Timeline Leading to Development of the Beachside Sewer System – Phase I

Preview:

DESCRIPTION

Timeline Leading to Development of the Beachside Sewer System – Phase I. October 2003 – Using Series 2003 Revenue Bonds, City acquired assets of Palm Coast Utility System from Florida Water Services including the utility “service area” - PowerPoint PPT Presentation

Citation preview

Timeline Leading to Development of the Beachside Sewer System – Phase I

• October 2003 – Using Series 2003 Revenue Bonds, City acquired assets of Palm Coast Utility System from Florida Water Services including the utility “service area”

• July 2004 – McKim and Creed completed the “Beachside Master Plan”• January 2005 – Issued a Work Order to McKim and Creed to complete design of Beachside

Master Pump Station and Force Main• February 2006 – Purchased property on A-1-A for the Master Pump Station site• December 2006 – City issued Series 2007 Revenue Bonds which included funds to construct

Beachside Sewer System• October 2009 – Flagler County decided to abandon plans to construct Beverly Beach

wastewater plant, instead connect to Palm Coast• November 2009 – Concept was presented to City Council• November 2009 – An easement to cross the intracoastal waterway was obtained from the

Dunes Community Development District• February 2010 – First draft of an Interlocal Agreement between Palm Coast and Flagler was

prepared by City staff• 2011–2012 – Beachside Sewer System is on the City council Goals and Objectives and shown as

a “High Priority” project.• June 2012 – City Council approved the Interlocal Agreement with Flagler County