M cKenney’s equipped a central plant and piped utilities to production lines for a food packaging manufacturer moving into a larger facility. THE CHALLENGE In a very short timeframe, the McKenney’s team had to build out the central plant and get every manufacturing line machine connected at the customer’s new packaging plant. There was no time for pipe prefabrica- tion at the McKenney’s corporate campus, and there were no drawings linking utilities to production line machines being moved from the customer’s old facility. THE SOLUTION To expedite the work, McKenney’s set up a fabrication shop on-site and drew spool sheets in the job trailer. To connect each machine, the foreman and project manager visited the old facility several times to deter- mine the utility needs for each production line. THE RESULTS The project was completed on time and under budget—exceeding the customer’s expectations. Pleased with the outcome, the owner decided to continue the relation- ship with McKenney’s on future projects. Expediting a Smooth Move PROJECT NAME Foodservice Packaging Manufacturer PROJECT LOCATION Norcross, Georgia PROJECT TEAM Owner: Manufacturer General Contractor: The Conlan Company Architect: Fowler Design Associates, Inc. Engineer: AHA Consulting Engineers Mechanical Contractor: McKenney’s, Inc. SPECIALIZATIONS Design Assist Pipe Shop Prefab MARKETS Industrial Central Plants The content of this document is not intended as an endorsement. www.mckenneys.com © 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners. 404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316 704-357-1200 [email protected] 3601 Performance Road Charlotte, North Carolina 28214

Expediting a Smooth Move - Design Assist Services in Norcross, GA

Embed Size (px)

Citation preview

McKenney’s equipped a central plant and piped utilities to production lines for a food

packaging manufacturer moving into a larger facility.

THE CHALLENGEIn a very short timeframe, the McKenney’s team had to build out the central plant and get every manufacturing line machine connected at the customer’s new packaging

plant. There was no time for pipe prefabrica-tion at the McKenney’s corporate campus, and there were no drawings linking utilities to production line machines being moved from the customer’s old facility.

THE SOLUTIONTo expedite the work, McKenney’s set up a fabrication shop on-site and drew spool sheets in the job trailer. To connect each machine, the foreman and project manager

visited the old facility several times to deter-mine the utility needs for each production line.

THE RESULTSThe project was completed on time and under budget—exceeding the customer’s expectations. Pleased with the outcome, the owner decided to continue the relation- ship with McKenney’s on future projects.

Expediting a Smooth MovePROJECT NAME

� Foodservice Packaging Manufacturer

PROJECT LOCATION

� Norcross, Georgia

PROJECT TEAM

� Owner: Manufacturer

� General Contractor: The Conlan Company

� Architect: Fowler Design Associates, Inc.

� Engineer: AHA Consulting Engineers

� Mechanical Contractor: McKenney’s, Inc.

SPECIALIZATIONS

Design Assist

Pipe Shop Prefab

MARKETS

� Industrial

� Central Plants

The content of this document is not intended as an endorsement.

www.mckenneys.com© 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.

404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316

704-357-1200 [email protected]

3601 Performance Road Charlotte, North Carolina 28214