Steel Valley School District

Preview:

DESCRIPTION

Steel Valley School District. District Feasibility Study Community Dialog June 22, 2004. Agenda. Introduction Secondary school discussion Presentation on secondary school issues Table discussion on secondary school issues Summary of table discussions Elementary School Discussion - PowerPoint PPT Presentation

Citation preview

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley School District

District Feasibility Study

Community Dialog June 22, 2004

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Agenda

1. Introduction2. Secondary school discussion

• Presentation on secondary school issues• Table discussion on secondary school issues• Summary of table discussions

3. Elementary School Discussion• Presentation on Elementary school issues• Table discussion on Elementary school issues• Summary of table discussions

4. Closing

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Study Parameters and Direction

1. Evaluate the followings items at the High School / Middle school

• Indoor athletic facilities• Auditorium• Lower level of middle school

2. Evaluate Elementary Facilities

3. Make Recommendations

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Tasks Completed to Date

1. Evaluated facilities (June 9 and June 12, 2003)

2. Questionnaires and discussion with district faculty and staff (June 13, 2003)

3. Board workshop (September 11, 2003)4. Developed options5. Draft of study delivered to district

(November 7, 2003)6. Board Workshop (February 23,2004)

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Enrollment Evaluation (PDE projections 2002 enrollments)

Year K 1-5 6-8 9-12 total

2003 - 2204 112 827 564 716 2219

2004 – 2005 115 774 537 742 2168

2005 – 2006 127 742 530 728 2127

2006 – 2007 128 713 518 737 2096

2007 – 2008 125 700 497 717 2039

2008 – 2009 123 689 490 675 1977

2009 – 2010 120 702 441 680 1943

2010 – 2011 118 709 411 651 1889

2011 – 2012 115 689 401 629 1843

2012 – 2013 113 683 421 590 1807

Note: These projections do not include the effects of the Propel charter school

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Main Issues1. Gymnasium

• Provide additional gymnasium space• Renovate existing gymnasium and locker rooms• Provide storage and concession stand

2. Auditorium• Replace seating, lighting system, stage curtain

3. Middle school • Provide additional classrooms in lower level

Steel Valley High School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Gymnasium Option 1• Construct new

gymnasium

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Gymnasium Option 2• Renovate existing

pool into gymnasium

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Renovate existing Gym and Locker rooms

• Replace and level floor• Replace Bleachers• Rearrange lockers for

proper supervision• Repair cracks• Improve ventilation• Provide second exit from

gym

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

• Provide storage and concession stand

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Auditorium

Replace seating, Lighting system, Stage curtain, Rigging

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Middle school • Provide additional classrooms in lower

level

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley High School

Secondary School Table Discussion1. Gymnasium

• Provide additional gymnasium space• Renovate existing gymnasium and

locker rooms• Provide storage and concession

stand

2. Auditorium• Replace seating, lighting system, stage curtain

3. Middle school • Provide additional classrooms in lower level

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Elementary Program

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

1. Minimal renovations to all 3 schools based on priorities on building evaluation forms.

2. Renovations required to receive reimbursement from PDE

3. Renovations and additions to Woodlawn for district wide K-5, Convert Franklin into Administrative center

4. Demolish Woodlawn, construct new district wide K-5 school, Convert Franklin into Administrative center.

5. Renovate Woodlawn to replace Park, replace Barrett for K-5, Convert Franklin int administrative center.

Options

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Option 1 Priority levels• Level 1 - items that must be done in order to

meet current building codes• Level 2 - items that are recommended to do

to enhance the learning environment• Level 3 – items that need to be completed

and will be less expensive to do as a part of a larger construction project

Options

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Primary Center

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary SchoolOption 1Priority 1

• Repair cracks, reinforce foundation walls and ventilate crawl space• Repoint masonry• Replace doors• Provide ADA Signage• Correct ADA deficiencies for toilet partitions and toilet accessories• Repair steam leaks• Repair lining of chimney• Install backflow preventer• Abandon and repair emergency battery packs or replace generator

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary SchoolOption 1Priority 2

• Repair or replace flagpole• Replace exterior doors and frames• Adequate casework in classrooms and storage• EWC’s to be provided at an appropriate height• Install second boiler• Investigate ventilation dampers/perform steam

trap maintenance• Repair fixture leaks• Replace lighting

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary SchoolOption 1Priority 2

• Provide exterior lighting• Replace toilets and urinals• Provide appropriate site lighting• Provide permanent housing for district admin to remove

trailers• Provide Location inside of classrooms for student badges• Provide extended day Kindergarten and library• Separate district admin and classrooms

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary SchoolOption 1Priority 3

• Replace windows• Replace vinyl tile• Convert to a hydronic system• Install DDC controls• Replace piping system and fixtures• Install sprinkler system• Provide new electrical service entrance• Update copper electrical distribution• Replace phone system• Replace PA system• Provide lightning protection• Replace security system• Move office to current library location to monitor entry

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary SchoolOption 2

Renovate building to receive Reimbursement• Move school functions out of administrative wing• Additions to enable removal of trailers• Provide library

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary School

Kindergarten Wing

CR CR

Library

Block Access From Admin to Elementary

District Admin Entry

District Admin Wing

School Entry

School Admin

Addition

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Franklin Elementary School• Option 3 ,4, and 5 Convert to Administrative

CenterPossible rental space – daycare – office etc.

Office of the Superintendent

Remove existing trailers

BusinessOffice

Community UseM.P. Room/FacultyTraining

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 1Priority 1

• Replace deteriorating concrete and provide handrails for exterior stairs

• Replace exterior doors with aluminum doors • Replace interior doors• Install single electrical service • Abandon and repair emergency battery packs or replace emergency

generator• Replace batteries and repair emergency lighting• Install backflow preventer• Provide site lighting• Provide electronic monitoring devices

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 1Priority 2

• Install second emergency boiler • Investigate ventilation dampers and perform steam trap

maintenance• Install backflow preventer• Repair fixture leaks• Replace lighting• Provide exterior lighting• Correct relief plenums to comply with code• Replace toilet and urinal fixtures• Relocate buzzers

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 1Priority 3

• Provide appropriate playground equipment• Provide appropriate landscaping• Replace single pane windows• Remove asbestos tile/replace vinyl flooring/repair & restore

terrazzo flooring• Repaint walls and provide for continuity of materials• Replace base where required• Provide appropriate amount of casework• Replace furnishings• Convert to a hydronic system• Install DDC controls• Replace piping systems and fixtures

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 1Priority 3

• Install sprinkler systems• Update copper distribution• Replace phone system• Replace PA system• Provide lightning protection• Replace security system

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 2

Renovate building to receive Reimbursement

Ground

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Park Elementary SchoolOption 2

Renovate building to receive Reimbursement

GroundAddition

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett Elementary

01

02

03

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

04

06

05

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

09

08

07

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

10

11

1312

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

14

15

16

17

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

19

2120

18

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

22 24

23 25

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

26 27

28 29

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

30 31

32 33

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

34 35

36 36a

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

37

39 40

38

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

41

43

42

44

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

45 46

47 48

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

49

51

50 52

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

53

54

55 56

Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett ElementaryOption 1Priority 1

• Pave parking lot• Replace handicapped ramps• Replace curbs where needed• Provide proper drainage for relocatables• Reinforce or replace retaining walls• Replace handrails• Replace fencing

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett ElementaryOption 1Priority 1

• Repair drain pans/test for IAQ problems/clean air handling units and ductwork/perform steam trap maintenance

• Install backflow preventer• Abandon and repair emergency batter packs or replace

emergency generator• Replace batteries and repair emergency lighting• Make repairs a required to meet ADA Codes

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett ElementaryOption 1Priority 2

• Replace exterior metal doors• Install second boiler• Provide chiller room ventilation• Replace chilled water pumps• Insulate hot water storage tank• Repair fixture leaks• Replace service entrance• Replace building lighting• Increase site lighting• Correct relief plenums to comply with code• Replace toilet and urinal fixtures

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett ElementaryOption 1Priority 3

• Remove relocatable classrooms and establish paved lot for parking

• Provide age appropriate play equipment• Provide landscaping as possible• Repair masonry cracks• Replace windows• Replace carpeting and VCT• Replace interior doors• Replace and provide appropriate amount of casework• Convert to a hydronic system• Replace piping and chillers • Install DDC controls

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett ElementaryOption 1Priority 3

• Replace copper piping systems and fixtures• Install sprinkler systems• Update copper distribution• Replace phone system• Replace PA systems• Replace lighting protection• Replace security systems

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett Elementary School - Option 2Renovate building to receive Reimbursement• Remove relocatables and construct addition.

AdditionAddition

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett Elementary School - Option 2Renovate building to receive Reimbursement• Remove relocatables and construct addition.

Addition

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Barrett Elementary School - Option 5

Replace Barrett Elementary

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 3

Renovate building for district wide grades K-5

CR CR CR CR

CR

CR

CR

CR

CR

CR

CR

STO

Ramp

Gym

Music

Locker

LockerCR CR

Mech

STOArt

Basement

Addition

Existing

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 3

First Floor

Addition

Existing

Cafeteria CR CR CR CR

CR

CR

CR

CR

CR

KITT

COMP LIBT

CR CR T T

Courtyard

Upper Gym

Auditorium

SGI

Elevator

Admin

Entry

CR CR

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 3

CR CR CRT T

CR CR CR CRSGI

Second Floor

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 3

Third Floor

TTCR CR CR

CR CR CR CRSGI

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

New School – Option 4

Construct new building on Woodlawn site for district wide grades K-5.

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

South Butler Primary School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

South Butler Primary School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

South Butler Primary School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

South Butler Primary School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

South Butler Primary School

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 3

Renovate Woodlawn building for grades K-5 to replace Park

Third Floor

TTCR CR CR

CR CR CR CRSGI

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Woodlawn School – Option 5

Renovate building for grades K-5

Third Floor

TTCR CR CR

CR CR CR CRSGI

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Steel Valley School DistrictElementary School Table Discussion

1. Minimal renovations to all 3 schools based on priorities on building evaluation forms.

2. Renovations required to receive reimbursement from PDE

3. Renovations and additions to Woodlawn for district wide K-5, Convert Franklin into Administrative center

4. Demolish Woodlawn, construct new district wide K-5 school, Convert Franklin into Administrative center.

5. Renovate Woodlawn to replace Park and replace Barrett for K-5, Convert Franklin into Administrative center.

Burt Hill Kosar Rittelmann AssociatesSteel Valley School District

Thank You

To View this presentation go to:

The district’s web site at SVSD.k12.pa.us

Recommended