Courtesy, in part, of Motorola SPS.Thank You!

Welcome To

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 2: 1.tpm awareness information en

2

Courtesy, in part, of Motorola SPS.Thank You!

About T.P.M.

After World War ll. Japanese industries determined that to complete successfully in the world market

they had to improve the quality of their products. to do so, they imported management and manufacturing

techniques from United States and adapted them to their circumstances. Subsequently, their products became

known throughout the world for their superior quality, focusing world attention on Japanese- style

management techniques.

TPM DEVELOPMENT PROGRAM

Implementing Total Productive Maintenance

Seiichi Nakajima.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 3: 1.tpm awareness information en

3

Courtesy, in part, of Motorola SPS.Thank You!

WHAT IS T.P.M. ??

Definition of T.P.M :T.P.M. IS: A PRODUCTIVE MANUFACTURING SYSTEM with the TOTAL

Participation of: Managers, Supervisors, Engineers,

Technicians and Operators.

T.P.M. Includes the Following Benefits:

• Maximize Overall Equipment Effectiveness

• Establishment a Complete System of Maintenance for the Machine Entire

Life

• Create a Better Work Environment, Promoting the Participation for All

Employees

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 4: 1.tpm awareness information en

4

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. = Medical Science of Equipment

PRODUCTION Foton AUTOMATION B-820

VIDEO-AUTO DIE-BONDER MODEL 8030A

POWER

HEATER

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 5: 1.tpm awareness information en

5

Courtesy, in part, of Motorola SPS.Thank You!

The Main objective of TPM is :Zero Interruptions

Zero DefectsZero Accidents

Throughout total employees participation from Top Management to Operators,based in the following activities:

Autonomous Maintenance• Planned Maintenance

• Individual Improvement

• Quality Maintenance

• Early Equipment Management

• Education/Training (People Development)

• Safety

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 6: 1.tpm awareness information en

6

Courtesy, in part, of Motorola SPS.Thank You!

PILLARS OF TPM

AUTONOMOUS

MAINTENANCE

QUALITY

MAINTENANCE

PLANNED

MAINTENANCE

INDIVIDUAL

IMPROVEMENT

TRAINING

PEOPLEDEVELO

SAFETY

EHS

EARLY

EQUIP

MANAGEMENT

P

5S´s

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 7: 1.tpm awareness information en

7

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M.Total Productive Manufacturing

People , Equipment and ProductImprovement by Working Together.

EXCELLENCE

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 8: 1.tpm awareness information en

8

Courtesy, in part, of Motorola SPS.Thank You!

PLANTOVERVIEW

PLANT

OVERVIEW

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 9: 1.tpm awareness information en

9

Courtesy, in part, of Motorola SPS.Thank You!

TPMSelf Assessment

PLANT

OVERVIEW

TPMSelf Assessment

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 10: 1.tpm awareness information en

10

Courtesy, in part, of Motorola SPS.Thank You!

TPM Self AssessmentBackground:

∆1991 First attempt to implement TPM.∆ TPM consultant provides training to selected Managers,Supervisors and Engineers.∆ One coordinator with experience in Process and Maintenanceis assigned to lead TPM.∆ Literature and materials, prepared and distributed.

Lack of support and involvement results on failing theimplementation.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 11: 1.tpm awareness information en

11

Courtesy, in part, of Motorola SPS.Thank You!

TPM Self Assessment1996

∆ One Staff Mgr. is assigned to lead the TPM Implementationplant wide.

∆ A core team is formed on 2Q/96 with key people from differentdepartments to coordinate the implementation.∆ Model equipment is selected based on bottle neck operation.∆ Equipment conditions analysis performed.∆ Most of the teams cover the initial cleaning.∆ Activities are focused on six big losses detected and 5 S´s

implementation.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 12: 1.tpm awareness information en

12

Courtesy, in part, of Motorola SPS.Thank You!

AsiaBenchmarking

PLANT

OVERVIEW

TPMSelf Assessment

AsiaBenchmarking

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 13: 1.tpm awareness information en

13

Courtesy, in part, of Motorola SPS.Thank You!

TPM BenchmarkingAsia Facilities

Facility 1 April1996

Facility 2Facility 3

Committee:

Objective:

Cayman Systems USA 513 777-3394©1998 Revision A 980810

May

June

4 Chosen Folks

Learn from Asia success experiences in TPMimplementation and come up with directions forPlant implementation.

TPM Awareness Information

Page 14: 1.tpm awareness information en

14

Courtesy, in part, of Motorola SPS.Thank You!

Benchmarking Conclusions

Total management involvement.

T.P.M. Manager (dedicated).

A well defined implementation process.

Provide people with time to work on it. ( 4- 6 Hr./wk ).

Each staff has their own T.P.M. Promoter full time.

Focused in Consultant X model.

Focused in just one product line per area.

Budget assigned for consulting and external training.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 15: 1.tpm awareness information en

15

Courtesy, in part, of Motorola SPS.Thank You!

TPMPLANT

OVERVIEW

TPMSelf Assessment

AsiaBenchmarking

TPMImplementation

Cayman Systems USA 513 777-3394©1998 Revision A 980810

Implementation

TPM Awareness Information

Page 16: 1.tpm awareness information en

16

Courtesy, in part, of Motorola SPS.Thank You!

IMPLEMENTATION/CONSULTANT

* Q3 1996, Consultant X is selected to be Consultant.

* Training of Managers, Team leaders and Team members

* Master Plan Defined

* TPM. implementation initiated according to Consultant X recommendations

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 17: 1.tpm awareness information en

17

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. POLICY# ESTABLISH AN INTEGRATED STRUCTURE TO PROMOTE T.P.M.

AS A COMPANY CULTURE.

# MAXIMIZE OVERALL EQUIPMENT EFFECTIVENESS

# TOTAL EMPLOYEE INVOLVEMENT.

# CULTIVATE EQUIPMENT & PROCESS RELATED EXPERTISE THROUGHOUTSHOP FLOOR. ( Autonomous Maintenance, Planned Maintenance etc..)

# ESTABLISH A RELIABILITY AND MAINTAINABILITY SYSTEM TO MAXIMIZEEQUIPMENT LIFE TIME. (Planned Maintenance Autonomous Maintenance,Individual Improvement, Early Equipment Management.)

# ALL EMPLOYEES MUST PARTICIPATE IN T.P.M TRAINING PROGRAM.

# ALL AREAS MUST FOLLOW T.P.M. ESTABLISHED GUIDE LINES.

# DEPARTMENT HEAD IS RESPONSIBLE TO ACCOMPLISH AND SUPPORTT.P.M. GOALS.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 18: 1.tpm awareness information en

18

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. PLANT WIDE STRUCTURE

TPM

T.P.M. Office ResponsiblePlant Manager

5 ´sAutonomousMaintenance

PlannedMaintenance

IndividualImprovement

QualityMaintenance

EarlyEquipment

ManagementSafety

TrainingPeople

Development

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 19: 1.tpm awareness information en

19

Courtesy, in part, of Motorola SPS.Thank You!

PROMOTION STRUCTURE(OVERLAPPING SMALL GROUPS)

PLANTMANAGER

STAFF MANAGERS

OPERATIONS

TPM PILLARS& PROMOTION

OFFICE

TPMPROMOTERS

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

DEPARTMENTMANAGERS

DEPARTMENTSUPERVISORS

TPM TEAM

Page 20: 1.tpm awareness information en

20

Courtesy, in part, of Motorola SPS.Thank You!

VISION STATEMENT:TPM

PLANT WIDE

IMPLEMENTATION

Q1 2000

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 21: 1.tpm awareness information en

21

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. IMPLEMENTATION ACTIVITIES

MANAGER TEAMS

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 22: 1.tpm awareness information en

22

Courtesy, in part, of Motorola SPS.Thank You!

PREPARATION / PLANNING STAGE

# DEFINE PILOT LINES

# AMOUNT OF MACHINES INCLUDED PER LINE

# DEFINE CORE TEAM MEMBERS OF EACH LINE

# SELECT TEAM MEMBERS PER MACHINE

# START ACTIVITIES IN PILOT MACHINES (bottle neck.)

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 23: 1.tpm awareness information en

B-820

B-609

V-701

23

Courtesy, in part, of Motorola SPS.Thank You!

Line and Machine Selection

B-820

Machine 1 Machine 2N-661

POWER

HEATER

Machine 3 Machine 4B-609

V-701

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 24: 1.tpm awareness information en

START

TA

TPM Implementation PlanACTIVITIES

DEFINE STRATEGIES

1996 1997 1998 1999 2000Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

PREPARATION

STAGE

MASTER PLANORGANIZATION

INTRODUCTION TRAININGPUBLICITY

1TPM

2 3

IMPLEMENTA

MODEL MACHINESMachine 1Machine 2Machine 3Machine 4

EXTENDIMPLEMENTATION

SIMILARPRODUCTION LINES

KICK

OFF

AUTONOMOUS MAINTENANCE&

REDUCE 6 BIG LOSSESEXTEND SIMILAR MACHINES

30%to

50%

TION

RGET

COMPLETEIMPLEMENTATIONDEFINED AREAS

100%

Page 25: 1.tpm awareness information en

TPM 90 Days Explosion PlanOctober November December

ww40 ww41 ww42 ww43 ww44 ww45 ww46 ww47 ww48 ww49 ww50 ww51 ww52Machine 1

PILOT TEAM Step 3Planned maintenance

6 big lossesIndividual Improvement

Start

StartStart

Start10 Extension teams19 Extension teams

step 1-2Start step 1

4 mc7 mc

3 mc6 mc

3 mc6 mc

Machine 2PILOT TEAM Step 2-3

Planned maintenanceStart

Start6 big losses

Individual ImprovementStep 1 Step 2

Step 111 Extension teams step 1-2 B-613 3 mc 2 mc 2 mc B-601 L-604

Machine 3PILOT TEAM Step 2-3

Planned maintenance6 big losses

Individual ImprovementStart

Start

Start

Start

6 Extension teams2 Extension teams

Machine 4PILOT TEAM

step 1-2Start step 1

Step 1-2

Start

Start

2 mc 4 mc

Planned maintenance6 big losses

Individual ImprovementStart

Start

Start4 extension teams Start step 1 a-820 a-821 J-701 J-601

PILLARS IMPLEMENTATION MODELGANTT

TPM Activity Board Extension TeamsServer Data collection M1 M2 M3 M4

GM AuditTeam presentationsTPM Office AuditConsultant visitTPM MeetingLocal BOOT CAMPTPM MCOE MEETING, JAPANPillars meeting

Page 26: 1.tpm awareness information en

M

CO

DENIAL

M

MEN

T

T

I

RESISTANCE

EXPLORATION

26

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. TRANSITION CURVEPOLICIES DEVELOPMENTT.P.M. PROMOTION OFFICE START

MANAGEMENT MACHINESFOCUS IN FEW EQUIPMENT

T.P.M. PROMOTION DELEGATIONINCLUDE T.P.M. IN PERFORMANCEMANAGEMENT PLAN.INCLUDE T.P.M. IN JOB

KICK OFF

FOCUS TRAININGSUCCESS STORIES5 S´s

CONSULTANTIN

DESCRIPTION.ACCELERATEDDEPLOYMENT.

CONSULTANTOUT

DEVELOP DATA COLLECTION SYSTEMATTENTION TO FOCUS TEAMSTRAINING DEPLOYMENTIMPLEMENTATION PLANRESOURCE IMPLEMENTATION

GOALS SETTING FORALL ORGANIZATION.

LOOK FOR ADDITIONAL WAYSTO DEPLOY T.P.M.

FINISH CONFLICT WITH THE CULTUREORGANIZATION ALIGNMENTREWARD SYSTEMCONTROL CHAOS

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 27: 1.tpm awareness information en

2X

27

Courtesy, in part, of Motorola SPS.Thank You!

KEY GOALS

1.- TOTAL EQUIPMENT EFFECTIVENESSA) Equipment BreakdownB) M.T.B.A.C) M.T.B.F.

2.- REJECT CAUSED BY LINE EQUIPMENT

3.- LINE REJECT RATE

4.- CYCLE TIME

5.- FATAL ERROR AT CUSTOMER

6.- ON TIME DELIVERED

7.- MANUFACTURING COST

%HOURS/MONTHMINUTESHOURS

PPM

%

DAYS

# OF

%

USD

851/101x10x1x2x

1/5

1/5

0.8X

0

98

20% LESS

8.- LABOR PRODUCTIVITY

Cayman Systems USA 513 777-3394©1998 Revision A 980810

K.UNITS /# OF D/L

TPM Awareness Information

Page 28: 1.tpm awareness information en

28

Courtesy, in part, of Motorola SPS.Thank You!

AUTONOMOUS MAINTENANCE.

MANUFACTURING SPECIALIST

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 29: 1.tpm awareness information en

29

Courtesy, in part, of Motorola SPS.Thank You!

AUTONOMOUS MAINTENANCE IS:

Maintenance performed by equipment operators.

THE FIRST 3 STEPS OFAUTONOMOUS MAINTENANCE.

STEP # 1 INITIAL CLEANING.

STEP # 2 COUNTERMEASURES FOR THE CAUSESOF FORCED DETERIORATION AND IMPROVINGHARD-TO-ACCESS AREAS.

STEP # 3 MAKING A TENTATIVE CLEANING/LUBRICATION STANDARD.

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 30: 1.tpm awareness information en

3

7

2

30

Courtesy, in part, of Motorola SPS.Thank You!

AUTONOMOUSMAINTENANCE

5

4

Selection

Formats:Daily Cleaning &Initial InspectionHot Spots, CAP-DO5W´s Develop One

Major Problems Point lesson

6

Put F Tags

Step # 1

Initial Cleaning

StandardizationCleaning /Lubrication

Initial Cleaning(Inspection)

Training inOne Point Lesson

Photos BeforePhotos After

1

8

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 31: 1.tpm awareness information en

3 7

31

Courtesy, in part, of Motorola SPS.

AUTONOMOUSMAINTENANCE

5

Thank You!

4

Put “F” Tags

Failures AnalysisWhy´s Analysis

Actions inSources ofContamination &Hard access areas

Step # 2

6

Find & ListAreas of HardAccess

Sources ofContamination &

Hard Access Areas

Modify Covers ForEasy Visualization

& QuickDisassemble

Find & ListSources ofContamination Remove “F” Tags

Cayman Systems USA 513 777-3394©1998 Revision A 980810

2 Initial InspectionFinal Inspection

(Audit)

1

TPM Awareness Information

8

Page 32: 1.tpm awareness information en

46

373

32

Courtesy, in part, of Motorola SPS.

AUTONOMOUSMAINTENANCE

5

Thank You!

Verifyactual time

Improve time ofexecution

Detailactivities

Vs estimated

Put “F” Tags(Establish time& frequency)

Step # 3TentativeStandards

Remove“F” Tags

Cleaning / Lubricationimplementation Apply activities to

similar machines

22

Develop tentativestandards 8

1

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 33: 1.tpm awareness information en

443427

12

33

Courtesy, in part, of Motorola SPS.Thank You!

TPM Teams Status

October 1997

•Number of Hot Spots detected:•Number of Hot Spots solved:•One Point Lesson developed:•One Point Lesson Taught:•Number of teams on TPM:•Teams on step 3:•Teams on step 2:•Teams on step 1:

284126

24

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 34: 1.tpm awareness information en

34

Courtesy, in part, of Motorola SPS.Thank You!

PLANT

OVERVIEW

TPMSelf Assessment

AsiaBenchmarking

TPMImplementation

Expansion Plan

Cayman Systems USA 513 777-3394©1998 Revision A 980810

Expansion Plan

TPM Awareness Information

Page 35: 1.tpm awareness information en

1998

35

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. DEPLOYMENT

LINE

FLOW

CURRENT EQUIPMENT IN T.P.M.

SAME KIND OF EQUIPMENT

1999/2000 EXPANSION

1997

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 36: 1.tpm awareness information en

Line

36

Courtesy, in part, of Motorola SPS.Thank You!

PROJECTED PROGRESS IN TEAMS Q-1’ 98

A.M. STEP # 1 A.M. STEP # 2 A.M. STEP # 3

Wafer ProcessLine 1

Line 2

Line 3

Line 4

Cayman Systems USA 513 777-3394©1998 Revision A 980810

11

03

03

04

TPM Awareness Information

16

11

08

01

03

01

01

01

Page 37: 1.tpm awareness information en

37

Courtesy, in part, of Motorola SPS.Thank You!

T.P.M. FOLLOW-UP

TEAMSPRESENTATION

TEAMSAUDITS

TEAMSMEETING

Consultant X MANAGERSVISITS PRESENTATION

6 TEAMS

PER

MONTH

6 TEAMS

PER

MONTH

WEEKLY TWO DAY

EVERY

TWO

MONTHLY

MEETING

MONTHS

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 38: 1.tpm awareness information en

38

Courtesy, in part, of Motorola SPS.Thank You!

PLANT

OVERVIEW

TPMSelf Assessment

AsiaBenchmarking

TPMImplementation

Expansion Plan

Pilot TeamCase Study

Cayman Systems USA 513 777-3394©1998 Revision A 980810

Pilot TeamCase Study

TPM Awareness Information

Page 39: 1.tpm awareness information en

39

Courtesy, in part, of Motorola SPS.Thank You!

PILOT MACHINE

N-62361

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 40: 1.tpm awareness information en

40

Courtesy, in part, of Motorola SPS.Thank You!

Defectives30

25

20

23

20

25

22

1820

21

1719

23

15

10

55

78

65

9

6

3 4 3 32

4

6

8

65

4

76

0N-662361 N-61162 N-634766

JAN 96JUN

FEBJUL

MARAUG

APRSEP

MAYOCT 96

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 41: 1.tpm awareness information en

%T.C.

ENE./96MAR MAY JUL

OCT./96ABR

%T.C.

ABR

AGO

ENE./96AGOMAR MAY SEPFEB JUN JUL

SEPFEB JUN

OCT./96

%T.C.

FEB JUN AGOMAROCT./96ENE./96

MAYABR JUL SEP

41

Courtesy, in part, of Motorola SPS.Thank You!

DOWN TIME25%

23% 23%

20% 20% 20%

N-66236115%

10%

17%18%

12%

15%

18% 18%

5%

0%

25%

20%

N-66324215%

10%

5%

12%11%

10%11%

8%9%

7%6%

8%10%

0%

25,00%

20,00%

15,00%

N-649666 10,00%

5,00%7,50% 8%

4%

7%9%

5%3%

5% 6%8%

0,00%

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 42: 1.tpm awareness information en

42

Courtesy, in part, of Motorola SPS.Thank You!

CLEANING IS INSPECTION....

5’S

AUTONOMOUS

MAINTENANCE

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 43: 1.tpm awareness information en

43

Courtesy, in part, of Motorola SPS.Thank You!

INSPECTION IS DETECTION.

CRASH

Broken Part

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 44: 1.tpm awareness information en

44

Courtesy, in part, of Motorola SPS.Thank You!

PRESSURECORRECT

INCORRECT

TO MUCHPRESSURE

CORRECT

GAUGE

ALIGNMENT

INCORRECT

NO

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 45: 1.tpm awareness information en

45

Courtesy, in part, of Motorola SPS.Thank You!

CORRECT CENTERING

INCORRECT

Dummy Part

CORRECT

SYMMETRY

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

INCORRECT

BENT

Page 46: 1.tpm awareness information en

46

Courtesy, in part, of Motorola SPS.Thank You!

CONTACT

CORRECTINCORRECT

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 47: 1.tpm awareness information en

47

Courtesy, in part, of Motorola SPS.Thank You!

TO STANDARDIZE AND

PREVENT RECURRENCE

One Point Lesson

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 48: 1.tpm awareness information en

48

Courtesy, in part, of Motorola SPS.Thank You!

MACHINEPERFORMANCE

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 49: 1.tpm awareness information en

Abr MayOct-96Sep-96 Dec-96Jan-97

AgoMarFeb Jun Jul

%D.T.

Nov-96Apr May

Dec-96 Jan-97Feb

Oct-96Mar Aug SepJun Jul

Sep

49

Courtesy, in part, of Motorola SPS.Thank You!

Defectives25

20

15

23

18

“ZERO”

1010

6

Defectives

5 3

12

0 0 0 0 00

25%

20%18%

DOWN TIME

20%

P.C. BOARDDAMAGED

15% 15%

12%10%

5%

9%8%

7%5%

6%4%

3% 3%0%

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 50: 1.tpm awareness information en

3

50

Courtesy, in part, of Motorola SPS.Thank You!

WHAT IS NEXT?

6 Big

LINK Losses

44

AutonomousMaintenance

Planned

Maintenance

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information

Page 51: 1.tpm awareness information en

51

Courtesy, in part, of Motorola SPS.Thank You!

Cayman Systems USA 513 777-3394©1998 Revision A 980810 TPM Awareness Information