PRACTICAL ASPECTSOF DEVELOPING
A CDM PROJECT
- Jinesh Amlani (Market Analyst)
- Nishikant Singh (Consultant)
- A DEVELOPER’S PERSPECTIVE
W orksho p on Carbon Credits and The Sugar Industry
1st
October, 2007
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 2/10
OVERVIEW OF THE CDM CYCLE
SelectingConsutant
Data Collection
6 weeks
Preparation of PCN/PDD
4 Weeks
Validation
14 weeks
Request forRegistration
8 weeks
Registered
Verification
(Every year)
4 weeks
Issuance
6 weeks
Trading
4 weeks
DNA Clearance – MoEF
8 weeks
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 3/10
HANDLING STEP ZERO – AN ESSENTIAL
• UNFCCC wants an official communicationthat the benefits from CDM were considered
• Best form of such an official communication isa ‘BOARD RESOLUTION’.
• The Board Resolution confirms that theProject Developer had seriously consideredthe CDM Revenue
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 4/10
ADDITIONALITY – TECHNICAL & FINANCIAL
Financial Additionality
Low Internal Rate of Return(IRR)
Difficulty in arranging finance
Technical Additionality:
Boiler above 90 kg/cm2 New Turbine design
Additionality means ‘How the project is different’
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 5/10
MONITORING ASPECTS
SUGAR DISTILLERY Quantity of Heat Generated Methane recovered using Flow Meters
Quantity of Electricity Generated Quantity of Heat / Electricity Generated
Quantity of Biomass Used COD of the spent wash before andafter treating
Should be robust &efficient
There should be a back-up for all
parameters
Any possibility of aleakage should be
considered
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 6/10
Villagers
Employees
State PCBReg. Com
Financial Inst.
LOCAL STAKEHOLDERS’ CONSULTATION
Phase I : Identifying and Inviting
Posters
Circulars
Letter
Phase II : The D Day
Attendance Sheet
Explain about CDM Invite/Take Comments
Phase III : Reviewing Comments and taking Actions
– Positive Comments : Most Welcome
– Negative Comments : Take remedial Actions
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 7/10
VALIDATION & REGISTRATION
Executive Board registers the project for a small fee
Validators validate the PDD (for a fee) and forward itto EB for registration
Four preferred Validators (DOEs) operating in India:
BVQi DNV SGS TUV-SUD
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 8/10
FINALLY !! REALIZING THE MONEY
Trading of CERs
Spot Forward
CER Certificates are issued after verification is done
Annual verification of the project has to be done by a DOE.
CER meter is down, once the project is registered.
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 9/10
LETS MAKE MOST OF
THE MOMENT…
8/9/2019 Sugar Conference Ahemdabad.gensOL Ppt
http://slidepdf.com/reader/full/sugar-conference-ahemdabadgensol-ppt 10/10
Data required for preparation of PIN & PDD Name of Project Promoters and Contact Details
Project Construction Start & Completion Date
A copy of Detailed Project Report (DPR)
Copy of Power Purchase Agreement
Copies of All Clearances Required.
Financing Details of the Project.
Subsidy element in the Project.
Copy of EIA conducted.
The projects that have been taken up by the company to become anenvironment friendly organization.
Project Promoter’s Credentials.
Comments of Ministry of Environment & Forests (if any). Social Responsibilities fulfilled by the Company.
Details of the Monitoring Equipment, used to measure steamproduction, electricity generation and export, bagasse consumed.
Name and Designation of the person monitoring the Project
Recommended