SHIP CONSTRUCTION, KEY NOTES FOR THIS

FASCINATING PROCESSRoberto Morante Villareal

Marine Engineer & Naval Architect

MATERIALS & MARINE STRUCTURES DEPARTMENT MANAGER

R+D

COTECMAR

Km 9 Via Mamonal - Cartagena

rmorante@cotecmar.com

roberto.omar.morante.villareal@gmail.com

SHIP CONTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

SHIPBUILDING OVERVIEW

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

KEY CONCEPTS

• Long history from the earliest beginnings of mankind

• Very traditional and conservative

• Slow introduction of change

• Basic approach is similar over the years

• Change from wood to iron to steel

• Change from oars to sail to steam with paddlewheel to propeller to diesel

• Factors impacting shipbuilding (compared to automobile and aircraft industry)Portability of the product - able to pick it up anywhere in the worldUse in world trade - product travels all over the worldFlags of convenienceForeign labor costs/conditionsWorld trade growthNational goals (policies)Relatively low labor skills required for both shipbuilding and ship operationLabor intensive with easily transferred shipbuilding skills and contribution to balance of payments makes it an attractive industry for developing countries

Relatively low investment cost.

• Shipbuilding Industry made up of many segments

• Company Types: depends on where you are in supply chain

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING

AROUND THE

WORLD

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Largest shipbuilding countries in world are Japan and Korea

each at about 33% of world demand

Europe comes in at a paltry 10%

China growing fast at 2% per year. Currently about 9%

To maintain its leading position Japan has been able to

improve productivity at an average of 7% per year over the

past 20 years.

Korean productivity is lower at 5% per year but still

impressive. U.S. shipbuilding struggles to improve at an

annual rate of 2 ½%

SHIPBUILDING AROUND THE WORLD

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

THE WORLD FLEET AS A WHOLE

Ship Type Category Number

Cargo Ships 40 000

Passenger Vessels 7 500

Naval Ships and Craft 26 500

Other Self-Propelled Vessels 42 000

Barges and Other Inshore

Vessels

238 000

Total 354 000

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING AROUND THE WORLD

THE WORLD FLEET OF NAVAL SHIPS AND CRAFT

Ship Type Category Number

Aircraft Carriers 30

Submarines 600

Large Surface Combatants 800

Small Surface Combatants 8150

Mine-Warfare Ships and Craft 1070

Amphibious-Warfare Ships and

Craft

5200

Seagoing Auxiliaries 1700

Service and Other Craft 8900

Total 26 450

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

MARINE COMPANIES AND EMPLOYMENT

Companies/

Organizations

Employment

(000s)

Industry

Sector Min. Max. Min. Max.

Ship Design 350 450 25 35

Shipbuilding 450 500 335 400

Manufacturing 800 1,000 500 800

Ship Operation 2000 3000 1750 2250

Navies 400 450 2500 2750

Ship Repair 500 600 100 120

Totals 4500 6000 5200 6355

Min/Max Range given due to uncertainty

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

MAJOR SHIPYARDS

Region Countrie

s

Yards

North America 1 3

South America 1 1

Western Europe 6 9

Eastern Europe 1 1

Asia 4 25

World Total 13 39

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

MEDIUM-SIZED SHIPYARDS

Region Countrie

s

Yards

North America 1 6

Western Europe 8 23

Eastern Europe 4 7

Asia 5 40

World Total 18 76

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SMALL SHIPYARDS

Region Countries Yards

North America 2 36

South America 5 13

Western Europe 14 144

Eastern Europe 8 37

Africa 2 10

Australasia 1 10

Asia 11 110

World Total 47 347

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

NUMBER OF SHIPS DELIVERED ANNUALLY

Country Number Revenues

(US $ Billions)

USA 5 – 8 11

Germany 30 – 40 5

Japan 175 – 250 20

Korea 150 – 200 15

China 20 - 40 2

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

European

Shipbuilding

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

GENERAL OBSERVATIONS

• The shipyards are the few private shipyards that

are still trying to compete in commercial shipbuilding.

• Their productivity is still lower than Japan but is

similar to Korea.

• Some of the shipyards have a very long history (up to

300 years) whereas some are relatively new (50 years)

• They have all been “modernized” but three of them

were the reconstructed East German Shipbuilders and

are the most modern.

•Most shipyards receive some subcontracted structural

blocks. However the Dutch carry it to the extreme of

having hulls subcontracted which they complete.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Kvaerner Masa Turku Shipyard Findland

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Flensburgh Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Volkeswerft Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Volkeswerft Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aker MTW Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aker MTW Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aker MTW Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Kvaerner Warnow Shipyard Germany

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Asian Shipbuilding

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

GENERAL OBSERVATIONS

•Japan became the world shipbuilding leader in

1960s. Taking about 30 years to accomplish it.

•Japanese shipyards have production workers of 700

to 1,200, of which up to 50% could be in-house sub

contractors.

•Japanese shipyards deliver from 5 VLCCs to 21 Bulk

Carriers per year.

•Japanese shipyard annual steel throughput is from

120,000 to 200,000 tonnes.

•Japanese shipyards, as a block, are the most

automated.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Kawasaki Shipyard Japan

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

IHI Kure Shipyard Japan

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Oshima Shipyard Japan

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Sanoyas Shipyard Japan

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Samho Shipyard Korea – Hyundai Subsidiary

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Daewoo Shipyard Korea

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Samsung Shipyard Korea

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hanjin Busan Shipyard

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

GUANGZHOU Shipyard

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHANGHAI WAIGAOQIAO Shipyard

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Dalian New Shipyard

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hyundai Shipyard Korea

The World’s Largest Shipyard

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hyundai Shipyard Korea

The World’s Largest Shipyard

MARKETS, DEMAND AND SUPPLY IN SHIPBUILDING

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

KEY CONCEPTS:

• Market Share of different types of ships - Large

Medium

Niche

• Changing value over time of different ship types per CGT

• World Shipbuilding capacity is 50% greater than demand

• Result is fierce competition and prices below construction cost

• This requires subsidies in some form or other from governments

• Korea has increased its shipbuilding capacity by 50% over 1994-96, whereas most other countries are constraining their ambitions

• China is increasing number and capacity of shipyards, and their capability in size and complexity of ships

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING MARKETS (Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DEMAND AND SUPPLY

• 40+ Million GT World shipbuilding annual capacity

• Current annual shipbuilding demand 30+ Million GT

• Demand has peaked, capacity still increasing mainly

in China but in Korea repair yards are being

converted into new construction yards.

• Competition is fierce and shipbuilding subsidies are

required by most countries

• Profit levels are low <5%

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING MARKETS

Markets Segments by Ship TypeLARGE VOLUME

Bulk Carriers

General Cargo

Tankers

INTERMEDIATE VOLUME

Container Ships

RO RO Ships

Chemical Tankers

Ferries

Reefer Ships

NICHE VOLUME

Passenger /Cruise Ships

Car Carrier

LPG Carrier

Oil/Bulk/Ore

LNG Carrier

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SUPPLY (Continued)

• Hyundai, with 6 drydocks and 16,000 workers

produces 60 to 70 ships per year.

• Daewoo, with 3 drydocks and 8,000 workers

produces 30 to 40 ships per year

• Japanese shipyards focus assembly on 1 dry-dock

and produce 6 to 8 ships per year.

• General Dynamics with two shipyards and 14000

workers produce 4 ships per year.

• Newport News Shipbuilding with 18,000 workers

produce one aircraft carrier every 4 to 5 years plus a

few submarines

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

FACTORS EFFECTING SHIPBUILDING MARKETS,

DEMAND AND SUPPLY

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

FACTORS AFFECTING SHIPBUILDING MARKETS,

DEMAND AND SUPPLY

• Freight rates and scrapping rates depend on surplus

Tonnage.

• Surplus tonnage for tankers is reducing and, of course, is

impacted by the double hull requirement

• Surplus for bulk carriers is at ten year higher.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DESIGN FOR

PRODUCTION

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

ProductionDesign

• concurrent

• interactive

cost

time

created

determined

DESIGN AND PRODUCTION MUST WORK INTERACTIVELY

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DFP PRINCIPLES

There are two main principles for DFP for ships, namely 1)

all design should strive for simplicity, and 2) all design should

be the best suitable for a given shipyard facility.

These can be further expanded as follows:

Simplicity in Design•reduction in joint weld length,

•minimum number of parts,

•minimum number of parts to be formed,

•part standardization,

•reduction of part variability,

•minimum fitting/fairing of erection joints,

•elimination of need for highly accurate fitting,

•integration of structure and outfit,

•elimination of need for staging, and

•consideration of access.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DFP PRINCIPLES (Continued)

Matching to Shipyard Facilities

•checking that blocks and machinery package units and

outfitted blocks are within shipyard lifting capability,

•assembly and block sizes fit panel line, workstations and

door openings,

•use maximum plate sizes and corresponding block breaks

to minimize connecting joint weld length, and

•maximize design for in-shop versus on-ship work.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DFP IN BASIC DESIGN

HULL FORM USAGE

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

• Merchant Ship

• Naval & Coast Guard Vessel

• Recreational Vessel

• Utility Tugs

• Research & Environmental Ship

• Ferries

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DFP IN BASIC DESIGN

HULL FORM BY SUPPORT

TYPE

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

• Aerostatic Support

- ACV (Air Cushion Vehicles)

- SES (Captured Air Bubble)

• Hydrodynamic Support

- Hydrofoil

- HYSWAS (HYdrodynamic Small Waterplane

Area Ship)

-Planning Hull

• Hydrostatic Support

- Conventional Ship

- Catamaran

- SWATH (Small Waterplane Area Twin Hull)

- Deep Displacement

• Submarine

- Submarine

- AUV/ROV

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aerostatic Support

- Supported by cushion of air generated by a

fan.

- ACV (Air Cushion Vehicle)

hull material : rubber

propeller : placed on the deck

amphibious operation

- SES (Surface Effect Ship)

side hull : rigid wall(steel or FRP)

bow : skirt

propulsion system : water jet propulsion,

supercavitating propeller, not amphibious

operation

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aerostatic Support

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

E

Aerostatic Support

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Aerostatic Support

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Planning Hull- supported by the hydrodynamic pressure developed under the hull at high speed

- V or flat type shape- commonly used in pleasure boat, patrol boat,

missile boat, racing boat

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrofoil Ship

- supported by a hydrofoil, like wing on an

aircraft

- fully submerged hydrofoil ship

- surface piercing hydrofoil ship

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrodynamic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic Support

• Displacement ship

- conventional type of ship

- carries high payload

- low speed

• SWATH - small waterplane area twin hull (SWATH)

- low wave-making resistance

- excellent roll stability

- large open deck

- disadvantage : deep draft and cost

• Catamaran/Trimaran

- twin hull

- other characteristics are similar to SWATH

• Submarine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Hydrostatic SupportSHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

DFP IN BASIC DESIGN

HULL FORM DEVELOPMENT

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

The Design Spiral

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ship Hull Form and Geometry

• Since the ship is a 3-dimensional shape, data

in x, y and z directions is necessary to

represent the ship hull.

•Table of Offsets

•Lines

- body plan (front View)

- shear plan (side view)

- half breadth plan (top view)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Figure 2.2 - The Projection of Lines onto 3 Orthogonal Planes

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Figure 2.3 - The Half-Breadth Plan

Intersection of planes (waterlines) parallel to the

baseline (keel).

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Figure 2.4 - The Sheer Plan

Intersection of planes (buttock lines) parallel to the

centerline plane

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Figure 2.6 - The Body Plan

Intersection of planes to define section line

Sectional lines show the true shape of the hull

form

Forward sections from amidships : R.H.S.

Aft sections from amid ship : L.H.S.

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP SURFACE FAIRING

• Maximize parallel body

• Maximize flat of bottom and flat of side

• Use a straight line stem profile

• Use a flat vertical transom

• Make sure the forefoot shape has fair frame lines

• Select a bilge radius so that one plate width can

handle bilge strake

• Eliminate shape that forces decision to use

castings in the stem and stern

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

EconoForm: Entirely flat or conical surfaces, patented in 1999

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Fishing vessel Tug

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ship Hull Form and Geometry

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

DESIGN/PRODUCTION

INTERFACES

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Design/Production Interfaces

• Implementation of the Build Strategy in order to:

Prepare a design that takes into account agreed

processes, facilities and equipment

design out non-value work

ensure integration of steel and outfit work to give

shortest delivery schedule

increase STANDARDIZATION

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Design/Production Interfaces (Continued)

• Definition of processes and standards to allow simple of

effective planning systems to be used.

• Development of Interim Product System

• Production simplification

• Definition of optimum methods based on existing

facilities and equipment to maximize flowline production

• Identification of facility and equipment changes that will

improve productivity

• Communication of change to technical and planning

functions

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Design/Production Integration (Continued)These can be seen in the following current shipbuilding

practices:

Use of 3D product model as design/ production integrator,

Product-oriented Work Breakdown Structures (PWBS),

Intermediate product catalogs/databases,

Development of Shipbuilding Policies,

Use of Build Strategies,

Preparation of engineering as workstation informationpackages,

Use of Concurrent Engineering and associated teams toensure design/production engineering, and

The use of design build plans by the most recentdesign/planning

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

Engineering for Ship Production (Cont.)SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering

for Ship

Production

(Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering

for Ship

Production

(Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering

for Ship

Production

(Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering

for Ship

Production

(Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering

for Ship

Production

(Continued)

     

BLOCK A MEGA-BLOCK B + C BLOCK D BLOCK E BLOCK F

Vosper Thornycroft

BAE Marine Barrow

BAE Marine Govan

UK MOD TYPE 45 SHIP GRAND BLOCK BREAKDOWN

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Engineering for Ship Production (Cont.)

UK MOD TYPE 45 SHIP BOW GRAND BLOCK

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

UK MOD TYPE 45 SHIP BOW GRAND BLOCK

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

UK MOD TYPE 45 BOW SECTION DESTROYER

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

UK MOD TYPE 45 MID BODY DESTROYER

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

COMPLETED UK TYPE 45 DESTROYER

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SPANISH FRIGATE BLOCK BREAKDOWN

Spanish Built Norwegian Frigate Block Breakdown

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

NAVAL SHIP ON-BLOCK OUTFITTING

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

NAVAL SHIP ON-BLOCK OUTFITTING

B&V Construction inside a Covered Floating Dry-dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING PROCESS

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING PROCESSES

• The shipbuilding process consists of fabricating raw

material into ship parts and assembling them, along

with purchased equipment and components (interim

products) to produce the finished product, namely the

ship.

• All shipyards have the same basic processes.

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPBUILDING PROCESSES

NON-CONSTRUCTION CONTRUCTIONAdministering StoringManaging HandlingMarketing PreparingDesigning CuttingEstimating FabricatingContracting WeldingEngineering AssemblingPlanning Block ConstructingOrdering/Buying Block Outfitting & PaintingManaging Material Block ErectingDelivering Zone OutfittingGuaranteeing Launching

Testing

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPYARD PROCESSES (Continued)

• Processing Equipment Structure

Blast & Prime

Cut and Mark

Plate Forming

Shape Forming

Panel Line

Assembly Line

Block Line

Curved Block Assembly

• Processing Equipment Pipe

Cutting

Flanging

Bending

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Structural Plate Parts

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Pipe Pieces

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Structural Profiles

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hull Fitting Parts

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Slot Web Frame System

Split Double Bottom Block Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Subassembly Pallets

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Block Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Assembly

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Curved Block Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Large Block being Outfitted

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Block Assembly Jig

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Outfitted Block Being Erected in Building Dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Being Outfitted

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Assembly

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Assembly

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Assembly

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Modern Covered Inclined Building Berth

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Building Dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Elevator for Mega Block Movement to Building Dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

A Very Heavy Lift Movement (14000 t)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Subcontracted Blocks (Some Outfitted) delivered on Barge

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Subcontracted Blocks (Some Outfitted) delivered on Barge

ZONE OUTFITTING

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

• Zone Construction is a management methodology based on organizing work by Zone rather than by System.

• Zone Construction relies as much on who does the planning, scheduling and control, as the actual tools and techniques for organizing the work.

• The intent of breaking the ship down into Zones is to reduce the management tasks in size by being “Product-oriented” rather than System-oriented.

• Zone construction may or may not use Advanced Outfitting.

ZONE CONSTRUCTION

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

The benefits of Zone Outfitting are:

• Reduced Work Package size and scope, by focusing on Zones rather that the ship or large portions of it.

• This results in a level that an individual is more capable of understanding and managing.

• Forcing all departments to pay attention to the planning and interfaces in which they are involved.

• Forcing Production to take an active role early in the product development.

• Promoting the use of multi-skilled teams.

• Engineering provides technical documentation that supports Zone Outfitting.

ZONE CONSTRUCTION (Continued)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

ADVANCED OUTFITTING

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

ADVANCED OUTFITTING

• It is the fitting to ship structure, before and after it is erected on the building berth, of outfit items at a significantly earlier time in the building sequence than is traditional.

• The organization of information and materials to a plan that applies labor and facilities to integrate ship’s structure and outfit materials at the earliest and most cost effective stage of the construction process.

• Advanced Outfitting is normally divided into three types, namely: On Unit On Block On Board

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

ADVANCED OUTFITTING (Continued)GOALS• Minimize on board outfitting• Reduce outfitting time thus total building time• Simplify outfit planning• Avoid interference between trades• Improve material handling• Improved use of cranes• Improved quality, productivity and worker safetyBENEFITS• Reduced/eliminated overhead work• Improved access, (workers and material) ventilation and

lighting• Reduced/eliminated scaffolding• Reduced/eliminated on board services• Improved tool/equipment availability

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

On-block Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

On-block Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

On-block Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Finish On-block Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Finish On-block Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Modular cabin Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Multilevel On-unit Advanced Outfitting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

LAUNCHING METHODS

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

End Inclined Sliding Launch

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

End Inclined Sliding Launch

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Launching Ways and Cribbing

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Rotating Fore Poppet

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Stern Cribbing and Shoring

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Center Ground Way with Teflon Strips

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Center Way Crushing Strip Fore Poppet

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Side Launching

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Side launching Excitement

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

To Have a Canal –> Will Build ships

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ship In Floating Dock Prior to Launch

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ingalls Launching Sequence

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Submersible Barge Launching System

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Getting the Foot out of the Shoe – Launching from Building Dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Building Ledge and Dry-dock

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Multiple Repair Ledges for Overflooding

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIPYARD EQUIPMENT

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Plates Leaving Blast and Prime Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling – Automated Guided Vehicle (AGV)

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Plasma Cutting and Marking Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Laser Cutting and Marking Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Automated Milling Machine – Two plates at a time

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Panel Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Laser Welding Panel Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Laser Welding Panel Line

Two Large Panel Lines

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Special Panel Turnover Device for Two-sided Welding

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling – Profile Magazine – pre-processing

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling – Profile Magazine – post-processing

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Profile Cutting and Marking Line with Conveyors

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling and Robotic Arm for Profile Cutting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Same Robotic Arm used for Welding and Cutting

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Semi Automatic Stiffener Fit and Tack Weld Station

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Sub Assembly Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Long Plate Butt and Girder Fillet Laser Welding Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Double Bottom Welding Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Material Handling for Robotic Tack Welding Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Stiffener Handling and Tack Welding

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Welding Subassembly Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Double Hull Welding Workstation

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Double Hull Welding Line

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Double Hull Welding Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Robotic Welding Machine Working with Curved Panels

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Rolls for Shaping Plate with Single or Minimum Double Curvature

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Ring Press for Shaping Plate with Double Curvature

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Hydraulic CNC Frame Bender

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Plate Shaping by Line-heating

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Early Tilt Table for Welding Curved Plate Panels

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Moving Curved Block Line – Pin Jigs on Platforms

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Modern (In Line) Tilt Table for Welding Curved Plate Panels

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Modern (In Line) Tilt Table for Welding Curved Plate Panels

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Pipe Stowage Magazine – pre processing

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Pipe Bending Machine

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling Automation – Conveyor Systems

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Material Handling Building Dock gantry/Goliath Cranes

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

Grand Block Elevator

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS Roberto Morante Villareal

THANKS

SHIP CONSTRUCTION, KEY NOTES FOR THIS FASCINATING PROCESS

Roberto Morante Villareal

Marine Engineer & Naval Architect

MARINE STRUCTURES & MATERIALS DEPARTMENT MANAGER

rmorante@cotecmar.com

roberto.omar.morante.villareal@gmail.com