ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011

Preview:

Citation preview

ROB at Koratty in lieu of LC No.54

Progress as on 3.6.2011

www.rbdck.com

Project Details

2

Total Length-423m

Carriage way width -7.5m

Foot path-1.5m wide on one side only

Railway span-42m (ie 11.27+21+10.53)

Approach span-134m(26+4x27)

Solid ramp portion

Pulikkakadavu side-107m,RE wall-71.65m

NH side -140m,RE wall-76m

Site Engineer :Santhosh G ,KITCO Manager :Jemymathew, RBDCK ,9447078783

3

•Consultant: KITCO Ltd

•Contractor : Cherian Varkey Construction Company Pvt Ltd

Manager in Charge RBDCK: JemyMathew, Contact No.

9447078783

Project Engineer KITCO :Santhosh G Contact

No:9447384217

Site Engineer CVCC: Shaji.M ,Contact No:9747004340

Site Engineer :Santhosh G ,KITCO Manager :Jemymathew, RBDCK ,9447078783

Progress graph as on 3.6.2011

5

SlNoActivity -Description

Total Quantity

Cumulative progress up to this week(1)

Balance work(2)

Cumulative delay in weeks afterSpplagmnt(3)

Work planned during the week(4)

Actual work done during the last week(5)

Short fall in the last week (6)

Work Planned for next week(7)

No of days remaing for completion as per the weekly plan

Remarks

1 Re wall towards NH side 100% 34 66 27 RR work 0 0 0 19 .

3Approach Span 5 4 1 33 - - - -

4 Pier cap 2no 1 3 36 0 0 0 0 18

5Pile (Rly)pulikakadavu side

4 4 5 55 0 0 0 0 02

6 Pile (Rly)Nh side 4 4 5 55 0 0 0 0 02

7 Piers (Rly) 2No 1 3 46 0 0 0 0

2nd lift of pier concreting at p1 completed

SlNoActivity -Description

Total Quantity

Cumulative progress up to this week(1)

Balance work(2)

Cumulative delay in weeks afterSpplagmnt(3)

Work planned during the week(4)

Actual work done during the last week(5)

Short fall in the last week (6)

Work Planned for next week(7)

No of days remaing for completion as per the weekly plan

Remarks

8R0AD WORK{WBM} towards pulikkakadavu side

100% 90% 0

9GIRDER(LAND SPAN)P2-P3 span

3 3 1 1 0 0 41 1st stage stressing over

10 P2-P3 span Shuttering of deck slab

Concreting of deck slab P2-P3

shuttering work of the deck slab of P2-P3 in progress

Concreting of deck slab on 10-6-2011

Heavy rain hampering the work in P2-P3 Span

11 Diaphram wall(P2-P3)

Reinforcement work completed

Concreting of end diaphragms

Concreting of two end diaphragms completed successfully

Work completed as planned

12RR work in the approach portion of Nh side

50

Re wall ,Kerb and hand rail towards Pulikkakadavu side completed

Activities which cannot be completed without caution

1 Pile 10Nos Pier -2Nos

Pier Cap-2 Nos

Deck -3slab

RR MASONRY WORK IN THE APPROACH PORTION IN THE N.H SIDE COMPLETED UPTO 50%.

THE BALANCE WORK IS PLANNED IN THE NEXT WEEK.

Material Stocking StatusCoarse Aggreagate (m3) 12 30 Remarks Fine Aggreagate(m3) 13 20 . Cement(bag) 25 34 Steel(MT) 7 11

Utility shifting Utilities to be shifted Status Remarks BSNL KSEB no hindrance KWA .

Others No hindrance i

10Site Engineer :Santhosh .G KITCO Manager :Jemymathew,

RBDCK ,9447078783

DATE 28-5-2011 30-5-2011 31-5-2011 01-06-2011 02-06-2011 03-06-2011

Weather hot Hot sunny RAINY RAINY RAINY

Climate

Labour Details

Date Labours

RR work at P1

Span P2-P3

Beam work

Mechanic and operators

Pier reinforcement

Total

28-05-2011 0 0 11 4 0 15

30-5-2011 0 0 12 4 0 16

31-5-2011 0 0 11 4 0 16

01-6-2011 0 6 12 3 0 21

02-6-.2011 0 6 12 3 0 21

03-6-2011 0 6 12 3 0 21

zSl.No

Date Activity

1 28-5-2011 1.Concreting of 1st end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3

2 30-5-2011 1.Concreting of 2nd end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3

3 31-5-.2011

1.Shuttering work of deck slab of span P2-P3

4 01-06-2011 1.Shuttering and reinforcement work of deck slab of span P2-P3

2. RR masonry work near P1 location.

5

6

02-6-2011

3-6-2011

1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location.

.

1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location.

Daily Activity Report

Work Done during last monthSl No Activity

Week 1 up to 6.6.2011

3rd Girder of P3-P2 span concreting

Week 2 up to 13.6.2011

1)Concreting of Pier P1 Ist lift (Approximately 2m) done.2)Premix bituminous work Ist layer completed at Pulikkakadavu side at the approach portion.

Week 3 up to 20.6.2011

1) 1st stage stressing completed for all three beams of the span P2-P3

2)Reinforcement and shuttering work of Cross beam or end diaphragm of the span P2-P3

3)Grouting of the ducts of all the beams in the span P2-P3.

Week 4 up to 27.5.2011

RR work and 2nd lift of Pier P1

Week 5 up to 3.6.2011

Diaphram wall concreting and RR work,Stagging work of deck slab

SHUTTERING OF DECK SLAB AT P2-P3

END DIAPHRAGM CONCRETE P2-P3 SPAN

SHUTTERING WORK OF DECK SLAB P2-P3 SPAN

HEAVY RAIN AT KORATTY

RR MASONRY AT P1-1.6.2011

RR MASONRY AT P1 2.6.2011

SHUTTERING OF DECK SLAB AT P2-P3

SHUTTERING OF DECK SLAB AT P2-P3