8/8/2019 Webinar 1 Ed 9 English
1/53
Photovoltaic Systems Training
Session 1 - Design
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Javier Relancio & Luis Recuero
Generalia Group
September 14th 2010
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
2/53
PHOTOVOLTAIC SYSTEM
Design, Execution, Operation & Maintenance
FACILITY DESIGN
Javier Relancio. Generalia Group. 14/09/2010
www.generalia.es
2http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
3/53
INDEX
Evaluation of the solar resource
Increasing the plant profitability from the design
Choosing the components
Photovoltaic facilities calculations
Single-line diagram
3http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
4/53
INDEX
Evaluation of the solar resource
Increasing the profitability of the plant from the design
Choosing the components
Photovoltaic facilities calculations
Single-line diagram
4http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
5/53
Characteristics of the solar resource: random and variable
Great quantity and quality of measurement stations, both the global radiation and its
components: direct and diffuse
These stations are insufficient to allow the evaluation of any geographical location
or with changeable topography.
The usage of Geostationary satellites images are
a tool that can cover this gap
They are more reliable than the interpolation
of the data from closer meteorological stations
Solar resource evaluation
5http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
6/53
Each day, we can find new
maps, which have less
uncertain measures
They allow a first approach to
the viability study for a solar
plant location
They can be considered
enough for small solar facilities
But, to get a completely certain measure, a rigorous solar radiation evaluation must
be done in situ.
Then, we could additionally compare them with the satellite information and
the closer meteorological stations
6
Source: NASA
Solar resource evaluation:Solar Radiation maps
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
7/53
7
INDEX
Evaluation of the solar resource
Increasing the plant profitability from the design
Choosing the components
Photovoltaic facilities calculations
Single-line diagram
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
8/53
OPTIMUM
PROFITABILITY
8
Towards the profitability ofthe plant from the design
Resource evaluation System losses (PR)
Shadows
Disconnections & Breakdowns
Panel tolerance
Pollution, dispersion & reflectance
Temperature
Inverter
Cables
Latitude
Longitude
Altitude
Data from closest
meteorological stations
Data from satellites
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
9/53
9
INDEX
Evaluation of the solar resource
Increasing the plant profitability from the design
Choosing the components
Photovoltaic facilities calculations
Single-line diagram
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
10/53
The inverter can be considered as the heart of a solar facility Its cost, in relation to the complete installation, is between 6% - 9%
Its performance is already between 95 %-97 %
It is important to know about their operation principles. We can find 3 options:
10
Inverters: Trends
MULTI POWER STAGES ONE POWER STAGE
MULTI CONTROLLED
POWER STAGES
The electrical companies can ask for galvanic isolation transformers when the connection
is in low voltage
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
11/53
11
Inverters: features
The inverter main features are:
Maximum Input Voltage:
The PV generator voltage must be under the
inverter maximum input voltage
MPPT Voltage:
It is the range where the inverter is able to get
the Maximum Power Point from the PV
generator I-V profile.
The PV generator voltage must be within this
range in the different conditions and weatherduring the whole year.
Source: SolarMax
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
12/53
12
Other important parameters are:
Inverter efficiency:
As it is shown in the graphic, the inverter has a different efficiency depending on the load. Usually,
the manufacturers give the maximum efficiency and the european efficiency, which is the weighting
of the different efficiencies when the load is: 5%, 10%, 30%...100%
Inverter temperature range:
This is really important, as in some places the temperature can reach over 40, and extra cooling
might be considered
Inverters: Features
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
13/53
13
Crystalline or Thin-film Panels
Visual identification:
Mono crystalline Poli crystalline Thin film A-Si:H
Source: Atersa
They are cheaper, but they need larger surfaces & structures
The guaranteed output power is not as precise as in Mono/Poli crystalline modules
There are no references from facilities producing an important amount of years
Thin film panel observations:
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
14/53
14
Crystalline or Thin film modules
CRYSTALLINE PANEL PRICE* TEMPERATUREINFLUENCE
Mono crystalline
Poli crystalline
THIN FILM PANEL
CGIS (Copper-Gallium-IndiumSelenide)
CIS (Copper-Indium Selenide)
CdTe (Cadmium telluride)
A-Si:H triple (Amorphous silicon
triple union)A-Si:H tandem (Amorphous silicon
double union)
A-Si:H single (Amorphous silicon)
EFFICIENCY REQUIREDSURFACE
* This information can be altered depending on each manufacturer price policy
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
15/53
15
PV Module Specs
Source: Atersa
The most important electrical spec is the panel efficiency
The highest the efficiency is, we will require a smaller
surface to reach a certain output power
Voltage and current parameters are not determinant, as we
can connect the panels in series or in parallels to fit the
inverter input.
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
16/53
16
PV Module Specs
Source: Atersa
Source: QS Solar
Among panels with different technologies: we can find big differences, as we can see in the technical
information below.
The losses due to temperature affect the production
specially in countries with latitudes between 0 35
Among panels with the same technology: the
thermal coefficient is quite similar among the
different manufacturers & models
A: Si Polycrystalline
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
17/53
Concentration technology is still being developed
Fresnel Lens (and other kinds)
Refractive optical system
Concentration up to 500x
Potential cost savings
Improvement in cell efficiency: from actual 30% towards 40%
Increasing the concentration: from actual 500x towards 1000x
Hardest challenges
Extremely accurate suntracking (Accuracy < 0.1 - 0.2): High costs
Optical elements degradation
Cooling systems are required
17
Concentration Panel
Source: Everphoton
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
18/53
The protections to be installed are:
18
Example: ABB S800PV (Specifications)
S800PV-S High Performance MCB
Versions: 2P, 3P & 4P
Current: Up to 80 A
Voltage: 800 Vdc with 2P & 1200Vcc with 3P & 4P
S800PV-M Switch-Disconnector
Versions: 2P, 3P & 4P
Current: Up to 125 A
Voltage: 800Vcc with 2P & 1200Vcc with 3P & 4P
Protections
ACMiniature Circuit
Breaker (MCB)
ACDifferential
DCFuses
Source: ABB
DCMiniature Circuit
Breaker (MCB)
AC sideDC side
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
19/53
19
Overvoltage protections
To protect the installation against overvoltage we must
install high energy varistors close to the element that we
want to protect
The main aim of this device is to detect an overvoltage
within a certain period of time and then divert it to the
ground
The device may be destroyed depending on the power to
be diverted to the ground
Type 150 275 320 385
According to standard IEC 61643 1
Maximum voltage (AC/DC) Uc(L-N/N-PE) 150/200V 275/350V 320/420V 385/500V
Nominal discharge current (8/20) In (L-N/N-PE) 20/20 kA
Maximum discharge current (8/20) Imax(L-N/N-PE) 40/40 kA
Protection Level Up (L-N)
Up (N-PE)
< 0.9 kV < 1.5 kV < 1.5 kV
< 2 kV
< 1.9 kV
Tracking current If(L-N/N-PE) > 100 A RMS
Response time tA (L-N/N-PE) < 25 ns / 100 ns
8/8/2019 Webinar 1 Ed 9 English
20/53
20
Cables
Cable Requirements for PV facilities
The facility has a lifetime of over 25 years
From solar panel to inverter: weatherproof for outdoor conditions and
suitable for indoor conditions (in houses or industries)
From inverters to meters: direct burial or inside cable ducts
If medium-voltage is required, it might be suitable:
For underground installation (inside cable ducts)
For aerial installation
Source: TopCable
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
21/53
21
Cables
It is recommended to use*: Specific PV usage cable
RZ Cable
Main features:
Conductor: electrolytic copper Insulation: halogen free
Cover: fireproof; low emissions (corrosive gas & toxic smokes) in
case of fire
To avoid health damages and device damages
Obligatory in public locations
A comparative table can be found in next slides
Source: TopCable
* Based in previous slide considerations
8/8/2019 Webinar 1 Ed 9 English
22/53
22
Cable FV
CABLE FV
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
23/53
23
Cable RZ
CABLE RZ
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
24/53
24
Typical elements (used in every electrical installation):
Earth peg: different sizes depending on the required depth
(from 1,5 to 2,5 meters)
Cable: copper without cover >35mm2.
Depending on the installation:
Low-power installations: it would be enough to use several
earth pegs connected by a copper cable (without cover)
High-power installations: a copper cable grid is usually used
(without cover). Depending on the physical measures, earth pegs
can be also used.
Earthing System
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
25/53
25
Required elements for a Medium-voltage installation:
Transformer:
With the same power as the PV inverter output.
With the following features:
Mineral oil bath
Accessible neutral (in low-voltage)
Natural cooling
Three-phase voltage reduction: MV - LV
Medium-voltage cells:
We can find different types, such as:
Measurement cell
Automatic switch cell
They can be remotely controlled
Depending on each connection requirement, the company might
define the devices, and the cost may vary drastically.
Transformation stations
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
26/53
26
The meter must be certified in the country where it will be used
Typical specifications to meet are:
Class 1.0 ( Class B)
Bidirectional
Optical & RS 485 outputs
Depending on the installed power the meter can be directly connected
or coil inductors are to be used.
Metering Device
Source: Circutor
The most usual cases are:
The grid connected PV facility exports all the generated electricity towards
the grid, except the consumption of its own devices: Inverters, Monitoring &communications devices, Auxiliary services, Suntracking devices
The grid connected PV facility uses the network as a battery. This type is
known as Net metering
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
27/53
27
Grid connection point
MT PV Facility
In order to avoid shadowing, MV cable will be buried underground
Usual voltage will be between 15 kV 30 kV (Although it can be a
different one depending on each country)
An underground to aerial link will be done, to connect with the power line
of the electric company
Source: Centelsa
Main features for the copper cable
Density g/cm3 8,89
Resistivity Ohm mm2/km 17.241
Conductivity (%IACS) 100.0
Breaking strength Mpa 220
Elongation % 25 30
Corrosion resistance Excellent
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
28/53
28
Grid connection point
The MV cable requires a reinforcement to guarantee that the electrical
distribution is homogeneous.
This reinforcement is done in three layers (triple extrusion):
Conductor reinforcement
Insulation
Insulation reinforcement
The cable requires also an external
cover to provide resistance to:
Humidity
Fire
UV sunlight
Impact
Chemicals agents
Source: Centelsa
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
29/53
29
INDEX
Evaluation of the solar resource
Increasing the plant profitability from the design
Choosing the components
Photovoltaic facilities calculations
Single-line diagram
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
30/53
30
Radiation (Wh/m2)
Electric Energy (Wh)
PR = 0,74 - 0.78
System Losses
Considerations:
1. The values considered in the following slides are estimated values and should only be used as an
approach. They may vary depending on each location.
2. A detailed Performance Ratio study is fundamental to evaluate the profitability of each solar facility
Towards the PR (Performance Ratio)definition
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
31/53
1. Temperature. (9%) +10C 4% received energy
2. Inverter. We can consider about 6%. New inverters can reach 4%
3. Cable: AC, DC & other electric devices: < 2%
4. Panel tolerance. It shouldnt be higher than 3%
5. Pollution, dispersion & reflectance.
1. Fixed panel: aprox.3%
2. Suntracking system: 2%.
In urban areas, it should de increased by 2%
6. Shadowing. They should be below 4%. In case of using suntracking
systems, a shadowing study might be necessary.
7. Other losses (incidences, etc).
1. Fixed panel: 2%
2. Suntracking system: 4%.
31
100%
91%
87,4%
85,6%
83%
80,6%
77,3%
75,8%
System Losses evaluation
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
32/53
Choose cool locations, as elevated areas
Select inverters with high efficiency and Maximum Power Point Tracking (MPPT)
Consider extra cable sizing avoiding long traces with voltage drops
Choose solar panels with tolerances between +/- 2-3%
Cleaning the modules in long periods without rain
Balance the separation between panel rows (to avoid shadowing) with the
optimization of the surface area
Minimize the impact of breakdowns, with a preventive maintenance.
32
Keys to optimize the PR
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
33/53
Depending on the type of installation, the shadowing study and the surface optimization,
the project profitability may vary.
The main aspect to study are:
Azimuthal deviation from the south (North hemisphere) or north (South hemisphere)
Tilt of the solar panel
Shadows of extern elements Shadows of own elements
33
Shadowing evaluation
FIX - GROUND SUNTRACKING-GROUND FIX - ROOF INTEGRATION
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
34/53
1. Distance between panel rows
A basic rule would be to avoid shadows during the 4 central hours of the day, in
the day of the year with less radiation.
This implies calculating the angle of the sun (height regarding the line of the
horizon) to +/-2 hours regarding the solar midday. This angle will vary dependingon the latitude
The objective is to avoid that the top of the front panel projects a shadow to the
lowest part of the panel that is placed behind.
34
Fix - Ground
d= h / k
Latitude 29 37 39 41 43 45
k 1,600 2,246 2,475 2,747 3,078 3,487
8/8/2019 Webinar 1 Ed 9 English
35/53
2. Tilt angles
The optimum tilt angle of the solar panel can be expressed by the following
simplified formula: Tilt = Latitude 10
In Spain, tilt angles from 30 to 33 is considered as optimum, but tilt angles
between 20 40 dont mean considerable system losses
Tilt angles below 15 in urban areas may cause system losses due to pollution
and dirt accumulation on the panels.
Local land slope will be logically taken into account, which can help reducing
distance between the panel rows to improve the surface profit. (Obviously, the
opposite effect can happen)
35
Fix - Ground
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
36/53
3. Orientation angle
The most favorable orientation is 0 South (North hemisphere).
An orientation deviation below 20 (East or West) cause negligible system losses.
The following graph (which is valid for a 40 latitude) shows how additional losses
may appear depending on the combination of orientation and tilt angle.
36
Fix - Ground
8/8/2019 Webinar 1 Ed 9 English
37/53
A practical example: Solar Plant in Valdecarabanos (Spain)
Placement optimization
37
Suntracking - ground
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
38/53
Previous tasks:
Environmental conditions
Urban conditions
Topography
External elements shadowing study (trees, electrical posts, etc)
Own elements shadowing study: direct & crossed (in suntracking
cases)
Definition of the distance between suntrackers (or panel rows)
38
Suntracking - ground
Location optimization
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
39/53
39
Location optimization. Shadowing study
Suntracking - ground
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
i f
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
40/53
40
As grid connected solar facilities are considered as an investment, we have to choose
between the following cases:
To place the solar panels at the optimum tilt and orientation angle.
To adapt the solar panels to the roof shape
We should take into account:
Impact of angle orientation.
Impact of tilt angle.
Impact of shadows
Comparison between adapted VS optimum
Roof geometrical limits
Remarks: be careful with panels from
the same row in different planes
Fix - Roofs
OPTIMUM ANGLE & ORIENTATION
ROOF ADDAPTED
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
A hit t l i t ti
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
41/53
41
Two possibilities:
To avoid visual impact, adapting the solar panels to the roof shape
To integrate the panel as a constructive element with a certain function:
Electricity generation
Sunshade effect: special panels which allow some sunlight to gothrough
Innovative design: usually special structures are required, and this
may increase the installation costs
In architectural integration, the solar facility is not considered as just an
profitable investment, but also as an image and design element
Architectural integration
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
A l d ti
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance8/8/2019 Webinar 1 Ed 9 English
42/53
We will consider that the radiation, in the south of Madrid (Spain), for a certain
year can be around 4.77 kW-h/m2 (Average)
42
Annual production
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenancehttp://www.leonardo-energy.org/training-pv-systRecommended