D82 D6 D85 D99 B74
Affected Wells
Perc
en
tag
e o
f L
ost
Pro
du
cti
on
The improvement generated a 92% reduction in lost production
In this category
Pareto After Improvement Implemented
MCS
Downtime Hours After BHP Improvement - Pareto Analysis
0
2000
4000
6000
8000
10000
12000
14000
Quo
ta P
rodu
ced
BH P
ump Failure
Pum
ped Off
Eng
ine Failure
SI (Flare
d Gas
)
Rec
over
Loa
d Oil
Tur
naroun
d
Line
Bre
ak
Roa
d Con
ditio
ns
Pum
p Cha
nge
WCT R
eque
st
Shu
t In
Gea
r Box
Mec
hanica
l Failure
Upg
rade
Rod
s Parted
SEF
Tes
t Other W
ell
Tan
k Roo
m W
ater
Press
ure Surve
y
Fue
l Gas
Com
pres
sor Dow
n
Equ
ipmen
t Failure
Rod
Hun
g Up (D
EF)
High Line
Pre
ssure
No Nom
ination
High Tan
k Le
vel
Wor
kove
r
Pig S
tuck
Spa
rk P
lug
Pow
er F
ailure
DEF
Sad
dle Brg
High Press
ure
Polishe
d Rod
Well H
ead
Flow Line W
axed
Off
Low IG
Hole in Tub
ing
Ignitio
n
Plug
Water D
ispo
sal P
roblem
Clutch
Ben
t Polishe
d Rod
Weigh
ts M
oved
Gen
erator F
ailure
Line
Froze
n Off
Water S
witc
h
Oil Switc
h
Prasc
o Failure
High Disch
arge
Press
ure
Water In
jection Problem
Coo
ler Fro
zen
Battery D
own
Low O
il
Tan
k Switc
h
Reasons for Downtime
Do
wn
tim
e H
ou
rs
The improvement generated a 32% reduction in downtime in this category
Pareto After Improvement Implemented
MCS
The improvement generated a 32% reduction in downtime in this category
Bottom Hole Pump Failure - Affected Wells:
Impact on Downtime After Improvement
0 0
28
5
10
15
53.3
1 0.7
0
5
10
15
20
25
30
D4 B57 D80 B63 D59 D82 D6 D85 D99 B74
Affected Wells
Perc
en
tag
e o
f D
ow
nti
me
Pareto After Improvement Implemented
MCS
Production Before and After Improvement Bottom Hole Pump
(BHP): 40% Improvement in Production
420.4
590
0
100
200
300
400
500
600
700
D4 + B57 Average Production With
Existing Pump
D4 + B57 Average Production With
Improved Pump
Barr
els
of
Oil E
qu
ivale
nt
(BO
E)
Pro
du
ced
Per
Day
Production Improvements
MCS
Benefits and Costs
Costs:
• 4 meetings, 1 hour each for 11 operators, 1 production engineer, 1
facilities engineer and 1 production supervisor. These meetings
were integrated into the unit’s monthly production meetings.
• Cost of Pareto Analysis/data gathering by business analyst.
• Onsite consultant cost.
• Incremental costs of 2 new BHPs.
Pareto Analysis, data gathering 30 Hrs X $50/Hr $1,500
Quality Consultant Support $3,000 $3,000
Cost of New 100HP BHP 2 X $12,000 $24,000
Less , Cost of old BHP 2 X $7,000 -$14,000
$14,500
Cost Category/Description Value & Calculation Final Cost
Total Cost
MCS
Benefits and Costs Reduction in annual Downtime for BHP Failures:
• D4 = 55.5 days
• B57 = 15.5 days
• Total = 71 downtime days eliminated
Reduction in Service Rig Costs:
• Service rig time = 53 days
• Service rig costs reduced by: 53 days X $10,000/day = $530,000/year
Oil That Could Have Been Produced Annually Without Downtime:
• D4 + B57 lost production = 14,580 BOE
• 14,580 X $23 net/BOE = $335,300/year
Additional Oil Being Produced With The 100HP BHP:
• D4 (94 BOE/day) + B57 (75.4BOE/day) = 169.4 BOE/day increase (AVG)
• 169.4 BOE/day X 365 days/year = 61,800 BOE/year
• 61,831 BOE/year X $23 net/BOE = $1,422,000/year
Annual Cost Savings by Not Replacing BHPs
• 14 BHP failures in D4 and B57 X $7,000/BHP = $98,000.
MCS
Benefits Summary
Benefits Summary:
• 61,800 BOE annual production increase (40%) from incremental production ($1,422,000 revenue increase).
• 14,580 BOE annual shortage eliminated (92%) with reduction in downtime ($335,300 revenue increase).
• $530,000 annual savings in service rig costs.
• $98,000 annual savings by not replacing bottom hole pumps.
• Total Benefits = $2,385,300 (less $14,500) = $2,370,800
• With the low bid policy, the company was saving $5,000 per BHP, but was losing $2,370,800 per year in production revenues, incremental production and service rig costs!
MCS
“End the practice of awarding business
on the basis of price tag alone.
Instead, minimize total cost.”
Dr W. Edwards Deming
Point #4
MCS
Improvement: ACT
• After the success of this initiative, the team’s recommendation to leadership was to run all wells requiring a replacement bottom hole pump with the higher quality, high reliability pumps.
• This initiative prompted a corporate change in the field procurement policy led by the VP of Operations from low bid alone, to considering price, quality, reliability and serviceability equally in critical equipment purchases from that point onward.
MCS
“At first I was really sceptical about this
quality stuff. But now, even if the company
were to cancel the program, I would still
operate my field and facilities this way
because it’s become “my operation” and
it’s the right thing to do”
Field Operator
MCS
Plant Maintenance Initiative to Reduce
Downtime and Improve Production in the First
Half Hour of Start-Up in a Sawmill Operation
Case Study 2
MCS
How was the Initiative Identified?
• The Plant Manager and Area Supervisor sponsored the Continuous Improvement process for the plant.
• Focus was on three priorities: – Achieve 1 million board feet per day
– Top quartile in margin
– Improve Recovery (LRF) from 268 – 278
• It was agreed that the CI projects needed to address one or more of the three priorities to be approved.
MCS
What Was Needed to get the Initiative Started?
• The Area Supervisor, Plant Manager and consultant held CI awareness sessions with each division, maintenance and support functions.
• The “on the bus” expectation was delivered.
• Discussions, meetings and relationship building with the Maintenance supervisor and crew were critical.
• Identification of the pain points of maintenance and the operation.
• Gathering of data to pinpoint the opportunities.
• Development and implementation of an improvement plan.
• Implementation of a reinforcement plan.
• Weekly gathering and posting of progress – the “Continuous Improvement Wall”.
MCS
“What occupies most of the work of
Maintenance?”
“Completing maintenance orders to fix
equipment breakdowns!”
MCS
Categories of Work Typical Breakdown by %
(Adapted From Bill Conway)
•20% of work is value added from the customer’s perspective
•30% of work consists of doing rework (NVA)
•20% of the time people are performing unnecessary work and not working
•Continuous improvement focuses on increasing the % of VA work, by eliminating duplication, rework and unnecessary work from the process
Not Working
(Authorized)
Value Added Work
Unnecessary Work
(Rework)
Necessary Work (Non-Value Added)
Unnecessary Work (Non-Value Added)
15%
20%
10% 15%
30%
Not Working
(Unauthorized) 10%
MCS
Sawmill Flow
28” Canter
Merchandiser/
Cutoff Saw
Debarkers
20” Canter
Board Edger Unscrambler Trimmer
J-Bar
Stacker
Out-feed Log Yard Green
Yard
MCS
Setting the Stage: The Focus on Results
Meetings with Maintenance Manager and team to identify potential areas of improvement
Plant – 3 Priorities
• Improve Recovery (LRF) from 268 – 278
• Achieve 1 million board feet per day
• Top quartile in margin
Achieve 1 million board feet per day
• Current Production Baseline: 938,000 board feet per day (58,625 board feet per hour)
• Desired Production: 1,000,000 board feet per day
• Record Production Day: 1,064,000 board feet per day
• To achieve 1 MM board feet per day, there needs to be an increase in Mill Production of:
• 62,000 board feet per day (6.6%), or
• 31,000 board feet per shift, or
• 3,875 per hour (based on 16 hours of operation).
MCS
Identification of Potential Improvement Opportunities
Top Areas of Focus
• Determine specifics around plant downtime (e.g.. what are the downtime categories, what are the associated hours, costs, or losses for each downtime category etc.)
• Chips need the right bark content
• Chips quality is determined by chipper set up
• Saw Quality/Deviation (in progress)
• PMs – need more people to fully put in place, need to track how many jobs are currently being done and completed
• Control of costs and where costs are going needs to be addressed
• Need full alignments twice a year, currently once a year (in progress)
• 16 other Areas of Focus were also identified
Next Steps:
• Determine what data (e.g.. downtime is available)
• Meet to review CI projects from the sawmill and planer mill to ensure Maintenance CI projects are aligned with their CI projects
• Develop plans for one or two CI projects (including KPIs) for Maintenance
MCS
High Level Improvement Plan
CI Project Focus:
Reduce Plant Downtime in the first 30 minutes of start-up
Data Gathering:
• Gather plant downtime or start up issues during the first half hour of the plant start up on both plant streams to create performance baseline.
• Start Nov 29 – Dec 24 (20 days, 40 data points).
• Graveyard Supervisor to collect the information using check sheets completed daily and data entered into the tracking spreadsheet.
• Data includes: Where the downtime occurred (equipment or location), cause, length of downtime.
• Areas of Focus include: canters, trimmer, debarkers.
Discovery:
• Identify key downtime categories causing downtime to production
MCS
High Level Improvement Plan Plan:
• Develop action plans to address most critical downtime issues first.
• Ensure tracking system is in place, data is gathered daily, graphs posted weekly.
• Reduce maintenance issues, Increase uptime, Increase throughput.
Do:
• Implement solutions.
• Track and communicate results to the plant/supervisors/superintendents, graveyard crew.
Check:
• Review downtime daily, weekly and over the next 5 weeks.
• Compare to baseline downtime.
• Impacts to production.
• Impacts to downtime.
Act:
• Standardize improved maintenance practices.
• Continue to monitor downtime in the first 30 minutes of startup.
• Focus on new areas of improvement.
MCS
Quality Tools Used
• PDCA
• Check sheets
• Pareto Analysis
• Root cause/5 Why’s
• Company trouble shooting, problem solving
techniques and preventative maintenance
practices
MCS
Baseline: Downtime - First 30 Minutes of Start Up
Baseline: Total Downtime Minutes Nov 29 - Dec 24
0
10
20
30
40
50
60
70
80
90
100
Deb
arke
rs
Gan
g - M
echa
nica
l
No
Logs
Can
ter -
Mec
hanica
l
Can
ter -
Electric
al
Mer
ch
Jam
Ups
Cur
ve -
Electric
al
Opt
imizat
ion
No
Logs
DLI
- M
echa
nica
l
DLI
- Ele
ctric
al
Log
Stuck
Chip
Was
te S
yste
m
Knife
Cha
nge
PLC O
ptim
izatio
n
Chip
Was
te S
yste
m
Photo
Eye
Downtime Categories393 Total Minutes of Downtime Over 20 Production Days
19.65 Average Minutes of Downtime in the First 1/2 Hour of Production Per Day
Do
wn
tim
e in
Min
ute
s
MCS
Next Steps
• Now that we had a baseline we could measure the impact on production and downtime: – 19.65 min of downtime per day in the first 30 minutes
of production
– 1 hour of production = 58,625 board feet
– 1 minute of production = 977 board feet
– 19.65 min of downtime in the first 30 minutes was reducing production by 19,200 board feet per day.
– Based on 250 production days per year, this downtime had an impact of 4,800,000 board feet per year – approximately 5 production days annually!
MCS
Next Steps
• With all of the key downtime categories identified with the proper metrics, the Maintenance Team began targeting the downtime issues with the biggest impacts.
• A variety of problem solving tools were used including root cause analysis, mechanical trouble shooting, and the “5 Why’s”.
• The targeted improvements were implemented focusing on the “critical few” first then on the “trivial many”.
MCS
Results After Implementing Improvements
Total Downtime in the First 30 Minutes of Production
Dec 27 - Jan 28
0
10
20
30
40
50
60
70
80
90
100
Canter -
Electrical
Optimization Curve Saw
Change
Lumber Line Curve -
Electrical
PLC
Optimization
Canter -
Mechanical
Downtime Categories113 Total Minutes of Downtime - 25 Production Days
4.5 Average Minutes of Downtime Per Day
Do
wn
tim
e M
inu
tes
MCS
Pareto Comparison Before & After Improvement
Baseline: Total Downtime Minutes Nov 29 - Dec 24
0
10
20
30
40
50
60
70
80
90
100
Deb
arker
s
Gang
- Mech
anical
No
Logs
Can
ter -
Mec
hanica
l
Can
ter -
Electric
al
Merc
h
Jam
Ups
Cur
ve -
Electric
al
Optim
izat
ion
No
Logs
DLI
- M
echan
ical
DLI
- Ele
ctric
al
Log S
tuck
Chip W
aste S
yste
m
Knife C
hange
PLC Optim
izatio
n
Chip W
aste S
yste
m
Photo
Eye
Downtime Categories393 Total Minutes of Downtime Over 20 Production Days
19.65 Average Minutes of Downtime in the First 1/2 Hour of Production Per Day
Do
wn
tim
e in
Min
ute
s
Total Downtime in the First 30 Minutes of Production
Dec 27 - Jan 28
0
10
20
30
40
50
60
70
80
90
100
Can
ter -
Ele
ctric
al
Opt
imizat
ion
Cur
ve S
aw C
hang
e
Lum
ber L
ine
Cur
ve -
Elect
rical
PLC O
ptim
izat
ion
Can
ter -
Mec
hani
cal
Downtime Categories113 Total Minutes of Downtime - 25 Production Days
4.5 Average Minutes of Downtime Per Day
Do
wn
tim
e M
inu
tes
The net impact from the improvement was a reduction in downtime
from 19.65 minutes to 4.5 minutes per day - a 15.15 minute or a
77% reduction in downtime in the first 30 minutes of production.
On an annualized basis, the impact to production was 14,803 board feet
increase per day, or 3,700,000 board feet annualized increase.
This was the equivalent of approximately 4 days of added production
MCS
Performance Improvement Comparison Downtime Minutes and Categories:
Performance Before and After Improvements
0
5
10
15
20
25
30
35
Nov
29-
Dec
3
Dec
6-1
0
Dec
13-
17
Dec
20-
24
Impr
Imple
men
ted
Dec
27-
31
Jan
3-7
Jan
10-1
4
Jan
17-2
1
Jan
24-2
8
Time Frames
Avg
Do
wn
tim
e M
inu
tes P
er
Day
0
2
4
6
8
10
12
Nu
mb
er
of
Cate
go
ries P
er
Week
Avg DT Minutes/Day # of DT Categories/Week
Avg DT Minutes/Day: 19.65
Avg DT Minutes/Day: 4.5
Baseline Avg: 19.68 minutes DT, 6.75 Categories/Week Improvement Avg: 4.5 Minutes DT, 2.5 Categories/Week
MCS
Benefits Summary Production
• 14,800 board feet increase per day (3.7MM Board Feet/Year)
• This increase contributed to 23.9% of the production target increase to help the plant achieve a 1,000,000 board feet per day level
Downtime
• 19.65 min to 4.5 in the first 30 minutes, (77% reduction)
• 98 minutes of downtime/per week in the first 30 minutes, to 22.6 min
• Number of downtime categories reduced from 18 to 7, (61% reduction)
Revenue
• Mill net price per 1000 board feet averaged $340
• 3.7MM board feet of additional annual production added $1,258,000 in additional annualized revenues
MCS
Reducing Corporate Wide Rig Release to
On-Stream Cycle Time to Increase Production
and Cash Flow For an Oil & Gas Company
Case Study 3
MCS
How was the Initiative Identified?
• The initiative was driven by the executive team which established “Reducing Rig Release to On-Stream Cycle Time by 10%” as a corporate goal.
• This goal had been in place for the previous 2 years without any visible improvement. In fact, cycle time was actually increasing each year.
• Challenges: – A specific improvement approach was not in place;
– Performance metrics were not consistently understood;
– Significant data integrity issues, and;
– Operations teams were rewarded on different criteria than cycle time reduction.
MCS
What Was Needed to get the Initiative Started?
• Engagement and support of the executive team, and the Business Process Council.
• Conducted an AS-IS assessment of the process from “Rig Release to On-Stream”.
• Defined and standardize the various terms of the process.
• Created an understanding of what data is available, and the quality of that data.
• Engagement of Asset Teams and establishment of improvement goals.
• Identification of causes of issues and improvement opportunities at the interface points within the process.
MCS
Corporate Goal:
“Reduce Rig Release to On-Stream Cycle
Time by 10%”
• Challenge to the organization was lack of
understanding regarding:
– What is Rig Release to On-Stream Cycle
Time? Why is it important?
– How is rig release determined?
– How is On-Stream determined?
– 10% reduction from what baseline?
– How would performance be tracked?
MCS
Rig Release to On-Stream Model
Rig Release
(from lease) On-stream
Tie In Start
To End
Completion
Start to End
Well Drilled
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
Tie-In End
To On-stream
Demonstrated
Capability to
Produce
Rig Release
(from lease)
Completion
Start to End
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End On-stream
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End
Rig Release
(from lease)
Completion
Start to End
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End On-Stream
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
Tie-In End
To On-Stream
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
MCS
Rig Release to On-Stream Model
Rig Release
(from lease) On-stream
Tie In Start
To End
Completion
Start to End
Well Drilled
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
Tie-In End
To On-stream
Demonstrated
Capability to
Produce
Rig Release
(from lease)
Completion
Start to End
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End On-stream
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End
Rig Release
(from lease)
Completion
Start to End
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End On-Stream
Tie In Start
To End
Rig Release
(from lease)
Completion
Start to End
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
Tie-In End
To On-Stream
Rig Release
To Completion
Start
Completion
End to Tie-in
Start
Core Tasks
Cycle Time Focus on Handoffs in the “White Space”
MCS
Key Findings in the AS-IS Analysis
• Lack of understanding by asset teams of the impacts of cycle time on cash flow – rewarded on NPV. Asset teams were not reinforced or measured on cycle time.
• Communication issues between disciplines, lack of understanding of internal customer needs.
• Lack of a standardized planning process.
• Drilling was highly correlated to the winter season and availability of budget at the beginning of the calendar year.
• Data capture system training was inconsistent, data not properly entered or maintained, terms and definitions not well understood.
MCS
“Success requires putting attention on
your intention”
Deepak Chopra
Wellness and Motivational Speaker
MCS
Recommendations Planning • Implement a disciplined and standardized planning and
scheduling approach.
• Plan well in advance to take advantage of contractor availability.
• Focus drilling on identified season, rather than only when capital is available.
• A corporate approach to Physical Execution i.e.: Western Canada macro planning, load leveling, resource optimization, allocation, redeployment.
• Drill wells that will only be tied in within 4-6 months, reduce stranded capital and delayed production.
• Contingency planning should be encouraged among teams.
• A regular review of wells that carry over between seasons or years, to limit future occurrences.
MCS
Recommendations
Communication • More frequent (daily) communication between ALL
stakeholders, would help to understand and quickly address other’s issues and identify onset of potential problems/delays.
• Earlier communication between the Asset Teams and Joint Interest would help address 3rd party issues before delays manifest.
• Similarly, early discussion with Surface Land would help to identify known contentious land issues and possibly develop alternate routes/locations.
• Handoffs between asset teams and service groups AND Facilities with Production Operations need to be more clearly defined and optimized.
MCS
Recommendations
Well Launcher (Data Capture System) • Standardize all WL fields/definitions, especially “tie in end”.
• Mandatory WL training for all Asset Team members.
• Asset Managers need to be accountable for ensuring WL status/data is accurately entered and up to date.
MCS
Recommendations
Goals
• All teams to set and monitor cycle time goals for their areas, and sub teams facilitated by team leads.
• Recommend that cycle time goals be stated using medians and average.
• Link Asset Team goals directly to the corporate goal – report performance on a regular basis using a balanced scorecard approach vs. a single metric.
Teams would report on:
• RR to OS cycle time by asset team.
• Production impacts (delays or acceleration).
• Data integrity (% of WL fields/statuses that are complete and accurate per project).
MCS
“If I had 1 hour left to live, I would
spend 55 minutes planning,
and 5 minutes executing”
Albert Einstein
MCS
Improvement Methodology and Tools
• Business Process Management/Improvement.
• Cycle time analysis to focus on reduction of cycle time at interface points within the process (the “white space”).
• Cross functional team engagement and reinforcement
• Charting of performance and development of a Performance Dashboard.
• Team feedback, reinforcement and recognition.
• We did not focus on improving the actual work in the core activities, but rather addressed delays between the core activities in the “white space”.
MCS
Performance Baseline Measurement
MCS
Cumulative Average Cycle Time
2006-2007 Rig Release to Onstream Comparisons
164
155
145142
144147
150153
157154
158 159
60
80
100
120
140
160
180
Jan Feb March April May June July Aug Sep Oct Nov Dec
Cycle
Tim
e D
ays
2006 (Baseline) 2007 (Baseline)
131
Performance Baseline Measurement
MCS
Cumulative Average Cycle Time 2006-2007 With
2008 Target
164
155
145142 144
147150
153157
154158 159
60
80
100
120
140
160
180
Jan Feb March April May June July Aug Sep Oct Nov Dec
Cy
cle
Tim
e D
ay
s
2006 (Baseline) 2007 (Baseline) 2008 (Target)
143
131
Performance Baseline Measurement
MCS
Improvement Plan/Execution
• Work with each of the 11 asset teams and leaders to Establish clear cycle time goals for each asset team.
• Implement identified improvements specific to each team.
• Establish and implement a reinforcement plan: – Establish a team and corporate scorecard for cycle time and
track/publish results on a monthly basis to the company intranet
– Support teams in analyzing performance data, pinpointing opportunities, and implementing improvements
– Engage executive leadership and the Physical Execution Council on a monthly basis
– Coach Asset Managers in providing positive reinforcement to their teams
MCS
Performance Improvement Measurement
MCS
Cumulative Average Cycle Time 2006-2007 With
2008 Target
164
155
145142 144
147150
153157
154158 159
60
80
100
120
140
160
180
Jan Feb March April May June July Aug Sep Oct Nov Dec
Cy
cle
Tim
e D
ay
s
2006 (Baseline) 2007 (Baseline) 2008 (Target)
143
131
Performance Improvement Measurement
MCS
Cumulative Average Cycle Time
2006-2008 Rig Release to Onstream Comparisons
164
155
145142 144
147150
153157
154158 159
129 127
9592 92 94
99 98 96
8580 80
60
80
100
120
140
160
180
Jan Feb March April May June July Aug Sep Oct Nov Dec
Cycle
Tim
e D
ays
2006 (Baseline) 2007 (Baseline) 2008 Actuals 2008 (Target)
143
131
Performance Improvement Measurement
MCS
Benefits Summary: Process Improvements
• 49% reduction in rig release to on stream cycle time (79 days).
• Data quality (completeness and accuracy) improved from 72% to 97% compared to base year.
• Key delays were discovered in internal administrative handoffs between departments with improvement in the completion process, and a slight increase in the tie-in process. All handoff delays were reduced through:
– a focus on continuous improvement, with team goals tied to the corporate goal,
– reinforcement of team performance with the performance scorecard and leadership follow through:
• improved communication and planning within and between functions and teams,
• clarification of roles and responsibilities,
• creating awareness of impacts of delays on cash flow.
• This led to changes in managing cross functional business/admin processes and creating a focus on continuous improvement.
MCS
Benefits Summary: Bottom Line Impacts
• 49% reduction in rig release to on stream cycle time (79 days).
• One time cash flow impact for 2008 was approximately $43MM, due to a production increase of 741,000 BOE for 2008 (approximately 2030 BOE/day increase).
• Each day the cycle time was reduced, generated over $550,000 in additional cash flow in 2008.
MCS
Considerations From the Case Studies
MCS
Considerations From The Case Studies
• Be clear/specific on the business results the initiatives are trying to improve – acquire sponsorship at the right levels.
• Engage affected individuals and teams in the planning and implementation of the improvements.
• Establish a few specific metrics, supported by reliable data.
• Establish good baselines of performance and track progress to illustrate the impact and magnitude of the improvements - use charts and make them visible.
• Utilize the right Quality Tools and methods for each initiative, vs. a “one size fits all”.
• Be disciplined in using your chosen improvement methodology – results can take time, but shortcuts don’t work!
• Provide recognition, feedback and reinforcement on a frequent basis, especially from the immediate supervisor, and senior leaders whenever possible.
MCS
Questions?
Contact Information:
Gordon Masiuk (403) 880-0917
www.business-performance-excellence.ca
Thank You!