Project Progress As On 30th May,2014

MY HOME ABHRA TOWER-”A” AS ON 30.05.14

1.1st Floor To 17th Floor Slabs Completed2.External Brick Work Completed

MY HOME ABHRA TOWER-”B” AS ON 30.05.14

1.1st Floor To 17th Floor Slabs Completed2.External Brick Work Completed

MY HOME ABHRA TOWER-”C” AS ON 30.05.141.1St Floor To 17th Floor Slabs Completed

2.External Brick Work Completed

MY HOME ABHRA TOWER-”D” AS ON 30.05.14

1.1St Floor To 17th Floor Slabs Completed2.External Brick Work Completed

MY HOME ABHRA TOWER-”E” AS ON 30.05.14

1.1St Floor To 17th Floor Slabs Completed2.External Brick Work Completed