Project NamePerformance Contract Steam Decentralizationand HVAC Replacement

Project LocationNorth Carolina

Project TeamOwner: North Carolina Department of CorrectionsPrime Contractor: NORESCO, LLC

Specializations

Engineer: BWA Engineering PATurnkey Design Builder: McKenney’s, Inc.

Design/Assist

Pipe Shop PrefabSheet Metal Shop Prefab

Government

MarketsPerformance Contractor

Energy Management

Supporting an energy-service performance contractor, McKenney’sdeveloped and installed several energy conservation measures (ECM)—including new domestic hot water (DHW), heating hot water (HHW) and HVAC systems.

The ChallengeThe facilities had existing steam boiler plants, chillers and HVAC equipment that had to remain operational during the ECM upgrades.A plan was needed to tie in the new systems without incurring service interruptions in high security, limited access work areas.

The SolutionDuring project development, McKenney’s provided design/assist services to advance a phasing plan to meet facility requirementsand avoid service interruptions. Temporary services were provided when facility interruptions were unavoidable. Components for theDHW, HHW systems and rooftop units for the HVAC systems were prefabricated—including boiler/pump skids that could be quickly installed—to minimize the team’s time on premise.

The content of this document is not intended as an endorsement.

The ResultsMcKenney’s installed the ECMs with minimal downtime and increased HVAC performance levels while reducing energy costs. Startup,commissioning and owner training resources led to a clean project close out.

1056 Moreland Industrial BoulevardAtlanta, Georgia 30316P: 404-622-5000

[email protected]

3601 Performance RoadCharlotte, North Carolina 28214P: 704-357-1200

Atlanta Office:

Charlotte Office:

www.mckenneys.com