PS - SPS days 18th January 2006. SPS Activities & Hardware Commissioning. Table of content. Short summary main activities 2005 Planning review : Remaining site activities Hardware tests Start up organisation SPS team Some pictures Final words…. Completed activities 2005. Magnets - PowerPoint PPT Presentation
Citation preview
Nicolas GILBERT (AB-ABP) 1January 18th, 2006
PS - SPS days18th January 2006
PS - SPS days18th January 2006
SPS Activities&
Hardware Commissioning
Nicolas GILBERT (AB-ABP) 2January 18th, 2006
Table of contentTable of content
Short summary main activities 2005
Planning review :– Remaining site activities
– Hardware tests
Start up organisation SPS team
Some pictures
Final words…
Nicolas GILBERT (AB-ABP) 3January 18th, 2006
Completed activities 2005Completed activities 2005
Magnets– Replacement quadrupole jacks (ring magnets)
Beam transfer– LSS4 : replacement MSE protection element (TPSG4 beam diluter)
– LSS6 : major upgrade extraction channel (fast extraction to LHC), including new
septa protection (TPSG6) and 4 MKEs
– New bumper configuration in LSS6
– New transfer line configuration for TI2 (+ old T1 removed)
Beam instrumentation (mainly SPS points 4, 5 and 6)– New BIPMH in LSS5
– Instrumentation moves (BSHV, BPSM, BRCV, …)
– Removal all BI monitors in TT60 (obsolete slow extraction to West Area)
Nicolas GILBERT (AB-ABP) 4January 18th, 2006
Completed activities 2005Completed activities 2005
RF : Upgrade of SPS damper in LSS2
Experiment : Removal of the 2 Roman Pots in LSS5 (LHC experiment
TOTEM)
Civil Engineering : Vault repair in LSS3 (lots of contributions !)
Support– AT/VAC : frequent interventions (beam line configurations, access,
removal TAL 11431, …)
– SC/RP : control during access to tunnel
– TS/SU : general check alignments, altimetry, …
– TS/CV : various interventions on cooling networks & ventilation ducts
– TS/EL : change of irradiated cables in LSS6, as well as in TDC2 including removal of PVC cables
– TS/IC – HM : involved in all transport issues
Nicolas GILBERT (AB-ABP) 5January 18th, 2006
SPS planningSPS planning
patrols
Nicolas GILBERT (AB-ABP) 6January 18th, 2006
Start up organisationStart up organisation
Weekly SPS coordination meetings from January
Short daily coordination meeting once SPS access
restricted (from feb.) with directly concerned people
Regular SPS planning update, available under
Web/EDMS
Major update of SPS drawings (more than 250 updated layout
drawings up to now by TS/MME) available soon in CDD
Nicolas GILBERT (AB-ABP) 7January 18th, 2006
Some pictures …Some pictures …
TIDVG : upgraded version to be installed in LSS1
Nicolas GILBERT (AB-ABP) 8January 18th, 2006
Some pictures …Some pictures …
The Roman Pot set- up during test beam in the SPS in summer 2004
Now removed from ECX5
Nicolas GILBERT (AB-ABP) 9January 18th, 2006
Some pictures …Some pictures …
TPSG6/MST
(July 2005)
TPSG4
TPSG6/MST
(Jan 2006)
SPS Extraction line
Nicolas GILBERT (AB-ABP) 10January 18th, 2006
Some pictures …Some pictures …
MOPOS consolidation : Passive RC component in original adapter replaced by PCB
About 250 adaptors (=125 MOPOS) to be replaced early 2006
Nicolas GILBERT (AB-ABP) 11January 18th, 2006
Final words…Final words…
Useful info :– BT & BI contribution to SLI project see EDMS see EDMS
624554624554– MOPOS activities see EDMS 679896see EDMS 679896 – LSS3 vault repair see EDMS 675246 see EDMS 675246 – SPS detailed planning see EDMS 476624see EDMS 476624
Specials Thanks to :– Alan Spinks (SPS technical coordination)
– Jose Monteiro (SPS planning)
– SPS team (AB & AT divisions)