DESCRIPTION
You can get better details about JIT from this presentation.
Citation preview
TVS-Mysore
TIME - TWO HOURS
TVS-Mysore
ABOUT HIRANO SAN
Full name - Mr HIROYUKI HIRANO
Consultant on - JIT
Author of - JUST IN TIME - FACTORY REVOLUTION
PREACHES & PRACTICES INNOVATION
TVS-Mysore
JIT FACTORY REVOLTUION
BY
Mr HIROYUKI HIRANO
TVS-Mysore
JIT FACTORY REVOLUTION
STEPS IN IMPLEMENTING JIT PRODUCTION
STEP 1
AWARENESS REVOLUTION
MAINTENANCE & SAFETYJIDOKA-HUMAN AUTOMATION
KANBANMULTI -PROCESS OPERATIONS
QUALITY ASSURANCECHANGEOVER
VIS
UA
L C
ON
TR
OL
MA
NP
OW
ER
RE
DU
CT
ION
STEP 4
LEVELLING
STEP 2
5 S
STEP 5
STANDARDISED OPERATIONS
STEP 3
FLOW MANUFACTURING
JUST IN TIME
TVS-Mysore
TOPICS
1 INTRODUCTION
2 AWARENESS REVOLUTION
3 5S
4 FLOW MANUFACTURING
5 STANDARD OPERATIONS
6 MULTI PROCESS HANDLING
7 REDUCING WORKER HOURS
8 LEVELLING PRODUCTION
9 JIDOKA
10 CHANGEOVER
11 QUALITY ASSURANCE
12 KANBAN
13 MAINTENANCE & SAFETY
JIT FACTORY REVOLUTION
TVS-Mysore
1 INTRODUCTION
WITHIN CELL - ONE PIECE FLOW
- REDUCED SETUP TIME
- IMPROVED M/Cs TO INFORM OPERATORS ABOUT PROBLEMS
- MEASURES TO PREVENT DEFECTS & BREAKDOWNS
BETWEEN CELLS - SMALL LOTS - UNIFORM SIZE - KANBAN
- PULL CONTROL
“JIT MEANS TRIMMING LOSSES - AN ORDEAL FOR SURVIVAL”
CELL SHOULD BE FLEXIBLE
FLEXIBILITY TO ADAPT TO CHANGES IN DEMAND, PRODUCT MIX & PRODUCT DESIGN
JIT FACTORY REVOLUTION
TVS-Mysore
2 AWARENESS REVOLUTION
OPERATORS TO LEARN NEW METHODS - TRAINING
INSTALL NEW CORPORATE CULTURE
CHANGE IN THE WAY OF THINKING
ASSUME CURRENT PRODUCTION SYSTEM IS THE WORST
HAVE CLEAR POLICIES FOR RESISITANCE
JIT FACTORY REVOLUTION
TVS-Mysore
TEN COMMANDMENTS OF INNOVATION
10 - INNOVATION NEVER ENDS
1 - DISCARD FIXED IDEAS
2 - THINK HOW IT CAN BE DONE THAN, HOW IT WON’T
3 - DENY STATUS QUO
4 - DON’T SEEK PERFECTION
5 - CORRECT MISTAKES AS SOON AS THEY ARE FOUND
6 - INNOVATION NEEDS NO MONEY
7 - PROBLEMS ARE OPPORTUNITIES TO USE OUR BRAINS
8 - ASK WHY 5 TIMES
9 - IDEAS OF 10 ARE BETTER THAN KNOWLEDGE OF 1
JIT FACTORY REVOLUTION
TVS-Mysore
INNOVATION CYCLE
IMPROVEMENT CYCLE
KAIZEN
ACT PLAN
CHECK DO
JIT FACTORY REVOLUTION
INNOVATION CYCLE
KAIKAKU
ACTTARGET
DO
CHECK
PLAN
IMAGEVISION /
PICTURE / DREAM
TVS-Mysore
3 5S
SHITSUKE - DISCIPLINE
SEIRI - PROPER ARRANGEMENT
SEITON - ORDERLINESS
SEISO - CLEANLINESS
SEIKITSU - CLEANUP
WE ARE BEHIND TIMES IF WE STILL SWEEP THE FLOORS
JIT FACTORY REVOLUTION
TVS-Mysore
4 FLOW MANUFACTURING
PRODUCING ONE PIECE AT A TIME
CYCLE TIME IS THE TIME IT TAKES TO CARRY ONE PART ALL THE WAY THROUGH THE CELL
MULTI PROCESS HANDLING & SMALL INLINE MACHINES
MONTHLY QUANTITY REQUIRED
DAILY RATE =
WORKING DAYS PER MONTH
WORKING HOURS / DAY
TAKT TIME =
DAILY RATE
JIT FACTORY REVOLUTION
TVS-Mysore
5 STANDARD OPERATIONS
RULES & METHODS TO PRODUCE QUALITY PRODUCTS,
SAFELY & INEXPENSIVELY
BY EFFICIENT ARRANGEMENT OF PEOPLE, PRODUCT & MACHINES
STANDARD OPERATIONS BULLETINS & MANUALS ON WORK METHODS
JIT FACTORY REVOLUTION
TVS-Mysore
6 MULTI PROCESS HANDLING
DE-LINEATE JOBS PERFORMED BY MACHINE & OPERATORS
(MACHINES CAN WORK INDEPENDENTLY)
MAKE CELLS U SHAPED & GIVE MACHINES JIDOKA FUNCTION
OPERATORS TO STAND WHILE WORKING
TRAIN OPERATORS TO BE MULTI SKILLED
ONE OPERATOR HANDLES SEVERAL PROCESS IN A CELL
JIT FACTORY REVOLUTION
FOLLOW RABBIT CHASE - PRODUCTIVITY MAY GO UP
TVS-Mysore
7 REDUCING OPERATOR HOURS
MAKE MACHINES EASY TO MOVE BY ATTACHING CASTORS
STANDARDISE OPERATIONS SO EVERYONE CAN PERFORM THE JOB
TRAIN OPERATORS THROUGH JOB ROTATION TO BE MULTI SKILLED
DO NOT ASSIGN FIXED NUMBER OF OPERATORS TO ANY PROCESS
IT SHOULD VARY ACCORDING TO PRODUCTION QUANTITY
TO PRODUCE GOODS WITH MINIMUM NUMBER OF OPERATORS
ADJUSTING TO CHANGING MARKET REQUIREMENTS
JIT FACTORY REVOLUTION
TVS-Mysore
8 LEVELLING PRODUCTION
CALCULATE CYCLE TIMES BASED ON MONTHLY VOLUMES
MAKE CYCLE LIST BASED ON CYCLE TIME
SHORTEN CHANGEOVER TIMES
CREATE SMOOTH FLOW
INFORMATION & PARTS ARE DELIVERED TO THE LINE SEVERAL TIMES DAILY
TO PRODUCE THE SAME QUANTITY OF AN ITEM EVERY DAY
JIT FACTORY REVOLUTION
TVS-Mysore
LINE CYCLE TIME = 4.8 min / UNIT
WORK TIME = 480 min / DAY
LEVELLED PRODUCTION X = 50 - ONE IN 9.6 min
Y = 30 - ONE IN 16 min
Z = 20 - ONE IN 24 min
2000
MONTHLY REQUIRED - X = 1000
Y = 600
Z = 400
MONTHLY PRODUCTION SCHEDULE X = 50 / DAY
(20 WORKING DAYS) Y = 30 / DAY
Z = 20 / DAY
DAILY PRODUCTION SCHEDULE X = 50 - 08:00 - 12:00
Y = 30 - 12:30 - 15:00
Z = 20 - 15:00 - 16:30
JIT FACTORY REVOLUTION
TVS-Mysore
JIT FACTORY REVOLUTION
SEQUENCING OF PARTS FOR LEVELLED PRODUCTION
X - ONE IN 9.6 MINUTES Y - ONE IN 16 MINUTES Z - ONE IN 24 MINUTES
Z X Y X Y X Z X Y X Y X Z X Y X Y X Z X Y X Y X Z
4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8
4.8 9.6 14.4 19.2 24.0 28.8 33.6 38.4 43.2 48.0 52.8 57.6 62.4 67.2 72.0 76.8 81.6 86.4 91.2 96.0 100.8 105.6 110.4 115.2 120.0
At the end of 480 minutesX 50
Y 33
Z 17
TVS-Mysore
9 JIDOKA
MANUAL ----- MECHANISATION ---- AUTOMATION ---- AUTONOMATION
AUTOMATION WITH A HUMAN TOUCH
AUTONOMATION - AUTOMATIC CONTROL OF DEFECTS
INSTALL A MECHANISM ( SENSOR) IN THE MACHINE
THAT PERMITS THEM TO DETECT DEFECTS
&
STOPS THE MACHINE WHEN DEFECTS OCCUR
POKA YOKE
JIT FACTORY REVOLUTION
TVS-Mysore
10 CHANGEOVER
BOLTS ARE OUR ENEMIES
THE TIME BETWEEN THE LAST GOOD PRODUCT OF ONE TYPE TO THE FIRST GOOD PRODUCT OF THE NEXT TYPE
STEP 1 - ANALYSE CHANGEOVER
STEP 2 - IDENTIFY & ELIMINATE WASTE
STEP 3 - MAKE INTERNAL CHANGEOVERS EXTERNAL
STEP 4 - IMPROVE INTERNAL CHANGEOVERS
(Bolts tighten with one turn, eliminate adjustment…)
STEP 5 - IMPROVE EXTERNAL CHANGEOVERS
(Use charts, assign workers…..)
CHANGEOVER TIME IS THE SUM OF INTERNAL & EXTERNAL TIMES
INTERNAL - PROCESS MUST BE STOPPED TO PERFORM CHANGEOVER
EXTERNAL - TIME SPENT WHILE THE PROCESS IS RUNNING
JIT FACTORY REVOLUTION
TVS-Mysore
11 QUALITY ASSURANCE
MAINTAINING QUALITY USING OPERATORS, MANUFACTURING SYSTEM DESIGN & PRODUCTION METHODS TO SATISFY CUSTOMER NEEDS
STEP 1 - OPERATOR - Disciplined, well trained & multi skilled
STEP 2 - MATERIALS - Source control
STEP 3 - MACHINES - Pokayoke, TEI for safety & maintenance
STEP 4 - METHOD - Flow manufacturing cells & standard operations
STEP 5 - INFORMATION - Visual control
JIT FACTORY REVOLUTION
TVS-Mysore
12 KANBAN
A TOOL THAT CARRIES INFORMATION TO FACILITATE PRODUCTION CONTROL
RULES
- SUBSEQUENT PROCESS GOES TO FORMER PROCESS FOR PARTS
- FORMER PROCESS PRODUCES QUANTITY REMOVED BY SUBSEQUENT PROCESS
- QUALITY IS BUILT INTO THE PRODUCT - DEFECT NOT SENT TO NEXT PROCESS
- KANBAN ALWAYS ACCOMPANY PRODUCT - VISUAL CONTROL
- PRODUCTION QUANTITIES ARE LEVELLED TO AVOID FLUCTUATIONS
- REDUCING KANBAN REVEALS PLACES WHERE IMPROVEMENTS ARE NEEDED
PRODUCTION ORDERING KANBAN - WITHDRAWAL / CONVEYANCE KANBAN
JIT FACTORY REVOLUTION
TVS-Mysore
13 MAINTENANCE & SAFETY
4 RULES OF SAFETY
SEPARATE MACHINES FROM OPERATORS
FOLLOW SAFETY STANDARDS
FOLLOW RULES
FIND REAL CAUSES & PREVENT
3 RULES OF MAINTENANCE
CLEAN UP
OIL APPLICATION
CHECK
JIT FACTORY REVOLUTION
TVS-Mysore
HIRANO SAN
GUIDELINES
TVS-Mysore
HIRANOSAN GUIDELINES
D R E A M
CURRENT
TVS-Mysore
HIRANOSAN GUIDELINES
Use KAIKAKU in place of KAIZENKAIZEN KAIKAKU
Small change
making better
Big change
Revolution
(Continuos improvement) (Innovation)
TVS-Mysore
HIRANOSAN GUIDELINES
INTO THE NEW STAR = FUTURE
IDEAL SYSTEM AS GOOD
(inductive approach) (deductive approach)
ANALYSIS OF CURRENT CONDITIONS
Use JIT improvement in place of IE improvementIE improvement JIT improvement
INNOVATION = IN NOVA TION
TVS-Mysore
HIRANOSAN GUIDELINES
STEP : 2 SMALL FOREST
(HASHI)
STEP : 3
SINGLE TREE
(KI)
STEP : 1
FOREST
(MORI)
STEPS FOR KAIKAKUSTEPS FOR KAIKAKU
TVS-Mysore
HIRANOSAN GUIDELINES
STEP : 1 AS A WHOLE
I
D
JH
EC B A
G
F
SUPPLIER
CUSTOMER8
STEP : 3IN A MACHINE
STEP : 2 IN A CELL
I
D
JH
EC B A
G
F
STEPS FOR KAIKAKUSTEPS FOR KAIKAKU
TVS-Mysore
HIRANOSAN GUIDELINES
Guidelines
* Focus on managament benefit (Watch the forest)
IE benefit will not be much visible & require
money (Ki)
* Introduce “Rabbit chase” (including sub assembly)
* Have only one hour stock for process
* Introduce Auto door open & close
TVS-Mysore
HIRANOSAN GUIDELINES
* Introduce auto ejection of component
* Introduce auto fixture cleaning
* Have uniform cycle time
* Have single Input / Output point in a machine
* Do not have common machine for two parts in a cell
* Standardize process sign board
* Adhere to 3R (3-regulations)
1. Name 2. Quantity 3. Location
Guidelines
TVS-Mysore
HIRANOSAN GUIDELINES
* Introduce single piece work flow
1. Fix the WIP required
2. No Dango production
* Big sign board
(nick name should be decided by concerned operators)
* Have KAIKAKU board in cell
* Empty bin should be kept on bottom rack
(without reversing)
Guidelines
TVS-Mysore
HIRANOSAN GUIDELINES
* Have separate trolley for “tested ok”&“to be tested”
(Tsurube concept)
* We must figurise operator movement - operator to be on the move
(operator should stand only while working)
* Use both hands wherever required
* KIT implementation in engine assy
(for big parts which require body twist while picking & occupying more space)
Guidelines
TVS-Mysore
HIRANOSAN GUIDELINES
* Work flow line should be “straight line”
(3M I - Man, Machine, Material & Information)
No shoulder movement
(paper kept under the arm should not fall)
Loading point should be at elbow level
No up&down (DEKO BOKA)or zig-zag
* No back tracking
* No return movement without any work
(Loading & unloading should be done by the same person)
Guidelines
TVS-Mysore
HIRANOSAN GUIDELINES
* Implement the KAIKAKU points immediately
within one day - A rank
within two days - B rank
more than two days - C rank
if it is required to have time more than three days,
then plan today and have A rank for plan
Guidelines
TVS-Mysore
HIRANOSAN GUIDELINES
MUDA TORI(PROCEDURE TO REMOVE WASTE)
BIG ISLAND
STEP I - HITO ATSUMEOPERATOR GATHER
A B C
FOR PRODUCTIVITY TO IMPROVE : NEVER SMALL ISLANDS - ONLY BIG ISLAND
SMALL ISLANDS
ABC
TVS-Mysore
HIRANOSAN GUIDELINES
MUDA TORI - contd...(PROCEDURE TO REMOVE WASTE)
STEP IV - SHOUZINRESULT
STEP II - SHIGOTO ATSUMEVALUE GATHER
BCAB
STEP III - MUDA ATSUMEWASTE GATHER
TOOLCHANGE IN A BIG ISLAND - STOP ALL MACHINES AND DO
TVS-Mysore
HIRANOSAN GUIDELINES
TSURUBE(Pronounced as THU RU BE, means SUPPLY ONE, RECEIVE ONE)
IF, IN A CELL, A PART HAS TO GO OUT FOR AN INTERMEDIATE OPERATION, FOLLOW TSURUBE SYSTEM
400 Years ago
in Japan
TVS-Mysore
HIRANOSAN GUIDELINES
REVERSE FLOW OPERATION OF A CELL
GYAKUJUN - REVERSE SEQUENCING
MAN & WORK FLOW IN OPPOSITE DIRECTIONS
SEIJUN - CORRECT SEQUENCING
MAN & WORK FLOW IN THE SAME DIRECTION
OUT
2 3 4 5 6 71
2 3 4 5 6 71
OUT
IN
IN
2 3 4 5 6 71
OUT
6 5 4 3 2 17
IN
IN
OUT
WORK
MAN
WORK
MAN
JAPANESE - RANK A LINES
TVS-Mysore
HIRANOSAN GUIDELINES
DETAILS AT ENTRANCE OF A CELL
CELL NAME BOARD
WHEEL HUB CELL
TAKT TIME / CYCLE TIMETAKT TIME = 104 SECONDS
CYCLE TIME = 129 SECONDS
CELL LAYOUT
R-40
BRO
ACH
R-50
F-40
WASH R&F-30DRILL
F-10
TURNR-20
TURN
R-10
TURN
F-20
TURN
P
TR
TR
P
SHOP SIGN BOARD FOR ALL AREAS - VCS ON TOP OF BOARDS
MAN MACHINE CHART
HAND -
MACHINE -
WALKING -
WAITING -
TVS-Mysore
HIRANOSAN GUIDELINES
DETAILS AT ENTRANCE OF A CELL - contd...
PROCESS DETAILS
PROCESS No. - 10
PROCESS NAME - TURNING & FACING
CYCLE TIME - 108 SECONDS
OPERATORS NAME & PHOTO
M1007 - NAGARAJAM1033 - LOKESHA
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN
LOCATION FOR TROLLIES & PALLETS TO BE CONVENIENT TO OPERATOR
TR
TR
R-40
BR
OA
CH
R-50
F-40
WA
SH
R&
F-30
DR
ILL
F-10
TURNR-20
TURN
R-10
TURN
F-20
TURN
P P
OPERATOR / PART FLOW DIRECTION TO BE ANTICLOCKWISE
OPERATOR WALKING ZONE INSIDE CELL TO BE MARKED BY WHITE LINE - FOR FREE MOVEMENT
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN
OPERATOR EYE LEVEL TO BE MAINTAINED AT SAME LEVEL WITHIN THE CELL
PROVIDE REMIDER TOKENS FOR OPERATORS TO USE DURING BREAKS
OPERATOR HAND MOVEMENT TO BE AS A FLOW
NO BACK TRACKING / NO SHOULDER MOVEMENT
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN - contd...
DENOTE PROCESS TIMES IN SECONDS & SETUP TIMES IN MINUTES
GAUGES TO BE KEPT ON THE MACHINE - NOT ON GAUGE STANDS
FLOW DIRECTION TO BE MARKED ON CHUTES
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN - contd...
LOOSE WIRES
MACHINES TO BE CLOSE TO EACH OTHER
- BRING CHECK POINTS TO REAR OR FRONT OF MACHINE
- MAKE ACCESSORIES BEHIND THE MACHINE EASILY MOVABLE
- AS A LAST OPTION MOVE MACHINES APART
DO NOT HAVE SNAKES ON THE FLOOR
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN - contd...
PROVIDE TAB SWITCH FOR CYCLE START
PROVIDE AUTO UNCLAMP & AUTO UNLOADING
IT IS CHEAPER TO AUTOMATE UNLOADING THAN LOADING
eg: NET TO CATCH PART WHEN CHUCK IS OPENED / EJECTOR IN THE FIXTURE WITH CHUTE TO BRING PART OUT
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN - contd...
OPERATOR NOT TO WATCH THE MACHINE - MAN MACHINE SEPARATE
AT EACH MACHINE OPERATOR TO LOAD PART, PICK UNLOADED PART & HIT TAB SWITCH AS HE MOVES TO NEXT MACHINE
OPERATOR TO OPERATE ALL MACHINES - MPO - RABBIT CHASE
TVS-Mysore
HIRANOSAN GUIDELINES
CELL DESIGN - contd...
HAVE ALL DETAILS DISPLAYED RATHER THAN IN FILES - OPEN SYSTEM
PROVIDE WIRE IN FRONT OF MACHINES TO HANG VCS
PROVIDE PROPER ILLUMINATION TO INSIDE OF CELL
MONITOR PRODUCTIVITY OF CELL - OUTPUT / MAN
TVS-Mysore
HIRANOSAN GUIDELINES
TYPES OF CELLS
PLUS LINE
W LINE
U LINE
FLOWER LINE
T LINE
HAVE SIGNAL AT CENTER TO INDICATE TO OPERATOR WHICH CELL TO OPERATE
TVS-Mysore
HIRANOSAN GUIDELINES
ASSEMBLY
MARK IN & OUT ON SUPERMARKET STANDS TO INDICATE FLOW OF PARTS
MARK LINE ON CONVEYOR TO INDICATE START OF WORK FOR OPERATOR
TIME BETWEEN STOP OF WORK & COINCIDING OF LINE IS SLACK IN THAT STAGE
WAITING MUDA WILL BE VISIBLE
LOSS RATIO = 100 - BALANCING RATIO
TAKT TIME x TOTAL No. OF STAGESBALANCING RATIO = x 100
OPERATION TIME
TVS-Mysore
HIRANOSAN GUIDELINES
ANDONS
HIRE ANDON
CONCENTRATION
AAASDASDKRWQEOF
KJFSDKLJKFASD4FULLEMPTY
TAXI ANDON
SEPARATION
ROW BROW A
11
1816 17
64 5
1513 14
31 2
10 1297 8
TVS-Mysore
HIRANOSAN GUIDELINES
ANDONS
ALL ANDONS TO BE OF THE SAME ORDER
ALL ANDONS TO BE OF THE SAME HEIGHT - VISIBLE FROM GANGWAY TSLTC20 TC30
TSLTC20 TC30
TSLTC20 TC30
TSLTC20 TC30
PET BOTTLES - LOW COST
TVS-Mysore
HIRANOSAN GUIDELINES
THREE REGULATION FOR KEEPING PARTS
Bolts
4 Pallets
1000x4
3 - SPECIFY QUANTITY
Bolts
1 - PROVIDE LOCATION
2 - PROVIDE IDENTIFICATION / NAME BOARD
SPECIFY INVENTORY OF MATERIAL IN DAYS - INVENTORY OF WIP IN HOURS
TVS-Mysore
HIRANOSAN GUIDELINES
STORAGE OF PARTS
DO NOT KEEP PARTS BELOW KNEE LEVEL
DO NOT KEEP PARTS ABOVE EYE LEVEL
TVS-Mysore
HIRANOSAN GUIDELINES
YELLOW LINE
MARK TIGER LINE FOR CROSSING
YELLOW LINE - MEN & MATERIAL
YELLOW LINE IS A WALL
CANNOT / DO NOT CROSS IT
TVS-Mysore
HIRANOSAN GUIDELINES
YELLOW LINE
AVOID PROTRUSIONS INTO THE GANGWAY - YELLOW LINE IS A WALL
MARK ARROWS ON GANGWAYS TO SHOW WALKING DIRECTION
MARK “STOP” SIGN AT INTERSECTIONS OF GANGWAYS
STOP
ST
OP
PROVIDE CHAMFERS AT CORNERS OF GANGWAYS
TVS-Mysore
HIRANOSAN GUIDELINES
KAIKAKU MEASURES
* Productivity - In terms of out/shift
* Inventory - Total WIP
* Lead time - Time to convert raw material to finish
* Walking distance - In terms of steps/cycle
* Operators - In numbers
* Cycle time - Rhythm at which product comes out
* Takt time - Available time in sec / (qty. to be supplied)
(does not include allowance)
TVS-Mysore
HIRANOSAN GUIDELINES
* Understand JITs 10 commandments
* Understand Hiranosan’s guidelines
* Conduct audit assuming yourself as Hiranosan
* Follow the KAIKAKU steps
Implement “Self KAIKAKU”
TVS-Mysore
BIG ISLAND - WHEEL HUB & PANEL
OUTPUT (Scooty & Spectra) - 600 / day in 2 shifts
TVS-Mysore