Transmission for Renewable Energy

Preview:

Citation preview

1Law of Renewable Energy WEBINAR SERIES

Transmission for Renewable Energy:Efficient Solutions to Integration Issues

Law of Renewable Energy

WEBINAR SERIES

PRODUCED BY EUCI ● June 23 , 2011

To order any of these books please contact

Angel Giovannone at (503) 294-9422 or amgiovannone@stoel.com

2Law of Renewable Energy WEBINAR SERIES

3Law of Renewable Energy WEBINAR SERIES

Jason A. Johns

Associate

Portland, OR

(503) 294-9618

jajohns@stoel.com

4Law of Renewable Energy WEBINAR SERIES

Marcus Wood

Partner

Portland, OR

(503) 294-9434

mwood@stoel.com

5Law of Renewable Energy WEBINAR SERIES

Jennifer H. Martin

Partner

Portland, OR

(503) 294-9852

jhmartin@stoel.com

6Law of Renewable Energy WEBINAR SERIES

Timothy L. McMahan

Partner

Portland, OR

(503) 294-9517

tlmcmahan@stoel.com

7Law of Renewable Energy WEBINAR SERIES

Agenda

• Interconnection

• Reliability

• Transmission Service

• Market Changes

• Permitting

8Law of Renewable Energy WEBINAR SERIES

Interconnection

• Which interconnection procedures apply?– First, you need to determine if your interconnection is subject to

state or federal jurisdiction

– If Federal, the procedures that apply may depend on thefacility’s size

• Small Generator = ≤ 20 MW

• Large Generator = > 20 MW

9Law of Renewable Energy WEBINAR SERIES

Interconnection Services

• What types of interconnection service are available?– Energy Resource service = Allows generator to connect to the

transmission system and be eligible to deliver electric outputusing existing firm or non-firm transmission on an “as available”basis

– Network service = Allows generator to connect to thetransmission system:

• In a manner comparable to that which the TP integrates its owngenerating facilities to serve native load customers; or

• In an RTO or ISO with market-based congestion management, inthe same manner as all other Network Resources

• Which service should I choose?

10Law of Renewable Energy WEBINAR SERIES

Negotiating theInterconnection Agreement

• Under FERC’s LGIA, the terms are standard and changes must beapproved by FERC

• Negotiations focus on:

– Milestones (schedule and payments)

– Cost allocation (contingent facilities)

– Operational Characteristics

• Facilitating use of one interconnection capacity by more than oneproject or owner

– Phasing

– Joint Ownership Agreements

– Partial Termination

11Law of Renewable Energy WEBINAR SERIES

Queue Congestion

• Small financial commitment to enter queue ($10k)

• Three serial studies

– Feasibility Study

– System Impact Study

– Facilities Study

• Little disincentive to withdraw; restudies were common

• So was suspension

• Little tied an interconnection customer to its LGIA,resulting in some walking away

12Law of Renewable Energy WEBINAR SERIES

Interconnection Queue Reform

• December 2007 Technical Conference– Serial study practices being slowed by new entry into queues &

speed at which projects could develop

– Interconnection delays causing trouble in meeting RPS obligations

• March 2008– Order issued as a result of technical conference

– RTOs/ISOs ordered to report status of respective queues

– Identified three needed changes:

• Increased requirements for entering the queue

• Eliminate the Feasibility Study

• First-ready, first-served vs. first-come, first-served

13Law of Renewable Energy WEBINAR SERIES

Queue Backlogs

• California ISO

– 361 pending interconnection requests (105,000 MW)

– 68,000 MW of renewable energy

– CAISO’s historic peak demand: 50,270 MW

• Southwest Power Pool

– 255 pending interconnection requests (57,000 MW)

– 50,000 MW related to wind generation (176/196 requests over twoyears)

• Midwest ISO

– 348 pending interconnection requests (80,000 MW)

– 65,000 MW related to wind generation

– Could not clear queue until 2050

14Law of Renewable Energy WEBINAR SERIES

The Results

• California ISO– Clustering with queue windows (two per year)

– 2 studies (Phase I and Phase II)

– Increased, non-refundable financial requirements

• Southwest Power Pool– 3 queues, your choice (IFS, PISIS, DISIS)

– Suspension only allowed for 18 months after Effective Date

– Shared Network Upgrades will be built upon execution

• Midwest ISO– Milestones provide “first-ready, first-to-proceed”

– No suspension for economic reasons (force majeure only)

– Once a GIA is signed, Network Upgrades will be built

– ABSOLUTELY NO AMENDMENT TO ISD

15Law of Renewable Energy WEBINAR SERIES

Risk Analysis

What are the risks in filing unexecuted?

16Law of Renewable Energy WEBINAR SERIES

Interconnection Capacity Rights

Aero Energy, 116 FERC ¶ 61,149

• Developer sought interconnection and transmissionservice on jointly-owned transmission line

• Transmission line joint owners intended to developgeneration that would use respective capacity rights

• Sagebrush claimed all but 3 MW of transmissioncapacity was reserved

• FERC stated Sagebrush partners have capacity rights, if:– Demonstrate pre-existing contractual obligations; or

– Specific expansion plans, including definitive dates, and milestones met

17Law of Renewable Energy WEBINAR SERIES

Milford Wind Corridor

129 FERC ¶ 61,149

• Milford’s Request:– 88-mile, 345 kV interconnection line with 1,000 MW capacity

– Built to serve multi-phase wind development

– Closed financing for entire line; PPA for 200 MW

– Accelerated 100 MW of Phase II

– All phases to be operational by 2015

• FERC approved request based on specific expansionplans, and material progress toward meeting milestones

18Law of Renewable Energy WEBINAR SERIES

Terra-Gen Dixie Valley

132 FERC ¶ 61,215

• Owner of the Dixie Valley Line

• 60 MW existing geothermal facility

• Sought priority rights to 360 MW

• FERC Ruling– Awarded priority to 60 MW capacity

– Remaining 300 MW subject to open access

19Law of Renewable Energy WEBINAR SERIES

Boundary Tested

Puget Sound Energy, 133 FERC ¶ 61,160

• Developing multi-phased 1,250 MW wind project

• 1,250 MW interconnection built with 350 MW Phase I

• Environmental studies; EIS; conditional use permit

• Interconnection agreement signed for 1,250 MW

• Phases IV and V targeted for 2029

• FERC Ruling– Puget may reserve to serve native load

– Line must be placed under OATT

20Law of Renewable Energy WEBINAR SERIES

Reliability Standards

• Are reliability standards mandatory?– YES10

– Generators are obligated to register

• Who is subject to registration?• Single 20 MVA unit

• Multiple units at 75 MVA

• Regardless, are you material to reliability?

• Who oversees compliance? NERC, RROs

21Law of Renewable Energy WEBINAR SERIES

WECC vs. Gen Ties

Cedar Creek Wind

• 76-miles, 230 kV tie

• Ownership change 4 milesfrom POI

• TO operatedrelaying/protection systemsat POI

• 10 x 34.5 kV, 3 x 230 kVbreakers at generator

• Registered as TO/TOP

Milford Wind Corridor

• 88-mile, 345 kV tie

• Full ownership

• Interconnecting at sub with2 GW connected

• 2 x 168 MVA GSUs on siteat generator

• Registered as TO/TOP

22Law of Renewable Energy WEBINAR SERIES

FERC Decision

Cedar Creek Wind

• Material to reliability

• CC owns/controlsequipment on one end ofthe tie line

• Must be coordinated withequipment at remote end

• Fault could lead to loss of600 MW CCGT

Milford Wind Corridor

• Material to reliability

• Owns/operates equipmentat generator

• Must be coordinated withequipment at remote end

• Fault could lead to loss of1800 MW

23Law of Renewable Energy WEBINAR SERIES

Nobody wants responsibility for a blackout

24Law of Renewable Energy WEBINAR SERIES

Transmission Service

• My facility is already interconnected, why do I needtransmission service?

– Interconnection service provides no delivery rights

– Unless your purchaser is taking power at the busbar, you willneed to purchase transmission service

• Where do I reserve and buy transmission service? OASIS

• What types of service are available?

– Point-to-point vs. Network

– Short-term vs. Long-term

– Firm vs. Non-firm

– Conditional firm

25Law of Renewable Energy WEBINAR SERIES

Transmission Service

• Are transmission providers required to treat everyone bythe same rules?– Yes, FERC Order 888 requires that transmission service be

provided on an open, non-discriminatory basis

– Transmission providers particularly may not favor affiliates

• What are the types of transmission providers?– RTOs/ITCs are independent because they do not actually own or

control electric generation resources

– Many transmission owners, however, remain as integratedtransmission and generation utilities

– Some types of transmission providers (e.g., BPA, TVA, WAPA) aresubject to limited FERC authority

26Law of Renewable Energy WEBINAR SERIES

Obtaining Transmission Service

• Are there costs associated with requesting transmission?– If the system does not have available capacity, a developer may

have to pay to upgrade the transmission system toaccommodate the requested service

• How much will transmission cost?– Integrated transmission/generation utilities may charge the

higher of:

• Incremental costs; or

• An embedded cost rate

Associated with the requested transmission service

– RTO transmission service may be priced on a different basis

27Law of Renewable Energy WEBINAR SERIES

Imbalances

• When do imbalances occur?– When the hourly generation as scheduled is different than the

actual hourly generation delivered from a facility

– Someone has to make up the difference

• How are imbalance penalties assessed?– The charges are tiered, i.e., the larger the deviation from your

schedule, the larger the charge

– Variable generators are exempt from the most expensive tier

28Law of Renewable Energy WEBINAR SERIES

Imbalances (cont.)

• How can I avoid imbalances?– Good forecasting

– Shaping & Firming arrangements whereby the supplier will takeor provide energy, as applicable, in hours when the actualgeneration differs from the scheduled amount

– Participating in applicable RTO intermittent generation protocols

– Delivering to the purchasing utility at the generation projectbusbar

– Delivering using network transmission service

29Law of Renewable Energy WEBINAR SERIES

Ancillary Services

• Purpose = products designed to maintain reliability onthe grid

• Types of Ancillary Services

30Law of Renewable Energy WEBINAR SERIES

Intra-Hour Wind Integration

• What is intra-hour wind integration service?– Some transmission providers claim that intra-hour variations in

output of intermittent resources impose added costs on thetransmission system operator

– Integration service follows variable resources with dispatchablefacilities in order to make up moment-to-moment differences ingeneration output within the scheduling hour

• Example: BPA

• Best Approach: pass the costs to your purchaser

31Law of Renewable Energy WEBINAR SERIES

FERC VER NOPR

• Issued November 18, 2010

• Comments were due March 2, 2011

• Issued to address barriers to the integration of variableenergy resources

32Law of Renewable Energy WEBINAR SERIES

FERC VER NOPR (cont.)

• FERC proposed to revise the current pro forma OATTand LGIA in three ways to address VER integration:– Intra-hour scheduling, at intervals of 15 minutes (TPs can permit

shorter scheduling intervals)

– Power production forecasting

• TP – those TPs who propose volumetric differences in the Schedule10 rate would be required to provide VER power productionforecasting

• ICs – requirement to provide meteorological and operating data tointerconnecting TPs; requirement to report forced outages reducinggenerating capacity by 1 MW or more for 15 minutes or more (SGIAexempted)

33Law of Renewable Energy WEBINAR SERIES

FERC VER NOPR (cont.)

– New Generator Regulation Service, Schedule 10, to give TPs amechanism to recover the costs of capacity used to providedgenerator regulation reserves , both for the transmissioncustomer serving load within the transmission provider’s BAAand for exports

• Applicable to all generators, but a TP may apply to FERC to chargea volumetric difference for VERs if the TP can justify that the VERsimpose a different per unit impact on the system

• BUT, no volumetric difference permitted without intra-hourscheduling and power production forecasting

34Law of Renewable Energy WEBINAR SERIES

• Pre-2009– No separate service or rate

• FY 2009– Within Hour Wind Balancing Service Rate

• $.68/kw.-mo.

• FY 2010-2011– Within-Hour Wind Balancing Service Rate

• $1.29/kw.-mo.

• Initially proposed at $2.72/kw.-mo

The Rapid Revolution of BPA’sWind Balancing Service

35Law of Renewable Energy WEBINAR SERIES

• Three components– Regulation

– Following

– Imbalance

• Based on a pre-established amount of balancingreserves

• DSO 216

• Persistent Deviation Penalty

A Closer Look at BPA’sCurrent Wind Balancing Service

36Law of Renewable Energy WEBINAR SERIES

DSO 216

• How does this fit in?– BPA monitoring inc or dec reserves deployed from the FCRPS

– Requires different responses:

• 85% deployed (warning)

• 90% deployed

– Overgeneration: wind plants must limit wind generation to theirschedule plus proportional allocation of dec reserves

– Undergeneration: wind plant schedules curtailed to actualoutput plus proportional allocation of inc reserves

• 100% deployed

– Overgeneration: wind plants limited to schedule

– Undergeneration: schedules cut to actual output

37Law of Renewable Energy WEBINAR SERIES

Source: www.bpa.gov, as of May 3, 2011

38Law of Renewable Energy WEBINAR SERIES

Source: www.bpa.gov, as of June 20, 2011

39Law of Renewable Energy WEBINAR SERIES

Source: www.bpa.gov, as of June 20, 2011

40Law of Renewable Energy WEBINAR SERIES

Environmental Redispatch

• Background – the “June Event”

• BPA issues proposal to address high water / high windevents; seeks comments

• Final Interim Record of Decision issued May 13, 2011

• Challenge pending at FERC

41Law of Renewable Energy WEBINAR SERIES

CAISO Market Changes

• Renewable Integration Market & Product Review –Phase 1; proposal:– Lower energy bid floor from -$30/MWh to -$300/MWh

– Elimination of PIRP after end of 2014; limited grandfathering

• Renewable Integration Market & Product Review –Phase 2; early stages

42Law of Renewable Energy WEBINAR SERIES

Queue Reform, Rd. 2

• Cal ISO GIP– Clearer financial security posting requirements

– Scalability issues addressed

• Midwest ISO– Tougher to proceed to DPP

– Net Zero Interconnection Service

– Dispatchable Intermittent Resource

43Law of Renewable Energy WEBINAR SERIES

Generation Transmission Linesand Permitting

• What if it’s part of generation facility?

• What if it’s an independent energy facility?

• The “but for” test: “related and supporting” or “stand alone”?

• When does a line upgrade become a new facility? Ramifications?

44Law of Renewable Energy WEBINAR SERIES

Ramifications in Permitting

• Interrelated and interdependent facilities-NEPA and otherunpleasantness

45Law of Renewable Energy WEBINAR SERIES

Locating Transmission Lines

• The pressure to co-locate transmission lines within existing corridors(new lines on existing poles; new poles)

• Logic from the perspective of permitting agencies-land disturbanceand environmental considerations

• Issues of facility control, outages and O& M

46Law of Renewable Energy WEBINAR SERIES

What’s In It for the Land Owner?

Lost opportunities, costs and agricultural impacts

47Law of Renewable Energy WEBINAR SERIES

Partnering with Utilities

• Land control – advantages of partnering with utility

• Off-site substation construction costs, engineering anddesign, and practical capabilities of “going it alone”

48Law of Renewable Energy WEBINAR SERIES

QUESTIONS?

Law of Renewable Energy

WEBINAR SERIES

PRODUCED BY EUCI ● June 23 , 2011

49Law of Renewable Energy WEBINAR SERIES

50Law of Renewable Energy WEBINAR SERIES

Recommended