Project Kick-off Meeting

Preview:

DESCRIPTION

Project Kick-off Meeting. INTHEAT. Professor Robin Smith Process Integration Limited. Manchester 17 December 2010. History of the Project. Background research and collaboration: EPSRC project (UK) in heat transfer intensification (2009 – 2011) Initiated by UNIMAN, PIL and CALGAVIN mid 2009 - PowerPoint PPT Presentation

Citation preview

Project Kick-off MeetingProfessor Robin Smith

Process Integration Limited

Manchester 17 December 2010

History of the Project

• Background research and collaboration: EPSRC project (UK) in heat transfer intensification (2009 – 2011)

• Initiated by UNIMAN, PIL and CALGAVIN mid 2009• PIL assumed coordinating role (mid 2009)• Submitted to FP7-SME-2010-1 (Dec 2009)• Invitation to commence contract negotiations

(March 2010)• Negotiations completed end September 2010• Project commenced 1 December 2010

Project Overview

Intensified Heat Transfer Technologiesfor Enhanced Heat Recovery - INTHEAT

Contract number: 262205

Starting date: 1 December 2010

Duration: 24 months

Project Objectives• Enhancing our understanding of heat exchange under

fouling • Technical innovation for heat transfer intensification for

heat recovery • Proposing new materials of improved economic and

environmental performance as heat transfer media (with focus on advanced heat exchanger with polymer materials

• Combining enhanced heat transfer innovative design with process integration to achieve the synergy of novel technologies

• Demonstration of applicability and economic-environmental benefit of novel heat-transfer enhancement techniques and the new design methods proposed

• Effective technology transfer to the wide range academic and industrial communities

Partners

• Process Integration Limited (PIL), UK• Cal Gavin Limited (CALGAVIN), UK• Akstionernoe Obshchestvo ‘Sodrugestvo-T’ (SODRU),

Ukraine• Makatec Apparate GmbH (MAKATEC), Germany• Oikos, svetovanje za razvoj, d.o.o. (OIKOS), Slovenia• The University of Manchester (UNIMAN), UK• University of Bath (UNIBATH), UK• Paderborn University (UPB), Germany• University of Pannonia (UNIPAN), Hungary• EMbaffle B.V. (EMBAFFLE), The Netherlands

Work Package Structure

Demonstration

WP 1Analysis of intensified heat

transfer under fouling

WP 2Combined tube-side and shell-side heat exchanger

enhancement

WP 3Heat Exchangers made of

Plastic Materials

WP 4Design, retrofit and control of

intensified heat recovery networks

WP 5Putting into practice

WP 6Technology transfer

WP 7Management

RTD

Exploitation

Management

Contract specific terms

• Duration of the project is 24 months• Commencement date: 1 December 2010• Maximum financial contribution by EC:

EUR 1,155,000• Pre-financing at the level of EUR 693,000

(minus Guarantee Fund EUR 57,750)• Reporting periods:

– P1 from month 1 to month 9– P2 from month 10 to the last month of the project

Contract specific terms

• Applicable law: terms of GA, EC and EU acts related to FP7, Financial Regulation application to the general budget and other EC and EU law, and on subsidiary basis, the law of Belgium

• Communication with EC through the coordinator

Contract specific terms

Review number

Tentative timing Planned venue of review

Comments, if any

1Mid-term review meeting to be done after Month 11

Brussels

RP1 (Month 9) + 75 days Go/No-go decisions will be based on the performance of the developed materials by Month 9 Overall project review Monitoring WP progress and collaboration Risk analysis/contingency measures Corrective actions if neededWPs involved: WP1, WP2, WP3, WP6, WP7

2Final review meeting within Month 26

Manchester

Fine tuning of draft final reports (submitted in advance - 10 days berore) will be discussed Overall project review WP outcome (research, dissemination) review Exploitation WPs involved: WP4, WP5, WP6, WP7

MilestonesMilestone number

Milestone name WP numbers Lead benefi ciary number

Delivery date from Annex

Comments

M1.1 Fouling mitigation research completed

WP1

7 UNIBATH

Month 12 Complete set of experiments

accomplished and mathematical models

verified

M2.1 Software modules implementing tube- and shell side enhancement developed

WP2

CALGAVIN

Month 18 Beta version tested

M3.1 Optimised design spiral wound plastic heat exchanger

WP3

MAKATEC

Month20 Experimental comparison of prototype with

standard type , and mathematical models

verified

M4.1 Retrofit methodology for heat exchanger networks prone to fouling deposition developed

WP4

6 UNIMAN

Month 20 Report submitted

MilestonesM4.2 Software tool for

screening and analysis design and retrofit HEN options taking into account the intensified heat exchanger parameters

WP4

6 UNIMAN

Month 24 Beta version developed and tested, user guide printed

M5.1 Case studies for methodology application in chemical, refinery and food industries carried out

WP5

1 PIL

Month 24 Report submitted

M6.1 Training Workshop WP6 9 UNIPAN Month 18 Workshop completed

M6.2 Four Dissemination events attracting the European clusters carried out

WP6

9 UNIPAN

Month 8, 12, 18, 22

Four Dissemination event completed

Project Deliverables

• 19 deliverables of them 7 confidential, 12 public

• Deliverables shall be submitted to EU within 45 days following the end of the planned date

• The coordinator will distribute the template for the project deliverables in January

• Lead participant: Coordinates the preparation of the Deliverables, ensures contribution from partners is prepared on time, ensures quality of Deliverable

Project Deliverables

Need to be submitted using the electronic system

Financial Guidelines

• Each SME (Contractor) should sign a sub-contracting agreement with RTD Partners (Sub-Contractors) who carry out the research work for them.

• The Coordinator will circulate draft sub-contracting agreement in next few days.

Financial GuidelinesSuggested distribution of sub-contracting payments

in line with the DoW’s Tables A3 and B3

1,050,000

Financial Guidelines

Will be circulated among Partners

Financial Guidelines

• The pre-finance has been sent to the Coordinator, but due to technical issues had to be sent back to REA. The pre-finance is due to arrive in January-February.

• Pre-finance has been EUR 635,250 which is 635,250 / 1155000 = 0.55 of the overall requested EU contribution. Hence the prepayment will be distributed proportionally to the total EU contribution to each partner

Financial Guidelines

Partner

Requested EU contribution,

€Prepayment

PIL 245,600 135,080

CALGAVIN 255,000 140,250

Sodrugestvo-T 232,000 127,600

MAKATEC 221,000 121,550

OIKOS 177,000 97,350

UNIMAN 6,800 3,740

UNIBATH 4,400 2,420

UPB 4,400 2,420

UNIPAN 8,800 4,840

EMBAFFLE 0 0

Total 1,155,000 635,250

Estimated prefinance distribution

Project PM efforts

Activity type 1

PIL 2

CALGAVIN 3 SODRU 4

MAKATEC 5

OIKOS 6

UNIMAN 7

UNIBATH 8

UPB 9

UNIPAN 10 EMBAFFLE

Total

RTD/Innovation activities

WP1 1.5 4 2.5 0 0 3 14 2 6 0 33

WP2 1.5 4 2.5 0 0 14 1 0 1 0.5 24.5

WP3 0 0 0 11 0 0 0 20 0 0 31

WP4 2 3 2.5 0 0 11 9 4 9.5 0.5 41.5

Total Research 5 11 7.5 11 0 28 24 26 16.5 1 130

Demonstration activities

WP5 2 2 2.5 4 5 4 4 8 5 0.5 37

Total Demo 2 2 2.5 4 5 4 4 8 5 0.5 37

Consortium Management activities

Total Management 6

6

Other activities

WP6 0 2 1.5 0 3 3 4 0 5.5 0 19

Total other 0 2 1.5 0 3 4 4 0 4 0 18.5

Total 13 15 11.5 15 8 35 32 34 27 1.5 192

Decision Making Mechanism

European Commission - Technical Officer

Exploitation and Dissemination Management

(WP 7)

Coordinator (WP 7)

Technical Management

(WP 7)

Steering Committee – decision making body(All Consortium Members)

Workpackage Management (WP Committees / WP Leaders)

Consortium Agreement

An updated version of the Consortium Agreementwill be circulated at this meeting

Amendments: in Exclusions section

Please check carefully before we send the updated version to REA!

Future Meetings Planning

• June 2011 – your suggestions?

• Mid-term review meeting to be done after Month 11 (December 2011) – Brussels

• June 2012 – your suggestions?

• November 2012 – your suggestions?