Stormwater: A New Environment

A New Strategy

Overview

• Norfolk leading in developing adaptation strategies

• Current infrastructure conditions

• New normal—rainfall conditions are changing

• Adaptation approach

• Prioritization discussion

2

Government Funding Focus

• Federal Government• Coastal & river flood risk reduction

• US Army Corps of Engineers assists local gov’t to fund floodwalls, berms, etc.• Requires 35% local match

• Commonwealth of Virginia• Stormwater

• No-interest loans and small grant program to improve water quality and control water quantity

• Local Government• Stormwater quality and quantity management

• Coastal flood management

3

Norfolk Leadership: Innovation in Action

Dutch Dialogues VIRGINIA

4

Overdue for an Upgrade

• Design Standard➢ 10 year rain event—5.5

inches of rainfall within a 24 hour period

• Current System Capacity➢ 2 year rain event—3.5 inches

of rainfall within a 24 hour period

Current Stormwater System

5

Rainfall Exceeding 2-year Rain Event

6

The New Normal

• Heavy rainfall events are increasing

• Potential 20% increase in design standard➢Today’s 10yr is tomorrow’s 6yr

event

• More than 50% of rainfall events occur during elevated tidal events➢Making it difficult to clear the

systemP. Pomerenk Dec. 2016, Trends in Rainfall…

7

Ground Conditions

PercentImpervious

Surface

• The yellow, orangeand red areas are mostly paved or hard—causing more water to run off more quickly

Current Conditions

8

Citywide Trunk-line Capacity & Condition Analysis

Low PriorityMedium PriorityHigh Priority

Current Conditions

9

Constrained Under Ground

10

Storage Zone

Infiltration Zone

Green Infrastructure Best Practices Zones

Current Conditions

• Purple areas show where water can move into the ground using raingardens, pervious pavers, etc.

• Green areas show where the water table is high so that water will sit on top rather than move into the ground.

11

Resilient Layered Strategy

Goal is to hold as much rain as close to where it falls as possible

• Retain

• Absorb

• Clean

• Release

12

New Stormwater Retention Strategy• Increase underground capacity

• Pipes to increase flow and storage

• Cisterns

• Increase above ground capacity• Ponds/Wetlands

• Restored Creeks

• Bioswales

• Rain Gardens/Corner bumpouts

• Pervious Pavement

• Cisterns

• Rain barrels

• Increase system clearing ability• Pumps and force mains

13

City Council Policy & Citizen Engagement Leading the Way

• Green Infrastructure Plan

• New Zoning Code

• Stormwater Fee Reduction program

• Vision 2100

• Retain Your Rain grants

• Adopt a drain program

• WAZE Connected Citizens Program

14

Prioritization of Stormwater Projects

Current Methodology• Problem areas

• Capacity of existing systems

• Existing infrastructure

• Location of recently completed CIP or large projects

• Private property values

• Infrastructure conditions

• Classification of road

• Critical city infrastructure

• Economic development focus area

15

Combined FY 2019 Operating and CIP Budget

Capital Projects$8,600,000

Infrastructure O&M$5,284,354

Debt Service$3,727,006

Street Sweeping$2,082,128

Engineering Program$1,883,541

Administrative Costs$1,330,571

Environmental Program$955,494

36%

4%

6%

22%

16%

9%

8%

Total FY 2019 Investment

$23.9 Million

16

Council Discussion

What keeps Norfolk viable?

• Resident Concerns• Keep our houses from flooding

• Keep mobility

• Reduce neighborhood flooding

• City Prioritization?• Keep critical transportation networks clear

• Transformational projects

• Coordinate invest with large infrastructure projects

St. Paul’s Area Transformation

Ohio Creek: Upgrading existing systems

Fairmount Park

17

New Revenue Investments

• $5M • 2 neighborhoods – master plan, trunk lines, 2 phases of construction

• St. Paul’s design & construction

• Upgrade equipment, operations and maintenance

• $10M• 4 neighborhoods - master plan, trunk lines, 3 phases of neighborhood construction

• St. Paul’s design & construction

• Upgrade equipment, operations and maintenance

• $15M• 4 neighborhoods - master plan, trunk lines, 4 phases of neighborhood construction

• St. Paul’s design & construction

• Add check valves to outfalls

• Upgrade equipment, operations and maintenance