View
666
Download
0
Embed Size (px)
DESCRIPTION
Working together for success, 14th October 2013
Citation preview
Cookham Wood -LEAN AND MEAN
WIPM CONFERENCE
14TH October 2013
Jane FoulkesAssociate DirectorF+G Project Management Team
Helen BrydsonSenior Project ManagerF+G Project Management Team
Meet Jane and Helen
The agenda
• The backgroundGovernment collaborative initiatives
• Pre-construction Phase:BIMContractor Collaboration
• Construction PhaseThe site and build – sequencing and constructionAppointed TeamStakeholder engagementWorking together to overcome challenges
• Summary
• Any Questions?
Scope:• New build 179 place Houseblock • New build Education facility with workshop and classroom space• BREEAM Excellent• Mothball existing Ash & Beech Wings
Procurement :• 2-stage tender • Design & Build
Contract:• Partnering Contract::
PPC 2000
Value:• £19 Million (incl. client risk, local commissioning)
Programme:• 20 November 2012 – 10th January 2014
• Education Building – mid-November 2013• Houseblock Completion – mid November 2013• A&B Wing Mothball works completion – mid January 2014
Project information
Key Lean/Collaborative Initiatives:
• Government BIM Early Adopter Project
• Soft Landings Trial Project
• Project Bank Account
• MoJ Lean Training Trial Project
The drive for Lean, Partnering and BIM
3 key ways we worked collaboratively to achieve BIM
• Keeping BIM in perspective
• Helping the Client understand what he wants from BIM
• Bringing the Contractor in early
Event Sep 11 Oct 11 Nov 11 Dec 11 Jan 12 Feb 12 Mar 12
Won the job
Tender issue date
Project put on hold
Project restarted plus BIM
Revised Tender date
3 month design in BIM period
Cookham Wood Pre-Tender Time Line
A Mean Programme
In the beginning....
Project Process
BIM Process
Keep BIM in perspective: A process within a process
BIM Client Requirements
(EIR’s)
Standards
Software Platforms
Stake-holders
BIM Deliverables
Managing Change
Co-ordinates
Planning the work and data
segregation
File Security
Level of Detail
H+S
Help the Client understand what he wants from BIM
Help the Client understand what he wants from BIM
Snapshot of BIM outputs
Requirements:• BIM 3-d model • BIM drops at end of design (drop 3) and construction (drop 4)• Cobie Output (Excel)
Achieved to date:• BIM drop 3• Construction drawings formed from 2D cuts of model• Model presented to end user (Governor) – useful and successful tool
Discussions ongoing:• Format for BIM drop 4• Level of information for BIM drop 4• How to utilise BIM data for end user maintenance database requirements/input
Contractor collaboration and the form of contract
PPC 2000 Road Map
Job starts on site
Stage 2: Constructor develops design
Constructor submits DPP and AMP Clients team evaluate
Tender awarded and Partnering Agreement signed
Stage 1: Tenders returned and evaluated
Constructors submit IPP Evaluation basis: 70% cost, 30% quality
TenderProject tendered to constructors on existing framework
Client Design
Client design team develop outline proposals
Client appoints design team
Designers, QS, Client Representative.
Add picture
Construction Phase
The site and build
Existing
Prison (‘Live Side’)
Water Main way leave
New
Breach
Perimeter Fence
Houseblock
Education Building
Temporary
Site (‘non-operational
side’)
Contractors Site setup
Gatelock/fence breach
The site and build
Houseblock
• 2 spur houseblock with central core area• 3 levels• Pre-cast concrete pods• Pods cast offsite, assembled onsite• Single cells with en-suite wet-room
Education
• 2 storey, steel framed education building• Ground floor – practical skills (workshops,
kitchen)• First floor - classrooms
Project team
Cookham Wood, Rochester (Site Based): Client Liaison Officers (CLO): - Faithful+Gould:
LondonClientMinistry of Justice
Client Representatives (CR) – Faithful + Gould:
Cost Consultant and CDM-CSweett Group
PlymouthM&E Technical Assessor (TA):URS
RedditchLead Technical Assessor (TA):hln Architects
BirminghamConstructorInterserve
Constructor Lead DesignersArups
Key stakeholders working collaboratively
• MoJ Departments:• Technical Services Dept• Lean Task Group .
• Establishment• Governor• Works Dept.• Security • Education Staff• Project Liaison Officer• Young Offenders
• Local Residents
• BIM Task Group
• Local Planning Authority
• Lean Training Providers
Working together to overcome issues
Planning:• Late discharge of planning - delay to commencement of main works
Unforeseen Ground Conditions:• Continual foundation design evolution in line with programme
Inclement weather:• Extended cold winter / spring
• Concrete batching plant unable batch• Temperatures too low for resin application
Constructor Design Development and Co-ordination:• RAG report • Samples of all finished products required on site (e.g. sample resin cell, sample door viewer)
Early Warning Mechanisms:• Overcoming conflict •Team resolution
Closed
Live
Collaborative programme monitoring
0.00%1.00%2.00%3.00%4.00%5.00%6.00%7.00%8.00%9.00%10.00%11.00%12.00%13.00%14.00%15.00%16.00%17.00%18.00%19.00%20.00%21.00%22.00%23.00%24.00%25.00%26.00%27.00%28.00%29.00%30.00%31.00%32.00%33.00%34.00%35.00%36.00%37.00%38.00%39.00%40.00%41.00%42.00%43.00%44.00%45.00%46.00%47.00%48.00%49.00%50.00%51.00%52.00%53.00%54.00%55.00%56.00%57.00%58.00%59.00%60.00%61.00%62.00%63.00%64.00%65.00%66.00%67.00%68.00%69.00%70.00%71.00%72.00%73.00%74.00%75.00%76.00%77.00%78.00%79.00%80.00%81.00%82.00%83.00%84.00%85.00%86.00%87.00%88.00%89.00%90.00%91.00%92.00%93.00%94.00%95.00%96.00%97.00%98.00%99.00%100.00%0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
110%
0%
15%
0%
24%
0%
33%
0%
33%
0%
32%
0%
32%
0%
36%
45%
0%
54%
0%
63%
0%
71%
0%
75%
0%
75%
0%
74%
0%
61%
0%
33%
0%
33%
0%
42%
0%
62%59%
0%
64%
0%
67%
0%
63%
0%
63%59%
0%
59%
0%
59%
0%
59%
65%
0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%0%
Progress
Bu
ffer
Con
su
med
Project
Stakeholders
TeamBIM
Lean
Summary
Any questions?