Sir Francis Drake Boulevard€¦ · Sir Francis Drake Boulevard. Corridor Rehabilitation....

Preview:

Citation preview

Sir Francis Drake BoulevardCorridor Rehabilitation

Transportation Authority of MarinJuly 8, 2019

Item 10c - Powerpoint

35

Presenter
Presentation Notes
Call to Order – County’s opening remarks

Outline Overview of the project

Project goals and objectives

Review of project history

Review of schedule

Review examples of improvements along corridor

Review of cost estimate

Item 10c - Powerpoint

36

Project Limits

3

Item 10c - Powerpoint

37

Presenter
Presentation Notes
Dan

Project Goals and Objectives Asphalt pavement repair, replacement, and rehabilitation.

Close sidewalk gaps and improve pedestrian crossing safety.

Update traffic timing.

Improve traffic flow and reduce congestion.

Improve transit access.

Improve bicycle access and safety.

Replace MMWD aging infrastructure

Conduct an economically viable project

4

Item 10c - Powerpoint

38

Presenter
Presentation Notes
Dan

Project History TAM 2013 Strategic Plan programs Project Funding 2013-2014 Initial Studies and Surveys 2014-2016 Development of Alternatives MMWD identifies Pipeline Replacement Project 2015-present Community Meetings, Site Walks, Workshops

Formation of Advisory Committee meetings (TAC and CAC) 2017 EIR Scoping 2018 Certified EIR 2018-2019 Project Design

TODAY 75% Plans, Specs, and Estimates are complete

5

Item 10c - Powerpoint

39

Presenter
Presentation Notes
Should we include when DEIR and FEIR review periods took place

Project Schedule Summer 2019: Hire Construction Management firm

September 2019: 100% Construction Documents

Fall 2019: Bid SFDB Project

Spring 2020: Begin Construction Two years of construction

Item 10c - Powerpoint

40

La Cuesta Drive at Bon Air Shopping Ctr. Shift median on north side to allow dedicated right turn

Before After

Item 10c - Powerpoint

41

Ash Avenue Lighted crosswalk Remove U-turn lane

Item 10c - Powerpoint

42

Elm Avenue bus stop Shift bus stop closer to Elm Avenue Input from Marin or GG Transit

Item 10c - Powerpoint

43

Toussin Avenue RRFB Lighted crosswalk

Item 10c - Powerpoint

44

Corridor Rehab – Cost Summaryo $6,350,000 Pavement Rehabilitation

o $6,050,000 Intersection Reconfigurations

o $3,000,000 Traffic Signals

o $1,000,000 Signal Interconnect (future)

o $1,000,000 Miscellaneous Concrete

o $500,000 Landscape

$17,900,000 Corridor Rehab Cost (estimate at 75% CD)

Item 10c - Powerpoint

45

Total Project - Cost Summaryo $17,900,000 Corridor Rehab Project Costs

o $800,000 Street Light

o $2,100,000 MMWD Waterline Improvements

o $2,080,000 Construction Management (10%)

$22,880,000 Total Project Cost (estimate at 75% CD)

Item 10c - Powerpoint

46

Total Project – Funding Summary o $800,000 County street light construction

o $2,100,000 MMWD waterline construction

o $208,000 MMWD construction management

o $100,000 TDA grant HAWK

o $11,928,213 TAM corridor rehab

o $7,743,787 shortfall corridor rehab

$22,880,000 Total Project Cost (estimate at 75% CD)

Item 10c - Powerpoint

47

TAM Measure A – Funding Summary o $800,00 Project Planning & Outreach 06/2013

o $550,000 Environmental Clearance (EIR) 11/2016

o $1,200,000 Design 05/2018

o $11,928,213 Construction Today

$14,478,231 Total TAM Project Allocation

Item 10c - Powerpoint

48

End of Presentation

Questions?

www.marincounty.org/sfd

Item 10c - Powerpoint

49

Manor Road to Wolfe Grade At Grade Crosswalk Increase visibility of pedestrians at Manor Road Lengthen turn pockets

Item 10c - Powerpoint

50

Bon Air Road Move crosswalk to west side

Item 10c - Powerpoint

51

Eliseo Drive and Barry Way Crosswalk removed from north side of SFDB & shifted north Shift median east to allow three lanes on north side

Item 10c - Powerpoint

52

McAllister to Laurel Grove Widen sidewalk on south side Remove slip lanes

Item 10c - Powerpoint

53

Year 1 ConstructionProjects currently proposed to be built in 2020: Eliseo Drive intersection La Cuesta Drive intersection El Portal Drive intersection Bon Air Road intersection Ash & McAllister Ave Elm Avenue Bus stop Toussin Avenue ADA curb ramp replacement MMWD pipelines

Item 10c - Powerpoint

54

Year 2 ConstructionProjects proposed to be built in 2021: Corta Comada to Laurel Grove College Avenue controller replacement Median work Includes curb shift for third lane Median shift for future path on north side

between El Portal and Bon Air Road Street Lights Conduits and pull boxes for adaptive signals Pavement and striping Guardrail updates

Item 10c - Powerpoint

55

Lighting

Existing

Proposed

Item 10c - Powerpoint

56

Project Website https://www.marincounty.org/depts/pw/divisions/transportation/transportation/sir-francis-drake-boulevard-rehabilitation

Item 10c - Powerpoint

57

Segment 1: Ross Terrace to Manor RoadReplace pipeline with 7,200 feet of 6”-12” inch WSP.

Item 10c - Powerpoint

58

Segment 2 Eliseo Dr to West of 101Replace pipeline with 1,000 feet of 18 inch WSP.

Item 10c - Powerpoint

59

THIS PAGE LEFT BLANK INTENTIONALLY

60

Recommended