Project Management for Renovating Department Store
CaseStudy : Tesco Lotus on Saraburin Branch
1* 2 3
E-mail: Kearttisak76@hotmail.com1*s.rakkarn2010@gmail.com2 praponiekbu@gmail.com3
Kesrttisak See-on1*SakchaiRakkarn2 Prapon Srihomchai3
Master of Engineering Program, Department of Engineering Management
Graduate School, Kasem Bundit University E-mail: Kearttisak76@hotmail.com1*s.rakkarn2010@gmail.com2 praponiekbu@gmail.com3
Tesco Lotus
Tesco Lotus Tesco Lotusextra
Tesco Lotus
PERT/CPM Microsoft Project
Microsoft Project
176 27,830 Microsoft Project
3 3 27,230 120 150
Microsoft project 139 28,740 180 240
Microsoft project 221 27,450
165 Microsoft project 157 Microsoft project
3
. . 2556 16-18 2556
Microsoft project
PERT/CPM
Abstract
This paper is concerned about the study of project management for renovating of Tesco Lotus
department store in Saraburi Branch. The job delivery problem is not on time under the resource management of operation time, labor and machines/equipments. These conditions originate from no good
planning. So, we aim to renovate Tesco Lotus becomes Tesco Lotus Extra within delivery time. Applying
the PERT/CPM technique is analyzed for project management by Microsoft Project program. The historical data of 3 branchs is applied by Pharam 3, Bangna and Nawanakhorn branch. The results of
delivery time planning are improved about 60-70%. Therefore, the planning result of Tesco Lotus in Saraburi branch will spend 176 days, which suppose to be very closed operation time in practical.
Keywords: PERT/CPM, Renovate Planning, Tesco Lotus Extra
1.
Tesco Lotus
Tesco Lotus Tesco Lotusextra
[1]
Tesco Lotus
Microsoft Project
PERT/CPM
[2], [3], [4]
2.
2.1 PERT
CPM
PERT CPM
[5]
. . 2556 16-18 2556
1) (Gantt Chart)
A.
B.
C. D.
1 2 3 4 5 6
( ) 1 Gantt Chart
A. 2
1 3 B. 2
PERT CPM
2) PERT CPM
3) (Network)
(Network)
PERT CPM
4)
5) PERT CPM
CPM
2
ES
LS
EF LF
TF FF
t
Earliest start time
latest start time
earliest finish time latest finish time
total float free float
time
6)
a.
b.
c.
1
d.
3
e.
[6],[7],[8]
2.2 Microsoft
Project Microsoft Project
Microsoft Office
[9]
3. /
. . 2556 16-18 2556
2
3.1
3.2
1.
2.
3.
4. /
2
Microsoft Project
Microsoft project
27,830
176
4
( . ) ( )
Sale area 8,300 122
Gross lease 6,310 130
Food court 1,180 103
Back office 2,740 54
Parking 4,850 107
Motorcycle 200 14
Car service 470 28
Car wash 140 28
27,830 176
3
1 27,830 sqm. 27,830 sqm.
2 11,390 sqm. 8,300 sqm.
3 3,962 sqm. 7,230 sqm.
4 2,280 sqm. 4,500 sqm.
5 + Kiosk 137 sqm. 140 sqm.
6 756 sqm. 1,370 sqm.
7 4,272 sqm. 3,480 sqm.
8 809 units 890 units
9 179 units 200 units
10 - sqm. 476 sqm.
11 357 sqm. 140 sqm.
. . 2556 16-18 2556
150 139 240 221 165 157050100150200250300
3
4.1 Microsoft
project Microsoft project
176
1
13 13 8,600
2
Stationary, Bikes, Toys, OS Lease Shop 2 13
8
163
4.2
Microsoft project
Microsoft project
5
/
1.
3
4 4 620 1
2.
6 6 650 2
3.
3 4 600 1.5
4 3
Microsoft project
5
5.1
Microsoft Project
. . 2556 16-18 2556
5.2
Microsoft Project
2 1)
3
Appliance and Electronic, Check Stand, New
Customer Toilet
13 8,600
2)
Stationary, Bikes,
Toys, OS Lease Shop 2 13 8
163
Microsoft project
Microsoft project
1) 3
120
150 Microsoft
project 139
2)
180
240 Microsoft
project 221
3)
120
165
Microsoft project
157
(Project
Time Management)
(Project Risk management)
(Project Quality
Management)
(Project Scope Management)
[10]
[1] . 2555. :
. 2 2 -
2549. 204 � 219
[2] . 2553.
. 13 � 31 [3] . 2549.
Microsoft Project .
[4] . . 2530. MBASIC . . -
2527. 43-53
[5] . 2555. .
. .
. . 2556 16-18 2556
[6] . 2541.
CPM PERT. : [7] . . CPM & PERT
:
[8] . . CPM PERT. :
. .
[9] . 2555. Microsoft Project. :
[10] . ,
.