Summer 2009 Capital Projects
Elementary Debt Exclusion Work Summer 2009
Presentation for Town Meeting April 2010
Capital Projects Summer 2009
Elementary Debt Exclusion • Hardy • Hunnewell• Schofield• Fiske• Upham
• Time Frame for summer work– Last day of school for teachers was Thursday, June 24,
2009. Work began immediately after that.– The 42 work days between June 30 and August 27
described the time frame for all the moving and work.
Summer 2008 • Roof replacement• Master Clock and Bell System
Summer 2008 • Roof replacement• Master Clock and Bell System
Summer 2009 • Flooring abatement and replacement in selected rooms• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)
Old flooring was abateddown to a wood subfloor.
Old flooring was abateddown to a wood subfloor.
A new wood subfloor was installed in preparation for the new tile.
Joints were patched
Joints were patched
and new tile installed.
Classroom and entry way tile
Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.
Ceiling tiles were removed. A new ceiling with new lights and new acoustical panels were installed.
New boiler installation
The DPW completed work on a redesigned Hardy Road with increased parent drop off and pick up area.
Summer 2008 • Master Clock and Bell System• Exterior lights and interior carpet
Summer 2008 • Master Clock and Bell System• Exterior lights and interior carpet
Summer 2009 • Flooring abatement and replacement• New air exchange units in gymnasium ceiling• Roof replacement
New flooring was installed in 5 elementary schools.
New flooring was installed in 5 elementary schools.
Point distressed masonry
Point distressed masonry
Replace wood gutters
Point distressed masonry
Replace wood gutters
New roof on the flat section
Summer 2008 • Roof replacement• Master Clock and Bell System
Summer 2008 • Roof replacement• Master Clock and Bell System
Summer 2009 - Phase I (required packing and moving of all rooms in the work area)• Ceiling abatement and replacement
• New fire protection• New lighting
• Flooring abatement and replacement• Enlarge two student bathrooms on cafeteria level• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)
Summer 2008 • Roof replacement• Master Clock and Bell System
Summer 2009 - Phase I• Ceiling abatement and replacement
• New fire protection• New lighting
• Flooring abatement and replacement• Enlarge two student bathrooms on cafeteria level• Gymnasium ceiling abatement / plaster / paint• Boiler replacement (in process)
Summer 2010 - Phase II• Window replacements for both wings• Continued floor and ceiling abatement and replacement
An area of old ceiling previously abated as a result of water damage
The old ceiling was removed in preparation for the installation of fire protection (sprinkler system), new lights and a new suspended ceiling.
New smoke and acoustical stops were installed above the new suspended ceiling in walls separating classrooms.
New ceiling tile and new lighting
New ceiling tile and new lightingbrightened the hallways.
Floor preparation and new tile in the cafeteria
New tile in the cafeteria
New tile in the cafeteria
Two student bathrooms on the cafeteria level were renovated and are now ADA compliant.
Old carpet flooring
New tile flooring
In the process of replacing the gym ceiling the gym floor was damaged.
The floor was sanded, lines repainted and new coats of sealant applied.
Excavation and extensive new piping was required to add the new sprinkler system.
Fiske’s old boilers removed and ready for disposal.
New boilers ready for installation.
Summer 2008 • Master Clock and Bell System• New roof with improved roof drainage
Summer 2008 • Master Clock and Bell System• New roof with improved roof drainage
Summer 2009 • Flooring abatement and replacement in front hallway and entryway• Boiler replacement (in process)
Schofield’s entrance hallway rug was replaced with tile.
Entrance to the Schofield boiler room
Entrance to the Schofield boiler room
Entrance to the Schofield boiler room
New Boilers
Summer 2008 • Master Clock and Bell System
Summer 2008 • Master Clock and Bell System
Summer 2009 (required packing and moving of classrooms to complete the work)• New Roof• Flooring abatement and replacement• Gymnasium ceiling abatement / plaster / paint • Boiler replacement (in process)
Roofing work was completed more quickly than last summer.
Roofing work was completed more quickly than last summer.
On site demolition of the old boiler was required in preparation for installation of the new heating system.
On site demolition of the old boiler was required in preparation for installation of the new heating system.
Gym ceilings at
Upham, Hardy and Fiske
were abated and replaced
this summer.
Gym ceilings at
Upham, Hardy and Fiske
were abated and replaced
this summer.
Gym ceilings at
Upham, Hardy and Fiske
were abated and replaced
this summer.
New classroom tile
New classroom tile
New stair and landing tread
New classroom tile
New stair and landing tread
New hallway tile