► Introductions

► Scope of Services

► DBE requirements

► Schedule

► Q & A

Agenda

2

Scope of RFP

► Purpose: To retain two qualified construction management

firms to provide construction management services, one for

each of the following projects:

YBI Southgate Road Realignment Improvements

Design-Bid-Build Project Delivery Method

Yerba Buena Island (YBI) Westside Bridges Project

Construction Manager/General Contractor Project Delivery

Method

3

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Yerba Buena Island Westside Bridges Project

Project Setting

5

Seismic Strategy – Retrofit and Replacement

6

Structure No. 1 (Retrofit)

7

Structure No. 4 (Retrofit)

Structure No. 7A / 7B (Retrofit)

Structure No. 8 (Retrofit)

Replacement Structures 2, 3 and 6

11

Replacement Structures 2, 3 and 6

12

Replacement Structures – Unstable Soil Swale

CABLE HOUSE

13

Replacement Structure 2

Replacement Structure 3

Replacement Structure 6

Replacement Project

17

Replacement Project

18

Replacement Project

19

TIMMA Tolling

20

Traffic Handling

21

Project Challenges

► Steep terrain, unstable soils

► Environmental constraints

Birds

Plants

► Storm water

► Coordination with Caltrans – SFOBB Ramps

► Coordination with TICD

Construction Detour

Construction Traffic

22

Project Status

► Retrofit Bridges

Environmental Approval Complete

Design is 35% Complete

► Replacement

Environmental Approval – Fall 2017

Design is at Preliminary Conceptual

23

Project Delivery

► Schedule

NTP Pre-Construction Services : August/September 2017

NTP Construction Services: January 2019

Construction Complete: December 2020

► Estimated construction cost

$48 Million

► Delivery method

CM/GC

24

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Yerba Buena Island Southgate Road

Realignment Improvements

Project Setting

26

Project Timing

• Macalla Construction

spring 2018

• Southgate

Construction Spring

2018

• Treasure Island Road

(West Side Bridges)

Construction Spring

2019

27

Southgate Project Elements

28

Project Elements- Structure Components

29

Access Control

30

Quarters 8 Building

31

Preliminary Cost EstimateCosts in ($ Millions)

Roadway – $9.0

Utility Relocation – 0.5

Structures – 9.7

Landscaping – 0.4

S. Bridgehead Foundation – 1.5

Mobilization – 2.0

Contingency (15%) – 3.4

Subtotal Construction Cost - $26.5M

32

Advance Components

33

Schedule

NTP Pre-construction Services : August/September 2017

NTP Construction Services: April 2018

Construction Complete: June 2019

34

Response Requirements

35

RFP > SECTION VI > Pages 18-24

► Technical Proposal

Limited to 40 pages

Excluded from page limitations

Cover Letter

Table of contents

Résumés

DBE certificates

Exhibits

Cost Proposal

Separate submission in sealed envelope

Refer to page 23 for requirements

Evaluation Criteria

36

RFQ > SECTION VI > Pages 24-25

► Proposal

1. Proposer Information and Understanding of Project

Objectives (15 points)

2. Technical and Management Approach (50 points)

3. Capabilities and Experience (35 points)

DBE Requirements

37

RFP > Section VII > Pages 25-26

DBE Goal: 10.2%

By the proposal due date, firms must:

Be certified by the California Unified Certification Program

(DBE certification)

Submit:

Exhibit 10-O1 – Local Agency Consultant Proposal DBE

Commitment

Exhibit 10-O2 – Local Agency Consultant Contract DBE

Commitment

Exhibit 15-H – DBE Information – Good Faith Efforts

Proposal Schedule

38

RFP > Pages 1-2

DUE DATE SELECTION PROCESS

May 23 5:00 PM deadline for proposers to submit written questions to info@sfcta.org.

May 26 Written responses to questions issued; addenda if necessary (via www.sfcta.org)

June 122:00 PM deadline for proposals and sealed cost proposals. Late submissions not

accepted.

June 16 Invitation to Interview issued to short list of proposers (if necessary)

June 22 Interviews (scheduled if necessary)

June 28 Recommendation to Citizens Advisory Committee for award (subject to change)

July 11 Recommendation to Transportation Authority Board for award (subject to change)

Questions are due by 5pm on Tuesday, May 23rd to info@sfcta.org.

July 25 Transportation Authority Board awards contract (subject to change)

SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY

Questions and Answers

Southgate Schedule

Final Design start – June 2017

Advance Construction Elements – through Dec. 2017

Environmental Revalidation – Spring 2018

Permits – Spring 2018

Advertise Bid Package – Spring 2018

Construction Start – Summer 2018

Construction complete - Summer 2019

40