My Home Vihanga - Status Report as on 07.12.2013

Preview:

DESCRIPTION

My Home Vihanga Status Report

Citation preview

Project Progress – 07th Dec 2013

LABOUR CAMP

SIDE VIEW

STUB COLUMNS DONE & BACKFILLING IN PROGRESS

STUB COLUMNS ALSO COMPLETED FOR A-B & C-D GRIDS SOUTH SIDE VIEW

A B C D

STUB COLUMNS ALSO COMPLETED FOR C-D & E-F GRIDS SOUTH SIDE VIEW

C D E F

FOOTINGS IN PROGRESS FOR H-J GRIDS SOUTH SIDE VIEW

H J

PCC & FOOTINGS IN PROGRESS SOUTH SIDE VIEW

K J G F

PCC & FOOTINGS IN PROGRESS SOUTH SIDE VIEW

E D C A

FOOTINGS DONE AND CURING IN PROGRESS –EAST SIDE VIEW

FOOTINGS IN PROGRESS –NORTH EAST VIEW

BLOCKS EXCAVATION IN PROGRESS

BLOCKS IN PROGRESS

BLOCKS IN PROGRESS

WORK PROGRESS

WORK PROGRESS

SUB STATION WORK IN PROGRESS

BATCHING PLANT -1 MOBALIZED;BATCHING PLANT-2 FOUNDATION IN PROGRESS