Upload
deltek
View
703
Download
1
Tags:
Embed Size (px)
Citation preview
EPM-209 Earned Value Management is a “System of Systems”
Delivered by:
Kelly Meassick, PMP,Charter Performance Management Group
Copyright © 2010 Deltek, Inc. 2
Agenda
• Overview of Earned Value Management
• Processes: Project Management Using Earned Value
• Technology: Tools and Interfaces
• People: Key Roles
• EVMS Implementation: Lessons Learned
Copyright © 2010 Deltek, Inc. 4
Overview of EVM
• Overview of Earned Value Management
– Overview
– ANSI /EIA 748 Earned Value Management System Standard
– EVMS is a “System of Systems”
5
Earned Value Management is…
• Earned Value Management Is a PROJECT MANAGEMENT METHODOLOGY that Uses Objective Measures that Enable Project Managers to Objectively Analyze and Report Project Performance
• EVM Is Used to Identify, Communicate and Manage the Resource Effect of Technical and Schedule Problems
• Earned Value Management Provides the Ability to Compare COST of the Work Completed with the VALUE of the Work Completed
Copyright © 2010 Deltek, Inc.
Actual costs(ACWP)
Perform
ance Measurement Baseline (P
MB)
ManagementReserve
Budget atComplete
}
$
DaysReport Date Completion date
02468
10121416182022
2 4 6 8 10 12 14 16 18 20
Estimate At Complete (EAC)
Budgeted costs
(BCWS)
Earned Value
(BCWP)
BAC
MR
Completing the Picture
6Copyright © 2010 Deltek, Inc.
7
Organization
Planning, Scheduling and Budgeting
Accounting
Analysis and Management Reports
Revisions and Data Maintenance
NDIA ANSI/EIA 748 EVMS Standard
32
Gu
idelin
es
≈1
37
Typ
ical A
ttri
bu
tes
5 Guidelines19 Typical Attributes
10 Guidelines36 Typical Attributes
6 Guidelines26 Typical Attributes
6 Guidelines20 Typical Attributes
5 Guidelines36 Typical Attributes
Copyright © 2010 Deltek, Inc.
8
SchedulingTool
AccountingSystem
(i.e. Cost Point)
EVM Tool(i.e. Cobra)
(i.e. MS Project)
Technology
EVMS is a “System of Systems”
Copyright © 2010 Deltek, Inc.
9
Hours by Project & Task
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
EAC / ETC
Schedule Status
Reports, Analytics
Control Acct Plans (CAP)
Reports (ContractPerformance Report,
Variance Analysis Report)
PMB
Program Logs
Actual and Accrued Costs
AccountingSystem
(i.e. Cost Point)
Budgets
EVM Tool(i.e. Cobra)
Charge Codes
(i.e. MS Project)
Material, ODC, Subcontractor Costs
EVM data, Metrics
Processes
EVMS is a “System of Systems”
Copyright © 2010 Deltek, Inc.
10
Hours by Project & Task
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
EAC / ETC
Schedule Status
Reports, Analytics
Control Acct Plans (CAP)
Reports (ContractPerformance Report,
Variance Analysis Report)
PMB
Program Logs
Actual and Accrued Costs
Project Management
Team
Management, Stakeholders
AccountingSystem
(i.e. Cost Point)
Budgets
EVM Tool(i.e. Cobra)
Charge Codes
(i.e. MS Project)
Material, ODC, Subcontractor Costs
EVM data, Metrics
Technology – Processes – People
People
EVMS is a “System of Systems”
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 12
Processes
• Processes: Project Management Using Earned Value
– Proposal/Project Concept Phase
– Project Initiation/Baseline Establishment Phase
– Project Execution/Performance Phase
13
Project Lifecycle
• Earned Value “Work Products” Are Developed, Controlled and Maintained throughout the Project Lifecycle
Proposal / Project
Concept Phase
Project Initiation / Baseline
Establishment Phase
Execution / Performance
Phase
Copyright © 2010 Deltek, Inc.
14
Statement of Work or Contract Mod
Outputs: SOW/WBS Matrix, WBS Index, WBS Dictionary
Assign Control Account
Responsibility
Identify Project Organizations and
Subcontractors
Develop Master Schedule; Estimate
Resources
Define Requirements, Key Events and
Deliverables
Pro
ject
Co
ntr
ols
&
Sch
ed
ulin
gR
esp
on
sib
ilitie
s
Identify Manageable Work
Segments
Prepare Initial Time-Phased
Estimates
Output: Responsibility Assignment Matrix (RAM)
Outputs: Organization Breakdown Structure (OBS)
PM
/ C
AM
R
esp
on
sib
ilitie
s
Submit Proposal
Output: Integrated Master Plan (IMP)
Identify Risks
Output: Time-phased Estimates (incl. Sub and Material estimates)
Outputs: Integrated Master Schedule (IMS), Subcontractor Schedules
Proposal Phase
Copyright © 2010 Deltek, Inc.
15
Output: Updated Control Account Plans (CAP)
Outputs: Updated SOW/WBS Matrix,WBS Index and Dictionary
Output: Resource Allocation Notices, UB and MR
Output: Updated Integrated Master Plan (IMP)
Output Performance Measurement Baseline (PMB)
Contract Award
Authorize Project Allocate
ResourcesUpdate Scope,
Key Events, Deliverables,
Work Segments
Pro
ject
Co
ntr
ols
&
Sch
ed
ulin
gR
esp
on
sib
ilitie
s
PM
/ C
AM
R
esp
on
sib
ilitie
s
Update Risk Register
Outputs: Updated IMS& Sub Schedules
Develop Control Account
Plans Create Project Baselines Update
Schedules
Output: Contract Approval Notification
Establish Project
Charge Codes
Baseline Establishment Phase
Copyright © 2010 Deltek, Inc.
16
1. Define The Work
2. Schedule the Work
3. Allocate Budgets100
4060
1525
30 Time
Dol
lars
Contract Budget Base
PMB
Performance Measurement Baseline
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 17
Developing the PMB
• Develop the Scope Baseline:
– Authorize the Project
– Define the Project Scope, Major Deliverables, and Milestones
– Develop Work Breakdown Structure
– Identify Responsible and Performing Organizations
– Identify Control Accounts and Assign Responsibility
• Develop the Schedule and Budget Baselines:
– Develop the Project Schedules
– Develop Control Account Plans (CAPs)
– Integrate CAPs into Detailed Project Schedules
– Approve the Performance Measurement Baseline
18
Scope Baseline Development
Statement of Work
Develop High-Level Schedules
Pro
ject
Co
ntr
ols
&
Sch
ed
ulin
gR
esp
on
sib
ilitie
s
Output: Responsibility Assignment Matrix (RAM)
Outputs: Organization Breakdown Structure (OBS)
PM
/ C
AM
R
esp
on
sib
ilitie
s
Outputs: High-Level Schedule
Output: Risk Register
Develop Control Account
PlansDevelop Detailed
Schedules
Outputs: High-Level Schedule, Integrated Master Schedule (IMS)
Develop Performance Measurement
Baseline
Output: Performance Measurement Baseline (PMB)
Outputs: SOW/WBS Matrix, WBS Index, WBS Dictionary
Assign Control Account
Responsibility
Identify Program Organizations and
SubcontractorsDefine
Requirements, Key Events and
Deliverables Identify Manageable
Work Segments
Output: Integrated Master Plan (IMP)
Identify Risks
Output: Control Account Plans (CAP)
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 19
Scope Baseline
• Step 1: Authorize the Project
• Step 2: Define the Project Scope, Major Deliverables, and Milestones
• Step 3: Develop the Work Breakdown Structure (WBS)
• Step 4: Identify Responsible & Performing Organizations
• Step 5: Identify Control Accounts & Assign Responsibility
20
Schedule & Budget Baseline Development
Statement of Work
Develop High-Level Schedules
Pro
ject
Co
ntr
ols
&
Sch
ed
ulin
gR
esp
on
sib
ilitie
s
Output: Responsibility Assignment Matrix (RAM)
Outputs: Organization Breakdown Structure (OBS)
PM
/ C
AM
R
esp
on
sib
ilitie
s
Outputs: High-Level Schedule
Output: Risk Register
Develop Control Account
PlansDevelop Detailed
Schedules
Outputs: High-Level Schedule, Integrated Master Schedule (IMS)
Develop Performance Measurement
Baseline
Output: Performance Measurement Baseline (PMB)
Outputs: SOW/WBS Matrix, WBS Index, WBS Dictionary
Assign Control Account
Responsibility
Identify Program Organizations and
SubcontractorsDefine
Requirements, Key Events and
Deliverables Identify Manageable
Work Segments
Output: Integrated Master Plan (IMP)
Identify Risks
Output: Control Account Plans (CAP)
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 21
Schedule & Budget Baselines
• Step 1: Define the IMS Framework
• Step 2: Develop Control Account Plans
• Step 3: Select an Earned Value Technique (EVT)
• Step 4: Develop the Detailed Project Schedules
• Step 5: Validate the Time-Phase Budgets
22
Mech Design
Elec Design
100% of work is planned in control accounts
Drafting
Proj
ect
Eng
Mfg
Test
Desig
nQ
uality
Work Breakdown Structure
Project
Eng Mfg Test
Design Quality
Vehicle
Transmission Frame Assembly Suspension
Frame SeatsFenders
Fender RodsFender Body
ControlAccount
ControlAccount
ControlAccount
ControlAccount
O N D J FFY 07
$ $ $ $
$ $ $ $$ $ $ $
$ $ $ $
ControlAccount$1000
Intermediate
Master
Detail
ControlAccount$2500
ControlAccount$1200
ControlAccount$4000
Control Account Planning
Copyright © 2010 Deltek, Inc.
23
Output: Updated CAPs
Outputs: Internal Mgt Reports and CPR; Corrective Action Report
Output: Variance Analysis Report
Output: Updated Program Log
Output: Revised Estimates
Output: Updated Schedules
Outputs: Subcontractor cost and schedule status
Manage Overhead
Rates
Accumulate Costs
Work Authorizations
Measure Performance;
Forecast ETCs; Analyze EACs
Analyze Variances
Develop and Analyze
Performance Reports; Develop Corrective Action
Plans
Maintain Program
LogsStatus
Schedules
Outputs: Work Authorization Forms
Manage Subcontractors &
Inter-company Organizations
Acc
ou
ntin
g
Re
spo
nsi
bili
ties
Pro
ject
Co
ntr
ols
&
Sch
ed
ulin
gR
esp
on
sib
ilitie
s
PM
/ C
AM
Re
spo
nsi
bili
ties
Project Execution Phase
Copyright © 2010 Deltek, Inc.
Measuring Performance
Work the Plan
Define the Work
Plan the Work
Collect Results
Measure Performance Against the Plan
Analyze Variances
Change Control
Institute Appropriate Corrective Actions
24Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 25
Measuring Performance
• Step 1: Status Control Account Plans and Schedules
– Update Schedules
– Update Status of Work Packages
– Update Estimates to Complete
• Step 2: Calculate Earned Value
• Step 3: Accumulate and Integrate Actual Costs
• Step 4: Calculate Variances, Indices and Estimate at Completion (EAC) Costs
Copyright © 2010 Deltek, Inc. 26
EVM Analysis Objectives
• Current Status Determination
– Where are we today
• Forecast for the Future
– What is the estimated cost at completion
• Identify Trends (no surprises)
– Where are we headed
• Indications for Management Action
27
Control Account CumulativeWork Package BCWS BCWP ACWP CV SV
1.1 11100 Project Management1.1.1 Project Management and Control 82,445 82,445 65,168 17,277 0
Control Account Totals: 82,445 82,445 65,168 17,277 0
1.2.1 13100 ABC Solution Design, Development & Verification1.2.1.1 ABC System Design 198,672 198,672 146,769 51,903 01.2.1.2 ABC Solution Implementation 115,741 19,592 73,469 -53,877 -96,1491.2.1.3 System Verification 55,450 19,394 9,824 9,571 -36,0551.2.1.4 ABC User Manual Update 13,631 133 0 133 -13,4981.2.1.5 Alternative Test Scenario and Support 0 0 2,436 -2,436 0
Control Account Totals: 383,494 237,791 232,497 5,294 -145,703
1.2.2 13100 ABC System Production Deployment1.2.2.1 Deployment Preparation 4,095 464 0 464 -3,6321.2.2.2 Deployment Support 0 0 0 0 01.2.2.3 Post-Deployment Support 0 0 0 0 0
Control Account Totals: 4,095 464 0 464 -3,632
Grand Total 470,035 320,700 297,665 23,035 -149,334
EVM Report Example
Copyright © 2010 Deltek, Inc.
28
Control AccountWork Package EVT BAC EAC VAC
1.1 11100 Project Management1.1.1 Project Management and Control LoE 110,514 66,050 63,464
Control Account Totals: 110,514 66,050 44,464
1.2.1 13100 ABC Solution Design, Development & Verification1.2.1.1 ABC System Design 50-50 198,672 146,769 51,9031.2.1.2 ABC Solution Implementation User Def 115,741 211,546 -95,8051.2.1.3 System Verification 30-70 75,276 48,441 26,8351.2.1.4 ABC User Manual Update User Def 13,631 44,277 -30,6451.2.1.5 Alternative Test Scenario and Support 50-50 0 53,105 -53,105
Control Account Totals: 403,320 504,138 -100,818
1.2.2 13100 ABC System Production Deployment1.2.2.1 Deployment Preparation % Comp. 10,238 18,618 -8,3801.2.2.2 Deployment Support % Comp. 17,103 17,103 01.2.2.3 Post-Deployment Support % Comp. 1,570 1,570 0
Control Account Totals: 28,912 37,291 -8,380
Grand Total 542,746 607,479 -64,733
EVM Report Example
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 30
Technology
• Technology: Tools and Interfaces
– Using Deltek’s Cobra as the EVM engine
– Integrating Cobra with Microsoft Project or Primavera P6
– Integrating Cobra with Cost Point or GCS Premier
– Enhancing analysis and reporting with wInsight
Accomplisments
Events
Criteria
Integrated Master Plan (IMP)
Work Packages
Control Accounts
Tasks
Integrated Master Schedule (IMS)
WBS
Work Breakdown Structure (WBS)
EVM Tool /Performance Management
System (Cobra)Responsibility Assignment Matrix
(RAM)
Organization Breakdown Structure
(OBS)
Cross - referenced
Statement of WorkCross - referenced
Iterative Risk Assessments
Risk Mitigation Action Plans
Supplemental Schedule
Relationship Between Work Products
Copyright © 2010 Deltek, Inc.
32
Hours by Project & Task
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
EAC / ETC
Schedule Status
Reports, Analytics
Control Acct Plans (CAP)
Reports (ContractPerformance Report,
Variance Analysis Report)
PMB
Program Logs
Actual and Accrued Costs
Project Management
Team
Management, Stakeholders
AccountingSystem
(i.e. Cost Point)
Budgets
EVM Tool(i.e. Cobra)
Charge Codes
(i.e. MS Project)
Material, ODC, Subcontractor Costs
EVM data, Metrics
Technology – Processes – People
Integrating Technology
Copyright © 2010 Deltek, Inc.
35
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
Control Acct Plans (CAP)
PMB
Budgets
EVM Tool(i.e. Cobra)
(i.e. MS Project)
Schedule Integration into Cobra
Copyright © 2010 Deltek, Inc.
36
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
Control Acct Plans (CAP)
PMB
Budgets
EVM Tool(i.e. Cobra)
(i.e. MS Project)
Schedule Integration into Cobra
Schedule Status
Copyright © 2010 Deltek, Inc.
37
Actual Cost Integration into Cobra
Hours by Project & Task
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
EAC / ETC
Schedule Status PMB
Program Logs
Actual and Accrued Costs
AccountingSystem
(i.e. Cost Point)
Budgets
EVM Tool(i.e. Cobra)
Charge Codes
(i.e. MS Project)
Material, ODC, Subcontractor Costs
Copyright © 2010 Deltek, Inc.
38
wInsight Enhancement
Hours by Project & Task
SchedulingTool
Schedule Dates
Work Breakdown Structure (WBS)
Scope Definition, Requirements, Key Events
Manageable Work Segments,Dependencies
EAC / ETC
Schedule Status PMB
Program Logs
Actual and Accrued Costs
AccountingSystem
(i.e. Cost Point)
Budgets
EVM Tool(i.e. Cobra)
Charge Codes
(i.e. MS Project)
Material, ODC, Subcontractor Costs
Reports, Analytics
wInsight
EVM data, Metrics
Copyright © 2010 Deltek, Inc.
Copyright © 2010 Deltek, Inc. 41
People
• People: Key Roles
– The Control Account Manager’s Role
– The Project Manager’s Role
– The Project Control Analyst’s Role
42
Responsible and accountable for planning and executing the scope of the control accounts assigned within the designated schedule and budget
Detail plans the scope into discrete work packages, level of effort and planning packages that support the schedule
Subdivides the allocated budget to the work packages so that it is time-phased and reflects the way in which actual costs are expected to be incurred
Identifies and obtains specific resources required to perform the work
Assigns an performance measurement technique to each work package that supports the performance goals (time-phased budget)
Responsible and accountable for planning and executing
the scope of the control accounts assigned within the
designated schedule and budget
Detail plans the scope into discrete work packages, level
of effort and planning packages that support the
schedule
Subdivides the allocated budget to the work packages so that it is time-phased and
reflects the way in which actual costs are expected to
be incurred
Identifies and obtains specific resources required to perform
the work
Assigns an earned value method to each work package that supports the performance
goals (time-phased budget)
The CAM is the
PROJECT MANAGER
for his assigned
scope, schedule and cost
Company
Eng Mfg Test
Design Quality
Control Account Manager
Copyright © 2010 Deltek, Inc. 43
Project Manager
• Review Internal Monthly Performance Reports
• Review All Variance Analysis Reports (VARS) with CAMS and Program Analysts
– Determine if performance trends for any control account warrant a VAR
– Determine if any activities’ cost, schedule or technical performance risk warrant a VAR even though the threshold for the control account may not have been exceeded
• Review and Approve Corrective Action Plans Initiated by CAMS with Follow-up to Closure
• Review of the Run-out Efficiency snd Performance Efficiency Changes Required to Meet the Current ETC Plan
Copyright © 2010 Deltek, Inc. 44
Project Control Analyst
• Work with the CAMs to status schedule activities terms
• Facilitate the transfer of schedule status from the scheduling system to the EVM system
• Facilitate the transfer of actual costs from the accounting system to Cobra
• Work with CAMs to assess the status and trends for technical, schedule, and cost performance
• Support the CAMs in performing Variance Analysis
• Maintain Contract Budget Base, Management Reserve, and Undistributed Budget logs
Copyright © 2010 Deltek, Inc. 45
EVMS Documentation
• The Backbone of the EVMS Is the Company’s EVM System Description and the Associated Policies, Procedures, Templates, Desktop Instructions
Policies, Procedures and Templates
Earned Value Management System Description Program Baseline Control & Maintenance P & P EVMS Roles and Responsibilities Guidelines Program Status Updates P & P Program Integration P & P Material Management P & P Program Directives Guidelines Indirect Cost Management P & P Work Breakdown Structure (WBS) P & P Performance Analysis and Reporting P & P Organization Breakdown Structure (OBS) P & P Integrated Master Plan (IMP) P & P Responsibility Assignment Matrix (RAM) P & P Subcontractor Management P & P Program Scheduling P & P Material Management P & P Control Account Planning P & P EVMS Surveillance P & P Rates P & P EVMS Surveillance Plan Fiscal Calendar P & P Undistributed Budget P & P Subcontractor Management P & P Management Reserve P & P Performance Measurement Techniques P & P Actual Cost Accumulation P & P Work Authorization P & P
Copyright © 2010 Deltek, Inc. 46
EVMS Documentation (cont.)
• Sample Desktop Work Instructions:
Desktop Work Instructions
Program Scheduling Work Instructions Control Account Plan Work Instructions Program Baseline Control and Maintenance Work Instructions Program Status Updates Work Instructions Performance Analysis and Reporting Work Instructions Rates Work Instructions Fiscal Calendar Configuration in Cobra Work Instructions
Copyright © 2010 Deltek, Inc. 47
EVMS Training Modules
• Sample Training Modules:
EVMS Training Modules
Work Breakdown Structure (WBS) Subcontractor Management Organization Breakdown Structure (OBS) Undistributed Budget Responsibility Assignment Matrix (RAM) Actual Cost Accumulation Control Account Planning EVMS Surveillance Fiscal Calendar Indirect Cost Management Integrated Master Plan (IMP) Labor Recording Management Reserve Material Management Performance Measurement Techniques Performance Analysis and Reporting Program Integration Program Baseline Control & Maintenance Program Scheduling Program Directives Guidelines Program Status Updates Work Authorization Performance Measurement Baseline Development
Control Account Manager (CAM) Certification Training
Copyright © 2010 Deltek, Inc. 49
Lessons Learned
• Potholes to Avoid:Procrastination Delaying the EVMS implementation or
making it dependant on the award of a contract
Complacency Not being current on EVM requirements
Unrealistic Expectations Underestimating the time and resources needed to implement an ANSI-compliant EVMS
Wandering Aimlessly Not having clear EVMS goals and implementation roadmap
Underestimating Cultural Impact Not planning for the organizational change impact that the EVMS will have
Lack of Discipline Not following up the EVMS implementation with a formal surveillance program
Business as Usual Not managing the EVMS relationship with your customer
Copyright © 2010 Deltek, Inc. 50
Questions
• Kelly Meassick, PMP
– (256) 755-0449