Takanori SekiguchiALPS Report, Dec. 26th, 2013 1

Prototype Test of Type-B

Takanori Sekiguchi

KAGRA F2F MEETINGFeb. 2015

Takanori SekiguchiALPS Report, Dec. 26th, 2013 2

• Overview of SAS prototype test• Payload prototype test• Status & plan of full type-B test

Contents

Takanori SekiguchiALPS Report, Dec. 26th, 2013 3

Prototype Test Status

Assembly Performance

Pre-isolator

GAS filter

Payload

Full System Undergoing TBD

Pre-isolator

GAS filter

Payload

Takanori SekiguchiALPS Report, Dec. 26th, 2013 4

Payload Prototype Test

Takanori SekiguchiALPS Report, Dec. 26th, 2013 5

Payload Prototype Test in NAOJPurpose:• Check the assemblability

and feasibility• Test the local control using

OSEMs

Takanori SekiguchiALPS Report, Dec. 26th, 2013 6

Structure of payload

Bottom Filter

Intermediate Mass/Intermediate Recoil Mass

Mirror / Recoil Mass

Takanori SekiguchiALPS Report, Dec. 26th, 2013 7

(Rough) Assembly ProcedureSuspend mirror & RM

Takanori SekiguchiALPS Report, Dec. 26th, 2013 8

(Dummy) mirror suspended by φ0.2 steel wires

Recoil mass suspended by φ0.6 tungsten wires

Winches to suspend masses

Height measure to check the wire length

Takanori SekiguchiALPS Report, Dec. 26th, 2013 9

(Rough) Assembly ProcedureSuspend IM from BF

Takanori SekiguchiALPS Report, Dec. 26th, 2013 10

Tuning masses(weight control & balancing)

Takanori SekiguchiALPS Report, Dec. 26th, 2013 11

Screw to change the suspension point

Tuning pitch frequency~0.2 Hz

Takanori SekiguchiALPS Report, Dec. 26th, 2013 12

(Rough) Assembly ProcedureSuspend IRM

Takanori SekiguchiALPS Report, Dec. 26th, 2013 13

IRM (without OSEMs)Suspended by 3 wires

Screws for changing suspension points

Takanori SekiguchiALPS Report, Dec. 26th, 2013 14

Cable clip

Cabling of electrical wires

Takanori SekiguchiALPS Report, Dec. 26th, 2013 15

• Compensation masses to get enough weight for GAS filter

Feedback to the design• Separate OSEM parts for easier

assembly

… and so on.

Takanori SekiguchiALPS Report, Dec. 26th, 2013 16

Control Test

Takanori SekiguchiALPS Report, Dec. 26th, 2013 17

OSEMUnit of a shadow sensor and a coil-magnet actuator

(Current Design)

LED

PD

flag

coil

magnetlens

Takanori SekiguchiALPS Report, Dec. 26th, 2013 18

OSEMCalibration results of shadow sensors of 4 prototype units

Sensitivity: ~6.5 V/mm

Takanori SekiguchiALPS Report, Dec. 26th, 2013 19

OSEMShadow sensor noise

~ 5e-10 m/√Hz @ 10 Hz

Takanori SekiguchiALPS Report, Dec. 26th, 2013 20

OSEMActuation force by an OSEM actuator

~1.7 [N/A]

Takanori SekiguchiALPS Report, Dec. 26th, 2013 21

Actuator Diagonalization (Mirror)

X Y

Z

3 DoFs we want to sense with 4 sensors:

4 actuators we use to actuate 3 DoFs:

The actuation matrix D is improved by measurement.

1st guess

(Actuator Diagonalization)

1

2

3

4

Takanori SekiguchiALPS Report, Dec. 26th, 2013 22

Actuator Diagonalization (IM)

Z

6 DoFs we want to sense with 6 sensors:

1st guess

X

Y

5

6

78

9 10

6 actuators we use to actuate 6 DoFs:

Takanori SekiguchiALPS Report, Dec. 26th, 2013 23

Implementation in Digital SystemMEDM Screen for type-B SAS control (under development)

Sensor Matrix Actuator Matrix

Signal Flow

Signals from shadow sensors

ActuationSignals

Takanori SekiguchiALPS Report, Dec. 26th, 2013 24

Transfer functions (Mirror)

Pitch

Yaw

Length

White noise is injected to virtual actuators

Takanori SekiguchiALPS Report, Dec. 26th, 2013 25

Transfer functions (IM)

Takanori SekiguchiALPS Report, Dec. 26th, 2013 26

Damping ControlDamping servo is applied to the 6-DoF motion of IM and 3-DoF motion of the mirror

Derivative filter(viscous damping)

Takanori SekiguchiALPS Report, Dec. 26th, 2013 27

In-loop performanceOSEM signal of IM longitudinal motion

OSEM signal of IM yaw motion

3 μm 0.6 μm

30 μrad 2 μrad

Takanori SekiguchiALPS Report, Dec. 26th, 2013 28

Optical LeverOptical levers to monitor mirror angles / displacement

1W SLD

Half Mirror

QPD2

QPD1 Collimator

Takanori SekiguchiALPS Report, Dec. 26th, 2013 29

Out of loop performanceOptical lever signals about mirror pitch motion

Optical lever signals about mirror yaw motion

35 μrad 13 μrad

50 μrad 12 μrad

Takanori SekiguchiALPS Report, Dec. 26th, 2013 30

Full Type-B Test

Takanori SekiguchiALPS Report, Dec. 26th, 2013 31

Full Type-B Test@TAMA West-End Room

• Full type-B prototype will be assembled and tested in vacuum

• Overall performance is to be checked by using optical lever

Takanori SekiguchiALPS Report, Dec. 26th, 2013 32

Current Status• Vacuum system preparation• Height of the chamber is to be checked

Takanori SekiguchiALPS Report, Dec. 26th, 2013 33

Current Status• Cleaning and remanufacturing of IP base• Finished on Jan. 28

Takanori SekiguchiALPS Report, Dec. 26th, 2013 34

Current Status• Vacuum pod for geophone (seismometer) manufactured• Assembling and cabling should be done

Takanori SekiguchiALPS Report, Dec. 26th, 2013 35

Current Status• An assembly frame is designed.

Takanori SekiguchiALPS Report, Dec. 26th, 2013 36

Schedule• According to KAGRA schedule, prototype test is to

be finished until the end of March.

• Extremely tight!

Takanori SekiguchiALPS Report, Dec. 26th, 2013 37

Main Tasks

• Consider assembly procedure.• Do mechanical tuning (leveling, weight control, etc.)• Make an assembly manual (for installation of actual system)• Manufacture in-vacuum electrical cables• Design servo filter in mathematical model• Prepare digital system interface

Red: Important for KAGRAViolet: Time-consuming tasks

Takanori SekiguchiALPS Report, Dec. 26th, 2013 38

We need your help!!

• We call for KAGRA-shift

• This prototype test is an absolutely important stepin considering installation procedure of actual system, and getting more realistic plan/schedule of VIS installation

39

iKAGRA schedule 2014 2015  10 11 12 1 2 3 4 5 6 7 8 9 10 11 12Fabry-Perot-Michelson

VIS installation                                                              

Stack install   Stack                                     

MC suspension install     MC                                         

PR2 & PR3             frame/payload procurement

PR2 & PR3                      

IXA & EXA (Xarm cavity)                   

frame/payload procurement

IXA & EXA                

IYA & EYA (Yarm cavity)                      

frame/payload procurement    IYA & EYA          

BS             modifying prototype     

payload procurement

BS                      

Xarm commissioning                            

Xarm commissioning          

Full commissioning                                    Full commissioning    

Observation                                    

Obs.

                                                      

Michelson                                                               

VIS installation                                              

Stack install   Stack                                     

MC suspension install     MC                                         

PR2 & PR3             frame/payload procurement

PR2 & PR3                      

IXA & IYA                                              

EXA & EYA                   frame/payload procurement

EXA & EYA                

BS             modifying prototype     payload

procurementBS                      

Michelson commissioning                             

Michelson commissioning   

Observation                                                         Obs. 

Schedule of VIS installation: iKAGRA

Dec 2015 operation

Takanori SekiguchiALPS Report, Dec. 26th, 2013 40

END

Takanori SekiguchiALPS Report, Dec. 26th, 2013 41

Appendix

Takanori SekiguchiALPS Report, Dec. 26th, 2013 42

Close Loop TF

Recommended