Version 1.1.13©2013 Containment Solutions. All rights reserved.
Fiberglass Tank InstallationFor Petroleum & Oil/Water Separators
Agenda
• Introductions• Review Key Installation Procedures (PPT)• Written Exam• Contractor Documentation• Submit signed Attachment E
as a record of training• Review Missed Questions• 2-Year Renewal
2
Generally Used Terms
3
Important Documentation
4
Tank Installation InstructionsINST 6001
Referenced throughoutthe presentation
5
PRE INSTALLATION PREPARATIONSection A
6
Safety Reminders
• Pay close attention to the important safety comments throughout the Installation Instructions
• Remember to follow all OSHA, EPA and local regulations which apply
Section A 7
• Remember to barricade tank area
• Complete installation checklist
• Review shipping packet contents
Handling/Preparation
Section A 8
Handling/Preparation
• The Installation Checklist:– Is included in the installation
instructions, found in the shipping packet
– MUST be filled out for each tank on every project
– MUST be retained by the tank owner and provided to CSI to validate any future warranty claim
Section A 9
Handling/Preparation:• All tanks must be mechanically unloaded• Carefully unload all accessories to prevent damage
For temporary job site storage:• Use provided shipping pads or approved tank backfill• Chock tanks with sandbags• Place on smooth ground• Tie down tank in anticipation of high winds• Protect collars from freezing conditions
Handling/Preparation
Section A 10
Handling/Preparation
When tanks arrive at the job site, they should always be
mechanically unloaded
Section A 11
• There are different tank orientations for unloading or lifting into the excavation.
• Identify the tank lift lug orientation and use the appropriate method to lift the tank.
Handling / Preparation - Tanks
Section A 12
13
BED & BACKFILLSection B
Bed & Backfill
• Always use approved pea gravel or crushed stone
• Require sieve analysis from your backfill supplier
• Do not use sand or native soil• Alternative materials must be
approved in writing by CSI Tech Support prior to installation
Section B 14
• Clean and washed backfill material only.
• Crushed Stone no larger than 1/2”
• Rounded Pea Gravel no larger than 3/4”
• No more than 5% passing #8 sieve
Bed & Backfill
Section B 15
Backfill calculator on CSI website to confirm sieve analysis
Bed & Backfill
If backfill materials that meet CSI’s requirements are not available,
alternative materials can ONLY be used if written permission is obtained from CSI
prior to installation.
Section B 16
17
TANK TESTING PROCEDURESSection C
Testing All Fiberglass Tanks
Important Warning For all TestsNever pressurize tank over 5 psig or 3 psig for 12’ diameter tanks
Section C 18
Testing All Fiberglass Tanks
• Connect a “Tank Test Manifold” to a primary fitting
• Use pressure gauge of 15 psig or less (max ¼ psig increments)
• Use pressure relief device to ensure tank pressure does not exceed 5psig (3 psig for 12’ tanks)
Tank Test Manifold(Contractor Supplied)
Section C 19
Testing All Fiberglass Tanks
• For any tank model with a dry interstitial space (including a double-wall bulkhead) connect an “Annular Space Gauge and Valve” to an annular space fitting
Annular Space Gauge and Valve(Contractor Supplied)
Section C 20
Testing All Fiberglass Tanks
• Soap entire tank and inspect for air bubbles
• Soap all fittings and manways
• Contact CSI Field service immediately in the unlikely event a leak is discovered
Section C 21
Testing All Fiberglass Tanks
• Double-Wall Tank Tests are only in Sections D4 – D9
• Determine which section is appropriate• Follow each step of the instructions provided in the
Tank Installation Instructions
Only 3 of the possible 9 testing procedures are discussed in this presentation and only the critical steps are highlighted.You are responsible for all the steps in any of the 9 possibilities when installing CSI tanks.
Section D 22
SINGLE-WALL TANK TESTING PROCEDURESSection D
Section D1 - Testing Single-Wall Tanks
Steps 1-3: follow Installation Instructions
4. Pressurize tank to 5 psig maximum (3 psig for 12’ tanks).
5. Monitor the pressure readings for 30 minutes for any loss in pressure from the initial reading which may indicate a leak.
6. While under pressure, cover tank outer surface including fittings and manways, with soap solution and inspect.
Steps 7-10 : follow Installation Instructions
24
DOUBLE-WALL TANK TESTING PROCEDURESTANKS WITH DRY ANNULAR SPACE
Section D
Section D4 - Testing Double-Wall Tankswith Dry Annular Space
Steps 1-5: follow Installation Instructions
6. Pressurize tank to 5 psig maximum (3 psig for 12’ tanks).
26
Steps 7-8: follow Installation Instructions
9. Open valve between primary tank and annular space in order to pressurize the annular space using the existing pressure in the primary tank (pressure in the primary tank may drop slightly)
10. While under pressure, cover fittings and manway(s)with soap solution and inspect
Section D4 - Testing Double-Wall Tankswith Dry Annular Space
27
Steps 11-12: follow Installation Instructions
13. Maintain pressure on the annular space (see Figure D4-3)
14. Observe and monitor the gauge on the annular space for 30 minutes for any loss of pressure which may indicate a leak.
15. While under pressure, cover tank outer surface, including fittings and manway(s), with soap solution and inspect.
Steps 16-19: follow Installation Instructions
Section D4 - Testing Double-Wall Tankswith Dry Annular Space
28
DOUBLE-WALL TANK TESTING PROCEDURESTANKS WITH HYDROSTATICALLY MONITORED
SPACESection D
Section D7 - Testing Double-Wall Tanksw/ Hydrostatically Monitored Space
Step 1: follow Installation Instructions
2. Closely inspect outer wall for any trace of green monitoring fluid.
Steps 3-6: follow Installation Instructions
7. With a light, look inside for any monitoring fluid.
8. Replace and tighten fitting plug(s).
30
9. Connect “Tank Test Manifold” to a primary tank fitting.
10. Connect the pressure source to the “Tank Test Manifold.”
Section D7 - Testing Double-Wall Tanksw/ Hydrostatically Monitored Space
31
Section D7 - Testing Double-Wall Tanksw/ Hydrostatically Monitored Space
11. Pressurize primary tank to 5 psig maximum (3 psig for 12' tanks) (see Figure D7-2).
12. Close valve on “Tank Test Manifold.” Disconnect the air supply line.
13. Monitor the pressure for 30 minutes for any loss in pressure from the initial reading which may indicate a leak.
14. While under pressure, cover tank fittings and manway(s), with soap solution and inspect.
Steps 15-18: follow Installation Instructions
32
• Supplemental Document INST 6050
• Unique instructions for tanks under vacuum
• Record final vacuum level on Tank Installation Checklist
Testing Tanks Under Vacuum
33
EXCAVATIONSection E
Excavation Size
• Minimum spacing between tanks is 18” when no mechanical anchoring is required
• Tank spacing depends on soil in the excavation as well as the choice of anchoring systems
Section E 35
Excavation Size – Stable
• Minimum spacing between tanks and excavation walls, in stable soils
• Example: with no mechanical anchoring, a 10’ diamater tank will need a minimum 18” spacing between tanks and 24” spacing between the tank and the excavation walls
Section E 36
Excavation Size – Unstable
• Minimum spacing between tanks and excavation walls, in unstable soils
• In unstable excavations the spacing between the excavation walls and the tank should always be a minimum of ½ the diameter of the tank
Section E 37
Excavation Size
When job site conditions require an oversized hole, fill the entire
excavation with approved backfill.
Section E 38
39
GEOTEXTILE FABRICSection F
Geotextile Fabric (Filter Fabric)
Geotextile fabric is required between backfill and native soils for certain installations such as unstable soils, swampy areas and landfills to prevent backfill from migrating and thereby undermining support of
the tank, piping or paving.
Section F 40
Geotextile Fabric (Filter Fabric)
• Geotextile fabric should be used in tidal conditions, area of frequently changing ground water, and unstable soils
• Do not use plastic, or any other material that may tear or degrade, as a replacement for geotextile fabric
Section F 41
BURIAL DEPTHSection G
Burial Depth and Cover
• Minimum bedding under tank is 12” (18” in a wet hole) and a maximum of 24”
• Maximum standard burial depth is 7’
• Traffic pad must extend at least 12” beyond tank perimeter
• Minimum burial depth will vary according to job site conditions:– Traffic load– Mechanical anchoring– Number of tank sumps/risers
Section G 43
Burial Depth – No Traffic Load
• For No Traffic Loads:– 4’-10’ tanks need a
minimum of 24” backfill or 12” backfill and 4” reinforced concrete
– 12’ tanks need 42” backfill or 38” backfill and 4” reinforced concrete
Section G 44
Burial Depth – Traffic Load
• For Traffic Loads:– 4’-10’ tanks need a
minimum of 36” backfill or 18” backfill and 6” reinforced concrete
– 12’ tanks need 48” backfill or 36” backfill and 6” reinforced concrete
Section G 45
TANK ANCHORINGSection H
Tank Anchoring
The three common methods are:1. Deadmen Anchors2. Concrete Anchor Pad3. Overburden (no mechanical anchoring)
For minimum burial depths refer to the Anchoring Chart in Installation Instructions INST 6001 (Appendix A)
47
Mechanical Tank Anchoring
• If water can enter the tank excavation, CSI recommends mechanical anchoring
• Use only CSI fiberglass anchor straps
• Deadmen or concrete anchor pads may be used
• After installation, all exposed metal should be coated or galvanized to protect against corrosion
Section H 48
Tank Anchoring – Anchor Straps
For All Mechanical Anchoring:• Use correct length anchor
straps for each diametertank
• Anchor points must be aligned with designated anchor ribs (±1"). Do not use straps ►◄between ribs except on 4' tanks
• Use one anchor point per strap end
Section H 49
Tank Anchoring – Anchor Straps
• Anchor straps on fiberglass tanks:– Must have anchor points at the
bottom of the hole aligned within 1”
of the designated rib– Should be tightened with
turnbuckles (seen here) or come-alongs to give a “snug” fit
– Are available in a convenient man-out-of-hole split strap option
Section H 50
Unloading Deadmen:• Ensure lifting equipment is rated to handle the full
load before lifting• Use a minimum of 2 equally spaced anchor points
Tank Anchoring - Deadmen
Section H 51
Tank Anchoring - Deadmen
• Lay the deadmen in the excavation parallel to the tank and outside of the tank shadow
• Each tank requires its own deadman on both sides, or if one deadman is used between adjacent tanks, it must be doubled in width
• Place multiple deadmen, in contact, end to end
Section H 52
Standard installation is bottom of deadman even
with bottom of tank
Tank Anchoring – Anchor Pad
Using Anchor Pad:• As a minimum the anchor
pad for stable excavations must be at least 8" thick, with #6 rebar on 12" centers each way
• When a concrete anchor pad is used the tank and pad must be separated by at least 12” of approved pea gravel or crushed stone backfill
• Embedded anchor points must be designed for the working loads in Section H of the Installation Instructions
Section H 53
VERTICAL DIAMETER MEASUREMENTSSection I
Vertical Diameter Measurements
• Excessive Deflection (loss of vertical diameter) of any installed tank can create stress on the tank
• The major cause of deflection is the loss of tank support because of improper backfill material or installation method
• Compare all deflection measurements to the limits established by CSI on the Tank Installation Checklist
• There are 5 total vertical diameter measurements
Section I 55
Vertical Diameter Measurements
• “First Vertical Diameter Measurement”– After placement of tank
on backfill bed
• All measurements are recorded on the Tank Installation Checklist
Section I 56
Vertical Diameter Measurements
• “Second Vertical Diameter Measurement”– When mechanical anchoring
is completed– (only applicable if
mechanical anchoringis used)
• All measurements are recorded on the Tank Installation Checklist
Section I 57
Vertical Diameter Measurements
• “Third Vertical Diameter Measurement”– After backfill is to tank top
• All measurements are recorded on the Tank Installation Checklist
Section I 58
Vertical Diameter Measurements
• “Fourth Vertical Diameter Measurement”– When backfill is to subgrade,
but BEFORE the concrete pad
• All measurements are recorded on the Tank Installation Checklist
Section I 59
• “Fifth Vertical Diameter Measurement”– When backfill is to
subgrade, but BEFORE the concrete pad
• Complete Tank Installation Checklist
Final Tank Deflection Measurement
Section I 60
TANK INSTALLATION PROCEDURESSection I
Installation Procedures
Basic Installation Steps Overview:
1. Review all instructions and make sure you are compliant with proper procedures
2. Add Backfill Bed
3. Place Tanks in excavation on Backfill bed
4. Take First Vertical Diameter Measurement
5. Complete Mechanical Anchoring
6. Take Second Vertical Diameter Measurement
7. Backfill Tank to tank top
8. Take Third Vertical Diameter Measurement
9. Backfill to subgrade
10. Take Fourth and Fifth Vertical Diameter Measurements
62
Installation Procedure – DRY HOLE
• Minimum initial tank bed of 12” of approved backfill
• Probe first 12” lift under tank between 5 and 7 o’clock positions of tank
• Probe second 12” lift (most critical area)
Section I 63
Installation Procedure – DRY HOLE
• Probe first 12” lift under tank between the 5 and 7 o’clock position of tank
• The 5 and 7 o’clock position is the most critical area for support
• Probe second 12” lift
Section I 64
Installation Procedure – DRY HOLE
• Ballast tank only AFTER backfill is to top of tank
Section I 65
Installation Procedure – WET HOLE
• De-water hole as much as possible
• Place 18”- 24” backfill bed under tank
• Use only enough water ballast in tank to sink tank
• Keep tank vented to prevent pressurization• Ballast level inside tank should not be more than
12” above ground water level outside of tank
Section I 66
Installation Procedure – WET HOLE
Fiberglass tanks installed in unstable soils such as peat,
swamp or landfill type must have a hole size big enough to allow a minimum space equal to half the tank diameter from the ends and
sides of the tank to the excavation walls.
Section I 67
Internal Piping Clearances
• Internal piping should be a minimum 4” from bottom of tank (6” min. 12’ tanks)
Section K 68
External Piping Clearances
• Isolate external piping from the concrete pad• Attached piping must be free to move with tank
Section K 69
Venting and Filling
• Primary tank and annular space MUST be properly vented
• CSI recommends only gravity-filling of tanks• Avoid pressure deliveries if possible
– If not, install overfill shut-off equipment that disengages pump
– DO NOT over fill tank, or damage may occur, even if tank is vented
Section L & Section M 70
Manways
• DO NOT enter tank!!
• DO NOT exceed 50 ft./lb. torquewhen tightening manway bolts
• The load bearing capacity for a standard 22” manway installed is 1,200 lbs. for single-wall tanks and 2,400 lbs. for double-wall tanks
Section N 71
Tank Collars, Sumps
• Initial Jobsite Testing– The installation contractor
must test the tank sump to the secondary containment collar joint and the secondary containment collar to tank attachment before backfill is around the collar.
• All collars and tank sumps should be isolated from direct traffic loading
• All collars and tank sumps must be continuously monitored for leaks using an electronic monitoring sensor
Section P 72
Critical Installation Steps Review
1. Air/Soap test the tank
2. Use proper backfill material
3. Provide a proper bed for the tank
4. Evaluate if the tank will need to be anchored
5. Properly place and probe the first two 12” lifts of backfill under the haunches of the tank
6. DO NOT ballast the tank until backfill is to the top of the tank
7. Measure and Record all Vertical Diameter Measurements
73
74
TANK SUMP INSTALLAITON PROCEDURESSINGLE-WALL TANK SUMPS
Publication Inst 6030
Tank Sump Terms
75
Handling and Preparation
• Visually inspect the sump components for shipping damage. (If damage is found, contact CSI Field Service)
• Wear gloves.• Do not roll, drop, or bounce.• Set on smooth surface.• Secure sumps to prevent damage from
high winds. Proper precautions should be taken to protect adhesive channels.
INST 6030 76
Kit AD - Assembly Preparation
• Store kits indoors between 50° - 70° F
• Dry fit all sump components• Make necessary field cuts (+/- ¼”)• Remove rocks or debris from channel• Sand and clean mating surfaces• Wipe surfaces free of dust with a
clean cloth
INST 6030 77
Kit AD - Instructions
• Check adhesive container for expiration date• Thoroughly mix two part adhesive by hand or with a
powered mixer following the mixing instructions contained in the adhesive kit
INST 6030 78
Kit AD - Instructions
• Pour properly mixed adhesive into grout bag for easy installation into adhesive channel
• Add supplemental heat to tank sump when temperatures are below 60° F
INST 6030 79
Kit AD - Instructions
• Fill channel with adhesive using the grout bag or application tool
• Make two consecutive 360° passes with adhesive around each channel
• Allow adhesive to cure at least 24 hours without moving the joined parts
INST 6030 80
Layup Kit (Kit LK) - Instructions
• Optional Kit used in lieu of Kit AD• Thoroughly mix resin and
catalyst following the mixing instructions in the layup kit.
• Resin coat previously ground mating surfaces.
• Apply 3 layers of glass layup saturated with resin 360° around sump, centered on joint. All layup joints must overlap a minimum of 1" but not exceed 2” in circumferential direction.
• Roll layup until all air is removed.• Allow layup to cure at least 24 hours without
moving the joined parts.
INST 6030 81
Tank Sump Installation
• All joints must be sealed with either adhesive or layup material for a watertight sump
• Always vent sumps• All sumps must be continuously monitored for leaks
using an electronic leak monitoring sensor• Isolate sumps from direct traffic loading• Approved backfill is critical to long term
tank sump performance
INST 6030 82
Tank Sump Installation - Concrete Slabs
• Properly backfill around sump
• Place a 5' x 5' x 3/4" rigid board with appropriate cutout for access to sump top
• Use grade access manhole large enough to allow sump lid removal after installation
• Pour slab directly onto rigid board
INST 6030 83
Tank Sump Installation Checklist
Tank Sump Installation Checklist:
• Is included in the SW Sump Installation Instructions, found in the shipping packet
• MUST be properly filled out for each project
• MUST be signed by both the installing contractor and tank owner’s representative
• MUST be retained by the tank owner and provided at a later timeto CSI to validate any future warranty claim
INST 6030 84
Tank Technical Support(800) 537-4730(936) 756-7731
Field Service Department(800) 822-1997(814) 542-8520
For Additional Information: