Upload
eileen0692
View
2.608
Download
0
Tags:
Embed Size (px)
Citation preview
CHEANG EILEEN – CHIN PUI MAN – CHU SZI WEI – HIEW YEN NEE – LEONG CARMEN -LIEW HUI EN – TAN HENG YEE – YONG SEH LI 1006A77249 0310331 0314160 0314212 0314953 0314920 0314941 0314345
SCHOOL OF ARCHITECTURE, BUILDING & DESIGN Bachelor of Science (Honours)(Architecture)
BUILDING CONSTRUCTION 1 [ARC 1413]
Assignment 1: Experiencing Construction
Table of content
Chin Pui Man Chin Pui Man (2.0)
& Yong Seh Li (2.1)
Tan Heng Yee & Hiew Yen Nee
Cheang Eileen & Chu Szi Wei
Carmen Leong (5.1,5.2,5.3) Tan Heng Yee (5.2) Cheang Eileen (5.4) Liew Hui En (5.5) Hiew Yen Nee (5.6) Yong Seh Li (5.7)
Chin Pui Man (6.0) Liew Hui En (6.1)
Cheang Eileen Chu Szi Wei
1.0 Introduction
1.1 Introduction of Site
2.0 Sites and Safety
3.0 External Work
4.0 Foundation
5.3 Wall
5.5 Formwork
3.1
Setting out and Earth Work
2.1 Plants and Machinery
4.1 Foundation type and construction process (from site visit & reference)
5.2 Slab
5.4 Staircase
6.0 Roof
6.1 Roof type and construction process (from site visit & reference)
5.6 Door
5.1 Beam and Column
5.7 Windows
7.0 Summary
7.1 Reference
As architects and the building industry continue to design and build structures that dif fer in design, type, materials and building method, i t has become important that each party stay familiar with both basic and new concepts of building construction. As t ime pass by, construction methods are constantly being replaced by new and more eff ic ient and cost effective methods to construct buildings. Therefore, architects need to improve with knowledge of building construction in order to fol low trend of technology.
1.0 Introduction
AIM: This project is to produce architects with knowledge of building construction by identifying difference types of building elements, construction process, details and materials. This report includes the studies and records of s ite and safety, external work, foundation, superstructure, roof and doors.
1.1Introduction of Sites
a.
De’ bunga Residence @
Ukay Perdana
Date of plan approval: Mac 2013
Project tit le
3 strata landed housing scheme (gated community) build 68 units of 3-storey semi-detached houses, 14 units of 3-storey house, 1 unit of electrical substations and 1 unit of guardhouse. Owner
STAR BASE SDN. BHD. [Company no: 521591-H] Level 22, Menara Maxisegar, Jalan Pandan Indah, 4/2 Pandan Indah 65100 Kuala Lumpur.
Architect
Ar. Lee Be Hsin 43-3 Jalan 1/1 16B Kuchai Entrepreneur Park, Off Jalan Kuchai Lama 58200 Kuala Lumpur.
Developer & Contractor Sierra Ukay Sdn. Bhd & Ijm Building Systems Sdn. Bhd. Ground Floor, Wisma IJM, Jalan Yong Shook Lin, 46050 Kuala Lumpur.
b. Altitude 236, Luxury Condominium
@ Bukit Manda’rina
Construction starts: September 2011.
Estimated of completion date: October 2014
Project tit le
One block of medium cost apartments of 38-storey high with 31-storey apartments (236 units), 1-storey residential facilities, 4-storey car park, 2 floor of M&E and services and 1 block annex parking 4 and ½ floor and 1 floor recreational facilities.
Owner & Developer MANDA ‘RINA SDN. BHD. Ground Floor, Wisma IJM, Jalan Yong Shook Lin, 46050 Kuala Lumpur.
Architect
PTA Design Sdn. Bhd. No. 37, Jalan Damai, Off Jalan Tun Razak, 55000 Kuala Lumpur.
Contractor Ijm Building Systems Sdn. Bhd. Ground Floor, Wisma IJM, Jalan Yong Shook Lin, 46050 Kuala Lumpur.
Safety management is established; a. Prevent injuries and illness b . To avoid direct and indirect cost that related to injuries and properties damages
Ways to prevent injuries and accidents; a. Train all employees on safety steps. b. Material handling and mobile equipment safety. c. Provide protective equipment
Site Safety
Signs warn hazards at locations where hazards exist.
S igna ls are moving signs provided by workers (eg: flagman, flash lights, honks, alarms) to warn possible or existing hazards.
Acc ident-Prevent ion Tags is used for temporary warning. (figure 2.2)
Head Protection
Protective hard hats are to minimize the rate and level which impact forces are transmitted to the brain, neck and spine. Refer to figure 2.3
Figure 2.0.1: Work Clothing
2.0 Sites and Safety
Hard hats
S tandard vest with stripes.
Long-s leeved work sh i r t . Nothing less than 4-inch sleeves.
C lose- f i t t ing or medium-fitting jeans.
Sa fety work shoes or boots.
Hard outer she l l ; to resists and defects blows to the head.
Shock-absorb ing l in ing; incorporate a headband and straps.
C l ip on sweatband; absorb sweats before trickles into eyes.
Peak; to protect eyes and face. Figure 2.0.5: Hard Hat Type 2
Figure 2.0.3: Signs Figure 2.0.4: Accident-‐prevention tag
Figure 2.0.2: Signs
Scaffolding & Planking Scaffold is a temporary structure used to support people and materials.
Safety Net Safety net is setup to provide fall protection.
Figure 2.0.6: Scaffolding at De’bunga Figure 2.0.9: Walk-‐through scaffold
Figure 2.0.7: Planking on scaffold to provide walking underneath
Figure 2.0.8: Proper planking system
Figure 2.0.11: Walkway on scaffold in between building and safety net
Wooden guardra i ls secured to frame
Tube-and-c lamp guardra i ls to protect outrigger/side platform -Can be adjustable in height and width.
• Walk-through scaffold is frequently used by masonry trade to provide greater height per tier and easier distribution of materials on platforms at intermediate levels.
Frames
Pile Driving Equipment A pile driver is used to drive poles or piles into the soil to give foundation support for buildings or structures. It is placed on a pile or pole
Excavator Excavator is heavy machinery composed of a boom, stick, bucket and cab upon rotating platform known as the ‘house’. The house sits on top of an undercarriage with tracks or wheels. Funct ion movement of excavator are achievable through the use of hydraulic fluid,
motors and cylinders. Is used to dig holes, foundations and trenches.
Compactor
A machine used to minimize the size of waste materials or soil through compaction.
Figure 2.0.10: Scaffolding at Altitude 236
2.1 Plants and Machinery
Figure 2.1.1: Pile Driving Equipment at De’Bunga
Guide consists heavy weight to enable to slide up and down easily in single vertical line. It is placed on a pole or pile. Figure 2.1.2: Parts of Pile
Driving Equipment
Figure 2.1.3: Excavators at De’ Bunga
Figure 2.1.4: Views and measurement of excavator
Hydraulics, steam, diesel or manual labor is used to raise weight. Once the weight reaches its optimum point, it will immediately released and smashes on to pile or pole in order to drive it into the ground soil.
Figure 2.1.5: Compactor at Altitude 236
Backhoe Loader Is an excavating equipment consists of digging bucket on the end of the two-part articulated arm. It is also used in construction, demolitions, light transportation of building materials, excavation, landscaping and paving roads.
Bulldozer A bulldozer is a crawler consist of a substantial metal plate, also known as blade, used to push large quantities of sand, soil and other materials during construction and generally equipped at the rear with a ripper to loosen compacted materials.
Figure 2.1.6: Backhoe loader at Altitude 236 Figure 2.1.7: Backhoe loader at De’Bunga
Figure 2.1.7: Part of backhoe loader
Figure 2.1.0: Overall view of bulldozer
Figure 2.1.9: Blade Figure 2.1.8: Ripper
Dump Truck Is used to transport loose material like sand, soil and dirt. It is equipped with an open-box bed, which is hinged at the rear and consists of hydraulic piston to lift up the front, enabling the material in the bed to be dumped on the ground behind the truck.
Rebar Bender A device used to bend steel bars and other heavy metals.
Tower Crane Tower crane is fixed to the ground on a concrete slab. It gives the best combination of height and lifting capacity and is used in construction of tall buildings. The base is attached to the mast that gives its height. It is further attached to the slewing unit, which enables the crane to rotate. On the top of the slewing unit, there are the long horizontal jib, shorter counter-jib, and the operator's cab. Forklift
Figure 2.1.11: Dump truck at De’Bunga
Figure 2.1.14: Brief explanation of rebar bender
Figure 2.1.12: View of dump truck
Figure 2.1.13: Rebar Bender at De’Bunga
Figure 2.1.15: Tower crane at Altitude 236 Figure 2.1.16: Sectional view of tower crane
Forklift truck is used to lift and transport building materials. Its components include the truck frame, counterweight, cab, overhead guard, power source, tilt cylinders, mast, carriage, load backrest and attachments.
Figure 2.1.17: Forklift at Altitude 236
1. Soil Testing
2. Land Surveying 5. Leveling and Grading 4. Cutting, Filling &
Compacting
3. Site Clearance
Collecting and identifying the sample of soil on site Purpose a) To ensure no hidden chemical/physical condition on site b) Help to choose suitable footing type. c) To know the ground water level to help whether need to carry out dewatering. How? a ) Excavation of Trial Hole ( 2m x1m)
I. Using machinery exactor II. Allow good visual
inspection of the strata b) Drilling boreholes
I. Using hand auger II. Inspection of strata can
only be done by excavated material brought up by auger
Purpose a) To ensure the
boundaries of the property is set precisely
b) To ensure building build at a right boundary
c) To avoid legal problem when construction start
Who ? By Land Surveyor How ? By using Theodolite
Removal of vegetation, stumps, roots and topsoil at least 2’ below subgrade Purpose a) To prevent soil
movement caused by decaying organic matter which may threaten the foundations or other elements of the surrounding site.
b) To prevent future problems like insect infestation, diseased wood and lawnmower damage
Earthmoving operation in which the material excavated and removed from one location is used as fill material at another location. Why? a) The land being filled is
going to be used for building foundations.
b) Compacting earth is to avoid settling.
Device
Bulldozer
Plate compactor
3.0 External Work
3.1 Setting out & Earth Work
Reshaping of the field surface to a planned grade Purpose a) To level the field to its best condition with minimal earth movement b) To provide a slope which fits water supply How? Dumpy level measures the height of two points on a horizontal plane, allowing the builder to measure whether a bit of ground is level or not. Phases of Land leveling operations 1. Rough grading 2. Land levelling 3. Land smoothing. Device
Skid-Steer loaders Dumpy level
6. Setting Out
6a. Pegging Out 6b. Setting Out Corner
Profiles
6c. Mark Builder’s Line 6d. Marking Out on the
Ground from the Profiles
Purpose To ensure that the various elements of the scheme are positioned correctly in all three dimensions. Equipment a) Wooden Pegs - provide with nail fixed at the top center to locate the station point b) Profile Boards - help to indicate the thickness of the wall and width of the foundation c) Builder’s Lines - made out of hemp, string or wire - must not stretch, sag or taut which can cause the profile board to displace or the line itself breaks Device
Theodolite Dumpy level Tripod
1. One of the building
corners will be set up as a
temporary benchmark
by placing a wooden peg
in the ground with a nail on top.
2. Mark two corner of the
building to set out the front line.
3. The lines of all the other
walls are measured from this front line using Pythagoras theorem.
4. After placing 4 pegs at
corner, measure the diagonals (Line x & y) and make sure both are in same lengths
1.When the positions of the corners of the building are known,
profile board will be
used to mark the positions and widths of the wall, foundations and excavation .
2.Saws cut in top of
profile board set horizontal and to know level
1.Saws cut in the top of
Profile board act as marks
and allow builder's line
stretching from notch to notch in opposite profile board -intersection of string mark corner of various part of substructure this black dot mark the corner of the wall to be built and should be exactly over the original wooden peg
1. Marking out on the ground follow the builder’s line as closely as possible by
sprinkle old cement, lime or saw dust on ground.
2. Remove the builder line to allow excavation to carry on as the line will disturb the subsequent work.
7. Trench Excavation
8. Subsoil Drainage System 9. Backfilling 10. Pavement
With the outline of the concrete marked on the ground, excavator digged out between the lines to form a trench How? By using JCB excavator
A drainage system above natural water table that drain away surface water Purpose ? a. Increase the stability of the ground and footings of building b. Reducing foundation movement due to the variation in the soil moisture content. Type of pipes a. Rigid-concrete pipe b. FlexibleHDPE Corrugated Pipe
Used to surround pipes that are buries beneath the surface Why? a. Helps to protect the pipe from damage. b. Acts as a foundation for the road pavement. How? a. Flowable type backfill b. Granular type backfill
Made up of three layers: a. Subgrade: Earth that has been graded to the desired elevation. b. Subbase: A course of material that is placed on the subgrade to provide drainage and stability. c. Base is placed on the sub- base to provide a stable platform for the concrete pavement slab. Why? a. These are essential for a strong,durable concrete pavement system. b. To maintain a good system of roads which is the underlying backbone of our infrastructure.
A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. It usually forms part of the foundation of a building, typically a multi-story building, structure or support base for heavy equipment. The cast concrete pile cap distributes the load of the building into the piles. A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.
4.after the completion of a bored pile , the remaining reinforced bars are then extended to form starter bars and the concrete pile is then extended up to ground level or beyond such that the floors of the building rests on the pile.
4.0 Foundation 4.1 Foundation type and construction process
Lateral Reinforcement
1. 2. 3.
4.
• Number of reinforcement bar used in columns may be varied instead of varying the size of columns.
• Formations of lateral reinforcement bars depends on the number of vertical reinforcement bars used in a column.
• Lateral ties should have a minimum diameter of 10mm. • Space between two ties is not more than 48 tie diameter. • Type of reinforcement used is usually T12, reinforcement steel with
a diameter of 12mm.
Beam and Column Reinforced concrete column
• Reinforced concrete column is designed to carry compressive load.
• Reinforcement bar in concrete increases the column’s tensile strength.
• Size of columns differs according to the amount of load it has to bear.
• Length of overlapping reinforcement bar is forty times of the diameter of bar.
• Vertical reinforcement should not be less than 1% nor more than 8% of the cross sectional concrete beam.
• Types of reinforcement steel includes T12, T14, T16, T20, T25, T32 and T40.
• ‘T’ represents reinforcement steel and the numbers indicates the diameter.
• Concrete columns may be supported by isolated footings or by pile caps.
• Dowels tie column to supported beam or slab.
Rebars for columns
5.1 Beam & Column
Simply supported beam Fixed beam Con5nuous beam
• Beam is supported by two columns at both ends.
• Beams of a rela7vely short span uses this support.
• Beams that are fixed at both ends either to other beams or to two walls.
• It is can be supported by primary beams.
• A con7nuous beam has more than two supports distributed throughout its length.
• Used to support a beam of a large span.
BEAM SUPPORTING TYPES
Reinforced Concrete Beams • Without reinforcement, beam will crack when too much force is
applied to it.
• Longitudinal bar serves as tension reinforcement.
• BoCom bar withstands more tensile force because force is applied downwards.
• Depth of beam is span divided by 16
• Beam width should be equal or greater than width of suppor7ng column.
• S7rrups are placed perpendicular to the longitudinal bar to resist the ver7cal component of a diagonal force.
• Reinforced concrete beam is a horizontal structural component designed to carry load.
• Like columns, reinforcement bar is ins7lled to withstand tensile force.
Reinforcement bars of beam and slab
Steps to build Beams and Column
Setting up of reinforcement bars. The thickness of bars and the number of bars used depends on the load it has to bear.
1
2 7 6 5 4 3
Cladding of formwork using plywood.
Cement is being pumped and poured into the formwork. A concrete vibrator is then used to released trapped air and excess water.
When the concrete of the columns have dried up, cladding of formwork for beams can be done.
Reinforcement bars for beams are set up.
Cement is poured into the formwork. A concrete vibrator is then used to ensure that the concrete settle firmly in place.
Columns and beams are formed. Excess rebar on top of column is for continuation of rebar for next floor.
• Reinforced concrete slabs are plate structures
laid with reinforcement bar to withstand load.
• It is supported by beams. Hence, force
applied to slabs are transferred to beams.
Suspended Slabs
• Beam that supports the slab
Reinforced Concrete Slab
• Size of reinforcement bar used differs according to the load it has to bear.
• Reinforcement bar placed perpendicularly.
• Thickness of floor slab depends on the load it has to bear.
• Minimum thickness of slab is 100mm.
Reinforcement bars for slab.
5.2 Slab
Ground Slabs
Gravel Stone • Gravel Stone laid as a base to prevent the
capillary rise of groundwter. • Minimum thickness is 100mm.
Damp Proof Membrane • Polyethylene moisture barrier to prevent
water from entering the structure. • Thickness of polyethylene is 0.15mm
Concrete Slab • Thickness depends on the load it
has to bear. • Minimum thickness is 100mm. • Additives may be added to
increase surface hardness and abrasion resistance.
One-Way Slab • One way slabs are
reinforced in one direction and they are casted on a series of parallel beams or walls.
• Force is transferred in parallel to beams.
• Suitable for light load and span of slab is relatively short.
Two-Way Slab • Two way slabs are
reinforced in two directions. It is casted with supporting beams on all four sides.
• Force is transferred to all four sides to the beams.
• Suitable for heavy load. Shape of slab is relatively squarish.
Workers working on ground slab.
1. Ledger is set for the beams.
2. After setting the ledgers. Bearers
will be installed in an interval of
300mm.
Bearer
3. Plywood are installed sides by
sides and bases are installed
between the bearers
4.The props is set for slab
installation . Then ledgers for slab
will be set in an interval of 200mm .
Then,plywood decking will be laid on
the props setting.
Next is the entering of the
reinforcement cages of beams Plywood Decking
5. Spacer blocks are placed
on the plywood decking which
allow sufficient concrete
cover.
6. Electrical wiring system is
installed before placing the
bottom reinforcement.
7.Cement is poured to form
the concrete slab .The
cement is transported by a
concrete pump
8.Dismantlement of the
wooden formwork will occur
after the concrete gain certain
strength.
Types of wall
I. De’Bunga : a) Masonry Wall • Clay brick builds the wall. Bricks are laid in running bond. • Openings are spanned with lintels for installation of doors and windows. • Thickness of wall is 100mm.
5.3 WALL
Figure 5.4.1: Masonry Wall structure at De’bunga
Figure 5.4.2: Party Wall structure at De’bunga
II. Altitude 236 :
Reinforced concrete wall formed by Aluminium formwork • Walls formed by reinforced concrete is load bearing • Pouring concrete mix into formwork with reinforcement bar forms
reinforced concrete wall. • Minimum thickness of load bearing wall is 150mm and 205mm
for party walls.
b) Party Wall • The wall is built between two houses that are attached to each other. • Thickness of wall is 205mm. • Acts as a fire wall. It slows down the spread of fire to the neighbouring house.
Figure 5.4.3: Reinforced concrete wall at Altitude 236
Steps of construction wall
Concrete Column
Dowel Bar
• Acts as brick reinforcement.
• Placed at an interval of 4 rows of bricks
1
2 4 3
Level Peg • An indicator for
the thickness of the plaster.
X-met • Fastened in
between column and bricks to prevent cracking of plaster.
Dash • Mixture of
cement, sand and water.
• Applied onto concrete surface.
• To provide a rougher surface to hold plaster.
Concrete cement
X-met • Acts as brick
reinforcement. • Placed at an interval of
4 rows of bricks. Bricks
• Laid in running bond
Finishing
• Plaster will be done after masonry work.
• Plaster is a mixture of adhesive cement, sand and water.
Wooden formwork of staircase
v
1
2 3 4
5.4 STAIRCASE
Temporary panels along the stairway at construction area are set up and braced. Treads and risers on the panel are also laid out. Then, the slab thicknesses at a right angle to the slope of the stairway are measured and a line is snapped.
Temporary panels
Brace
Riser Tread Slab thickness
Rebar
Stringer width
Shores to be cut at angle Soffit panel thickness
Joist width
After that, lay out the soffit panel thickness, joist width and stringer width and snap lines. The next step, shore length and the side form width are determined.
Soffit panel
Joist
Stringer
Shores cut to length
Shores are cut to length and secured in position. Stringers are nailed to the tops of the shores, joists are nailed to the tops of the stringers and soffit panels are nailed in position. Then, the temporary panels are removed.
Front section
Rebar
Side forms
Cleats Riser form boards Stiffener
Bottom plate Top plate
Treads and risers are laid out on the side form. While the top and bottom plates and stiffeners are nailed through the side forms. Side forms are then fastened to the top of the joists. After the rebar has been placed, cleats and riser form boards are fastened to the side forms. Lastly, the front section is nailed into place.
Figure 5.5.1: Staircase construction formwork at Altitude 236
NOTE: The construct ion o f s ta i rs us ing system formwork at A l t i tude 236 is very s im i lar to wooden formwork such that segments o f the formwork are p ieced together l i ke a j igsaw. System formwork is a t an advantage whereby no wastage o f wood is produced and the a lumin ium mould can reuse over and over aga in . Th is prov ides a one- t ime investment for the contractor as we l l as compared to wooden formwork that can be used once and has to be d isposed o f a f ter usage.
Types of staircase
Both of the sites are having the same type of staircase, which is concrete sta i rs .
A concrete sta i r is designed as an inclined slab with steps formed on its
upper surface. Hence, it often requires careful analysis of load, span and support
conditions.
Shear key
Steel dowel
Nosing bars
Steel reinforcement as required
Horizontal bars extend into sidewall.
Beam support Figure 5.5.2: Longitudinal section of a concrete staircase
Stair Plans
1. De’bunga
Uses quarter- turn sta i r . Quar ter- turn s ta i r is a L-shaped stair, which makes a right-angled turn in the path of travel and its two flights are connected by an intervening landing which are equal in size.
Figure 5.5.3: Quarter-‐turn staircase
2. A l t i tude 236
Uses ha l f - turn sta i r . A half turn-stair turns 180 degrees at an intervening landing and this kind of stair is more compact than a single straight-run stair. Two flights connected by the landing here are also equal in size.
Figure 5.5.4: Half-‐turn staircase
ALUMINIUM FORMWORK SYSTEM
1. ARRIVAL AND UNLOADING OF CONTAINER 2.MATERIAL VERIFICATION 3. PRELIMINARY TASK BY JOBSITE 4. PREPERATION FOR SETTING 5. WALL SETTING 6. OPENING AND SUNKEN SETTING
7. KICKER SETTING 8. AL-BRACKET SETTING 9.SLAB SETTING 10. CONCRETE SETTING 11. AL – FORM DISMENTTLEMENT 12. INSTALLATION OF EXTERNAL WORKING BRACKETS STAIRCASE SETTING
5.5 Formwork
1.ARRIVAL AND UNLOADING OF CONTAINER
2.MATERIAL VERIFICATION
The panels inside each container is unloaded
The supervisor and client’s representative will verify material received based on the packing list. Once the verification is completed the panels is put in order based on set up location.
3. PRELIMINARY TASK BY JOBSITE
As preliminary task, the structural line must be drawn based on the shell plan.
Based on the structural line the rebar must be installed.
Before installing the panels, it is extremely Important to apply sufficient quantity of oil based form oil, in order to prevent the concrete to stick on the panel.
5. WALL SETTING
When installing the wall panels, the job site workers must start on one side of the wall and install the wall panels with the flat ties. Once the set up for one side is completed the opposite side will be completed with the PVC slits.
6. OPENING AND SUNKEN SETTING
Ones all wall panels had been installed, the installation of panels for opening area will start. Ones the up stand has been set up the installation of panels for window area is as follows.
4. PREPERATION FOR SETTING
FLAT TIE AND PVC SLEEVE
1. BEAM CAP SLAB PANEL 2. BEAM CAP SC 3. WALL END PANEL 4. BEAM CAP SC 5. BEAM CAP PANEL 6. PROP AND PROP HEAD
WALL PANELS
WEDGE AND ROUND PIN
1 2 2
3 3
4 4 5
6
Once the inner and outer panels had been installed, the kicker will be installed on the top of the wall panel in sure that the both four encore will be used while installing the kicker panel.
7. KICKER SETTING 8. AL-BRACKET SETTING
In order the keep the horizontality of the wall, the AL bracket and square pipe will be installed.
The assembly of the main beam will be done by assembling the middle beam, end beam and prop head together. When installing the slab, start with one standard panel at the corner of the room and then install the main beam. Remaining slab panels will be installed.
9.SLAB SETTING
Ones the assemble has been completed, the person in charge of the job site must clarify all panels and accessories had been installed correctly. When this clarification is done, concrete will be poured on wall, beam and slab .
10. CONCRETE SETTING 11. AL – FORM DISMENTTLEMENT
24 hours after pouring the concrete, the dismantlement will start with wall panels. Ones dismantled leave the wall panels , leave the panels along the wall by type and by location. Furthermore, when the panels of opening areas are dismantled insure that the prop remains in its place.
After dismantling the wall panels, the slab will be dismantled. While dismantling insure that the slab panel will not free fall on the floor or on the workers and the prop and prop head will stay in its place. The last area to be dismantled will be the slab corner.
KICKER
AL-BRACKET SQUARE PIPE
JOINT BAR
BEAM
SLAB PANELS
PIPE SUPPORT
PROP HEAD
MIIDDLE BEAM
When installing the external plat form, install them in a distance of 1.2 meters using the thyroids. Once the bracket of the plat form has been installed, install the timber for the platform and safety rail.
12. INSTALLATION OF EXTERNAL WORKING BRACKETS STAIRCASE SETTING
The staircase must be installed as follows. Installation of the wall panels on the down area.
Installation of the slab panel, beam and props. Installation of the upper part panels. Installation of the lower panels.
Using the same method shown, the installation and dismantlement of the aluminum formwork will be repeated until all of the floors are completed.
Installation of the side panels. Finally installation of the step and cap panels. Insure that there will always be props on two level, to support the slab .The external working platform must be installed on two levels.
STEP PANEL
CAP PANEL
WALL PLATFORM
TIMBER PLATFORM
SAFETY RAIL
ADVANTAGES OF ALUMINIUM FORMWORK SYSTEM
SPEED UP CONSTRUCTION PERIOD BETTER WORKING ENVIRONMENT INCREASE IN WORKER’S SAFETY INCREASE IN WORKFORCE’S SKILL
SLAB PANEL -used to support the concrete weight during concrete pouring and casting
PROP HEAD- used to joint the beams together and the prop head was connected with the pipe support
MIDDLE BEAM-Used to joint the prop heads and supports the slab panels
JOINT BAR-Used to joint the prop heads with the beams
WEDGE AND ROUND PIN- used to joint the Wall or Slab panels together.
FLAT TIE- used to joint the wall panel to the opposite side’s wall panel.
PVC SLEEVE-installed between the wall panel and the opposite side’s wall panels. Flat ties is inserted inside the PVC sleeve to prevent the casting of flat tie to the concrete.
AL-BRACKET AND SQUARE PIPE- used to allow horizontal straightness of the wall panels.
5.WALL
9. BEAM AND SLAB
DESCRIPTION OF ACCESSORIES
FLAT TIE WALL PROP HEAD AND PIPE SUPPORT STAIRS
CONCRETE PUMP PIPE
EXTERNAL PLATFORM
Door A door f rame is a building component used to hang a door. Frames used in residential buildings are typically made from wood. Its surrounds and supports the
entire door system.
5.6 DOOR
Figure 5.6.1: Wooden door frame at De’bunga
Figure 5.6.2: Wooden door frame at Altitude 236
Rough Opening An opening in a wall into which doorframe is fitted. Head Door jamb Stop/Doorstop The projecting part of doorframe against which a door closes. S i l l
Figure 5.6.3: Wooden door frame at Altitude 236
• To hold the doorframe before it gets harden/fix in position.
• To prevent from falling
Cas ing (Tr im) The moulding that surrounds the doorframe for looks. Jamb The door frame that surround the actual door. Attached to door by hinges. S top Small strip of wood that surrounds the entire inside perimeter of the door and stops the door from swinging in to far. H inges Attach the door to the doorjamb (frame).
Types of Door
Slab Door The most popular door that used by everyone
French/Hinged Door Two door panels that lock in the middle and swing in or out
Dutch Door The top part can be move while the bottom shut.
G l id ing Door A door with two or four panels that slide past one another
B i -Fo ld Door A system of hinged doors that stack against a wall
Sa loon Door A pair of lightweight swing doors often found in public bars
Types of Mechanism
Open Close
H inged Door The doors are hinged along one side to allow door to pivot away from the doorway in one direction but not in the other. The axis of rotation is usually vertical.
Open Close
Fo ld ing Door The door operated by fitting the pivots of one door into the top and bottom pivot brackets.
Open Close
S l id ing Door Pivot door slides allow the door to pivot open then slide back into the sides of the cabinet.
Open Close
Rotat ing Door The door typically consists of three or four doors that hang on a central shaft and rotate around a vertical axis within a cylindrical enclosure. It is either be mounted at the central pivot or attached to the door wings.
Types of Windows
5.7 WINDOWS
Single Casement Window Casement windows are hinged on the either side and open outward to the right or left. It is usually taller than wide, their entire sash opens to provide top-to-bottom light and ventilation.
Picture Window Picture window is a large fixed window in a wall, generally without glazing bars, or glazed with only minimum reflection of glazing bars near the edge of the window. Picture window provides an unblocked vie, as if framing a picture on the wall.
Single-hung Window Single-hung window has two sashes but typically the top sash is fixed and only the bottom sash slides. The advantage of sash window that it provides cooling effect of interiors during warm weather. By opening both top and bottom of a sash window by equal amounts allows warm air at the top of the room to escape, thus drawing cool air from the outside into the room through the bottom opening.
Fixed Window A fixed window cannot be opened. Its function is limited to allow light to enter. This type of window is used in where only light or vision is needed and there is no ventilation is possible because the use of trickle vents or over glass vents is absent in this type of window.
The hardwood sill helps to improve its weathering qualities, which overhangs the face of the brickwork. Where the window is set well back from the outer wall face, it is necessary to incorporate a precast concrete sub sill.
Mullions should be through tenoned into heads and sills, an the transoms stubtenoned into jambs and mullions.
Opening casements are held in a closed position by casement fasteners, while both casement and ventlights can be fixed in a number of open positions by means of casement stays, which may be either the peg or sliding varieties.
Installation of Casement Window
The window opening is spanned externally by a brick-on-edge arch backed by a reinforced concrete lintel.
As the flat arch has little strength it is supported by a mild steel angle, with ends built into the brickwork. The exposed edge painted for protection.
The window frame may be fixed to the sides of brick jambs.The jamb may be fixed to the brickwork by screwing or nailing to hardwood plugs let into mortar joints.
6.0 ROOF
Cross Gable
From the site at De’bunga, the roof
constructed is cross gable.
Lookout
A short bracket
for supporting
the overhang of
roof.
Fly rafter
Either of the end
rafters in the part
of a gable root
that projects
beyond the
gable wall.
Valley Rafter
A rafter
connecting the
ridge to the wall
plate along a
valley.
Valley Jack
A jack rafter
extending from
a valley rafter
to a ridge.
Cripple Jack
A rafter joining
a hip to a
valley.
Hip Rafter
A rafter forming the
junction of the
sloping sides of a
hip roof.
WOOD POST-BEAM
CONNECTION
METAL
STRAP
PLAT
E
FLATTER
SLOPES
BACK TO BACK
SHEAR PLATES
GREATER
SLOPES
i. RIDGE CONNECTION
ii. POST-BEAM CONNECTION
METAL FRAMING ANGLE
-BOTH SIDES OF BEAM
METAL TIE
STRAP
FLAT
ROOF
LOAD BEARING WALLS
1. WEAR COURSE
2. ROOFING MEMBRANE
3. RIGID FORM OR LIGHTWEIGHT CONCRETE
INSULATION
4. VAPOR RETARDER
5. SMOOTH TROWELED FINISH TO RECEIVE
INSULATION AND ROOFING
6. REINFORCED CONCRETE ROOF SLAB
PARAPET
WALL
ROOF SLAB ARE SUPPORTED BY BEARING WALLS OF
REINFORCED CONCRETE.
THE UPTURNED EDGE BEAM HAD FORM A PARAPET WALL.
THE FLAT ROOF IS SLANTED FOR WATER DRAINAGE.
SUMMARY:
Throughout the whole of this project, we manage to obtain more knowledge and guidance of Malaysian building construction methods compared to that of lecturers and in-class
learning. Besides that, we have learned that throughout the process of building construction, compromises are made and the plans produced by architects are not finalized and it’s a
process of evolutions that occurs from the beginning to the end of the project.
In the first site, De’Bunga Residence, we were able to witness a three-storey bungalow at its pre-roofing stage such that most of its structural components were already completed.
We learned the different names of materials in which the contractors used such as splash dash, beam starter bars, wire mesh and key holes in the mortar walls for the door frame. All of
which are rather new terms we have not learned in class. This help broaden our “architectural vocabulary” as some of these terms are not written in the books and vary from country to
country. At the same time, we were able to improve our observation skills.
During our second site at Altitude 236, we were fortunate enough to be able to visit a condominium in which we managed to experience a totally different variety of construction
methods such as using reinforced concrete to construct everything from walls to roofs and floors. The machinery used in high-rise construction is very different as well such that they
have to transport building materials from ground level all the way up to the construction area.
Lastly, we as a team would like to thank the people in which has given us guidance and took time to patiently explain the different components of the construction site. We would
also like to thank IJM the developer for allowing us to visit their construction site and for providing us with the information we need to complete our assignment.
7.0 Summary
7.1 Reference
1. Francis D.K. Ching (2008). Building Construction Illustrated (4thth ed.). Canada : John Wiley & Sons . (Original work published 1943).
- See more at: http://reffor.us/index.php#sthash.IAP1nV35.dpuf
2.Stephen Emmit and Christopher A. Gorse (2010). Scaffolding. Barry's Advance Construction of Buildings (2nd ed., pp. 13-63). United Kingdom, United Kingdom: Blackwell Publishing. (Original work published 2006).
-See more at: http://reffor.us/index.php#sthash.CGtvjdMz.dpuf
3.Watts, A. (2010). Modern Construction Handbook (2nd ed.). London, England: SpringerWienNewYork. (Original work published 2001). - See more at:
http://reffor.us/index.php#sthash.wuj9UxoZ.dpuf
4.Sarkar, S. K. (2012). Construction Technology (1st ed.). India: Oxford University Press. (Original work published 2008).
-See more at: http://reffor.us/index.php#sthash.MMZ0Vo1i.dpuf
5.Roy Chudley and Roger Greeno (2005). Construction Technology (4th ed.). Harrold, England: Personal Education Limited. (Original work published 1973). - See more at:
http://reffor.us/index.php#sthash.JpkMre3r.dpuf
6.Edward Allen and Joseph Iano (2009). Fundamentals of Building Construction Materials and Methods (5th ed.). Hoboken, New Jersey: John Wiley and Sons. (Original work published 1938).
-See more at: http://reffor.us/index.php#sthash.MfgdTH7J.dpuf
7. Deplazes, A. (2012). Constructing Architecture (2nd ed.). Basel, Switzerland: Birkhauser. (Original work published 1997) - See more at:
http://reffor.us/index.php#sthash.XyPGNvQQ.dpuf
8. Francis D.K. Ching (2013). Introduction to Architecture (1st ed.). Hoboken, New Jersey: John Wiley and sons. - See more at: http://reffor.us/index.php#sthash.QFmEW525.dpuf
9.Broadhurst, T. (n.d.). About the Old House Web. Retrieved October 9, 2013, from http://www.oldhouseweb.com/about-the-old-house-web.shtml
-See more at: http://reffor.us/index.php#sthash.MxlYMDQu.dpuf
10. Organizations of America States. (n.d.). Organizations of America States. Retrieved Oct 6, 2013, from http://www.oas.org/cdmp/document/codedraw/sectionb.htm
See more at: http://reffor.us/index.php#sthash.flvFOjAv.dpuf
11. bag, j. (2012, May 24). Kumkang Aluminium Formwork System [Video file] [Video file]. Retrieved Oct 17,2013, from
http://www.youtube.com/watch?v=I85iQCvOT_I - See more at: http://reffor.us/index.php#sthash.xIkWGGwz.dpuf
12. Cheah, D. (2011, Dec 10). Casting of 1st Floor Beam & Slab [Video file] [Video file]. Retrieved Oct 5,2013, from
http://www.youtube.com/watch?v=MquLVCiCYtw&feature=youtu.be - See more at: http://reffor.us/index.php#sthash.a6E3t6qM.dpuf