Interstate 5:NE 45th to NE 145th

Full Depth HMA Reconstruction

Page 2: 404 presentation

Location

• Location

• Interstate 5 Northbound Lanes from North 45th

Street to North 145th Street

Page 3: 404 presentation

Overview

• Location

• Interstate 5 Northbound Lanes from North 45th Street to North 145th Street

• Task

• Remove Current PCC Slabs

• Replace PCC with HMA

• Goals

• Reduce Cost

• Reduce Traffic Impacts

• Create a long lasting Sustainable Pavement

Page 4: 404 presentation

Existing Conditions

• Current Condition is Poor to Very Poor

• Built in the Early 1960s with a Design Life of 20 Years

• 9-inch thick PCC panels that are 15ft in length by 12 ft in width

• 11ft Lanes

• Extensive Panel Cracking and Faulting of Traverse Joints

• Extensive Wheel Path Wear and Pavement Surface Polishing

• Uncomfortable for Users

• Verge of not being able to Serve Traffic

Page 5: 404 presentation

Overall Scope

• I-5 Northbound

• NE 45th St to NE 145th St

• Remove 9” PCC and Replace with 13” HMA and 9” base

• Two Phases

• 5.2 miles at 21.2 lane miles total

Page 6: 404 presentation

Scope: Phase one

• Phase one

• NE 45th to Northgate Way overpass-express lanes

• Approximately 10.5 lane miles

• 3-4 lanes

Page 7: 404 presentation

Scope: Phase two

• Phase two

• Northgate Way overpass to NE 145th St- no express lanes

• Approximately 10.7 lane miles

• 5-6 lanes

Page 8: 404 presentation

Cost

• Construction (CA4PRS)

• Construction Costs: $12,700,000

• Roadway Costs: $16,000,000

• Supporting Costs: $300,000

• Total Cost: $29,000,000

• Agency (Real Cost)

• Life Cycle Agency Costs will be $25,000,000

• LCCA (Real Cost)

• Life Cycle User Costs will be $16,000,000

Page 9: 404 presentation

Construction Time

• Phase 1

• Begin on July 17th (After Independence Day)

• Continuous Closure

• Maximum Closure of 2 weeks

• Phase 2

• Begin on August 7th

• Continuous Closure

• Maximum Closure of 2 weeks (Finish before Labor Day)

Page 10: 404 presentation

Construction

• Maintain three lanes of traffic at all times

• Allow one lane for equipment and trucks to passing at all times

• Excavate and replace with crushed aggregate quickly

Page 11: 404 presentation

Sequencing: Phase one

• Crossover to express lanes

• Extend third lane: express lanes to main line

• Demolition & Excavation

• Grading & Paving

Page 12: 404 presentation

Sequencing: Phase two

• Remove crossover to express lanes

• Remove third lane: express lanes to main line

• Left three lane then right lanes

• Demolition & Excavation

• Grading & Paving

Page 13: 404 presentation

Equipment

Page 14: 404 presentation

HMA Plant Location

• ICON Materials will be contracted to supply HMA and aggregate from their Auburn Aggregate Resource and Asphalt Plant located in Auburn WA

• Plant Produces 500 tons/hr when aggregate is wet and 600 tons/hr when the aggregate is dry

• Average trucking time from the plant to site is 40 minutes during normal conditions and 70 minutes during heavy traffic

Page 15: 404 presentation

Demolition Materials

Page 16: 404 presentation

Productivity

• Phase 1

• Using 87% confidence interval productivity will be 6.55 lane miles per 7 day closure

• Requires two 7 day closures

• HMA trucks are greatest limit to productivity

• Phase 2

• Using 87% confidence interval productivity will be 6.50 lane miles per 7 day closure

• Requires two 7 day closures

• HMA trucks are greatest limit to productivity

Page 17: 404 presentation

Closures

• Phase 1 (45th St. to Northgate Way)

• Closes Friday July 17th 2015 at 11pm

• Must reopen by Monday August 2nd 2015 at 4am

• Phase 2 (Northgate Way to 145th St.)

• Closes Friday August 7th 2015 at 11pm

• Must reopen by Monday August 24th 2015 at 4am

Page 18: 404 presentation

Alternative Routes• SR-99

• Aurora

• SR-522 • Lake City/Bothell Way NE

• 15th Ave NE

• 11th/12th Ave NE

• 25th Ave NE

• Phinney/Greenwood Ave N

Page 19: 404 presentation

Traffic Impacts: Phase one

• Minimum impact southbound

• 20.3 mile maximum queue

• $25 million user cost

• 25% no show

• 15% detour

Page 20: 404 presentation

Traffic Impacts: Phase two

• Less impact southbound than phase one

• 26.4 mile maximum queue

• $25 million user cost

• 25% no show

• 15% detour

Page 21: 404 presentation

Critical Resources

• HMA Plant

• Plant is producing maximum capacity to provide for this project

• HMA Hauling Trucks

• High Spearman Correlation Coefficient

• Dependent upon plant production

• Travel (coffee stops, traffic, etc.)

Page 22: 404 presentation

Backup Plans

• The Seattle Asphalt Plant owned by ICON Materials will be on standby incase the main plant faults

• Located in the South Park neighborhood of South Seattle

• Produces 250 tons/hr when aggregate is wet and 300 tons/hr when aggregate is dry

• Average trucking time from this plant to the site is estimated to be 18 minutes in normal conditions and 30 minutes in heavy traffic

• Extra equipment such as pavers, buggies, rollers and dump trucks will be stored at the temporary storage facilities

Page 23: 404 presentation

Public Awareness

Page 24: 404 presentation

Potential Cost Savings

• Warm Mix Asphalt (WMA)

• Recycled Concrete

Page 25: 404 presentation

WMA vs. HMA

• I-90 WSDOT study near George, WA

• Less fuel consumed

• Lower CO2 quantities produced

Page 26: 404 presentation

Near Site Recycled Concrete

• Cost Savings

• Savings of $5 to $10 per ton

• $316,400 to $632,800 for the project

• Environmental Savings

• Less aggregate

• Less CO2

• Blah