NMP / EO-1 NMP EO-1 LE&O HANDBOOK September 24-26, 2000
Citation preview
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 1September 24-26, 2000
Section 1Master Timeline (Day 1-10)
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 2September 24-26, 2000
Launch
Recover Configuration from Safehold
Verify Sun-pointing
Acquire Earth- pointing
Turn on Ali Red Htr Turn on IRU Htr Turn on AST Turn on GPS
Use AST for Kalman Filter
Safehold Logic Test
60 sec Test Propulsion Burn
Pitch, Roll, Yaw, 90 degrees slews for IRU/TAM Cal
Use GPS for time to M5
EO-1 L&EODays 1-3
Thursday, May 18, 2000
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 3September 24-26, 2000
End TestBurn
Ali Power On
Power on WARP
X-Band Dump
Format Memory WARP RS 422 Test
X-Band Power On
Short and Normal Images
Ali HOPA Activations and Cover Test
Ali Tests and Internal Cals
EO-1 L&EODays 4-10
cont.
Thursday, May 18, 2000
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 4September 24-26, 2000
Test ASP Test LAmps Internal Cals &Tests Cover Tests Images
Ali Outgas Mode
Hyperion Power on
AC turn on
AC Images TEC-1 * 2 TEC-2 * 2 TEC-3 * 2
TDRSS Data Rate Tests
Outgassing Mode Check Cryo operation
EO-1 L&EODays 4-10 (cont.)
cont.
Thursday, May 18, 2000
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 5September 24-26, 2000
Day-By-Day Key Activities Description
. . . Joe Howard
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 6September 24-26, 2000
Day 1 Launch
– Fairing Separation First Acquisition through TDRSS at
2k from ATS Non_Coherent– Test Command through TDRSS
AOS McMurdo – Test Command through McMurdo
LOS McMurdo ATS goes to TDRSS– Separation From Launch Vehicle
into B-dot Mode– Solar Array Deployment
AOS Norway at 2k Send Command to switch rate to 32K
– Switch to ATS Buffer B – Playback SSR Launch Data– Close Data Set I
Monitor B-dot
Orbit 3– Drop off TDRSS coverage
but keep transponder on and configured between GN passes
Orbit 4– Verify sun pointing
acquisition– Turn on ALI outgas heater– Turn on IRU heater– Turn on AST– Turn on GPS
Orbit 6– Allow ACS to use Kalman
filter if converged Night Orbits
– Check TDRS 4,6,8 Kbps telemetry
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 7September 24-26, 2000
Day 2 Orbit 12 – Update M5 time if needed
Orbit 14– Move Solar Array 10 deg off index– Start ACE Safehold– Monitor safehold control
Orbit 16– Exit safehold– Turn back on IRU heaters– Turn back on AST power– Turn back on GPS power– Turn back on ALI outgas heater– Use Kalman filter
Orbit 17– Acquire Earth pointing mode
Orbit 18– Use GPS for timing in M5
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 8September 24-26, 2000
Day 3 Orbit 20– Load ATS– Turn off Slew control for safety
Orbit 28– Enable slew logic
Orbit 29– Pitch Slew out Settle 15 minutes and return (Execute
from ATS)(TDRSS) Orbit 31
– Yaw Slew out and back (from ATS)(TDRSS) Orbit 32
– Roll Slew out and back (from ATS)(TDRSS) Orbit 34
– Enable EFF in Monitor mode
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 9September 24-26, 2000
Day 4 Orbit 45
– Turn on X-band RSN– Turn on X-band RF without
WARP RF exciter– Playback S-band WARP RS422
data Orbit 46
– Dump WARP files X-band (Norway and SGS overlap)
Orbit 49– Re-dump WARP X-band data
(Wallops) Orbit 50
– WARP Memory test
Orbit 37– Load ATS
Orbit 41– Update any Power parameters– Turn off ALI radiator heaters– Allow DeltaV logic to execute
Orbit 42– Monitor 60 second thruster
burn from ATS (over Wallops) Orbit 43
– Turn back on the ALI rad heaters
Orbit 44– Turn on WARP and format
memory– RS-422 test
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 10September 24-26, 2000
Day 5 Orbit 60
– Enable RTSs for ALI cover opening DCE via ATS
Orbit 61– One 8 second and two 30 sec DCE
execution out of ATS (out of view)– Move cover to outgas position– Turn Heaters on to outgassing mode– Turn on Radiator Heaters
Orbit 62– S-band dump of 8 sec DCE– Another 30 sec DCE via ATS
Orbit 64– X-band dump of all ALI data
Orbit 52– Load ATS
Orbit 55– Turn on ALI– Turn off ALI radiator heaters
Orbit 56– ALI comprehensive test
Orbit 57– 8 second ALI lamp cal– S-band WARP replay– 30 second test pattern ALI data
collect Orbit 58
– X-band WARP playback Orbit 59
Release Launch Latch for ALI CoverRelease Launch Latch for ALI DiffuserOpen ALI CoverClose ALI Cover
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 11September 24-26, 2000
Day 6 Orbit 76
– AC Dark Earth image at TEC 1 for S-band downlink
Orbit 77– AC image at TEC 1 for S-band
downlink Orbit 78
– AC Dark Earth image at TEC 1 for X-band downlink
Orbit 79– AC image at TEC 1 for X-band
downlink– Test TDRSS pass at 4 Kbps
Orbit 80– Test TDRSS pass at 6 Kbps
Orbit 82– Test TDRSS pass at 8 Kbps
Orbit 83– Load ATS– X-band playback of AC data
Orbit 66– Load ATS
Orbit 70– Close ALI cover– Turn off ALI radiator heater
Orbit 71– Increase FDC limits in prep for Delta
V– Allow for Delta V to execute
Orbit 72– Monitor 13 minute Delta V via ATS
(TDRSS scheduled as needed) Orbit 73
– Reset FDC limits Orbit 74
– Re-open ALI cover– Re-turn on ALI radiator heaters
Orbit 75– Turn on ALI
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 12September 24-26, 2000
Day 7 Orbit 84– Power on Hyperion– Release WARP files with AC data
Orbit 85– Test ASPs– Test HYP Lamps
Orbit 86– HYP short internal cal
Orbit 87– HYP Cryo static drive test– S-band playback of short cal
Orbit 88– HYP heater test
Orbit 89– Heaters back to normal
Orbit 90– Cover open full– Cover open to sun cal position– cover close
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 13September 24-26, 2000
Day 8 Orbit 92– Load ATS
Orbit 99– HYP full length cal
Orbit 100– Close ALI cover– Turn off ALI radiator heater– X-band dump of Hyperion data– Allow for Delta V to go
Orbit 101– 12 min Delta V from ATS
Orbit 103– Open ALI cover– Turn on ALI radiator heater– Release Launch Latches on LFSA– Deploy LFSA
Orbit 104– Another full length Hyperion cal
Orbit 107– X-band playback of Hyperion data to Wallops
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 14September 24-26, 2000
Day 9 Orbit 109– Load ATS
Orbit 114– Close ALI cover– Turn off ALI radiator heater– Allow for Delta V to execute– Monitor 9 minutes Delta V
Orbit 115– Return ACS to 60 second burn limit
Orbit 116– Open ALI cover– Turn on ALI radiator heater
Orbit 117– HYP Cryo check start
Orbit 118– HYP Cryo check stop
Orbit 119– Hyperion heaters on for outgassing
NMP / EO-1 NMP EO-1 LE&O HANDBOOK
1 - 15September 24-26, 2000
Day 10 Orbit 121– Load ATS
Orbit 129– All instrument DCE (Procedure or ATS)
Orbit 130– X-band downlink (Alaska)
Orbit 131– X-band downlink (Wallops)
Orbit 132– All instrument short DCE
Orbit 133– S-band dump of short DCE