View
98
Download
14
Category
Preview:
DESCRIPTION
Building schedules of rates
Citation preview
MAIN INDEX
A Note
B Quick
C BSR 1 -Standard BSR
D Concrete misallanious
E Termite Treatment
Water proofing
F Plumbing - Gauge 600
G Electrical Work
H Doors & Window - 01 (Red Balow)
K Doors & Window - 02 (Teak)
L Doors & Window - 03
M Roof Work / Canopy
Roof plumbing
Roof insulation
N Roof Fram Work
O Special Floor Finishes
P Special Wall Finishes
Q Special Ceiling Finishes
R Special Man Holes
S Sanitary Fittings
T Timber Work
U Metal work
V Type of boundary walls
W Misallanious
X Painting
Y
a
Z Material Index
Conversion
Steel
Level to level
Concrete grade
General notes
Formulas
Triangle
Circle
Ellipse
Traprzoid
Hexagon
Sphere
Pyramide
Cone
CONVERSION
Note
Are
a
1 Perch =
1 Perch = 0.25 Rood
1 Rood = 40 Perch
1Rood = 0.25 Acres
1 Acres = 0.405 Hectares
1 Acres = 4 Rood
1 Acres = 160 Perch
1 Hectares = 2.47 Acres
1 Hectares = 9.88 Rood
1 Hectares = 395.37 Perch
= 10.76 ft2
=
=
=
=
=
Dis
tance
1 ft = 30.48 cm
1 m = 3.28 L.ft
1 m = 1.094 Yards
1 miles = 1.61 Km
3 ft = 1 Yards
1 miles = 5280 ft
=
=
=
=
Mass
1 Kg = 35.27 Ounce
1 Kg = 2.21 Pound
1 Pound = 16 Ounce
1 Tone = 2204.6 Pound
1 Tone = 1000 kg
1 Cwt = 50 Kg
=
=
=
=
=
272.25 ft2
1 m2
A A
D D
M M
Volu
me
=
= 220 Gallon
= 1000 Liter
1 Cube = 2.83 m3
1 Cube =
1 Gallon = 4.54 Liter
=
=
=
=
=
STEEL
6 mm Dia. 1 m = 0.222 Kg
10 mm Dia. 1 m = 0.617 Kg
12 mm Dia. 1 m = 0.889 Kg
16 mm Dia. 1 m = 1.58 Kg
20 mm Dia. 1 m = 2.469 Kg
25 mm Dia. 1 m = 3.858 Kg
32 mm Dia. 1 m = 6.321 Kg
LEVEL TO LEVEL
Unit Ground To First FloorGround To Second Floor
Concrete Cube 3% 5%
9" Brick Work Sqr 5% 7%
9" Brick Work Cube 5% 7%
1 m3 35.315 ft3
1 m3
1 m3
100 ft3 V V
Sqr 5% 7%
Reinforcement Cwt 2.50% 5%
Plastering Sqr 5% 10%
Painting Sqr 3% 6%
Floor Tiling Sqr 2% 4%
Wall Tilling Sqr 2% 4%
Roof Calicut Tiles Sqr 3% 6%
Roof Asbestos Sqr 3% 5%
Ceiling Work Sqr 3% 5%
CONCRETE GRADES
1 : 3 : 6 = Grade- 10
= Grade- 15
1 : 2 : 4 = Grade- 20
= Grade- 25
1 : 1 : 2 = Grade- 30
GENERAL NOTES
@
@ 1 TRACTOR LOAD HAVE TO 0.75 Cube
4 1/2" Brick Work
1 : 2 1/2 : 5
1 : 1 1/2 : 3
1 m3 OF CONCRETE NEED FOR 100 Kg STEEL
FORMULAS
*** Triangles
Area of all Triangles
Area = Base X Perpendicular Height
2
Area =
2 2 2
Area of equilateral Triangle
Area =
*** Circle
Circumference of a Circle
C = π d = 2π r
Area of a Circle
Area =
2
Area of a Sector of a Circle
A = arc x r
bc Sin C = ab Sin C = ac Sin B
0.433 x Side2
π r2 = circumferenece x r
A
B
c
b
a
h
2
A =
360 º
A = θº r²2
*** Ellipse
Area of Ellipse
A =
4
Circumference of Trapeziod
Approx. Circumference = π ( D+d)
2
*** Trapezoid
Area of trapeziod
A =
2
θº x π r²( θ = angle in degrees )
( θ = angle in radians )
π x Dd
a+b h
D d
a
b
h
θ
d
r
*** Hexagon
Area of Hexagon
A = 2.6 s²
Where S = Length of one side
*** Sphere
Total surface area of sphere
A =
Surface area of segment
π dh
Volume
V =
3
Volume of segment
3
6
Where a = radius of segment base
4π r2
As =
4 π r3
Vs = π h 2 ( 3r -h)
Vs = π h (h2 - 3a2)
b
s
h
r
*** Pyramid
Volume of pyramid
V = Base Area X Perpendicular Height
3
Volume of frustum
h ( A + a + Aa )
Where h = Perpendicular height
*** Cone
Area of curved surface of cone
A = π DL
2
Area of curved surface of frustum
π ( D+d ) L
2
Volume of cone
V = Base Area X Perpendicular Height
3
Volume of frustum
3
VF =
AF =
VF = Perpendicular Height x π ( R 2 + r 2 +Rr )
a
A
h
L
D
d
D
STEEL
Tor Steel Mild Steel
(6 x 6) /162
(10 x 10) /162 270 270
(12 x 12) /162 187 187
(16 x 16) /162 105 105
(20 x 20) /162 67 67
(25 x 25) /162 43 43
(32 x 32) /162 26 26
LEVEL TO LEVEL
Ground To Third Floor
7%
9%
10%
No. of 6m rods per metric Ton (Average)
10%
7.50%
15%
9%
6%
6%
9%
7%
7%
C
a
triangle
arc
segment
Frustum
L
GRADE Item Discription Unit
EXCAVATION & EARTHWORK
A 01 Sqr
A 02 Sqr
A 03 Cube
A 04 Cube
A 05 Cube
A 06 Cube
A 07 Cube
EXCAVATION & EARTHWORK
EXCAVATION & EARTHWORK
Clearing site & grubbing up all small trees not exceeding 500mm girth & including bushes scrubs, undergrowth hedges etc.
EXCAVATION & EARTHWORK
Excavation of top soil of average depth of 6'' and carting away surplus soil
EXCAVATION & EARTHWORK
Drains, earth in any soil except rock requiring blasting cut to gradient & shape as directed & depositing soil within site
EXCAVATION & EARTHWORK
Excavate trench for wall foundation in ordinary soil & part return fill in ram & depoisting surplus excavated material within site as derected.(not exceeding 5'- 0" deep.)
EXCAVATION & EARTHWORK
Excavate trench for wall foundation in ordinary soil & part return fill in ram, & depoisting surplus excavated material within site as directed.(exceeding 5'-0" but not exceeding 10'-0")
EXCAVATION & EARTHWORK
Excavate pit for column foundation in any material except rock requiring blasting, part return fill in ram, & depoisting surplus excavated material within site as directed.(not exceeding 5'- 0" deep.)
EXCAVATION & EARTHWORK
Excavate pit for column foundation in any material except rock requiring blasting, part return fill in ram, & depoisting surplus excavated material within site as directed.(exceeding 5'-0" but not exceeding 10'-0"deep)
Quick
A 08 Cube
A 09 Cube
A 10 Cube
A 11 Cube
A 12 Sqr
A 13 Sqr
A 14 Sqr
CONCRETE WORK CONCRETE WORK
CONCRETE WORK
CONCRETE WORK
CONCRETE WORK B 01 Concrete 1:3:6 (2") grade 10 Cube
CONCRETE WORK B 02 Concrete 1:3:6 (1") grade 10 Cube
CONCRETE WORK B 03 Concrete 1:2½:5 (1") grade 15 Cube
CONCRETE WORK B 04 Concrete 1:2:4 (3/4") grade 20 Cube
CONCRETE WORK B 05 Concrete 1:11/2:3 (3/4") grade 25 Cube
EXCAVATION & EARTHWORK
Cutting & levlling site in any material except rock requiring blasting including transporting up to 1/4 mile depositing & leveling
EXCAVATION & EARTHWORK
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers. (Earth available at site)
EXCAVATION & EARTHWORK
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers. (earth not avilable at site)
EXCAVATION & EARTHWORK
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers.(within Colombo Municipal limits)
EXCAVATION & EARTHWORK
Earth work support in trenches up to 5' 0'' deep.(open planking)
EXCAVATION & EARTHWORK
Earth work support in trenches up to 5' 0'' deep.(close planking)
EXCAVATION & EARTHWORK
Earth work support in trenches up to 10' 0'' deep. (close planking)
CONCRETE WORK B 05a Concrete1 :1:2 (3/4") grade 30 Cube
CONCRETE WORK B 06 Sqr
CONCRETE WORK B 07 Sqr
CONCRETE WORK B 08 Sqr
CONCRETE WORK B 09 4" thick ground floor slab (1:3:6 -1") Grade10 Sqr
CONCRETE WORK B 10 L.ft
CONCRETE WORK B 11 L.ft
CONCRETE WORK B 12 L.ft
CONCRETE WORK B 13 L.ft
CONCRETE WORK B 14 L.ft
CONCRETE WORK B 15 L.ft
CONCRETE WORK B 16 L.ft
CONCRETE WORK B 17 L.ft
CONCRETE WORK B 18 Concrete column in ground floor (1:2:4 3\4") Cube
2" thick blinding layer under wall / column foundation (1:3:6 -2") grade 10
2" thick blinding layer under wall/ column foundation (1:3:6 -1") grade 10
3" thick blinding layer under wall/ column foundation (1:3:6 -1") grade 10
Cement Concrete 1:2:4(3/4) lintol size 41/2'' x 6'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:2:4(3/4") lintol size 6'' x 9'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:2:4(3/4") lintol size 9'' x 9'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 9'' x 12'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 6'' x 13' 6'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 9'' X 13' 6'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 12'' x 13' 6'' with & including formwork
Cement Concrete 1:2:4(3/4")lintol size 4 1/2" x4 1/2" with & including formwork.(rein forcement paid seperately)
CONCRETE WORK B 19 9" x 9" Concrete columns in first floor Cube
CONCRETE WORK B 20 9" x 9" Concrete columns in second floor Cube
CONCRETE WORK B 21 9" x 9" Concrete columns in third floor Cube
CONCRETE WORK B 22 Cube
CONCRETE WORK B 23 12" x 12" Concrete columns in first floor Cube
CONCRETE WORK B 24 12" x 12" Concrete columns in second floor Cube
CONCRETE WORK B 25 12" x 12" Concrete columns in third floor Cube
CONCRETE WORK B 26 9" x 9" Concrete beams in ground floor level Grade 20 Cube
CONCRETE WORK B 27 9" x 9" Concrete beam in first floor Cube
CONCRETE WORK B 28 9" x 9" Concrete beam in second floor Cube
CONCRETE WORK B 29 9" x 9" Concrete beam in third floor Cube
CONCRETE WORK B 30 Concrete beams in ground floor level Grade 20 Cube
CONCRETE WORK B 31 Concrete beam in first floor Cube
CONCRETE WORK B 32 Concrete beam in second floor Cube
CONCRETE WORK B 33 Concrete beam in third floor Cube
CONCRETE WORK B 34 Concrete beams in ground floor level Cube
CONCRETE WORK B 35 Concrete beam in first floor Cube
CONCRETE WORK B 36 Concrete beam in second floor Cube
CONCRETE WORK B 37 Concrete beam in third floor Cube
Concrete columns in ground floor 10 no 12"x12" columns each 5' 0" high
CONCRETE WORK B 38 4" thick Concrete slab in first floor Grade 20 Sqr
CONCRETE WORK B 39 4" thick Concrete slab in second floor Sqr
CONCRETE WORK B 40 4" thick Concrete slab in third floor Sqr
CONCRETE WORK B 41 5" thick Concrete slab in first floor Sqr
CONCRETE WORK B 42 5" thick Concrete slab in second floor Sqr
CONCRETE WORK B 43 5" thick Concrete slab in third floor Sqr
CONCRETE WORK B 44 6" thick Concrete slab in first floor Sqr
CONCRETE WORK B 45 6" thick Concrete slab in second floor Sqr
CONCRETE WORK B 46 6" thick Concrete slab in third floor Sqr
CONCRETE WORK B 47 L.ft
CONCRETE WORK B 48 L.ft
CONCRETE WORK B 49 L.ft
CONCRETE WORK B 50 L.ft
CONCRETE WORK B 51 L.ft
CONCRETE WORK B 52 L.ft
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6''x 6'' with & including formwork (reinforcement paid seperately)
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 9'' with & including formwork (reinforcement paid seperately)
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 9'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 12'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 13' 6'' with & including formwork (reinfrcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 13 ' 6'' with & including formwork (reinforcement paid separately)
CONCRETE WORK B 53 L.ft
CONCRETE WORK B 54 L.ft
CONCRETE WORK B 55 Cube
CONCRETE WORK B 56 9" x 9" Concrete colomns in first floor Cube
CONCRETE WORK B 57 9" x 9" Concrete colomns in second floor Cube
CONCRETE WORK B 58 9" x 9" Concrete colomns in third floor Cube
CONCRETE WORK B 59 Concrete colomns in ground floor Cube
CONCRETE WORK B 60 12" x 12" Concrete colomns in first floor Cube
CONCRETE WORK B 61 12" x 12" Concrete colomns in second floor Cube
CONCRETE WORK B 62 12" x 12" Concrete colomns in third floor Cube
CONCRETE WORK B 63 9" x 9" Concrete beams in ground floor level Cube
CONCRETE WORK B 64 9" x 9" Concrete colomns in first floor Cube
CONCRETE WORK B 65 12" x 12" Concrete colomns in second floor Cube
CONCRETE WORK B 66 12" x 12" Concrete colomns in third floor Cube
CONCRETE WORK B 67 Concrete beam in ground floor level 9" x 12" Cube
CONCRETE WORK B 68 Concrete beam in first floor 9" x 12" Cube
CONCRETE WORK B 69 Concrete beam in second floor 9" x 12" Cube
Cement Concrete 1:11/2:3 (3/4") lintol size 12'' x 13' 6'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6'' x 4' 6'' with & including formwork (reinforcement paid separately)
Concrete colomns in ground floor 1 : 1 1/2 : 3(3/4") 16 no 9" x 9" columns each 5'0" high
CONCRETE WORK B 70 Concrete beam in third floor 9" x 12" Cube
CONCRETE WORK B 71 Concrete beam in ground floor level 12" X 12" Cube
CONCRETE WORK B 72 Concrete beam in first floor 12" x 12" Cube
CONCRETE WORK B 73 Concrete beam in second floor 12" x 12" Cube
CONCRETE WORK B 74 Concrete beam in third floor 12" x 12" Cube
CONCRETE WORK B 75 4" thick Concrete slab in first floor Cube
CONCRETE WORK B 76 4" thick Concrete slab in second floor Cube
CONCRETE WORK B 77 4" thick Concrete slab in third floor Cube
CONCRETE WORK B 78 5" thick Concrete slab in first floor Sqr
CONCRETE WORK B 79 5" thick Concrete slab in second floor Sqr
CONCRETE WORK B 80 5" thick Concrete slab in third floor Sqr
CONCRETE WORK B 81 6" thick Concrete slab in first floor Sqr
CONCRETE WORK B 82 6" thick Concrete slab in second floor Sqr
CONCRETE WORK B 83 6" thick Concrete slab in third floor Sqr
FORM WORK FORM WORK
FORM WORK
FORM WORK Sqr
FORM WORK B 86 Sawn formwork in 9"X 9" column in ground floor Sqr
FORM WORK B 87 Sawn from work in 9"x9" column in first floor Sqr
B 84 & B 85
Sawn formwork in sides of column foundation up to D.P.C level
FORM WORK B 88 Sawn from work in 9"x9" column in Second floor Sqr
FORM WORK B 88a Sawn from work in 9"x9" column in third floor Sqr
FORM WORK B 89 Sqr
FORM WORK B 90 Sawn from work in 9"x12" column in first floor Sqr
FORM WORK B 91 Sawn from work in 9"x12" column in Second floor Sqr
FORM WORK B 92 Sawn from work in 9"x12" column in third floor Sqr
FORM WORK B 93 Sawn formwork for sofit of first floor slab Sqr
FORM WORK B 94 Sawn formwork in soffit of slab second flor Sqr
FORM WORK B 95 Sawn formwork in soffit of slab third flor Sqr
REINFORCEMENT REINFORCEMENT
REINFORCEMENT
REINFORCEMENT B 96 kg
REINFORCEMENT B 98 16mm dia tor steel reinforcement up to first level. kg
REINFORCEMENT
B 99
kg
REINFORCEMENT
B 111
kg
REINFORCEMENT
B 113
kg
REINFORCEMENT
B 114
kg
Sown form work in 9"x 12" beam in ground floor 20'-0" long
25 mm & 20mm dia tor steel reinforcement in fdn, Ground & first level.
12mm dia &10mm dia tor steel reinforcement up to first level.
25mm dia &20mm dia tor steel reinforcement in second floor
16mm dia tor steel reinforcement in second floor level & third floor level
12mm & 10mm dia tor steel reinforcement in second floor level & third floor level
REINFORCEMENT
B 116
kg
REINFORCEMENT
B122
kg
BRICK WORK BRICK WORK
BRICK WORK C 01 Cube
BRICK WORK C 02 Cube
BRICK WORK C 03 Cube
BRICK WORK C 04 Sqr
BRICK WORK C 05 Sqr
BRICK WORK C 06 Sqr
BRICK WORK C 07 L.ft
BRICK WORK C 08 9''X 9'' Brick column in cement & sand 1: 5 in first floor L.ft
BRICK WORK C 09 L.ft
BRICK WORK C 10 L.ft
10mm & 6mm dia mild steel reinforcement up to first floor level
10mm & 6mm dia mild steel reinforcement in second floor level & third floor level
01- One brick thick brick wall in common brick in cement & sand 1:5 in ground floor level
One brick thick brick wall in common brick in cement & sand 1:5 in first floor
One brick thick brick wall in common brick in cement & sand 1:5 in second floor
Half brick thick brick wall in common brick in cement & sand 1:5 in ground floor
Half brick thick brick wall in common brick in cement & sand 1:5 in first floor
Half brick thick brick wall in common brick in cement & sand 1:5 in second floor
9''X 9'' Brick column in cement & sand 1: 5 in ground floor
9''X 9'' Brick column in cement & sand 1: 5 in second floor
12''X 12'' Brick column in cement & sand 1: 5 in ground floor
BRICK WORK C 11 L.ft
BRICK WORK C 12 L.ft
BRICK WORK C 13 Sqr
BRICK WORK C 14 Sqr
BRICK WORK C 15 Sqr
RUBBLE WORK RUBBLE WORK
RUBBLE WORK
RUBBLE WORK D 01 Cube
RUBBLE WORK D 02 Sqr
RUBBLE WORK D 03 Sqr
RUBBLE WORK D 04 Sqr
RUBBLE WORK D 05 Sqr
RUBBLE WORK D 06 Sqr
RUBBLE WORK D 07 Sqr
12''X 12'' Brick column in cement & sand 1: 5 in first floor
12''X 12'' Brick column in cement & sand 1: 5 in second floor
One brick thick brick wall in common brick in cement & sand 1:5 in ground floor level
One brick thick brick wall in common brick in cement & sand 1:5 in first floor level
One brick thick brick wall in common brick in cement & sand 1:5 in second floor level
6" X 9" Random rubble Masonry in cement & sand 1:5 in foundation
6" X 9" Random rubble Masonry in cement & sand 1:5 in 1' 6" thick wall
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 0" thick wall
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 6" thick wall
8" thick Solid block work in cement & sand 1;5 in ground floor (cavites un filled)
4" thick Solid block work in cement & sand 1:5 in ground floor ( cavite un filled)
6" thick Solid block work in cement & sand 1;5 in ground floor (Cavity un filled)
RUBBLE WORK D 08 Sqr
RUBBLE WORK D 09 Sqr
RUBBLE WORK D 10 Sqr
RUBBLE WORK D 11 Sqr
RUBBLE WORK D 12 Sqr
RUBBLE WORK D 13 Sqr
RUBBLE WORK D 14 Sqr
RUBBLE WORK D 15 Sqr
RUBBLE WORK D 16 Sqr
RUBBLE WORK D 17 Sqr
RUBBLE WORK D 18 Sqr
RUBBLE WORK D 19 Sqr
RUBBLE WORK D 20 Sqr
8" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
4" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
6" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
8" thick Solid block work in cement & sand 1;5 in second floor(cavities un filled)
4" thick Solid block work in cement & sand 1;5 insecond floor(cavities un filled)
6" thick Solid block work in cement & sand 1;5 in second floor(cavities un filled)
8" thick Hollow block work in cement & sand 1;5 in ground floor (cavites un filled)
4" thick Hollow block work in cement & sand 1:5 in ground floor ( cavite un filled)
6" thick Hollow block work in cement & sand 1;5 in ground floor (Cavity un filled)
8" thick Hollow block work in cement & sand 1;5 in first floor(cavities un filled)
4" thick Hollow block work in cement & sand 1;5 in first floor(cavities un filled)
6" thick Hollow block work in cement & sand 1;5 in first floor (cavities un filled)
8" thick Hollow block work in cement & sand 1;5 in second floor(cavities un filled)
RUBBLE WORK D 21 Sqr
RUBBLE WORK D 22 Sqr
ROOF WORK ROOF WORK
ROOF WORK
ROOF WORK E 01 Sqr
ROOF WORK E 02 L.ft
ROOF WORK E 03 Sqr
ROOF WORK E 04 L.ft
ROOF WORK E 05 Sqr
ROOF WORK E 06 Half round tile on asbastos sheet roof (crest only ) Sqr
ROOF WORK E 07 L.ft
ROOF WORK E 08 Sqr
ROOF WORK E 09 Sqr
4" thick Hollow block work in cement & sand 1;5 insecond floor(cavities un filled)
6" thick Hollow block work in cement & sand 1;5 in second floor(cavities un filled)
Calicut pattern tile hip roof in single storey building consisting of wall plate ridge plate beam struct rafters & reepers.
Calicut pattern ridge tile hip tile on single storey building in cement lime & sand 1;1;5 coloured to match tile
Corrugated asbastos cement sheet roofing with Timber fram in single storeyed building.
Asbastos ajestable close fitting ridge fixed complete with roofing screws or bolts
Corrugated asbastos cement sheet rooing with Timber frame in single storeyed building.
3/4" thick 9" high valance board fixed with brass screws to end of rafters with & including one coat of primer & two coats of enamel paint
Asbastos cement plian sheet ceiling with class 1 Timber frame consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2" cove moulding & 1/2"x1/2" beadings with painting
3/4" thick class 1 Timber ceiling with class 1 Timber frame consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2" cove moulding with painting
PLUMBING WORK PLUMBING WORK
PLUMBING WORK
PLUMBING WORK F 01 20mm diameter pvc pipe fixed to wall or slab L.ft
PLUMBING WORK F 02 25mm diameter pvc pipe fixed to wall or slab L.ft
PLUMBING WORK F 03 32mm diameter pvc pipe fixed to wall L.ft
PLUMBING WORK F 04 32mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 05 40mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 06 40mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 07 50mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 08 50mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 09 63mm diameter pvc pipefix to wall L.ft
PLUMBING WORK F 10 63mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 11 75mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 12 75mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 13 90mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 14 90mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 15 Supplying & fixing PVC bend 20mm dia. No
PLUMBING WORK F 16 Supplying & fixing PVC bend 25mm dia. No
PLUMBING WORK F 17 Supplying & fixing PVC bend 32mm dia. No
PLUMBING WORK F 18 Supplying & fixing PVC bend 40mm dia. No
PLUMBING WORK F 19 Supplying & fixing PVC bend 50mm dia. No
PLUMBING WORK F 20 Supplying & fixing PVC bend 63mm dia. No
PLUMBING WORK F 21 Supplying & fixing PVC elbow 20mm .dia. No
PLUMBING WORK F 22 Supplying & fixing PVC elbow 25mm .dia. No
PLUMBING WORK F 23 Supplying & fixing PVC elbow 32mm .dia. No
PLUMBING WORK F 24 Supplying & fixing PVC elbow 40mm .dia. No
PLUMBING WORK F 25 Supplying & fixing PVC elbow 50mm .dia. No
PLUMBING WORK F 26 Supplying & fixing PVC elbow 63mm .dia. No
PLUMBING WORK F 27 Supplying & fixing PVC tee 20mm .dia. No
PLUMBING WORK F 28 Supplying & fixing PVC tee 25mm .dia. No
PLUMBING WORK F 29 Supplying & fixing PVC tee 32mm .dia. No
PLUMBING WORK F 30 Supplying & fixing PVC tee 40mm .dia. No
PLUMBING WORK F 31 Supplying & fixing PVC tee 50mm .dia. No
PLUMBING WORK F 32 Supplying & fixing PVC tee 63mm .dia. No
PLUMBING WORK F 33 Supplying & fixing PVC faucet socket 20 mm dia No
PLUMBING WORK F 34 Supplying & fixing PVC faucet socket 25 mm dia No
PLUMBING WORK F 35 Supplying & fixing PVC faucet socket 32 mm dia No
PLUMBING WORK F 36 Supplying & fixing PVC faucet socket 40 mm dia No
PLUMBING WORK F 37 Supplying & fixing PVC faucet socket 50 mm dia No
PLUMBING WORK F 38 Supplying & fixing PVC faucet socket 63 mm dia No
PLUMBING WORK F 39 Supplying & fixing PVC Value socket 20 mm dia No
PLUMBING WORK F 40 Supplying & fixing PVC value socket 25 mm dia No
PLUMBING WORK F 41 Supplying & fixing PVC value socket 32 mm dia No
PLUMBING WORK F 42 Supplying & fixing PVC value socket 40 mm dia No
PLUMBING WORK F 43 Supplying & fixing PVC value socket 50 mm dia No
PLUMBING WORK F 44 Supplying & fixing PVC value socket 63 mm dia No
PLUMBING WORK F 45 Supplying & fixing PVC socket 20 mm dia No
PLUMBING WORK F 46 Supplying & fixing PVC socket 25 mm dia No
PLUMBING WORK F 47 Supplying & fixing PVC socket 32 mm dia No
PLUMBING WORK F 48 Supplying & fixing PVC socket 40 mm dia No
PLUMBING WORK F 49 Supplying & fixing PVC socket 50 mm dia No
PLUMBING WORK F 50 Supplying & fixing PVC socket 63 mm dia No
PLUMBING WORK F.51 Supplying & fixing PVC socket 63 mm dia No
PLASTER WORK PLASTER WORK
PLASTER WORK
PLASTER WORK G 01 Sqr
PLASTER WORK G 02 Sqr
PLASTER WORK G 03 Sqr
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth with neat lime in internal wall in ground floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in external wall in ground floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth in internal wall in first floor
PLASTER WORK G 04 Sqr
PLASTER WORK G 05 Sqr
PLASTER WORK G 06 Sqr
PLASTER WORK G 07 Sqr
PLASTER WORK G 08 Sqr
PLASTER WORK G 09 Sqr
PLASTER WORK G 10 Sqr
PLASTER WORK G 11 Sqr
PAVING WORK PAVING WORK
PAVING WORK
PAVING WORK H 01 Sqr
PAVING WORK H 02 Sqr
PAVING WORK H 03 Sqr
3/4" Thick plaster in cement lime & sand 1;1;5 finished semi rough in external wall in first floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in internal wall in second floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in external wall in second floor
1/2" Thick sides & soffits plaster in first floor slab in cement lime & sand 1:1:5 finished smooth with neat lime.
1/2" Thick sides & soffits plaster in second floor slab in cement lime & sand 1;1;5 finished smooth with neat lime
3/4" thick D.P.C. in cement and sand 1:3 finished with two coats of hot tar and blinded with sand.
1/2" Thick sides & soffits plaster in first floor beam in cement lime & sand 1:1:5 finished smooth with neat lime
1/2" Thick sides & soffits plaster in second floor beam in cement lime & sand 1:1:5 finished smooth with neat lime
3" Thick brick paving lime & sand 1:5 with & including 1/2" thick cement & sand 1:3 rendering finished smooth with neat cement
1/2" Thick cement rendering in cement & sand 1':3 finished smooth with neat cement
6" X6" White glazed tile including joint and point with tile grout & including 3/4" tk cement ^& sand 1;3 screed backing on ground floor
PAVING WORK H 04 Sqr
PAVING WORK H 05 Sqr
PAVING WORK H 06 Sqr
PAVING WORK H 07 Sqr
PAVING WORK H 08 Sqr
PAINTING WORK PAINTING WORK
PAINTING WORK
PAINTING WORK J 01 Sqr
PAINTING WORK J 02 Sqr
PAINTING WORK J 03 Sqr
PAINTING WORK J 04 Sqr
8" X8" White glazed tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on ground floor
12" X12" White glazed tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on ground floor
6" X6" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
8" X12" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
8" X8" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in ground floor internally
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in first floor internally
Prepare & apply approved type one coat of filler & two of weathershield paint to specified colour up to first floor level externally(ground floor)
Prepare & apply approved type one coat of filler & two of weathershield paint to specified colour above first floor level Externally
PAINTING WORK J 05 Sqr
PAINTING WORK J 06 Sqr
ELECTRICAL WORK
K 01 Pendent lamp without bulb and shade Point
K 02 wall bracket with out bulb and shade Point
K 03 5 amp socket outlets Point
READY MIX CONCRETE
L 01 Cube
L 02 Cube
L 03 Cube
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in sides and soffit of beam and slab in first floor level
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in sides and soffit of beams and slabs in second floor level
ELECTRICAL WORK
ELECTRICAL WORK
ELECTRICAL WORK
ELECTRICAL WORK
ELECTRICAL WORK
READY MIX CONCRETE
READY MIX CONCRETE
READY MIX CONCRETE
Suppying & placing ready mixed Concrete grade 20 (1:2:4 -3/4" ) in 125mm thick first floor slab
READY MIX CONCRETE
Suppying & placing redy mixed Concrete grade 20 (1:2:4 -3/4" ) in 225 x225mm columns in ground floor
READY MIX CONCRETE
Suppying & placing ready mixed Concrete grade 25 (1:1 1/2:3 -3/4" ) in 125mm thick first floor slab
L 04 Cube
L 05 Cube
L 06 Cube
L 07 Cube
L 08 Cube
DOORS & WINDOWS
M 01 Nos
M 02 Nos
M 03 Nos
HOT WATER PLUMBING
READY MIX CONCRETE
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-3/4) in 225mmx225mm columns in ground floor.
READY MIX CONCRETE
Suppying & placing ready mixed Concrete grade 20 (1:2:4-3/4) in 125mm thick first floor slab
READY MIX CONCRETE
Suppying & placing redy mixed Concrete grade 20(1:2:4-3/4") in 225mmx225mm columns in ground floor
READY MIX CONCRETE
Suppying & placing redy mixed Concrete grade 25 (1:11/2:3-3/4) in 125mm thick first floor slab
READY MIX CONCRETE
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-3/4") in 225mmx225mm columns in ground floor
DOORS & WINDOWS
DOORS & WINDOWS
DOORS & WINDOWS
singal hung door size 3'-6"x 7'-0" high overall with 4''x3'' class 1 Timber door frame and including 11/4" tk ordinary plywood door sash with and door lock with and including ironmongrey and painting
DOORS & WINDOWS
singal hung door size 3'-6"x 7'-0" high overall with 4''x3'' class 1 Timber door frame and including 11/4" tk flush panneld door sash with and door lock with and including ironmongrey and painting
DOORS & WINDOWS
window size 5'-0"x 6'-0" high overall with 4''x3'' class 1 Timber window frame and mullion comprising 1 tk glased window casement and including ironmongrey and painting
HOT WATER PLUMBING
N 01
supplying & laying hot Water pipe 20mm dia
L.ft
HOT WATER PLUMBING
HOT WATER PLUMBING
Unit
1.10 1.05 1.15
669.50 736.45 702.98 846.92 m2 72.04 79.24
836.88 920.56 878.72 1,058.65 m2 90.05 99.05
1,171.63 1,288.79 1,230.21 1,482.11 m3 414.00 455.40
1,339.00 1,472.90 1,405.95 1,693.84 m3 473.14 520.46
1,673.75 1,841.13 1,757.44 2,117.29 m3 591.43 650.57
1,506.38 1,657.01 1,581.69 1,905.56 m3 532.29 585.52
1,841.13 2,025.24 1,933.18 2,329.02 m3 650.57 715.63
Basic Rate Rate with Priliminery
Rate with O/H & Profit
Rate with priliminery
, O/H & Profit Basic Rate
Rate with Priliminery
1,815.42 1,996.96 1,906.19 2,296.50 m3 641.49 705.64
1,506.38 1,657.01 1,581.69 1,905.56 m3 532.29 585.52
4,141.63 4,555.79 4,348.71 5,239.16 m3 1,463.47 1,609.82
4,141.63 4,555.79 4,348.71 5,239.16 m3 1,463.47 1,609.82
4,609.25 5,070.18 4,839.71 5,830.70 m2 495.96 545.55
7,835.63 8,619.19 8,227.41 9,912.07 m2 843.11 927.42
6,414.33 7,055.76 6,735.04 8,114.12 m2 690.18 759.20
### ### ### ### m3 9,687.22 ###
### ### ### ### m3 9,687.22 ###
### ### ### ### m3 9,948.70 ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
4,852.84 5,338.13 5,095.49 6,138.85 m2 522.17 574.38
4,852.84 5,338.13 5,095.49 6,138.85 m2 522.17 574.38
6,706.36 7,376.99 7,041.68 8,483.54 m2 721.60 793.76
9,404.31 ### 9,874.53 ### m2 1,011.90 1,113.09
258.88 284.77 271.82 327.48 m 849.12 934.03
401.38 441.51 421.44 507.74 m 1,316.51 1,448.16
512.96 564.25 538.61 648.89 m 1,682.51 1,850.76
640.23 704.25 672.24 809.89 m 2,099.95 2,309.95
571.58 628.74 600.16 723.05 m 1,874.79 2,062.27
698.41 768.25 733.33 883.49 m 2,290.78 2,519.86
686.27 754.90 720.58 868.13 m 2,250.96 2,476.06
210.86 231.94 221.40 266.73 m 691.61 760.77
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m2 1,237.39 1,361.13
### ### ### ### m2 1,284.02 1,412.42
### ### ### ### m2 1,342.30 1,476.53
### ### ### ### m2 1,471.75 1,618.93
### ### ### ### m2 1,541.69 1,695.86
### ### ### ### m2 1,576.66 1,734.33
### ### ### ### m2 1,858.51 2,044.36
### ### ### ### m2 1,928.45 2,121.30
### ### ### ### m2 1,963.42 2,159.76
265.72 292.30 279.01 336.14 m 871.57 958.73
395.25 434.78 415.01 499.99 m 1,296.42 1,426.07
533.79 587.17 560.48 675.24 m 1,750.83 1,925.91
667.98 734.78 701.38 844.99 m 2,190.97 2,410.07
592.30 651.53 621.92 749.26 m 1,942.75 2,137.03
689.49 758.44 723.96 872.20 m 2,261.52 2,487.67
727.71 800.48 764.09 920.55 m 2,386.88 2,625.57
215.93 237.52 226.72 273.15 m 708.24 779.06
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m2 1,702.52 1,872.78
### ### ### ### m2 1,749.14 1,924.06
### ### ### ### m2 1,772.39 1,949.63
### ### ### ### m2 2,067.52 2,274.27
### ### ### ### m2 2,114.14 2,325.56
### ### ### ### m2 2,137.46 2,351.21
6,206.25 6,826.88 6,516.56 7,850.91 m2 667.79 734.57
9,880.58 ### ### ### m2 1,063.15 1,169.47
### ### ### ### m2 1,095.05 1,204.55
### ### ### ### m2 1,105.68 1,216.24
### ### ### ### m2 1,116.31 1,227.94
### ### ### ### m2 2,848.12 3,132.94
### ### ### ### m2 2,933.57 3,226.92
### ### ### ### m2 2,962.05 3,258.25
### ### ### ### m2 2,990.53 3,289.58
### ### ### ### m2 1,385.69 1,524.26
### ### ### ### m2 1,441.12 1,585.23
### ### ### ### m2 1,454.98 1,600.48
152.15 167.37 159.76 192.47 cwt 7,607.68 8,368.44
146.81 161.49 154.15 185.71 cwt 7,340.43 8,074.47
161.51 177.66 169.58 204.31 cwt 8,075.43 8,882.97
156.47 172.12 164.30 197.94 cwt 7,823.68 8,606.04
151.13 166.24 158.68 191.18 cwt 7,556.43 8,312.07
165.83 182.41 174.12 209.77 cwt 8,291.43 9,120.57
162.49 178.74 170.62 205.55 cwt 8,124.60 8,937.06
170.73 187.81 179.27 215.98 cwt 8,536.60 9,390.26
### ### ### ### m3 7,366.08 8,102.69
### ### ### ### m3 7,671.38 8,438.52
### ### ### ### m3 7,886.04 8,674.65
9,094.00 ### 9,548.70 ### m2 978.51 1,076.37
9,526.00 ### ### ### m2 1,025.00 1,127.50
9,958.00 ### ### ### m2 1,071.48 1,178.63
150.33 165.36 157.85 190.17 m 493.08 542.39
153.84 169.22 161.53 194.61 m 504.60 555.05
162.48 178.73 170.60 205.54 m 532.93 586.23
119.86 131.85 125.85 151.62 m 393.14 432.45
124.99 137.49 131.24 158.11 m 409.97 450.96
129.81 142.79 136.30 164.21 m 425.78 468.36
### ### ### ### m2 1,708.04 1,878.85
### ### ### ### m2 1,866.38 2,053.01
### ### ### ### m2 1,885.26 2,073.79
### ### ### ### m3 6,112.63 6,723.90
### ### ### ### m2 2,765.43 3,041.97
### ### ### ### m2 3,609.33 3,970.27
### ### ### ### m2 4,463.46 4,909.81
### ### ### ### m2 1,962.78 2,159.06
9,966.32 ### ### ### m2 1,072.38 1,179.61
### ### ### ### m2 1,421.27 1,563.40
### ### ### ### m2 1,998.87 2,198.76
### ### ### ### m2 1,108.46 1,219.31
### ### ### ### m2 1,457.36 1,603.10
### ### ### ### m2 2,031.82 2,235.01
### ### ### ### m2 1,141.42 1,255.56
### ### ### ### m2 1,524.84 1,677.32
### ### ### ### m2 1,567.74 1,724.52
8,027.60 8,830.36 8,428.98 ### m2 863.77 950.15
### ### ### ### m2 1,178.44 1,296.28
### ### ### ### m2 1,603.83 1,764.22
8,362.99 9,199.29 8,781.14 ### m2 899.86 989.84
### ### ### ### m2 1,214.53 1,335.98
### ### ### ### m2 1,636.79 1,800.46
8,669.27 9,536.19 9,102.73 ### m2 932.81 1,026.09
### ### ### ### m2 1,282.00 1,410.20
### ### ### ### m2 3,823.68 4,206.05
136.17 149.79 142.98 172.25 m 446.63 491.30
### ### ### ### m2 2,195.83 2,415.41
852.00 937.20 894.60 1,077.78 m 2,794.56 3,074.02
6,477.33 7,125.07 6,801.20 8,193.83 m2 696.96 766.66
### ### ### ### m2 1,104.70 1,215.17
374.16 411.57 392.86 473.31 m 1,227.23 1,349.95
### ### ### ### m2 1,927.99 2,120.79
### ### ### ### m2 3,133.69 3,447.06
57.54 63.29 60.42 72.79 m 188.73 207.60
83.14 91.45 87.30 105.17 m 272.70 299.97
107.37 118.11 112.74 135.82 m 352.18 387.39
114.70 126.17 120.44 145.10 m 376.22 413.84
147.50 162.25 154.88 186.59 m 483.81 532.19
154.83 170.32 162.57 195.86 m 507.85 558.64
201.42 221.56 211.49 254.79 m 660.65 726.71
208.75 229.62 219.18 264.06 m 684.69 753.16
310.59 341.65 326.12 392.89 m 1,018.73 1,120.60
317.92 349.71 333.81 402.17 m 1,042.77 1,147.05
513.76 565.13 539.44 649.90 m 1,685.12 1,853.63
521.09 573.20 547.14 659.17 m 1,709.17 1,880.08
653.76 719.14 686.45 827.01 m 2,144.33 2,358.77
661.09 727.20 694.14 836.28 m 2,168.38 2,385.21
1,062.89 1,169.18 1,116.03 1,344.56 No 1,062.89 1,169.18
56.72 62.39 59.56 71.75 No 56.72 62.39
50.10 55.11 52.61 63.38 No 50.10 55.11
65.10 71.61 68.36 82.35 No 65.10 71.61
130.80 143.88 137.34 165.46 No 130.80 143.88
203.50 223.85 213.68 257.43 No 203.50 223.85
322.62 354.88 338.75 408.11 No 322.62 354.88
26.82 29.50 28.16 33.93 No 26.82 29.50
41.10 45.21 43.16 51.99 No 41.10 45.21
54.10 59.51 56.81 68.44 No 54.10 59.51
85.80 94.38 90.09 108.54 No 85.80 94.38
136.50 150.15 143.33 172.67 No 136.50 150.15
221.62 243.78 232.70 280.35 No 221.62 243.78
35.45 39.00 37.22 44.84 No 35.45 39.00
53.73 59.10 56.42 67.97 No 53.73 59.10
77.50 85.25 81.38 98.04 No 77.50 85.25
115.92 127.51 121.72 146.64 No 115.92 127.51
188.76 207.64 198.20 238.78 No 188.76 207.64
289.00 317.90 303.45 365.59 No 289.00 317.90
31.82 35.00 33.41 40.25 No 31.82 35.00
42.10 46.31 44.21 53.26 No 42.10 46.31
50.10 55.11 52.61 63.38 No 50.10 55.11
86.80 95.48 91.14 109.80 No 86.80 95.48
117.50 129.25 123.38 148.64 No 117.50 129.25
177.62 195.38 186.50 224.69 No 177.62 195.38
31.82 35.00 33.41 40.25 No 31.82 35.00
42.10 46.31 44.21 53.26 No 42.10 46.31
46.10 50.71 48.41 58.32 No 46.10 50.71
82.50 90.75 86.63 104.36 No 82.50 90.75
111.20 122.32 116.76 140.67 No 111.20 122.32
175.32 192.85 184.09 221.78 No 175.32 192.85
27.82 30.60 29.21 35.19 No 27.82 30.60
37.10 40.81 38.96 46.93 No 37.10 40.81
48.10 52.91 50.51 60.85 No 48.10 52.91
70.80 77.88 74.34 89.56 No 70.80 77.88
106.20 116.82 111.51 134.34 No 106.20 116.82
162.32 178.55 170.44 205.33
4,517.00 4,968.70 4,742.85 5,714.01 m2 486.03 534.63
3,788.24 4,167.06 3,977.65 4,792.12 m2 407.61 448.38
4,949.00 5,443.90 5,196.45 6,260.49 m2 532.51 585.76
4,257.50 4,683.25 4,470.38 5,385.74 m2 458.11 503.92
5,381.00 5,919.10 5,650.05 6,806.97 m2 579.00 636.90
4,689.50 5,158.45 4,923.98 5,932.22 m2 504.59 555.05
5,637.50 6,201.25 5,919.38 7,131.44 m2 606.60 667.25
5,663.00 6,229.30 5,946.15 7,163.70 m2 609.34 670.27
5,578.00 6,135.80 5,856.90 7,056.17 m2 600.19 660.21
5,744.00 6,318.40 6,031.20 7,266.16 m2 618.05 679.86
6,176.00 6,793.60 6,484.80 7,812.64 m2 664.54 730.99
8,179.38 8,997.31 8,588.34 ### m2 880.10 968.11
2,835.50 3,119.05 2,977.28 3,586.91 m2 305.10 335.61
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
### ### ### ### m2 2,192.11 2,411.32
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
2,539.67 2,793.63 2,666.65 3,212.68 m2 273.27 300.59
2,796.17 3,075.78 2,935.98 3,537.15 m2 300.87 330.95
2,965.50 3,262.05 3,113.78 3,751.36 m2 319.09 351.00
3,390.83 3,729.92 3,560.38 4,289.40 m2 364.85 401.34
2,971.67 3,268.83 3,120.25 3,759.16 m2 319.75 351.73
3,144.47 3,458.91 3,301.69 3,977.75 m2 338.34 372.18
1,729.31 1,902.25 1,815.78 2,187.58 Point 1,729.31 1,902.25
1,548.05 1,702.85 1,625.45 1,958.28 Point 1,548.05 1,702.85
3,919.74 4,311.71 4,115.73 4,958.47 Point 3,919.74 4,311.71
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### m3 ### ###
### ### ### ### Nos ### ###
### ### ### ### Nos ### ###
### ### ### ### Nos ### ###
58.35 64.19 61.27 73.81 m 191.39 210.53
75.64 91.13
94.55 113.91
434.70 523.71
496.80 598.53
621.00 748.16
558.90 673.34
683.10 822.98
Rate with O/H & Profit
Rate with priliminery
, O/H & Profit
673.56 811.48
558.90 673.34
1,536.65 1,851.29
1,536.65 1,851.29
520.75 627.38
885.27 1,066.54
724.69 873.08
### ###
### ###
### ###
### ###
### ###
### ###
548.27 660.54
548.27 660.54
757.68 912.83
1,062.50 1,280.06
891.58 1,074.14
1,382.34 1,665.39
1,766.63 2,128.37
2,204.95 2,656.44
1,968.53 2,371.61
2,405.32 2,897.83
2,363.51 2,847.47
726.19 874.89
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
1,299.26 1,565.30
1,348.22 1,624.28
1,409.42 1,698.01
1,545.34 1,861.77
1,618.78 1,950.24
1,655.50 1,994.48
1,951.44 2,351.02
2,024.87 2,439.49
2,061.59 2,483.73
915.15 1,102.54
1,361.24 1,639.98
1,838.37 2,214.80
2,300.52 2,771.58
2,039.89 2,457.58
2,374.60 2,860.82
2,506.23 3,019.41
743.65 895.92
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
1,787.65 2,153.69
1,836.60 2,212.67
1,861.01 2,242.08
2,170.90 2,615.41
2,219.85 2,674.39
2,244.33 2,703.89
701.18 844.76
1,116.31 1,344.89
1,149.80 1,385.23
1,160.96 1,398.68
1,172.12 1,412.13
2,990.53 3,602.88
3,080.25 3,710.96
3,110.15 3,746.99
3,140.06 3,783.02
1,454.98 1,752.90
1,513.18 1,823.02
1,527.73 1,840.55
7,988.06 9,623.71
7,707.45 9,285.64
8,479.20 ###
8,214.86 9,896.95
7,934.25 9,558.88
8,706.00 ###
8,530.83 ###
8,963.43 ###
7,734.38 9,318.09
8,054.95 9,704.29
8,280.34 9,975.84
1,027.44 1,237.82
1,076.25 1,296.62
1,125.05 1,355.42
517.74 623.75
529.82 638.31
559.58 674.16
412.80 497.32
430.47 518.61
447.07 538.62
1,793.44 2,160.67
1,959.69 2,360.97
1,979.52 2,384.85
6,418.26 7,732.48
2,903.70 3,498.27
3,789.80 4,565.81
4,686.64 5,646.28
2,060.92 2,482.92
1,125.99 1,356.56
1,492.33 1,797.91
2,098.82 2,528.57
1,163.89 1,402.21
1,530.23 1,843.56
2,133.42 2,570.26
1,198.49 1,443.90
1,601.08 1,928.92
1,646.13 1,983.19
906.96 1,092.67
1,237.36 1,490.73
1,684.03 2,028.85
944.85 1,138.32
1,275.25 1,536.38
1,718.63 2,070.53
979.45 1,180.01
1,346.10 1,621.74
4,014.87 4,836.96
468.96 564.99
2,305.62 2,777.72
2,934.29 3,535.12
731.81 881.66
1,159.94 1,397.45
1,288.59 1,552.44
2,024.39 2,438.91
3,290.37 3,964.12
198.17 238.74
286.33 344.96
369.78 445.50
395.03 475.92
508.00 612.02
533.25 642.43
693.68 835.72
718.92 866.13
1,069.66 1,288.69
1,094.91 1,319.10
1,769.38 2,131.68
1,794.62 2,162.09
2,251.55 2,712.58
2,276.79 2,742.99
1,116.03 1,344.56
59.56 71.75
52.61 63.38
68.36 82.35
137.34 165.46
213.68 257.43
338.75 408.11
28.16 33.93
43.16 51.99
56.81 68.44
90.09 108.54
143.33 172.67
232.70 280.35
37.22 44.84
56.42 67.97
81.38 98.04
121.72 146.64
198.20 238.78
303.45 365.59
33.41 40.25
44.21 53.26
52.61 63.38
91.14 109.80
123.38 148.64
186.50 224.69
33.41 40.25
44.21 53.26
48.41 58.32
86.63 104.36
116.76 140.67
184.09 221.78
29.21 35.19
38.96 46.93
50.51 60.85
74.34 89.56
111.51 134.34
510.33 614.83
428.00 515.63
559.14 673.63
481.01 579.51
607.95 732.43
529.82 638.31
636.92 767.34
639.81 770.81
630.20 759.24
648.96 781.84
697.76 840.64
924.11 1,113.33
320.35 385.95
878.17 1,057.98
878.17 1,057.98
878.17 1,057.98
878.17 1,057.98
2,301.71 2,773.02
878.17 1,057.98
286.93 345.68
315.91 380.60
335.04 403.65
383.10 461.54
335.74 404.49
355.26 428.01
1,815.78 2,187.58
1,625.45 1,958.28
4,115.73 4,958.47
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
### ###
200.96 242.11
STANDARD BSR
Caterary Description Qty Unit
Excavation & earthwork
A1
Excavation & earthwork Labour
Excavation & earthwork Un/skilled Labour 1.00 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A2
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.25 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A3
Excavation & earthwork
Clearing site & grubbing up all small trees not exceeding 500mm girth & including bushes scrubs, undergrowth hedges etc.
Excavation of top soil of average depth of 6'' and carting away surplus soil
Drains, earth in any soil except rock requiring blasting cut to gradient & shape as directed & depositing soil within site
Main Index
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 days
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A4
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.00 days
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A5
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.50 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavate trench for wall foundation in ordinary soil & part return fill in ram & depoisting surplus excavated material within site as derected.(not exceeding 5'- 0" deep.)
Excavate trench for wall foundation in ordinary soil & part return fill in ram, & depoisting surplus excavated material within site as directed.(exceeding 5'-0" but not exceeding 10'-0")
Excavation & earthwork
A6
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.25 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A7
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.75 day
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A8
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Cutting & loading earth to tractor
Excavation & earthwork
Excavation & earthwork Un / skilled Labour 2.50 days
Excavation & earthwork
Excavate pit for column foundation in any material except rock requiring blasting, part return fill in ram, & depoisting surplus excavated material within site as directed.(not exceeding 5'- 0" deep.)
Excavate pit for column foundation in any material except rock requiring blasting, part return fill in ram, & depoisting surplus excavated material within site as directed.(exceeding 5'-0" but not exceeding 10'-0"deep)
Cutting & levlling site in any material except rock requiring blasting including transporting up to 1/4 mile depositing & leveling
Excavation & earthwork Transporting earth
Excavation & earthwork tractor 0.17 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A9
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.25 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A10
Excavation & earthwork Materials
Excavation & earthwork Earth with transport 1.35 Cube
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 day
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A11
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers. (Earth available at site)
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers. (earth not avilable at site)
Filling under floors with gravel or other approved quality of filling, spread, Watered & well rammed in 3'' thick layers.(within Colombo Municipal limits)
Excavation & earthwork Materials
Excavation & earthwork Earth with transport 1.35 Cube
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A12
Excavation & earthwork Assume 1.2 Sqr
Excavation & earthwork Note
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Materials
Excavation & earthwork 1½'' thick planks 40.00 Sq.ft
Excavation & earthwork 2'' x 6'' joist 40.00 l ft
Excavation & earthwork 2'' x 4'' joist 40.00 l ft
Excavation & earthwork Wire nails 0.50 kg
Excavation & earthwork
Excavation & earthwork 3% westege
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork for single use
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled Labour 0.50 day
Excavation & earthwork Un / skilled Labour 0.50 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Earth work support in trenches up to 5' 0'' deep.(open planking)
Consider trench 12'-0" long 3'-0" wide and 5'-0" deep open planking to both side. (class II Timber)
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A13
Excavation & earthwork Note
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Materials
Excavation & earthwork 1½" thick planks 110.00 Sq.ft
Excavation & earthwork 2'' x 6'' joist 40.00 l ft
Excavation & earthwork 2'' x 4'' joist 24.00 l ft
Excavation & earthwork Wire nails 0.50 kg
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork For single use
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled labour 0.75 day
Excavation & earthwork Un /Skilled labour 1.50 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A14
Excavation & earthwork assume 2 Sqr
Excavation & earthwork Materials
Excavation & earthwork 1½" thick planks 220.00 Sq.ft
Excavation & earthwork 12' 0'' long joist (2''x6'') 6.00 no
Excavation & earthwork 4' 0'' long props (2''x4'') 12.00 no
Excavation & earthwork Wire nails 2.00 kg
Excavation & earthwork
Excavation & earthwork Westage 3%
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork For single use
Earth work support in trenches up to 5' 0'' deep.(close planking)
Consider trench 10'-0" long 3'-0" wide and 5'-0" deep closed planking to both side (class II Timber)
Earth work support in trenches up to 10' 0'' deep. (close planking)
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled labour 2.00 day
Excavation & earthwork Un /Skilled labour 3.00 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Cost for one Sqr
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Concrete work B1 Concrete 1:3:6 (2") grade 10
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 13.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture(14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work Curing
Concrete work
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B2 Concrete 1:3:6 (1") grade 10
Concrete work
Concrete work MIXING Cost
Concrete work
Concrete work Materials
Concrete work Cement 13.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture (14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work
5% of labour Cost for scaffolding for scafolding
5% of labour Cost for scaffolding for scafolding
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B3 Concrete 1:2½:5 (1") grade 15
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 14.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture (14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
5% of labour Cost for scaffolding for scafolding
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B4 Concrete 1:2:4 (3/4") grade 20
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 18.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
5% of labour Cost for scaffolding for scafolding
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B5 Concrete 1:11/2:3 (3/4") grade 25
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 23.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 14/10 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B5a Concrete1 :1:2 (3/4") grade 30
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 31.00 bags
5% of labour Cost for scaffolding for scafolding
Concrete work Sand -rough 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B6
Concrete work
Concrete work Materials
Concrete work mixed Concrete 0.17 Cube
Concrete work (As per item B.01)
Concrete work 10% for Wastage
5% of labour Cost for scaffolding for scafolding
2" thick blinding layer under wall / column foundation (1:3:6 -2") grade 10
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B7
Concrete work Materials
Concrete work mixed Concrete 0.17 Cube
Concrete work (As per item B.02)
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B8
Concrete work Materials
Concrete work mixed Concrete 0.25 Cube
Concrete work (As per item B.02)
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
2" thick blinding layer under wall/ column foundation (1:3:6 -1") grade 10
3" thick blinding layer under wall/ column foundation (1:3:6 -1") grade 10
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B9
Concrete work
Concrete work Materials
Concrete work mixed Concrete (As per item no 2) 0.33 Cube
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.33 day
Concrete work Un / skilled Labour 1.33 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.25 day
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B10
Concrete work Assume 10 L.ft
Concrete work Materials
Concrete work Concrete (B.04) 0.02 Cube
Concrete work Sawn form work 13.70 S.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
4" thick ground floor slab (1:3:6 -1") Grade10
Cement Concrete 1:2:4(3/4) lintol size 41/2'' x 6'' with & including formwork (reinforcement paid separately)
Concrete work
Concrete work Cost for 1 L.ft with Preliminaries
Concrete work
Concrete work
B11
Concrete work Assume 10 L.ft
Concrete work
Concrete work Materials
Concrete work Concrete (B.04) 3.75 c.ft
Concrete work Sawn form work 20.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 L.ft with Preliminaries
Concrete work
Concrete work
Concrete work
B12
Concrete work
Concrete work Materials
Concrete work
Concrete work Concrete (B.04) 5.63 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1.0 l.ft with perlimanary
Concrete work
Concrete work
Cement Concrete 1:2:4(3/4") lintol size 6'' x 9'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:2:4(3/4") lintol size 9'' x 9'' with & including formwork
Concrete work
B13
Concrete work Materials
Concrete work Concrete (B.04) 7.50 c.ft
Concrete work Sawn form work 27.72 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1.0 l.ft with perlimanary
Concrete work
Concrete work
Concrete work
B14
Concrete work
Concrete work Materials
Concrete work
Concrete work Concrete (B 04) 5.60 c.ft
Concrete work Sawn form work 27.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft
Concrete work
Concrete work
Concrete work
B15
Concrete work Materials
Concrete work Concrete (B 04) 8.40 c.ft
Concrete work Sawn form work 30.00 s.ft
Concrete work
Concrete work Add
Cement Concrete 1:2:4(3/4") lintol size 9'' x 12'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 6'' x 13' 6'' with & including formwork
Cement Concrete 1:2:4(3/4") lintol size 9'' X 13' 6'' with & including formwork
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft
Concrete work
Concrete work
B16
Concrete work Materials
Concrete work Concrete (B 04) 11.20 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B17
Concrete work Materials
Concrete work Concrete (B 04) 1.37 c.ft
Concrete work Sawn form work 11.20 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Cement Concrete 1:2:4(3/4") lintol size 12'' x 13' 6'' with & including formwork
Cement Concrete 1:2:4(3/4")lintol size 4 1/2" x4 1/2" with & including formwork.(rein forcement paid seperately)
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B18
Concrete work 16no 9" x 9" columns each 5'-0" high
Concrete work .45 Cube (80 L.ft)
Concrete work
Concrete work Materials
Concrete work Mixed Concrete (As per item B.04) 0.45 Cube
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 50.00 gal
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for .45 Cubes
Concrete work Cost for 1 Cubes
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B19 9" x 9" Concrete columns in first floor
Concrete work 9" x 9" Concrete columns in ground floor
Concrete work Add
Concrete column in ground floor (1:2:4 3\4")
5% of labour Cost for scaffolding for scaffolding
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B20
Concrete work
Concrete work Cost of 9" x 9" columns
Concrete work
Concrete work Add
Concrete work Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B21 9" x 9" Concrete columns in third floor
Concrete work Cost of 9" x 9" columns
Concrete work
Concrete work Add
Concrete work Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B22
Concrete work
Concrete work Materials
Concrete work As per item B 04
Concrete work Mixed Concrete 0.50 Cube
Concrete work
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
9" x 9" Concrete columns in second floor
Concrete columns in ground floor 10 no 12"x12" columns each 5' 0" high
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Cost for one Cube without prelimineries
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B23
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B24
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B25
5% of labour Cost for scaffolding for scaffolding
12" x 12" Concrete columns in first floor
12" x 12" Concrete columns in second floor
12" x 12" Concrete columns in third floor
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 4 Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B26
Concrete work Assume 0.45 Cube
Concrete work Note 8 nos 9"x9' beam 10 ft long
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.45 Cube
Concrete work Add 5% Wastage
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work Add
Concrete work 3%of labour Cost for tools
Concrete work 5%of labour Cost for scaffolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B27 9" x 9" Concrete beam in first floor
Concrete work Cost of 9"x 9" beam
Concrete work Add
9" x 9" Concrete beams in ground floor level Grade 20
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B28 9" x 9" Concrete beam in second floor
Concrete work Cost of 9" x 9" beam
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B29 9" x 9" Concrete beam in third floor
Concrete work Cost of 9" x 9" beam
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B30
Concrete work 6 nos 9" x12" beam 10ft long 0.5 Cube
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work
Concrete work
Concrete work Tools
Concrete work Scaffolding
Concrete work
Concrete work Curing
Concrete beams in ground floor level Grade 20
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B31 Concrete beam in first floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B32 Concrete beam in second floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B33 Concrete beam in third floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B34 Concrete beams in ground floor level
Concrete work 5 nos 12"x12" beam 10 ft long
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Tools
Concrete work Scaffolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B35 Concrete beam in first floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 2 Un /Skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B36 Concrete beam in second floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B37 Concrete beam in third floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 4 Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B38
Concrete work
Concrete work
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.33 Cube
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labourfor Vibrator operator 0.50 day
Concrete work 2 Un /Skilled Labour 1.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work Scaffolding
Concrete work Tools
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B39 4" thick Concrete slab in second floor
Concrete work 4" thick Concrete slab in ground floor
Concrete work 2 Un /Skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
4" thick Concrete slab in first floor Grade 20
Concrete work
Concrete work
Concrete work B40 4" thick Concrete slab in third floor
Concrete work 4" thick Concrete slab in ground floor
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B41 5" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work Materials
Concrete work Mixed Concrete
Concrete work As per item B 04 0.42 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labourfor Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work Scaffolding
Concrete work Tools
Concrete work
Concrete work Curing
Concrete work Water
Concrete work Un / skilled Labour 100.00 gal
Concrete work 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B42 5" thick Concrete slab in second floor
Concrete work 5" thick Concrete slab in ground floor
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B43 5" thick Concrete slab in third floor
Concrete work 5" thick Concrete slab in ground floor
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B44 6" thick Concrete slab in first floor
Concrete work 0.5 Cube
Concrete work MIXING Cost
Concrete work Materials
Concrete work Mixed Concrete
Concrete work As per item B 04 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.67 day
Concrete work Vibrator operator 0.67 day
Concrete work 3 Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.67 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work Cost for 1 Sqr
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B45 6" thick Concrete slab in second floor
Concrete work 6" thick Concrete slab in first floor
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B46 6" thick Concrete slab in third floor
Concrete work 6" thick Concrete slab in first floor
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B47
Concrete work
Concrete work Materials
Concrete work Concrete (As per the item B 05) 1.85 c.ft
Concrete work Sawn form work 13.70 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B48
Concrete work Materials
Concrete work Assume 10L.ft
Concrete work
Concrete work Concrete As per item B 05 3.75 c.ft
Concrete work Sawn form work 20.00 s.ft
Concrete work
Concrete work Add
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6''x 6'' with & including formwork (reinforcement paid seperately)
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 9'' with & including formwork (reinforcement paid seperately)
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un /Skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B49
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 5.63 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
B50
Concrete work
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work As per item B 05
Concrete work Concrete 7.50 c.ft
Concrete work Sawn form work 27.72 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 9'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 12'' with & including formwork (reinforcement paid separately)
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
B51
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 5.60 c.ft
Concrete work Sawn form work 27.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B52
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 8.40 c.ft
Concrete work Sawn form work 30.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 13' 6'' with & including formwork (reinfrcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 13 ' 6'' with & including formwork (reinforcement paid separately)
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B53
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 11.20 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B54
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 1.37 c.ft
Concrete work Sawn form work 11.20 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un /Skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Cement Concrete 1:11/2:3 (3/4") lintol size 12'' x 13' 6'' with & including formwork (reinforcement paid separately)
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6'' x 4' 6'' with & including formwork (reinforcement paid separately)
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B55
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item B 05 0.45 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work Un Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
Concrete work
Concrete work
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 0.45 Cubes
Concrete work Cost for one Cube
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B56 9" x 9" Concrete colomns in first floor
Concrete work
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete colomns in ground floor 1 : 1 1/2 : 3(3/4") 16 no 9" x 9" columns each 5'0" high
5% of labour Cost for scaffolding for scaffolding
Cost for one Cube 9" x 9" colomns in ground floor
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B57
Concrete work
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B58 9" x 9" Concrete colomns in third floor
Concrete work
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B59 Concrete colomns in ground floor
Concrete work
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item B 05 0.50 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
9" x 9" Concrete colomns in second floorCost for one Cube 9" x 9" colomns in ground floor
Cost for one Cube 9" x 9" colomns in ground floor
10 no 12" x 12" colomns each 5' 0" high 0.50 Cube
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
Concrete work
Concrete work Curing
Concrete work
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 0.45 Cubes
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B60
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B61
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B62
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
5% of labour Cost for scaffolding for scaffolding
12" x 12" Concrete colomns in first floor
12" x 12" Concrete colomns in second floor
12" x 12" Concrete colomns in third floor
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B63
Concrete work 8 no 9" x 9" beam 10' 0" ft long 0.45 Cube
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item no 5 0.45 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work 3% of labour Cost for tools for tool
Concrete work Curing
Concrete work
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work Cost for 0.45 Cubes
Concrete work Cost for one Cube
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B64 9" x 9" Concrete colomns in first floor
Concrete work
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
9" x 9" Concrete beams in ground floor level
5% of labour Cost for scaffolding for scaffolding
Cost of one Cube in 9" x 9" beam in ground floor
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B65
Concrete work
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B66
Concrete work
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B67
Concrete work
Concrete work Materials
Concrete work
Concrete work Mixed Concrete As per item B 04 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
12" x 12" Concrete colomns in second floor
Cost of one Cube in 9" x 9" beam in ground floor
12" x 12" Concrete colomns in third floor
Cost of one Cube in 9" x 9" beam in ground floor
Concrete beam in ground floor level 9" x 12"
6 no 9" x 12" beam 10' 0" ft long 0.50 Cube
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B68 Concrete beam in first floor 9" x 12"
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B69
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B70
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work
Concrete beam in second floor 9" x 12"
Concrete beam in third floor 9" x 12"
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B71
Concrete work
Concrete work Materials
Concrete work mixed Concrete As per item B 05 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work for one Cube without Preliminaries
Concrete work
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B72
Concrete work
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete beam in ground floor level 12" X 12"
5 no 12" x 12" beam 10' 0" ft long 0.50 Cube
Concrete beam in first floor 12" x 12"
For one Cube 12" x 12" beam in ground floor
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B73
Concrete work
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B74
Concrete work
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B75 4" thick Concrete slab in first floor
Concrete work 0.33 Cube Grade 25
Concrete work Materials
Concrete work mixed Concrete As per item B 05 0.33 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.33 day
Concrete work Skilled Labourfor Vibrator operator 0.33 day
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.33 day
Concrete work Add
Concrete work
Concrete work
Concrete beam in second floor 12" x 12"
For one Cube 12" x 12" beam in ground floor
Concrete beam in third floor 12" x 12"
For one Cube 12" x 12" beam in ground floor
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work For one Sqr without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B76 4" thick Concrete slab in second floor
Concrete work
Concrete work
Concrete work
Concrete work 2 Un / skilled Labour 0.66 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B77 4" thick Concrete slab in third floor
Concrete work
Concrete work
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B78 5" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work 0.42 Cube
Concrete work
Concrete work Materials
Cost for 4"thick Concrete slab in ground floor
Cost for 4"thick Concrete slab in ground floor
Concrete work mixed Concrete As per item no 05 0.42 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B79 5" thick Concrete slab in second floor
Concrete work
Concrete work
Concrete work Un / skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B80 5" thick Concrete slab in third floor
Concrete work
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Cost for 5"thick Concrete slab in ground floor
Cost for 5"thick Concrete slab in ground floor
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B81 6" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work 0.50 Cube
Concrete work Materials
Concrete work mixed Concrete As per item no 05 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.67 day
Concrete work Vibrator operator operator 0.67 day
Concrete work 3 Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.67 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B82 6" thick Concrete slab in second floor
Concrete work
Concrete work 2 Un / skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B83 6" thick Concrete slab in third floor
5% of labour Cost for scaffolding for scaffolding
Cost for 6"thick Concrete slab in ground floor
Concrete work
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
FORM WORK
Formwork
Formwork
Formwork Materials
Formwork 1" thick plank 100.00 s.ft
Formwork 2"x1" 100.00 l.ft
Formwork 2"x2" 20.00 l.ft
Formwork Wire nails 1.00 kg
Formwork
Formwork Add
Formwork for Wastage 5%
Formwork Cost for for use
Formwork
Formwork Cost for one use
Formwork Mould oil 4.00 liter
Formwork
Formwork Labour
Formwork Skilled Labour 1.00 day
Formwork u/ Skilled Labour 1.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
B86
Formwork Assume 15 Sq.ft
Formwork Making mould
Formwork Materials
Formwork 1" thick plank class 11 18.00 s.ft
Formwork 2"x1" 9.00 l.ft
Formwork wire nails 0.50 kg
Formwork
Cost for 6"thick Concrete slab in ground floor
B84 & B85
Sawn formwork in sides of column foundation up to D.P.C level
Sawn formwork in 9"X 9" column in ground floor
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork u/ Skilled Labour 0.25 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Mouilding Cost for four uses
Formwork
Formwork Mouilding Cost for one uses
Formwork
Formwork B Assembling (Per one use)
Formwork Materials
Formwork 4"x2" Timber - 10 use 9.00 L.ft
Formwork 4"x2" Timber for props-10 use 48.00 L.ft
Formwork 16mm bolt - 20 use 6.00 no
Formwork Mould Oil 0.50 Liter
Formwork
Formwork Labour
Formwork Skilled Labour 0.06 Day
Formwork Un/ Skilled Labour 0.06 Day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork Labour Cost 5%
Formwork B Assebling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.13 Day
Formwork Un/ Skilled Labour 0.13 Day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork labour Cost 5%
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork Total Cost per use 15 s.ft
Formwork
Formwork
Formwork
Formwork
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
Formwork
B.87
Formwork Fost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.88
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
B.88a
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.89
Formwork A Making mould
Formwork Materials
Formwork 1" thick plank class 11 60.00 s.ft
Formwork 2"x1" 25.00 l.ft
Formwork Wire nails 1.00 kg
Sawn from work in 9"x9" column in first floor
For column in first floor add 3% to ground floor rate
Sawn from work in 9"x9" column in Second floor
For column in first floor add 4% to ground floor rate
Sawn from work in 9"x9" column in third floor
For column in first floor add 5% to ground floor rate
Sown form work in 9"x 12" beam in ground floor 20'-0" long
Formwork
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 1.00 day
Formwork Un/ Skilled Labour 1.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork A moulding Cost for one use
Formwork
Formwork B Assembling
Formwork 4"x2" Timber - 15 use 110.00 l.ft
Formwork 4"x2" Timber for props-10 use 22.00 l.ft
Formwork Mould Oil 0.50 liter
Formwork
Formwork Labour
Formwork Skilled Labour 0.50 day
Formwork u/ Skilled Labour 2.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork B assembling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork u/ Skilled Labour 0.25 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork Total Cost per use 55 s.ft
Formwork
Formwork
Formwork
Formwork Total Cost per use Sqr.
Formwork Preliminaries
5% of labour Cost for scaffolding for scaffolding (Scaffolding)
5% of labour Cost for scaffolding for scaffolding
5% of labour Cost for scaffolding for scaffolding
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
Formwork
B.90
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.91
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.92
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork B93 FORM WORK
Formwork
Formwork
Formwork Making mould
Formwork Materials
Formwork 1" thick plank class 11 100.00 s.ft
Formwork 2"x4" 55.00 l.ft
Sawn from work in 9"x12" column in first floor
for column in first floor add 3% to ground floor rate
Sawn from work in 9"x12" column in Second floor
for column in first floor add 4% to ground floor rate
Sawn from work in 9"x12" column in third floor
for column in first floor add 5% to ground floor rate
Sawn formwork for sofit of first floor slab
Formwork wire nails 2.00 kg
Formwork
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 0.75 day
Formwork u/ Skilled Labour 0.75 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Mouilding Cost for four uses
Formwork
Formwork Mouilding Cost for one uses
Formwork
Formwork B Assembling (Per one use)
Formwork Materials
Formwork 4"x2" Timber props- (10 uses) 250.00 l.ft
Formwork 2"x1" Timber for props-(10 uses) 50.00 l.ft
Formwork Base plate (10 uses) 20.00 no
Formwork Mould Oil 0.50 liter
Formwork
Formwork Labour
Formwork Skilled Labour 1.50 day
Formwork 2 u/ Skilled Labour 3.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork B Assebling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork 2 u/ Skilled Labour 0.50 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork
5% of labour Cost for scaffolding for scaffolding
5% of labour Cost for scaffolding for scaffolding
Formwork
Formwork
Formwork Total Cost per use 1Sqr
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
B. 94
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.95
Formwork Cost for ground floor
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
REINFORCEMENT
Reinforcement B96,B97,B101,B102,B106,&B107
Reinforcement
B 96
Reinforcement
Reinforcement Material
Reinforcement 25 dia Bars 50.00 Kg
Reinforcement Binding wire 0.25 Kg
Reinforcement
Reinforcement Wastage 10%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Sawn formwork in soffit of slab second flor
For beam in second floor add 4%to ground floor rate
Sawn formwork in soffit of slab third flor
For beam in third floor add 5%to ground floor rate
25 mm & 20mm dia tor steel reinforcement in fdn, Ground & first level.
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.00 day
Reinforcement Un Skilled Labour 1.00 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B98,B103,&B108
Reinforcement
B 98
Reinforcement
Reinforcement Material
Reinforcement 16 dia Bars 50.00 Kg
Reinforcement Binding wire 0.25 Kg
Reinforcement
Reinforcement Wastage 5%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.00 day
Reinforcement Un Skilled Labour 1.00 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B99,B100,B104,B105,B109&B110
Reinforcement
B 99
Reinforcement
Reinforcement Material
16mm dia tor steel reinforcement up to first level.
12mm dia &10mm dia tor steel reinforcement up to first level.
Reinforcement 16 dia Bars 50.00 Kg
Reinforcement Binding wire 0.75 Kg
Reinforcement
Reinforcement Wastage 10%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.25 day
Reinforcement Un Skilled Labour 1.25 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B111&B112
Reinforcement
B 111
Reinforcement
Reinforcement Ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement For scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
B 113
Reinforcement
Reinforcement ground floor rate
Reinforcement
25mm dia &20mm dia tor steel reinforcement in second floor
16mm dia tor steel reinforcement in second floor level & third floor level
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B114 & B115
Reinforcement
B 114
Reinforcement
Reinforcement ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B116,B117,B118,B119,B120&B121
Reinforcement
B 116
Reinforcement
Reinforcement Material
Reinforcement 6mm dia Bars 50.00 Kg
12mm & 10mm dia tor steel reinforcement in second floor level & third floor level
10mm & 6mm dia mild steel reinforcement up to first floor level
Reinforcement Binding wire 1.00 Kg
Reinforcement
Reinforcement Wastage 5%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.25
Reinforcement Un Skilled Labour 1.25
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B122 & B123
Reinforcement
B122
Reinforcement
Reinforcement ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.25 day
Reinforcement Un Skilled Labour 0.25 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement
Reinforcement
10mm & 6mm dia mild steel reinforcement in second floor level & third floor level
Masonary work BRICK WORK
Masonary work
C.01
Masonary work
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.50 day
Masonary work Un / skilled Labour 3.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.02
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.00 day
Masonary work Un / skilled Labour 3.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
One brick thick brick wall in common brick in cement & sand 1:5 in ground floor level
One brick thick brick wall in common brick in cement & sand 1:5 in first floor
Masonary work
Masonary work
C 03
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.25 day
Masonary work Un / skilled Labour 4.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.04
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un/skilled Labour 2.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
One brick thick brick wall in common brick in cement & sand 1:5 in second floor
Half brick thick brick wall in common brick in cement & sand 1:5 in ground floor
Masonary work
C.05
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un/skilled Labour 2.25 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
C.06
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.75 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Half brick thick brick wall in common brick in cement & sand 1:5 in first floor
Half brick thick brick wall in common brick in cement & sand 1:5 in second floor
Masonary work
C.07
Masonary work 10nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.25 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.08
Masonary work 10nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un/skilled Labour 1.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
9''X 9'' Brick column in cement & sand 1: 5 in ground floor
9''X 9'' Brick column in cement & sand 1: 5 in first floor
Masonary work
C.09
Masonary work
Masonary work 10nos column 5'-0" high
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.75 day
Masonary work Un / skilled Labour 1.75 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.10
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 60.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.00 day
Masonary work Un / skilled Labour 1.00 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
9''X 9'' Brick column in cement & sand 1: 5 in second floor
12''X 12'' Brick column in cement & sand 1: 5 in ground floor
Masonary work
C.11
Masonary work
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 60.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un / skilled Labour 1.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.12
Masonary work
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un/skilled Labour 1.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
12''X 12'' Brick column in cement & sand 1: 5 in first floor
12''X 12'' Brick column in cement & sand 1: 5 in second floor
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.13
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.00 day
Masonary work Un/skilled Labour 2.25 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.14
Masonary work
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.75 day
Masonary work Un/skilled Labour 3.25 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
One brick thick brick wall in common brick in cement & sand 1:5 in ground floor level
One brick thick brick wall in common brick in cement & sand 1:5 in first floor level
Masonary work
Masonary work
C.15
Masonary work
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.75 day
Masonary work Un/skilled Labour 3.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.01
Masonary work
Masonary work Materials
Masonary work Rubble 1.35 Cube
Masonary work Cement 5.00 bag
Masonary work Sand 0.40 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.00 day
Masonary work Un / skilled Labour 3.50 day
Masonary work
Masonary work Add
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
One brick thick brick wall in common brick in cement & sand 1:5 in second floor level
6" X 9" Random rubble Masonry in cement & sand 1:5 in foundation
Masonary work
D.02
Masonary work
Masonary work Materials
Masonary work Rubble 2.00 Cube
Masonary work Cement 7.50 bag
Masonary work Sand 0.60 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 4.50 day
Masonary work Un / skilled Labour 4.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.03
Masonary work Materials
Masonary work Rubble 2.70 Cube
Masonary work Cement 10.00 bag
Masonary work Sand 0.80 Cube
Masonary work Water 200.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 5.50 day
Masonary work Un / skilled Labour 5.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.04
Masonary work Materials
Masonary work Rubble 3.50 Cube
Masonary work Cement 12.00 bag
6" X 9" Random rubble Masonry in cement & sand 1:5 in 1' 6" thick wall
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 0" thick wall
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 6" thick wall
Masonary work Sand 1.00 Cube
Masonary work Water 300.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 6.50 day
Masonary work Un / skilled Labour 6.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.05
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.85 bag
Masonary work Sand 0.08 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.25 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.06
Masonary work Materials
Masonary work Block 112.00 no
Masonary work Cement 0.40 bag
Masonary work Sand 0.05 Cube
Masonary work Water 80.00 gal
Masonary work
Masonary work Labour
8" thick Solid block work in cement & sand 1;5 in ground floor (cavites un filled)
4" thick Solid block work in cement & sand 1:5 in ground floor ( cavite un filled)
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.50 day
Masonary work
Masonary work Tools 3% of labour Cost for tools
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.07
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.65 bag
Masonary work Sand 0.07 Cube
Masonary work Water 90.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 2.00 day
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.08
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled Labour 0.33 day
Masonary work
Masonary work Preliminaries
Masonary work
Scaffolding 5% of labour Cost for scaffolding
6" thick Solid block work in cement & sand 1;5 in ground floor (Cavity un filled)
8" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.9
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.10
Masonary work Materials
Masonary work Block work Cost for ground floor 7.00
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.11
Masonary work
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
4" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
6" thick Solid block work in cement & sand 1;5 in first floor(cavities un filled)
8" thick Solid block work in cement & sand 1;5 in second floor(cavities un filled)
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.12
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.13
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.50 day
Masonary work Un/skilled Labour 0.75 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
4" thick Solid block work in cement & sand 1;5 insecond floor(cavities un filled)
6" thick Solid block work in cement & sand 1;5 in second floor(cavities un filled)
Masonary work
Masonary work
D.14
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.85 bag
Masonary work Sand 0.08 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.25 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.15
Masonary work Materials
Masonary work Block 112.00 no
Masonary work Cement 0.40 bag
Masonary work Sand 0.05 Cube
Masonary work Water 80.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.50 day
Masonary work
Masonary work Tools 3% of labour Cost for tools
Masonary work
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
8" thick Hollow block work in cement & sand 1;5 in ground floor (cavites un filled)
4" thick Hollow block work in cement & sand 1:5 in ground floor ( cavite un filled)
Scaffolding 5% of labour Cost for scaffolding
Masonary work
Masonary work
D.16
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.65 bag
Masonary work Sand 0.07 Cube
Masonary work Water 90.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 2.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.17
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled Labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.18
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
6" thick Hollow block work in cement & sand 1;5 in ground floor (Cavity un filled)
8" thick Hollow block work in cement & sand 1;5 in first floor(cavities un filled)
4" thick Hollow block work in cement & sand 1;5 in first floor(cavities un filled)
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.19
Masonary work Materials
Masonary work Block work Cost for ground floor 7.00
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.20
Masonary work
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
6" thick Hollow block work in cement & sand 1;5 in first floor (cavities un filled)
8" thick Hollow block work in cement & sand 1;5 in second floor(cavities un filled)
Masonary work
Masonary work
Masonary work
D.21
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work Add
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.22
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.50 day
Masonary work Un/skilled Labour 0.75 day
Masonary work
Masonary work
Masonary work Add
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
4" thick Hollow block work in cement & sand 1;5 insecond floor(cavities un filled)
6" thick Hollow block work in cement & sand 1;5 in second floor(cavities un filled)
Roofwork
E.01
Roofwork Materials
Roofwork Class 1 Timber 5.55 c.ft
Roofwork Wastage 5%
Roofwork Reepers 2" x 2" 110.00 l.ft
Roofwork Wire nails 1.50 kg
Roofwork Calicut tiles 125.00 no
Roofwork Woodpreservitive 1.50 liter
Roofwork
Roofwork Labour
Roofwork Mason 2.00 day
Roofwork Un/skilled Labour 3.00 day
Roofwork
Roofwork Add
Roofwork Tools 3% of labour Cost for tools
Roofwork
Roofwork
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
Roofwork
E.02
Roofwork Materials
Roofwork Ridge tile 14.00 no
Roofwork sand 2.50 c.ft
Roofwork cement 0.35 bag
Roofwork lime 8.00 kg
Roofwork colouring powder 0.05 kg
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.50 day
Roofwork Un/skilled Labour 0.50 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Calicut pattern tile hip roof in single storey building consisting of wall plate ridge plate beam struct rafters & reepers.
Scaffolding 5% of labour Cost for scaffolding
Calicut pattern ridge tile hip tile on single storey building in cement lime & sand 1;1;5 coloured to match tile
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost per one L ft with Preliminaries
Roofwork
Roofwork
E.03
Roofwork
Roofwork Materials
Roofwork Class 1 Timber 3.50 c.ft
Roofwork wire nails 1.00 kg
Roofwork asbastos sheet 115.00 sq.ft
Roofwork J bolt 20.00 no
Roofwork woodpreservitive 1.00 liter
Roofwork
Roofwork Labour
Roofwork s/k labour 1.50 day
Roofwork Un/skilled Labour 2.50 day
Roofwork
Roofwork .
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.04
Roofwork Materials
Roofwork Ridge 4.00 pair
Roofwork Roofing screws 16.00 no
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.25 day
Corrugated asbastos cement sheet roofing with Timber fram in single storeyed building.
Asbastos ajestable close fitting ridge fixed complete with roofing screws or bolts
Roofwork Un/skilled Labour 0.25 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost per one L ft with Preliminaries
Roofwork
Roofwork
Roofwork
E.05
Roofwork Materials
Roofwork Asbastos sheet 115.00 s.ft
Roofwork J bolt 20.00 no
Roofwork woodpreservitive 1.00 liter
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.50 day
Roofwork 2 Un/skilled Labour 0.50 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.06
Roofwork Materials
Roofwork half round tile 500.00 no
Roofwork Labour
Roofwork 2 Un/skilled Labour 0.38 day
Roofwork
Corrugated asbastos cement sheet rooing with Timber frame in single storeyed building.
Half round tile on asbastos sheet roof (crest only )
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.07
Roofwork Materials
Roofwork Class 1 Timber 100.00 l.ft
Roofwork Wastage 5%
Roofwork Brass screws 100.00 no
Roofwork Wood primer 2.00 lit
Roofwork Enamel paint 4.00 lit
Roofwork Brush 0.10 no
Roofwork sand paper 3.00 no
Roofwork wood preservitive 2.00 lit
Roofwork
Roofwork Labour
Roofwork painter 1.00 day
Roofwork carpenter 3.00 day
Roofwork Un/skilled Labour 3.00 day
Roofwork
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost per one L.ft with Preliminaries
Roofwork
Roofwork
Roofwork
E.08
Assume 1.2 Sqr
Roofwork Materials
3/4" thick 9" high valance board fixed with brass screws to end of rafters with & including one coat of primer & two coats of enamel paint
Asbastos cement plian sheet ceiling with class 1 Timber frame consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2" cove moulding & 1/2"x1/2" beadings with painting
Roofwork 4"x2" 48.00 l.ft
Roofwork 2"x2" 72.00 l.ft
Roofwork 2"x1" 18.00 l.ft
Roofwork asbastos ceiling sheet 138.00 s.ft
Roofwork wire nails 1.50 kg
Roofwork 11/2" x 11/2" cove mouilding 44.00 l.ft
Roofwork 1/2" x 1/2" beading 48.00
Roofwork primer 1.50 l.ft
Roofwork Emlusion paint 1.75 l.ft
Roofwork Brush 0.07 no
Roofwork sand paper 2.00 no
Roofwork wood preservitive 1.00 lit
Roofwork
Roofwork
Roofwork Labour
Roofwork painter 1.25 day
Roofwork carpenter 2.25 day
Roofwork Un/skilled Labour 2.00 day
Roofwork
Roofwork
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.09
Roofwork Materials
Roofwork 4"x2" 48.00 l.ft
Roofwork 2"x2" 72.00 l.ft
Roofwork 2"x1" 18.00 l.ft
Roofwork 3/4" tk class 1 Timber ( Lumumidella ) 138.00 s.ft
Roofwork wire nails 1.00 kg
Roofwork 11/2" x 11/2" cove mouilding 44.00 l.ft
Roofwork primer 1.50 lit
Roofwork Emlusion paint 1.75 lit
Roofwork Brush 0.06 no
Roofwork sand paper 2.00 no
3/4" thick class 1 Timber ceiling with class 1 Timber frame consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2" cove moulding with painting
Roofwork wood preservitive 1.00 lit
Roofwork
Roofwork
Roofwork Labour
Roofwork painter 1.25 day
Roofwork Skilled labour 2.50 day
Roofwork Un/skilled Labour 2.50 day
Roofwork
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Plumbing PVC Pipe type 1000
Plumbing
F .01
Plumbing Materials
Plumbing 20mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
F.02
Plumbing Materials
20mm diameter pvc pipe fixed to wall or slab
25mm diameter pvc pipe fixed to wall or slab
Plumbing 25mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.03 32mm diameter pvc pipe fixed to wall
Plumbing Materials
Plumbing 32mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.04 32mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 32mm pipe 50.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.05 40mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 40mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 100.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.06 40mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 40mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing Others
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.07 50mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 50mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.08 50mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 50mm pipe 50.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.09 63mm diameter pvc pipefix to wall
Plumbing Materials
Plumbing 63mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing clipe & nails
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.10 63mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 63mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.11 75mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 75mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 100.00 grms
Plumbing Other
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.12 75mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 75mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing Other
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.13 90mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 90mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.14 90mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 90mm pipe 50.00 l.ft
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.15
Plumbing Materials
Plumbing 110mm pipe 50.00 l.ft
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
110mm diameter pvc pipe laying trench
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.16
Plumbing Materials
Plumbing bend 10.00 Nos
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.17
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Supplying & fixing PVC bend 20mm dia.
Supplying & fixing PVC bend 25mm dia.
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.18
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.19
Plumbing
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Supplying & fixing PVC bend 32mm dia.
Supplying & fixing PVC bend 40mm dia.
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.20
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.21
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Supplying & fixing PVC bend 50mm dia.
Supplying & fixing PVC bend 63mm dia.
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing ELBOW
Plumbing
F.22
Plumbing
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.23
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Supplying & fixing PVC elbow 20mm .dia.
Supplying & fixing PVC elbow 25mm .dia.
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.24
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.25
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Supplying & fixing PVC elbow 32mm .dia.
Supplying & fixing PVC elbow 40mm .dia.
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.26
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.27
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Supplying & fixing PVC elbow 50mm .dia.
Supplying & fixing PVC elbow 63mm .dia.
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing TEE
Plumbing F.28
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.50 hrs
Plumbing Un/skilled Labour 1.50 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.29 Supplying & fixing PVC tee 25mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 60.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.50 hrs
Plumbing Un/skilled Labour 1.50 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Supplying & fixing PVC tee 20mm .dia.
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.30 Supplying & fixing PVC tee 32mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.31
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 90.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Supplying & fixing PVC tee 40mm .dia.
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.32
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 120.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.33
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 200.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Supplying & fixing PVC tee 50mm .dia.
Supplying & fixing PVC tee 63mm .dia.
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing FAUCET SOCKET
Plumbing
F.34
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.35
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Supplying & fixing PVC faucet socket 20 mm dia
Supplying & fixing PVC faucet socket 25 mm dia
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.36
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un /Skilled labourer 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.37
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Supplying & fixing PVC faucet socket 32 mm dia
Supplying & fixing PVC faucet socket 40 mm dia
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.38
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.39
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Supplying & fixing PVC faucet socket 50 mm dia
Supplying & fixing PVC faucet socket 63 mm dia
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing VALUE SOCKET
Plumbing
F.40
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.41
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Supplying & fixing PVC Value socket 20 mm dia
Supplying & fixing PVC value socket 25 mm dia
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing 3% of labour Cost for tools
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.42
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.43
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Supplying & fixing PVC value socket 32 mm dia
Supplying & fixing PVC value socket 40 mm dia
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.44
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.45
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Supplying & fixing PVC value socket 50 mm dia
Supplying & fixing PVC value socket 63 mm dia
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing SOCKET
Plumbing F.46
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.47
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un /Skilled labourer 1.00 hrs
Plumbing
Plumbing Add
Supplying & fixing PVC socket 20 mm dia
Supplying & fixing PVC socket 25 mm dia
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.48
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.49
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Supplying & fixing PVC socket 32 mm dia
Supplying & fixing PVC socket 40 mm dia
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.50
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.51
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Supplying & fixing PVC socket 50 mm dia
Supplying & fixing PVC socket 63 mm dia
Plumbing
Plumbing Cost for 1 Nos with Preliminaries
Plumbing
Plumbing
Finishes
Finishes
G.01
Finishes Internal wall
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.50 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.02
Finishes External wall
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.33 day
Finishes un /Skilled labourer 1.33 day
Finishes
Finishes Add
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth with neat lime in internal wall in ground floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in external wall in ground floor
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.03
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.75 day
Finishes un /Skilled labourer 1.75 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.04
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.75 day
Finishes
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth in internal wall in first floor
3/4" Thick plaster in cement lime & sand 1;1;5 finished semi rough in external wall in first floor
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
Finishes
G.05
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.00 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
G.06
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.75 day
Finishes un /Skilled labourer 2.00 day
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in internal wall in second floor
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in external wall in second floor
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
G.07
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.25 hrs
Finishes un /Skilled labourer 2.00 hrs
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.08
Finishes
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.25 day
Finishes un /Skilled labourer 2.25 day
1/2" Thick sides & soffits plaster in first floor slab in cement lime & sand 1:1:5 finished smooth with neat lime.
1/2" Thick sides & soffits plaster in second floor slab in cement lime & sand 1;1;5 finished smooth with neat lime
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
Finishes
G.09
Finishes Materials
Finishes Cement 2.00 bags
Finishes Sand 0.11 Cube
Finishes Tar 8.00 Ltr
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.10
Finishes Materials
Finishes Cement 0.85 bags
Finishes Lime 60.00 kg
Finishes Sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.50 day
Finishes un /Skilled labourer 2.00 day
3/4" thick D.P.C. in cement and sand 1:3 finished with two coats of hot tar and blinded with sand.
1/2" Thick sides & soffits plaster in first floor beam in cement lime & sand 1:1:5 finished smooth with neat lime
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.11
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.75 hrs
Finishes un /Skilled labourer 2.25 hrs
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes H.01 PAVING
Finishes
Finishes brick 360.00 Nos
Finishes cement 2.00 bag
Finishes lime 30.00 Kg
Finishes sand 0.18 Cube
Finishes Water 25.00 gal
Finishes
Finishes Labour
1/2" Thick sides & soffits plaster in second floor beam in cement lime & sand 1:1:5 finished smooth with neat lime
3" Thick brick paving lime & sand 1:5 with & including 1/2" thick cement & sand 1:3 rendering finished smooth with neat cement
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.75 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H.02
Finishes Materials
Finishes Cement 1.25 bags
Finishes Sand 0.04 Cube
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.00 day
Finishes un /Skilled labourer 1.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H.03
Finishes Fixing only
Finishes Materials
Finishes Tile 400.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
1/2" Thick cement rendering in cement & sand 1':3 finished smooth with neat cement
6" X6" White glazed tile including joint and point with tile grout & including 3/4" tk cement ^& sand 1;3 screed backing on ground floor
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H4
Finishes Materials
Finishes Tile 225.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H5
Finishes Materials
Finishes Tile 100.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
8" X8" White glazed tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on ground floor
12" X12" White glazed tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on ground floor
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H6
Finishes Materials
Finishes Tile 400.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H7
Finishes Materials
Finishes Tile 150.00 no
Finishes Wastage 5%
6" X6" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
8" X12" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H8
Finishes Materials
Finishes Tile 225.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Painting PAINTING
8" X8" White glazed wall tile including joint and point with tile grout & including 3/4" tk cement & sand 1;3 screed backing on wall
Painting
J-01
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 0.75 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
J-02
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in ground floor internally
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in first floor internally
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-03
Painting Materials
Painting weathersheld paint 1.65 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.10 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 0.75 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-04
Painting Materials
Painting Weathersheld paint 1.65 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.08 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 1.00 day
Painting
Painting Add
Painting Tools
Prepare & apply approved type one coat of filler & two of weathershield paint to specified colour up to first floor level externally(ground floor)
Prepare & apply approved type one coat of filler & two of weathershield paint to specified colour above first floor level Externally
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-05
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting sand paper 1.00 no
Painting brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 1.00 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
J-06
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting sand paper 1.00 no
Painting brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.10 day
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in sides and soffit of beam and slab in first floor level
Prepare & apply approved type one coat of filler & two of emulsion paint to specified colour in sides and soffit of beams and slabs in second floor level
Painting un /Skilled labourer 1.10 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Electrical Electrical
Electrical K.01 Pendent lamp without bulb and shade
Electrical
Electrical Materials
Electrical 1/044 wire 0.25 coil
Electrical conduit pipe 5/8" 5.00 l.ft
Electrical Bend 1.00 no
Electrical ceiling rose 1.00 no
Electrical Holders 1.00 no
Electrical Switches 1.00 no
Electrical Switch box 1.00 no
Electrical Round block 1.00 no
Electrical Brass screws 1" 1.00 no
Electrical Brass screws 1/2" 2.00 no
Electrical Flexible wire 2 core 6.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.33 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.13 day
Electrical
Electrical Add
Electrical Tools
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Electrical
Electrical
Electrical K.02 wall bracket with out bulb and shade
Electrical Materials
Electrical 1/044 wire 0.25 coil
Electrical conduit pipe 5/8" 10.00 l.ft
Electrical Bend 2.00 no
Electrical Holders 1.00 no
Electrical Switches 1.00 no
Electrical Switch box 1.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.13 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.33 day
Electrical
Electrical
Electrical Add
Electrical Tools
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Electrical
Electrical
Electrical K.03 5 amp socket outlets
Electrical Materials
Electrical 5 amp socket outlets 1.00 no
Electrical 1/044 wire 0.25 coil
Electrical 7/044 earth wire 0.10 coil
Electrical conduit pipe 5/8" 10.00 l.ft
Electrical Bend 2.00 no
Electrical Switch box 1.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.13 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.33 day
Electrical
Electrical Add
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Concrete work
L.01
Concrete work
Concrete work Materials
Concrete work Ready mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator 3.00 day
Concrete work 12.00 day
Concrete work 18.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 3.00 day
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Suppying & placing ready mixed Concrete grade 20 (1:2:4 -3/4" ) in 125mm thick first floor slab
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Concrete work
Concrete work
L.02
Concrete work 30 m3 in Colombo Municipal area
Concrete work
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator 4.00 day
Concrete work 16.00 day
Concrete work 24.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 4.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.03
Concrete work 30m3 in Columbo Municipal area
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Suppying & placing redy mixed Concrete grade 20 (1:2:4 -3/4" ) in 225 x225mm columns in ground floor
222 no columns size 300x300mm &1500mm high.
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Suppying & placing ready mixed Concrete grade 25 (1:1 1/2:3 -3/4" ) in 125mm thick first floor slab
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 3.00 day
Concrete work 12.00 day
Concrete work 18.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 3.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.04
Concrete work 30m3 in Columbo Municipal area
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 1.00 day
Concrete work 16.00 day
Concrete work 24.00 day
Concrete work
Concrete work Add
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-3/4) in 225mmx225mm columns in ground floor.
222 no columns size 300x300mm &1500mm high.
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 4.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.05
Concrete work 20m3 in Columbo Municipal area
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.00 day
Concrete work 8.00 day
Concrete work 12.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Suppying & placing ready mixed Concrete grade 20 (1:2:4-3/4) in 125mm thick first floor slab
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.06
Concrete work 20m3 in Columbo Municipal area
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.75 day
Concrete work 11.00 day
Concrete work 16.50 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.75 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
L.07
Concrete work 20m3 in Columbo Municipal area
Suppying & placing redy mixed Concrete grade 20(1:2:4-3/4") in 225mmx225mm columns in ground floor
148 no columns size 300x300mm &1500mm high.
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Suppying & placing redy mixed Concrete grade 25 (1:11/2:3-3/4) in 125mm thick first floor slab
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.00 day
Concrete work 8.00 day
Concrete work 12.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
L.08
Concrete work 20m3 in Columbo Municipal area
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.75 day
Concrete work 11.00 day
4.00 Skilled labour for placing Concrete & prepairing top surface
6.00 un Skilled labour for placing Concrete & prepairing top surface
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-3/4") in 225mmx225mm columns in ground floor
148 no columns size 300x300mm &1500mm high.
4.00 Skilled labour for placing Concrete & prepairing top surface
Concrete work 16.50 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.75 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Wood work
M 01
Wood work
Wood work Materials
Wood work 4''x3" Timber 20.00 l.ft
Wood work Plywood door sash 1.00 no
Wood work 4"x3" butt hinges 1.50 pair
Wood work 3/4" brass screws 24.00 no
Wood work 6" iong barrel boilt 1.00 no
Wood work 12" long barrel boilt 1.00 no
Wood work 1/2" brass screws 12.00 no
Wood work mortice lock 1.00 no
Wood work enamel paint 1.25 ltr
Wood work wood primer 0.50 ltr
Wood work 4" brush 0.10 no
Wood work hold fast 6.00 no
Wood work sand paper 2.00 no
Wood work
Wood work labour
Wood work painter 0.33 day
6.00 un Skilled labour for placing Concrete & prepairing top surface
singal hung door size 3'-6"x 7'-0" high overall with 4''x3'' class 1 Timber door frame and including 11/4" tk ordinary plywood door sash with and door lock with and including ironmongrey and painting
Wood work carpainter 2.00 day
Wood work un skilld labourer 2.00 day
Wood work
Wood work Add
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Wood work
Wood work
Wood work
Wood work
M 02
Wood work
Wood work Materials
Wood work 4''x3" Timber 20.00 l.ft
Wood work 11/4" Timber plank 24.50 no
Wood work Wastage 5%
Wood work 4"x3" b utt hinges 1.50 pair
Wood work 3/4" brass screws 24.00 no
Wood work 6" long barrel bolt 1.00 no
Wood work 12" long barrel bolt 1.00 no
Wood work 1/2" brass screws 12.00 no
Wood work Mortice lock 1.00 no
Wood work Enamel paint 1.25 ltr
Wood work Wood primer 0.50 ltr
Wood work 4" brush 0.10 no
Wood work Hold fast 6.00 no
Wood work Sand paper 2.00 no
Wood work
Wood work Labour
Wood work painter 0.50 day
Wood work carpainter 3.50 day
Wood work un skilld labourer 2.50 day
Wood work
Wood work Add
singal hung door size 3'-6"x 7'-0" high overall with 4''x3'' class 1 Timber door frame and including 11/4" tk flush panneld door sash with and door lock with and including ironmongrey and painting
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Wood work
Wood work
Wood work
Wood work
M 03
Wood work Materials
Wood work 4''x3" Timber 30.00 l.ft
Wood work 1" Timber plank 6" wide. 23.00 no
Wood work Wastage 5%
Wood work glaze sheet 16.00 s ft
Wood work 4"x2" butt hinges 2.00 pair
Wood work 3/4" brass screws 32.00 no
Wood work casement fastner 2.00 no
Wood work casement stay 2.00 no
Wood work 1/2" brass screws 16.00 no
Wood work enamel paint 0.75 ltr
Wood work wood primer 0.25 ltr
Wood work 4" brush 0.10 no
Wood work hold fast 6.00 no
Wood work sand paper 1.00 no
Wood work
Wood work
Wood work labourer
Wood work painter 0.50 day
Wood work carpenter 3.50 day
Wood work un skilld labourer 2.50 day
Wood work
Wood work Add
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
window size 5'-0"x 6'-0" high overall with 4''x3'' class 1 Timber window frame and mullion comprising 1 tk glased window casement and including ironmongrey and painting
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Plumbing
N01
Plumbing Assume 15 L.ft
Plumbing
Plumbing Polybuthelene pipe 20.00 l.ft
Plumbing elbow 3.00 no
Plumbing faucet socket 2.00 no
Plumbing value socket 2.00 no
Plumbing cement sand and lime
Plumbing
Plumbing labour for placing pipe
Plumbing unSkilled labourer for chasing wall 0.33 day
Plumbing plumber 0.50 day
Plumbing Mason 0.13 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing 5% of labourer Cost
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 L.ft with Preliminaries
Plumbing
supplying & laying hot Water pipe 20mm dia
Rate Amount Amount
1 Sqr 736.45
650.00 650.00
19.50
669.50
66.95
736.45
1 Sqr 920.56
650.00 812.50
24.38
836.88
83.69
920.56
1 Cube 1,288.79
650.00 1,137.50
34.13
1,171.63
117.16
1,288.79
1 Cube 1,472.90
650.00 1,300.00
39.00
1,339.00
133.90
1,472.90
1 Cube 1,841.13
650.00 1,625.00
48.75
1,673.75
167.38
1,841.13
1 Cube 1,657.01
650.00 1,462.50
43.88
1,506.38
150.64
1,657.01
1 Cube 2,025.24
650.00 1,787.50
53.63
1,841.13
184.11
2,025.24
1 Cube 1,996.96
650.00 1,625.00
850.00 141.67
48.75
1,815.42
181.54
1,996.96
1 Cube 1,657.01
650.00 1,462.50
43.88
1,506.38
150.64
1,657.01
1 Cube 4,555.79
2,200.00 2,970.00
650.00 1,137.50
34.13
4,141.63
414.16
4,555.79
1 Cube 4,555.79
2,200.00 2,970.00
650.00 1,137.50
34.13
4,141.63
414.16
4,555.79
1 Sqr 5,070.18
125.00 5,000.00
165.00 6,600.00
165.00 6,600.00
160.00 80.00
18,280.00
548.40
18,828.40
4,707.10
950.00 475.00
650.00 325.00
800.00
24.00
5,531.10
4,609.25
553.11
6,084.21
5,070.18
1 Sqr 8,619.19
125.00 13,750.00
165.00 6,600.00
165.00 3,960.00
160.00 80.00
24,390.00
6,097.50
950.00 712.50
650.00 975.00
1,687.50
50.63
7,835.63
783.56
8,619.19
1 Sqr 7,055.76
125.00 27,500.00
780.00 4,680.00
160.00 1,920.00
160.00 320.00
34,420.00
1,032.60
35,452.60
8,863.15
950.00 1,900.00
650.00 1,950.00
3,850.00
115.50
12,828.65
6,414.33
1,282.87
14,111.52
7,055.76
1 Cube 30,156.32
740.00 9,620.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
18,682.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,062.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
27,414.83
2,741.48
30,156.32
1 Cube 30,156.32
740.00 9,620.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
18,682.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,062.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
27,414.83
2,741.48
30,156.32
1 Cube 30,970.32
740.00 10,360.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
19,422.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,802.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
28,154.83
2,815.48
30,970.32
1 Cube 34,226.32
740.00 13,320.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
22,382.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
24,762.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
31,114.83
3,111.48
34,226.32
1 Cube 38,296.32
740.00 17,020.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
26,082.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67 766.67
28,462.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
34,814.83
3,481.48
38,296.32
1 Cube 44,808.32
740.00 22,940.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
32,002.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
34,382.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
40,734.83
4,073.48
44,808.32
1 Sqr 5,338.13
14,000.00
21,062.67 3,580.65
358.07
3,938.72
950.00 237.50
650.00 650.00
887.50
26.63
4,852.84
485.28
5,338.13
1 Sqr 5,338.13
21,062.67 3,580.65
358.07
3,938.72
950.00 237.50
650.00 650.00
887.50
26.63
4,852.84
485.28
5,338.13
1 Sqr 7,376.99
21,062.67 5,265.67
526.57
5,792.23 5,792.23
950.00 237.50
650.00 650.00
887.50 887.50
26.63
6,706.36
670.64
7,376.99
1 Sqr 10,344.74
31,347.70
21,062.67 7,020.89
702.09
7,722.98
950.00 316.67
650.00 866.67
1,183.33
1,850.00 462.50
35.50
9,404.31
940.43
10,344.74
1 L.ft 284.77
31,114.83 575.62
13,234.77 1,813.16
2,388.79
950.00 118.75
650.00 81.25 200.00
2,588.79
258.88
25.89
284.77
1 L.ft 441.51
31,114.83 1,166.81
13,234.77 2,646.95
3,813.76
950.00 118.75
650.00 81.25 200.00
4,013.76
401.38
40.14
441.51
1 L.ft 564.25
31,114.83 1,751.77
13,234.77 2,977.82
4,729.59
950.00 237.50
650.00 162.50 400.00
5,129.59
512.96
51.30
564.25
1 L.ft 704.25
31,114.83 2,333.61
13,234.77 3,668.68
6,002.29
950.00 237.50
650.00 162.50 400.00
6,402.29
640.23
64.02
704.25
1 L.ft 628.74
31,114.83 1,742.43
13,234.77 3,573.39
5,315.82
950.00 237.50
650.00 162.50 400.00
5,715.82
571.58
57.16
628.74
1 L.ft 768.25
31,114.83 2,613.65
13,234.77 3,970.43
6,584.08
950.00 237.50
650.00 162.50 400.00
6,984.08
698.41
69.84
768.25
1 L.ft 754.90
31,114.83 3,484.86
13,234.77 2,977.82
6,462.69
950.00 237.50
650.00 162.50
400.00
6,862.69
686.27
68.63
754.90
1 L.ft 231.94
31,114.83 426.27
13,234.77 1,482.29
1,908.57
950.00 118.75
650.00 81.25 200.00
2,108.57
210.86
21.09
231.94
1 Cube 36,402.32
24,762.67 11,143.20
557.16
11,700.36
950.00 475.00
950.00 475.00
650.00 975.00
1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 25.00
650.00 162.50
187.50
14,891.86
33,093.02
3,309.30
36,402.32
1 Cube 37,117.32
33,093.02
650.00 650.00 650.00
33,743.02
3,374.30
37,117.32
1 Cube 37,474.82
33,093.02
650.00 975.00 975.00
34,068.02
3,406.80
37,474.82
1 Cube 37,832.32
33,093.02
650.00 1,300.00 1,300.00
34,393.02
3,439.30
37,832.32
1 Cube 35,622.18
24,762.67 12,381.33
619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00 925.00
57.75
96.25 154.00
0.50 25.00
650.00 162.50 187.50
16,191.90
32,383.80
3,238.38
35,622.18
1 Cube 36,337.18
32,383.80
650.00 650.00 650.00
33,033.80
3,303.38
36,337.18
1 Cube 36,694.68
32,383.80
650.00 975.00 975.00
33,358.80
3,335.88
36,694.68
1 Cube 37,052.18
32,383.80
650.00 1,300.00 1,300.00
33,683.80
3,368.38
37,052.18
1 Cube 36,595.84
24,762.67 11,143.20
557.16 11,700.36
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
0.50 50.00
650.00 216.67 266.67
14,971.03
33,268.95
3,326.89
36,595.84
1 Cube 37,310.84
33,268.95
650.00 650.00 650.00
33,918.95
3,391.89
37,310.84
1 Cube 37,668.34
33,268.95
650.00 975.00 975.00
34,243.95
3,424.39
37,668.34
1 Cube 38,025.84
33,268.95
650.00 1,300.00 1,300.00
34,568.95
3,456.89
38,025.84
1 Cube 35,796.34
24,762.67 12,381.33
619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.66 266.66
16,271.06
32,542.13
1,627.11
17,898.17
35,796.34
1 Cube 36,511.34
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.34
1 Cube 36,868.84
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.84
1 Cube 37,226.34
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.34
1 Cube 35,796.35
24,762.67 12,381.33
0.05 619.07
13,000.40
950.00 475.00
950.00 475.00
650.00 975.00
1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 50.00
650.00 216.67
266.67
16,271.07
32,542.13
1,627.11
17,898.17
35,796.35
1 Cube 36,511.35
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.35
1 Cube 36,868.85
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.85
1 Cube 37,226.35
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.35
1 Sqr 12,649.92
24,762.67 8,171.68
408.58
8,580.26
950.00 475.00
950.00 475.00
650.00 650.00
1,600.00
1,850.00 925.00 925.00
80.00
48.00
128.00
0.50 50.00
650.00 216.66
266.66
11,499.93
1,149.99
12,649.92
1 Sqr 13,126.58
11,499.93
650.00 433.33 433.33
11,933.26
1,193.33
13,126.58
1 Sqr 13,722.42
11,499.93
650.00 975.00 975.00
12,474.93
1,247.49
13,722.42
1 Sqr 15,045.80
24,762.67 10,400.32
520.02 10,920.34
950.00
950.00 475.00
650.00 975.00
1,450.00
1,850.00 925.00
0.03 43.50
0.05 72.50 116.00
0.50 50.00
650.00 216.66 266.66
13,678.00
1,367.80
15,045.80
1 Sqr 15,760.80
13,678.00
650.00 650.00 650.00
14,328.00
1,432.80
15,760.80
1 Sqr 16,118.30
13,678.00
650.00 975.00 975.00
14,653.00
1,465.30
16,118.30
1 Sqr 18,999.64
24,762.67 12,381.33
0.05 619.07 13,000.40
950.00 633.33
950.00 633.33
650.00 1,300.00 2,566.67
1,850.00 1,233.33
0.03 77.00
0.05 128.33 205.33
0.50 50.00
650.00 216.67 266.67
17,272.40
1,727.24
18,999.64
1 Sqr 19,714.64
17,272.40
650.00 650.00 650.00
17,922.40
1,792.24
19,714.64
1 Sqr 20,072.14
17,272.40
650.00 975.00 975.00
18,247.40
1,824.74
20,072.14
1 L.ft 292.30
34,814.83 644.07
13,234.77 1,813.16
2,457.24
950.00 118.75
650.00 81.25 200.00
2,657.24
265.72
26.57
292.30
1 L.ft 434.78
34,814.83 1,305.56
13,234.77 2,646.95
3,952.51
950.00 118.75
650.00 81.25
200.00
3,952.51
395.25
39.53
434.78
1 L.ft 587.17
34,814.83 1,960.08
13,234.77 2,977.82 4,937.90
950.00 237.50
650.00 162.50 400.00
5,337.90
533.79
53.38
587.17
1 L.ft 734.78
34,814.83 2,611.11
13,234.77 3,668.68 6,279.79
950.00 237.50
650.00 162.50 400.00
6,679.79
667.98
66.80
734.78
1 L.ft 651.53
34,814.83 1,949.63
13,234.77 3,573.39 5,523.02
950.00 237.50
650.00 162.50 400.00
5,923.02
592.30
59.23
651.53
1 L.ft 758.44
34,814.83 2,924.45
13,234.77 3,970.43 6,894.88
950.00 237.50
650.00 162.50
400.00
6,894.88
689.49
68.95
758.44
1 L.ft 800.48
34,814.83 3,899.26
13,234.77 2,977.82 6,877.09
950.00 237.50
650.00 162.50 400.00
7,277.09
727.71
72.77
800.48
1 L.ft 237.52
34,814.83 476.96
13,234.77 1,482.29 1,959.26
950.00 118.75
650.00 81.25 200.00
2,159.26
215.93
21.59
237.52
1 Cube 38,642.03
28,462.67 12,808.20
640.41
13,448.61
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 25.00
650.00 162.50
187.50
16,640.11
36,978.02
1,664.01
38,642.03
1 Cube 41,390.82
36,978.02
650.00 650.00 650.00
37,628.02
3,762.80
41,390.82
1 Cube 41,748.32
36,978.02
650.00 975.00 975.00
37,953.02
3,795.30
41,748.32
1 Cube 42,105.82
36,978.02
650.00 1,300.00 1,300.00
38,278.02
3,827.80
42,105.82
1 Cube 39,895.68
28,462.67 14,231.33
5% 711.57 14,942.90
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
0.50 25.00
650.00 162.50 187.50
18,134.40
36,268.80
1,813.44
19,947.84
39,895.68
1 Cube 40,610.68
36,268.80
650.00 650.00 650.00
36,918.80
3,691.88
40,610.68
1 Cube 40,968.18
36,268.80
650.00 975.00 975.00
37,243.80
3,724.38
40,968.18
1 Cube 41,325.68
36,268.80
650.00 1,300.00 1,300.00
37,568.80
3,756.88
41,325.68
1 Cube 40,869.34
28,462.67 12,808.20
5% 640.41 13,448.61
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.05 96.25
0.03 57.75
154.00
0.50 50.00
650.00 216.67 266.67
16,719.28
37,153.95
3,715.39
40,869.34
1 Cube 41,584.34
37,153.95
650.00 650.00 650.00
37,803.95
3,780.39
41,584.34
1 Cube 41,941.84
37,153.95
650.00 975.00 975.00
38,128.95
3,812.89
41,941.84
1 Cube 42,299.34
37,153.95
650.00 1,300.00 1,300.00
38,453.95
3,845.39
42,299.34
1 Cube 35,796.35
24,762.67 12,381.33
0.05 619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
16,271.07
32,542.13
3,254.21
35,796.35
1 Cube 36,511.35
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.35
1 Cube 36,868.85
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.85
1 Cube 37,226.35
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.35
1 Cube 40,069.85
28,462.67 14,231.33
0.05 711.57 14,942.90
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
18,213.57
36,427.13
3,642.71
40,069.85
1 Cube 40,784.85
36,427.13
650.00 650.00 650.00
37,077.13
3,707.71
40,784.85
1 Cube 41,142.35
36,427.13
650.00 975.00 975.00
37,402.13
3,740.21
41,142.35
1 Cube 41,499.85
36,427.13
650.00 1,300.00 1,300.00
37,727.13
3,772.71
41,499.85
1 Sqr 13,344.81
1 Cube 40,438.81
28,462.67 9,392.68
0.05 469.63 9,862.31
950.00 316.67
950.00 316.67
650.00 650.00 1,283.33
1,850.00 616.67
0.03 38.50
0.05 64.17 102.67
0.50 50.00
650.00 216.66 266.66
12,131.64
1,213.16
13,344.81
36,762.56
3,676.26
40,438.81
1 Sqr 26,377.35
1 Cube 41,868.81
12,131.64
650.00 429.00 429.00
12,560.64
1,256.06
26,377.35
38,062.56
3,806.26
41,868.81
1 Sqr 69,443.40
1 Cube 42,603.31
12,131.64
650.00 649.35 649.35
12,780.99
1,278.10
69,443.40
38,730.28
3,873.03
42,603.31
1 Sqr 17,404.97
28,462.67 11,954.32
597.72 12,552.04
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
15,822.70
1,582.27
17,404.97
1 Sqr 17,881.59
15,822.70
650.00 433.29 433.29
16,255.99
1,625.60
17,881.59
1 Sqr 18,119.26
15,822.70
650.00 649.35 649.35
16,472.05
1,647.21
18,119.26
1 Sqr 21,136.37
28,462.67 14,231.33
0.05 711.57 14,942.90
950.00 633.33
950.00 633.33
650.00 1,300.00 2,566.65
1,850.00 1,233.33
0.03 77.00
0.05 128.33 205.33
0.50 50.00
650.00 216.67 266.67
19,214.89
1,921.49
21,136.37
1 Sqr 21,612.99
19,214.89
650.00 433.29 433.29
19,648.18
1,964.82
21,612.99
1 Sqr 21,851.37
19,214.89
650.00 650.00 650.00
19,864.89
1,986.49
21,851.37
1 Sqr 6,826.88
125.00 12,500.00
33.00 3,300.00
55.00 1,100.00
160.00 160.00
17,060.00
853.00
17,913.00
4,478.25
20.00 80.00
950.00 950.00
650.00 650.00 1,600.00
48.00
6,206.25
620.63
6,826.88
1 Sqr 10,868.64
125.00 2,250.00
33.00 297.00
160.00 80.00
2,627.00
131.35
950.00 237.50
650.00 162.50
400.00
12.00
3,170.35
A 792.59
165.00 148.50
40.00 192.00
50.00 15.00
20.00 10.00 365.50
950.00 59.38
650.00 40.63 100.00
3% 3.00
5% 5.00
B 473.50
950.00 118.75
650.00 81.25 200.00
3% 6.00
5% 10.00
C 216.00
.
A+B+C 792.59
473.50
216.00
1,482.09
9,880.58
988.06
10,868.64
1 Sqr 11,194.70
9,880.58
296.42
10,177.00
1,017.70
11,194.70
1 Sqr 11,303.39
9,880.58
395.22
10,275.81
1,027.58
11,303.39
1 Sqr 11,412.07
9,880.58
494.03
10,374.61
1,037.46
11,412.07
1 Sqr 29,116.50
125.00 7,500.00
33.00 825.00
160.00 160.00 8,485.00
424.25
950.00 950.00
650.00 650.00 1,600.00
48.00
80.00
A 10,637.25
165.00 1,210.00
160.00 352.00
20.00 10.00 1,572.00
950.00 475.00
650.00 1,300.00 1,775.00
53.25
88.75
B 3,489.00
950.00 237.50
650.00 162.50 400.00
12.00
20.00
C 432.00
A+B+C 10,637.25
3,489.00
432.00
14,558.25
26,469.55
2,646.95
29,116.50
1 Sqr 29,990.00
26,469.55
794.09
27,263.63
2,726.36
29,990.00
1 Sqr 30,281.16
26,469.55
1,058.78
27,528.33
2,752.83
30,281.16
1 Sqr 30,572.32
26,469.55
1,323.48
27,793.02
2,779.30
30,572.32
1 Sqr 14,166.01
125.00 12,500.00
33.00 1,815.00
160.00 320.00
14,635.00
731.75
950.00 712.50
650.00 487.50
1,200.00
36.00
16,602.75
A 4,150.69
165.00 4,125.00
33.00 165.00
175.00 175.00
20.00 10.00 4,475.00
950.00 1,425.00
650.00 1,950.00 3,375.00
0.03 101.25
0.05 168.75
B 8,120.00
950.00 237.50
650.00 325.00 562.50
0.03 16.88
0.05 28.13 45.00
C 607.50
4,150.69
8,120.00
607.50
A+B+C 12,878.19
1,287.82
14,166.01
1 Sqr 14,732.65
12,878.19
515.13
13,393.32
1,339.33
14,732.65
1 Sqr 14,874.31
12,878.19
643.91
13,522.10
1,352.21
14,874.31
1 Cwt 7,607.68
106.40 5,320.00
100.00 25.00
5,345.00
0.10 534.50
80.18
5,959.68
950.00 950.00
650.00 650.00
1,600.00
48.00
7,607.68
152.15
15.22
167.37
1 Cwt 7,340.43
106.40 5,320.00
100.00 25.00
5,345.00
0.05 267.25
80.18
5,692.43
950.00 950.00
650.00 650.00
1,600.00
48.00
7,340.43
146.81
14.68
161.49
1 Cwt 8,075.43
106.40 5,320.00
100.00 75.00
5,395.00
0.10 539.50
80.93
6,015.43
950.00 1,187.50
650.00 812.50
2,000.00
60.00
8,075.43
161.51
16.15
177.66
1 Cwt 7,823.68
7,607.68
950.00 118.75
650.00 81.25
200.00
6.00
10.00
7,823.68
156.47
15.65
172.12
1 Cwt 7,556.43
7,340.43
950.00 118.75
650.00 81.25
200.00
6.00
10.00
7,556.43
151.13
15.11
166.24
1 Cwt 8,291.43
8,075.43
950.00 118.75
650.00 81.25
200.00
6.00
10.00
8,291.43
165.83
16.58
182.41
1 Cwt 8,124.60
106.40 5,320.00
100.00 100.00
5,420.00
0.05 271.00
81.30
5,772.30
950.00 1,187.50
650.00 812.50
2,000.00
60.00
8,124.60
162.49
16.25
178.74
1 Cwt 8,536.60
8,124.60
950.00 237.50
650.00 162.50
400.00
12.00
20.00
8,536.60
170.73
17.07
187.81
1 Cube 22,930.60
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 2,375.00
650.00 1,950.00
4,325.00
129.75
216.25
20,846.00
2,084.60
22,930.60
1 Cube 23,881.00
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 2,850.00
650.00 2,275.00
5,125.00
153.75
256.25
21,710.00
2,171.00
23,881.00
1 Cube 24,549.25
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 3,087.50
650.00 2,600.00
5,687.50
170.63
284.38
22,317.50
2,231.75
24,549.25
1 Sqr 10,003.40
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,187.50
650.00 1,300.00
2,487.50
74.63
124.38
9,094.00
909.40
10,003.40
1 Sqr 10,478.60
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,425.00
650.00 1,462.50
2,887.50
86.63
144.38
9,526.00
952.60
10,478.60
1 Sqr 10,953.80
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,662.50
650.00 1,625.00
3,287.50
98.63
164.38
9,958.00
995.80
10,953.80
1 L.ft 165.36
50 L.ft
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,425.00
650.00 812.50
2,237.50
67.13
111.88
7,516.50
150.33
15.03
165.36
1 L.ft 169.22
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
7,692.00
153.84
15.38
169.22
1 L.ft 178.73
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,662.50
650.00 1,137.50 2,800.00
84.00
140.00
8,124.00
162.48
16.25
178.73
1 L.ft 131.85
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 30.00
4,265.00
950.00 950.00
650.00 650.00 1,600.00
48.00
80.00
5,993.00
119.86
11.99
131.85
1 L.ft 137.49
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 30.00
4,265.00
950.00 1,187.50
650.00 650.00
1,837.50
55.13
91.88
6,249.50
124.99
12.50
137.49
1 L.ft 142.79
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 25.00
4,260.00
950.00 1,187.50
650.00 975.00 2,162.50
64.88
3.24
6,490.62
129.81
12.98
142.79
1 Sqr 17,461.40
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50
12,242.50
950.00 1,900.00
650.00 1,462.50 3,362.50
100.88
168.13
15,874.00
1,587.40
17,461.40
1 Sqr 19,080.05
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50 12,242.50
950.00 2,612.50
650.00 2,112.50 4,725.00
141.75
236.25
17,345.50
1,734.55
19,080.05
1 Sqr 19,273.10
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50 12,242.50
950.00 2,612.50
650.00 2,275.00 4,887.50
146.63
244.38
17,521.00
1,752.10
19,273.10
1 Cube 19,028.63
4,200.00 5,670.00
700.00 3,500.00
7,000.00 2,800.00
0.50 50.00
12,020.00
950.00 2,850.00
650.00 2,275.00
5,125.00
153.75
17,298.75
1,729.88
19,028.63
1 Sqr 28,271.10
4,200.00 8,400.00
700.00 5,250.00
7,000.00 4,200.00
0.50 75.00
17,925.00
950.00 4,275.00
650.00 2,925.00 7,200.00
216.00
360.00
25,701.00
2,570.10
28,271.10
1 Sqr 36,898.40
4,200.00 11,340.00
700.00 7,000.00
7,000.00 5,600.00
0.50 100.00
24,040.00
950.00 5,225.00
650.00 3,575.00 8,800.00
264.00
440.00
33,544.00
3,354.40
36,898.40
1 Sqr 45,630.20
4,200.00 14,700.00
700.00 8,400.00
7,000.00 7,000.00
0.50 150.00 30,250.00
950.00 6,175.00
650.00 4,225.00 10,400.00
312.00
520.00
41,482.00
4,148.20
45,630.20
1 Sqr 20,065.61
115.83 12,972.96
700.00 595.00
7,000.00 560.00
0.50 50.00
14,177.96
950.00 2,137.50
650.00 1,625.00
3,762.50
112.88
188.13
18,241.46
1,824.15
20,065.61
1 Sqr 10,962.95
59.86 6,704.32
700.00 280.00
7,000.00 350.00
0.50 40.00
7,374.32
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
9,966.32
996.63
10,962.95
1 Sqr 14,529.72
82.82 9,275.84
700.00 455.00
7,000.00 490.00
0.50 45.00
10,265.84
950.00 1,425.00
650.00 1,300.00 2,725.00
81.75
136.25
13,208.84
1,320.88
14,529.72
1 Sqr 20,434.56
18,241.46
950.00 118.75
650.00 216.67 335.42
18,576.88
1,857.69
20,434.56
1 Sqr 11,331.89
9,966.32
950.00 118.75
650.00 216.64
335.40
10,301.72
1,030.17
11,331.89
1 Sqr 14,898.66
13,208.84
950.00 118.75
650.00 216.64 335.40
13,544.24
1,354.42
14,898.66
1 Sqr 20,771.44
18,241.46 18,241.46
950.00 316.67
650.00 325.00 641.67
18,883.13
1,888.31
20,771.44
1 Sqr 11,668.79
9,966.32 9,966.32
950.00 316.67
650.00 325.00
641.67
10,607.99
1,060.80
11,668.79
1 Sqr 15,588.47
13,208.84 13,208.84
950.00 475.00
650.00 487.50 962.50
14,171.34
1,417.13
15,588.47
1 Sqr 16,027.11
83.05 9,301.60
700.00 595.00
7,000.00 560.00
0.50 50.00
10,506.60
950.00 2,137.50
650.00 1,625.00
3,762.50
112.88
188.13
14,570.10
1,457.01
16,027.11
1 Sqr 8,830.36
42.55 4,765.60
700.00 280.00
7,000.00 350.00
0.50 40.00
5,435.60
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
8,027.60
802.76
8,830.36
1 Sqr 12,047.24
62.67 7,019.04
700.00 455.00
7,000.00 490.00
0.50 45.00
8,009.04
950.00 1,425.00
650.00 1,300.00
2,725.00
81.75
136.25
10,952.04
1,095.20
12,047.24
1 Sqr 16,396.07
14,570.10
950.00 118.75
650.00 216.67 335.42
14,905.52
1,490.55
16,396.07
1 Sqr 9,199.29
8,027.60
950.00 118.75
650.00 216.64
335.40
8,362.99
836.30
9,199.29
1 Sqr 12,416.18
10,952.04
950.00 118.75
650.00 216.64
335.40
11,287.44
1,128.74
12,416.18
1 Sqr 16,732.94
14,570.10 14,570.10
950.00 316.67
650.00 325.00
641.67
15,211.77
1,521.18
16,732.94
1 Sqr 9,536.19
8,027.60 8,027.60
950.00 316.67
650.00 325.00
641.67
8,669.27
866.93
9,536.19
1 Sqr 13,105.99
10,952.04 10,952.04
950.00 475.00
650.00 487.50
962.50
11,914.54
1,191.45
13,105.99
1 Sqr 39,089.71
3,240.00 17,982.00
899.10
55.00 6,050.00
160.00 240.00
45.00 5,625.00
388.00 582.00
31,378.10
950.00 1,900.00
650.00 1,950.00
3,850.00
115.50
192.50
35,536.10
3,553.61
39,089.71
1 L.ft 149.79
45.00 630.00
75.00 187.50
700.00 245.00
14.50 116.00
0.50 0.03
1,178.52
950.00 475.00
650.00 325.00
800.00
24.00
40.00
136.17
13.62
149.79
1 Sqr 22,448.07
3,240.00 11,340.00
160.00 160.00
45.83 5,270.83
5.00 100.00
242.50 242.50
17,113.33
950.00 1,425.00
650.00 1,625.00
3,050.00
91.50
152.50
20,407.33
2,040.73
22,448.07
1 L.ft 937.20
45.00 180.00
15.00 240.00
420.00
950.00 237.50
650.00 162.50
400.00
0.03 12.00 12.00
0.05 20.00 20.00
852.00
85.20
937.20
1 Sqr 7,125.07
45.83 5,270.83
5.00 100.00
242.50 242.50
5,613.33
950.00 475.00
650.00 325.00
800.00
24.00
40.00
6,477.33
647.73
7,125.07
1 Sqr 11,293.44
20.00 10,000.00 10,000.00
650.00 247.00 247.00
7.41
12.35
10,266.76
1,026.68
11,293.44
1 L.ft 411.57
217.00 21,700.00
1,085.00
8.35 835.00
2,077.00 4,154.00
622.00 2,488.00
400.00 40.00
42.50 127.50
388.00 776.00
31,205.50
950.00 950.00
950.00 2,850.00
650.00 1,950.00
5,750.00
172.50
287.50
37,415.50
374.16
37.42
411.57
1 Sqr 19,709.98
135.50 6,504.00
55.00 3,960.00
33.00 594.00
23.75 3,277.50
160.00 240.00
- -
- -
312.75 469.13
550.00 962.50
400.00 26.67
42.50 85.00
388.00 388.00
16,506.79
950.00 1,187.50
950.00 2,137.50
650.00 1,300.00
4,625.00
138.75
231.25
21,501.79
17,918.16
1,791.82
19,709.98
1 Sqr 32,035.85
135.50 6,504.00
55.00 3,960.00
33.00 594.00
56.00 7,728.00
160.00 160.00
- -
2,077.00 3,115.50
550.00 962.50
400.00 24.00
42.50 85.00
388.00 388.00
23,521.00
950.00 1,187.50
950.00 2,375.00
650.00 1,625.00
5,187.50
155.63
259.38
29,123.50
2,912.35
32,035.85
1 L.ft 63.29
12.00 600.00
160.00
2.28 171.00
650.00
. 1,581.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
2,877.00
57.54
5.75
63.29
1 L.ft 91.45
33.00 1,650.00
160.00
2.28 171.00
880.00
2,861.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
4,157.00
83.14
8.31
91.45
1 L.ft 118.11
49.23 2,461.54
160.00
2.28 171.00
1,280.00
4,072.54
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
5,368.54
107.37
10.74
118.11
1 L.ft 126.17
49.23 2,461.54
2.28 171.00
1,280.00
3,912.54
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
5,735.04
114.70
11.47
126.17
1 L.ft 162.25
72.92 3,646.15
160.00
2.28 228.00
2,045.00
6,079.15
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
7,375.15
147.50
14.75
162.25
1 L.ft 170.32
72.92 3,646.15
2.28 228.00
2,045.00 5,919.15
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
0.03 50.63 50.63
84.38
7,741.65
154.83
15.48
170.32
1 L.ft 221.56
105.08 5,253.85
160.00
2.28 171.00
3,190.00
8,774.85
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
10,070.85
201.42
20.14
221.56
1 L.ft 229.62
105.08 5,253.85
2.28 171.00
3,190.00
8,614.85
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
10,437.35
208.75
20.87
229.62
1 L.ft 341.65
177.31 8,865.38
2.28 228.00
160.00
4,980.00
14,233.38
950.00 712.50
650.00 487.50 1,200.00
60.00
36.00
15,529.38
310.59
31.06
341.65
1 L.ft 349.71
177.31 8,865.38
2.28 228.00
4,980.00
14,073.38
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
15,895.88
317.92
31.79
349.71
1 L.ft 565.13
363.08 18,153.85
160.00
2.28 228.00
5,850.00
24,391.85
950.00 712.50
650.00 487.50 1,200.00
36.00
60.00
25,687.85
513.76
51.38
565.13
1 L.ft 573.20
363.08 18,153.85
2.28 228.00
5,850.00
24,231.85
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
26,054.35
521.09
52.11
573.20
1 L.ft 719.14
427.80 21,390.00
160.00
2.28 342.00
9,500.00
31,392.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
32,688.00
653.76
65.38
719.14
1 L.ft 727.20
427.80 21,390.00
2.28 342.00
9,500.00
31,232.00
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
33,054.50
661.09
66.11
727.20
1 L.ft 1,169.18
639.60 31,980.00
2.28 342.00
19,000.00
51,322.00
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
53,144.50
1,062.89
106.29
1,169.18
1 Nos 62.39
26.00 260.00
2.28 91.20
351.20
118.75 118.75
81.25 81.25
200.00
6.00
10.00
567.20
56.72
5.67
62.39
1 Nos 55.11
36.00 360.00
2.28 114.00
474.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
501.00
50.10
5.01
55.11
1 Nos 71.61
51.00 510.00
2.28 114.00
624.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
651.00
65.10
6.51
71.61
1 Nos 143.88
111.00 1,110.00
2.28 171.00
1,281.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,308.00
130.80
13.08
143.88
1 Nos 223.85
178.00 1,780.00
2.28 228.00
2,008.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
2,035.00
203.50
20.35
223.85
1 Nos 354.88
288.00 2,880.00
2.28 319.20
3,199.20
118.75 14.84
81.25 10.16
25.00
0.03 0.75 0.75
0.05 1.25 1.25
3,226.20
322.62
32.26
354.88
1 Nos 29.50
10 Nos
15.00 150.00
2.28 91.20 241.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
268.20
26.82
2.68
29.50
1 Nos 45.21
27.00 270.00
2.28 114.00
384.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
411.00
41.10
4.11
45.21
1 Nos 59.51
40.00 400.00
2.28 114.00
514.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
541.00
54.10
5.41
59.51
1 Nos 94.38
66.00 660.00
2.28 171.00
831.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
858.00
85.80
8.58
94.38
1 Nos 150.15
111.00 1,110.00
2.28 228.00
1,338.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,365.00
136.50
13.65
150.15
1 Nos 243.78
187.00 1,870.00
2.28 319.20
2,189.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
2,216.20
221.62
22.16
243.78
1 Nos 39.00
20.00 200.00
2.28 114.00
314.00
118.75 22.27
81.25 15.23
37.50
1.13
1.88
354.50
35.45
3.55
39.00
1 Nos 59.10
36.00 360.00
2.28 136.80
496.80
118.75 22.27
81.25 15.23
37.50
1.13
1.88
537.30
53.73
5.37
59.10
1 Nos 85.25
55.00 550.00
2.28 171.00
721.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
775.00
77.50
7.75
85.25
1 Nos 127.51
90.00 900.00
2.28 205.20
1,105.20
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,159.20
115.92
11.59
127.51
1 Nos 207.64
156.00 1,560.00
2.28 273.60
1,833.60
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,887.60
188.76
18.88
207.64
1 Nos 317.90
238.00 2,380.00
2.28 456.00
2,836.00
118.75 29.69
81.25 20.31
50.00
0.03 1.50 1.50
0.05 2.50 2.50
2,890.00
289.00
28.90
317.90
1 Nos 35.00
20.00 200.00
2.28 91.20
291.20
118.75 14.84
81.25 10.16
25.00
0.03 0.75 0.75
0.05 1.25 1.25
318.20
31.82
3.18
35.00
1 Nos 46.31
28.00 280.00
2.28 114.00
394.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
421.00
42.10
4.21
46.31
1 Nos 55.11
36.00 360.00
2.28 114.00
474.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
501.00
50.10
5.01
55.11
1 Nos 95.48
67.00 670.00
2.28 171.00
841.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
868.00
86.80
8.68
95.48
1 Nos 129.25
92.00 920.00
2.28 228.00
1,148.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,175.00
117.50
11.75
129.25
1 Nos 195.38
143.00 1,430.00
2.28 319.20
1,749.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,776.20
177.62
17.76
195.38
1 Nos 35.00
20.00 200.00
2.28 91.20 291.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
318.20
31.82
3.18
35.00
1 Nos 46.31
28.00 280.00
2.28 114.00
394.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
421.00
42.10
4.21
46.31
1 Nos 50.71
32.00 320.00
2.28 114.00
434.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
461.00
46.10
4.61
50.71
1 Nos 90.75
60.00 600.00
2.28 171.00
771.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
825.00
82.50
8.25
90.75
1 Nos 122.32
83.00 830.00
2.28 228.00
1,058.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,112.00
111.20
11.12
122.32
1 Nos 192.85
138.00 1,380.00
2.28 319.20
1,699.20
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,753.20
175.32
17.53
192.85
1 Nos 30.60
16.00 160.00
2.28 91.20 251.20
118.75 14.84
81.25 10.16 25.00
0.75
1.25
278.20
27.82
2.78
30.60
1 Nos 40.81
23.00 230.00
2.28 114.00 344.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
371.00
37.10
3.71
40.81
1 Nos 52.91
34.00 340.00
2.28 114.00 454.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
481.00
48.10
4.81
52.91
1 Nos 77.88
51.00 510.00
2.28 171.00 681.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
708.00
70.80
7.08
77.88
1 Nos 116.82
78.00 780.00
2.28 228.00 1,008.00
118.75 29.69
81.25 20.31 50.00
1.50
2.50
1,062.00
106.20
10.62
116.82
1 Nos 178.55
125.00 1,250.00
2.28 319.20 1,569.20
118.75 29.69
81.25 20.31 50.00
1.50
2.50
1,623.20
162.32
162.32
1,785.52
178.55
1 Sqr 4,968.70
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
4,517.00
451.70
4,968.70
1 Sqr 4,167.06
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,263.50
650.00 864.50 2,128.00
63.84
106.40
3,788.24
378.82
4,167.06
1 Sqr 5,443.90
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,662.50
650.00 1,137.50 2,800.00
84.00
140.00
4,949.00
494.90
5,443.90
1 Sqr 4,683.25
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,425.00
650.00 1,137.50 2,562.50
76.88
128.13
4,257.50
425.75
4,683.25
1 Sqr 5,919.10
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,900.00
650.00 1,300.00 3,200.00
96.00
160.00
5,381.00
538.10
5,919.10
1 Sqr 5,158.45
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,662.50
650.00 1,300.00 2,962.50
88.88
148.13
4,689.50
468.95
5,158.45
1 Sqr 6,201.25
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 2,137.50
650.00 1,300.00 3,437.50
103.13
171.88
5,637.50
563.75
6,201.25
1 Sqr 6,229.30
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,137.50
650.00 1,462.50 3,600.00
108.00
180.00
5,663.00
566.30
6,229.30
1 Sqr 6,135.80
700.00 1,400.00
7,500.00 825.00
50.00 400.00
0.50 10.00 2,635.00
950.00 1,425.00
650.00 1,300.00 2,725.00
81.75
136.25
5,578.00
557.80
6,135.80
1 Sqr 6,318.40
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,375.00
650.00 1,300.00 3,675.00
110.25
183.75
5,744.00
574.40
6,318.40
1 Sqr 6,793.60
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,612.50
650.00 1,462.50 4,075.00
122.25
203.75
6,176.00
617.60
6,793.60
1 Sqr 8,997.31
7.00 2,520.00
700.00 1,400.00
9.00 270.00
7,500.00 1,350.00
0.50 12.50 5,540.00
950.00 1,425.00
650.00 1,137.50 2,562.50
76.88
8,179.38
817.94
8,997.31
1 Sqr 3,119.05
700.00 875.00
7,500.00 300.00
0.50 12.50 1,187.50
950.00 950.00
650.00 650.00 1,600.00
48.00
2,835.50
283.55
3,119.05
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 22,410.03
80.00 12,000.00
600.00
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 15,428.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
20,372.75
2,037.28
22,410.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 2,793.63
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50 1,243.67
950.00 712.50
650.00 487.50 1,200.00
36.00
60.00
2,539.67
253.97
2,793.63
1 Sqr 3,075.78
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 950.00
650.00 487.50
1,437.50
0.03 43.13 43.13
0.05 71.88 71.88
2,796.17
279.62
3,075.78
1 Sqr 3,262.05
750.00 1,237.50
337.00 337.00
42.50 42.50
400.00 40.00
0.50 12.50
1,669.50
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
2,965.50
296.55
3,262.05
1 Sqr 3,729.92
750.00 1,237.50
337.00 337.00
42.50 42.50
400.00 33.33
0.50 12.50
1,662.83
950.00 950.00
650.00 650.00
1,600.00
48.00
80.00
3,390.83
339.08
3,729.92
1 Sqr 3,268.83
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 950.00
650.00 650.00
1,600.00
48.00
80.00
2,971.67
297.17
3,268.83
1 Sqr 3,458.91
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 1,045.00
650.00 715.00
1,760.00
52.80
88.00
3,144.47
314.45
3,458.91
1 Point 1,902.25
1850.00 462.50
6.23 31.15
16.00 16.00
35.00 35.00
65.00 65.00
108.00 108.00
32.00 32.00
20.00 20.00
10.00 10.00
5.00 10.00
25.00 150.00
sum
sum 939.65
650.00 81.25
950.00 316.67
650.00 214.50
950.00 118.75 731.17
21.94
36.56
1,729.31
172.93
1,902.25
1 Point 1,702.85
1850.00 462.50
6.23 62.31
16.00 32.00
65.00 65.00
108.00 108.00
32.00 32.00
sum
sum 761.81
650.00 81.25
950.00 118.75
650.00 214.50
950.00 313.50
728.00
21.84
36.40
1,548.05
154.80
1,702.85
1 Point 4,311.71
307.00 307.00
1850.00 462.50
18,100.00 1,810.00
49.00 490.00
16.00 32.00
32.00 32.00
sum
sum 3,133.50
650.00 81.25
950.00 118.75
650.00 214.50
950.00 313.50
728.00
21.84
36.40
3,919.74
391.97
4,311.71
1 m3 12,447.45
9,545.00 286,350.00
14,375.00
9,545.00 4,772.50
305,497.50
950.00 2,850.00
950.00 11,400.00
650.00 11,700.00
25,950.00
778.50
1,850.00 5,550.00 5,550.00
650.00 1,300.00
0.50 400.00
1,700.00
339,476.00
11,315.87
33,947.60
373,423.60
12,447.45
1 m3 12,841.97
9,545.00 286,350.00
14,375.00
9,545.00 4,772.50
305,497.50
950.00 3,800.00
950.00 15,200.00
650.00 15,600.00
34,600.00
1,038.00
1,850.00 7,400.00 7,400.00
650.00 1,300.00
0.50 400.00
1,700.00
350,235.50
11,674.52
35,023.55
385,259.05
12,841.97
1 m3 12,061.63
9,200.00 276,000.00
14,375.00
9,200.00 4,600.00
294,975.00
950.00 2,850.00
950.00 11,400.00
650.00 11,700.00
25,950.00
778.50
1,850.00 5,550.00
650.00 1,300.00
0.50 400.00
1,700.00
328,953.50
10,965.12
32,895.35
361,848.85
12,061.63
1 m3 13,248.77
10,005.00 300,150.00
14,375.00
10,005.00 5,002.50
319,527.50
950.00 950.00
950.00 15,200.00
650.00 15,600.00
31,750.00
952.50
1,850.00 7,400.00 7,400.00
650.00 1,300.00
0.50 400.00
1,700.00
361,330.00
12,044.33
36,133.00
397,463.00
13,248.77
1 m3 12,829.66
9,545.00 190,900.00
14,375.00
9,545.00 4,772.50 210,047.50
950.00 1,900.00
950.00 7,600.00
650.00 7,800.00 17,300.00
519.00
1,850.00 3,700.00 3,700.00
650.00 1,300.00
0.50 400.00
1,700.00
233,266.50
11,663.33
23,326.65
256,593.15
12,829.66
1 m3 13,273.49
9,545.00 190,900.00
14,375.00
9,545.00 4,772.50
210,047.50
950.00 2,612.50
950.00 10,450.00
650.00 10,725.00
23,787.50
713.63
1,850.00 5,087.50 5,087.50
650.00 1,300.00
0.50 400.00
1,700.00
241,336.13
12,066.81
24,133.61
265,469.74
13,273.49
1 m3 13,348.31
10,005.00 200,100.00
14,375.00
10,005.00 5,002.50
219,477.50
950.00 1,900.00
950.00 7,600.00
650.00 7,800.00
17,300.00
519.00
1,850.00 3,700.00 3,700.00
650.00 1,300.00
0.50 400.00
1,700.00
242,696.50
12,134.83
24,269.65
266,966.15
13,348.31
1 m3 13,792.14
10,005.00 200,100.00
14,375.00
10,005.00 5,002.50
219,477.50
950.00 2,612.50
950.00 10,450.00
650.00 10,725.00
23,787.50
0.03 713.63 713.63
1,850.00 5,087.50 5,087.50
650.00 1,300.00
0.50 400.00
1,700.00
250,766.13
12,538.31
25,076.61
275,842.74
13,792.14
1 no 1 Nos 22,523.24
214.00 4,280.00
5,000.00 5,000.00
360.00 540.00
5.58 133.92
490.00 490.00
550.00 550.00
- -
2,910.00 2,910.00
553.00 691.25
555.00 277.50
400.00 40.00
280.00 1,680.00
42.50 85.00
16,677.67
950.00 316.67
950.00 1,900.00
650.00 1,300.00
3,516.67
0.03 105.50 105.50
0.05 175.83 175.83
20,475.67
2,047.57
22,523.24
1 Nos 30,823.84
214.00 4,280.00
450.00 11,025.00
360.00
5.58 133.92
490.00 490.00
550.00 550.00
- -
2,910.00 2,910.00
553.00 691.25
555.00 277.50
400.00 40.00
280.00 1,680.00
42.50 85.00
22,162.67
950.00 475.00
950.00 3,325.00
650.00 1,625.00
5,425.00
162.75
271.25
28,021.67
2,802.17
30,823.84
1 Nos 20,227.42
214.00 6,420.00
100.00 2,300.00
115.00
75.00 1,200.00
275.00
5.58 178.56
- -
- -
- -
553.00 414.75
555.00 138.75
400.00 40.00
280.00 1,680.00
42.50 42.50
12,529.56
950.00 475.00
950.00 3,325.00
650.00 1,625.00
5,425.00
0.03 162.75 162.75
0.05 271.25 271.25
18,388.56
1,838.86
20,227.42
1 L.ft 64.19
-
-
-
-
-
650.00 216.67
950.00 475.00
950.00 118.75
810.42
24.31
40.52
875.25
58.35
87.53
962.78
64.19
CONCRETE MISSALANIOUS ITEM
Item Description Qty Unit Rate Amount Amount Remarks
15%
1 Grade 10
Consider 1 Sqr
Materials
Concrete 25.00 Cu.ft 274.15 6,853.71
Wastege 10% 10% 685.37
Reinforcement (6 mm) 22.00 Kg 146.81 3,229.79
10,768.87
Labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 1.00 Day 650.00 650.00
887.50
Add: 3% tools 3% 26.63
11,682.99 1,752.45 13,435.44
Preliminaries 10% 10% 1,168.30
Cost for 1 Sqr 12,851.29 1,927.69 14,778.98
O/H & Profit Amount O/H
& profit
3" thick blinding layer with reinforcement
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
2 Grade 25
Consider .45 Cube
Materials
Mixed concrete 0.45 Cube 28,462.67 12,808.20
(As per item B.05)
Add wastage 5% 5% 640.41
13,448.61
LAYING COST
Labour
Mason 0.50 Day 950.00 475.00
Skilled labour for vibrator 0.50 Day 650.00 325.00
3 U/sk labour 1.50 Day 650.00 975.00
1,775.00
Add: 3% tools 3% 53.25
Plant & equipment
Vibrator 0.50 Day 1,850.00 925.00
Curing
Water 100.00 Gal 0.50 50.00
U/sk labour 0.33 Day 650.00 216.67
266.67
16,468.53
9"x 9" concrete beams in ground floor level
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
36,596.73 5,489.51 42,086.23
Preliminaries 10% 1,646.85
18,115.38
Cost per 1 Cube 40,256.40 6,038.46 46,294.86
3 Grade 25
Consider .45 Cube ( 80 L.ft)
Materials
Mixed Concrete 0.45 Cube 28,462.67 12,808.20
(As per item B.04)
Add wastage 5% 5% 640.41
13,448.61
LAYING COST
Labour
Mason 0.50 Day 950.00 475.00
Skilled labour for vibrator 0.50 Day 950.00 475.00
3 U/sk labour 1.50 Day 650.00 975.00
1,925.00
Add: 3% tools 3% 57.75
Add: 5% scaffolding 5% 96.25
Plant & equipment
Vibrator 0.50 Day 1,850.00 925.00
Curing
Water 50.00 Gal 0.50 25.00
U/sk labour 0.25 Day 650.00 162.50
9"x 9" Concrete Column in ground floor level
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
187.50
16,640.11
36,978.02 5,546.70 42,524.72
Preliminaries 10% 1,664.01
18,304.12
Cost per 1 Cube 40,675.82 6,101.37 46,777.20
4 Grade 20
Consider 10 L.ft
Materials
Concrete 7.50 Cu.ft 311.15 2,333.61
Sawn form work 20.00 Sq.ft 264.70 5,293.91
Reinforcement 10.00 Kg 146.81 1,468.09
9,095.61
Add Extra cost of labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 0.25 Day 650.00 162.50
400.00
9,495.61
949.56 142.43 1,091.99
Preliminaries 10% 10% 949.56
Cost for 10.0 l.ft 10,445.17
Cost for1 L.ft 1,044.52 156.68 1,201.19
9''x 12'' plinth beam with & including formwork and reinforcement
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
5 Grade 20
Consider 10 L.ft
Materials
Concrete 5.63 Cu.ft 311.15 1,750.21
Sawn form work 15.00 Sq.ft 264.70 3,970.43
Reinforcement 10.00 Kg 146.81 1,468.09
7,188.73
Add Extra cost of labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 0.25 Day 650.00 162.50
400.00
Cost for 10.0 l.ft 7,588.73
758.87 113.83 872.70
Preliminaries 10% 10% 758.87
9''x9'' Plinth beam with & including formwork and reinforcement
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Cost for 10.0 l.ft 8,347.60
Cost for1 L.ft 834.76 125.21 959.97
6 Grade 25
Consider 10 L.ft
Materials
Concrete 4.50 Cu.ft 311.15 1,400.17
Sawn form work 17.50 Sq.ft 264.70 4,632.17
Reinforcement 5.00 Kg 146.81 734.04
6,766.38
Add Extra cost of labour
Skilled labourer 0.13 Day 950.00 118.75
Un skilled labourer 0.13 Day 650.00 81.25
200.00
6,966.38
696.64 104.50 801.13
Preliminaries 10% 10% 696.64
6'' x 9'' lintol with & including formwork & reinforcement
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Cost for 10.0 L.ft 7,663.02
Cost for 1 L.ft 766.30 114.95 881.25
7 Grade 25
Consider 10 L.ft
Materials
Concrete 1.88 Cu.ft 311.15 584.96
Sawn form work 12.50 Sq.ft 264.70 3,308.69
Reinforcement 5.00 Kg 146.81 734.04
4,627.69
Add Extra cost of labour
Skilled labourer 0.13 Day 950.00 118.75
Un skilled labourer 0.13 Day 650.00 81.25
200.00
4,827.69
6'' x 4 1/2'' lintol with & including formwork & reinforcement
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
482.77 72.42 555.18
Preliminaries 10% 10% 482.77
Cost for 10.0 l.ft 5,310.46
Cost for 1 l.ft 531.05 79.66 610.70
8 LAYING CHIP CONCRETE Kiri
Consider 1 Sqr
MIXING COST
Materials
Cement 2.37 Bags 740.00 1,753.80
Chip Metal 0.17 Cube 3,750.00 637.50
Water 21.00 Gal 0.50 10.50
Labour
Mixer operator 0.06 Day 950.00 57.00
U/sk labour 0.34 Day 650.00 221.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Plant & equipment
Concrete mixture (14/10) 0.06 Day 2,300.00 138.00
2,817.80
Add Wastage 10% 0.10 281.78
Labour
Sk labour 0.25 Day 950.00 237.50
Un sk labour 1.00 Day 650.00 650.00
887.50
Add 3% for tools 0.03 26.63
4,013.71 602.06 4,615.76
Preliminaries 10% 401.37
Cost for 1 Sqr 4,415.08 662.26 5,077.34
8.0 Grage 15 Chip Concrete Queens
MIXING Cost Assume 3" thick
Materials
Cement 14.00 bags 740.00 10,360.00
Sand 0.60 Cube 7,000.00 4,200.00
Metal (Chip) 1.00 Cube 3,750.00 3,750.00
Water 125.0 gal 0.50 62.50
18,372.50
Labour
Mixer operator 0.33 day 950.00 313.50
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Un / skilled Labour 2.00 day 650.00 1,300.00
1,613.50
Plant & Equipment
Concrete mixture (14/10) 0.33 day 2,300.00 759.00
Cost for one Cube 20,745.00
0.08 Cube 20,745.00 1,659.60
Add 10 % for Wastage 165.96
1,825.56
Labour
Skilled Labour 0.75 day 950.00 712.50
Un / skilled Labour 3.00 day 650.00 1,950.00
2,662.50
3% of labour Cost for Tool 79.88
Cost for one Sqr 4,567.94 685.19 5,253.13
Preliminaries 10% 456.79
Cost for 1 Sqr 5,024.73 753.71 5,778.44
10.0 3" thick flr conc. Including BRC mesh Queens
Consider 1 Sqr
Materials
0.25 Cube 28,154.83 7,038.71
Add 10 % for Wastage 703.87
7,742.58
mixed Concrete (G15)
mixed Concrete (G15)
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
BRC Mesh 100.0 Sq.ft 45.24 4,523.81
Labour
Skilled Labour 0.25 day 950.00 237.50
Un / skilled Labour 1.00 day 650.00 650.00
887.50
3% of labour Cost for Tool 26.63
13,180.51 1,977.08 15,157.59
Preliminaries 10% 1,318.05
Cost for 1 Sqr 14,498.56 2,174.78 16,673.35
B1
10 L.ft
Materials
Supply and fix 50x150mm precast pergolas.including two coats of filler and two coats of weather shied paint
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
50x 150mm pergolas 10.00 L.ft 90.00 900.00
Add 10% trance port 90.00
Sand 0.00 cube 7,000.00 7.00
Metal 0.01 cube 4,800.00 24.00
1,021.00
Labour
Sk labour 0.25 day 950.00 237.50
U/sk labour 0.25 day 650.00 162.50
400.00
Add
3% of labour cost for tool 12.00
5% of labour cost for scafolding 20.00
32.00
Add
Painting 13.30 Sq.ft 29.66 394.41 394.41
1,847.41 277.11 2,124.52
212.45 L.ft
Preliminaries 184.74 696.84 Lm
Cost for one cube with preliminaries 2,032.15 304.82 2,336.98
Kerbs
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Assume 10 L.ft
4" x 12" path edgings 10.00 L.ft 125.00 1,250.00
Transport 5% 62.50
Excavation 17.55 cu.ft 14.00 245.70
2" thick screed (grade 15) 2.18 cu.ft 285.00 620.73
2,178.93
Labour
Skill 0.25 Day 950.00 237.50
Un Skill 0.25 Day 650.00 162.50
400.00
3% of labour Cost for tools 12.00
2,590.93
Per L.ft 259.09 38.86 297.96
Laid 9" below ground,and bedded on grade 15 concrete 8"x4" base and 4"x4" haunch on either side;excavation ,backfilling,disposal of surplus,formwork
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
2 VANITY COUNTERS
8.00 2.00 0.17
Material
Concrete (grade 25) 2.72 Cu.ft 368.58 1,002.54
Formwork
18.04 Sq.ft 88.00 1,587.52
Reinforcement
9.12 kg 160.00 1,459.95
Cement rendering
34.04 Sq.ft 60.00 2,042.40
Titanium Cut & polish
ddt for basin 17.04 Sq.ft 207.50 3,535.80
Cost for one Vanity Counter 9,628.20 1,444.23 11,072.44
8' 0"x2' 0" ,2" thick, cantilevered from wall, reinforced with 10mm rods @ 8" c/c both ways all faces cement rendered, exposed faces finished with cut & polish 1:10 Titanium and cement floating with cut out for basins.
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
C
Assume 10 L.ft
9" Dia Concrete pipe 10.00 L.ft 362.50 3,625.00 3,625.00
Transport 5% 181.25
Joint
Cement 0.50 Bag 785.00 392.50
sand 0.01 Cube 5,500.00 55.00 447.50
Wastage 10% 44.75
Excavation 56.88 Cu.ft 14.00 796.25
Back fill 20.63 Cu.ft 15.00 309.38
Disposal 56.88 Cu.ft 10.00 568.75
6" thick concrete bed and hounch 17.50 Cu.ft 285.00 4,987.50
15.00 Cu.ft 285.00 4,275.00 10,936.88
Labour
Skill 1.00 Day 950.00 950.00
Un Skill 2.00 Day 650.00 1,300.00 2,250.00
67.50
17,552.88
Per L.ft 1,755.29
Precast reinforced concrete pipes laid 2' below ground
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
A
Assume 10 L.ft
18"x 12" RCC semi circular drain 10.00 L.ft 325.00 3,250.00 3,250.00
Transport 5% 162.50
Joint
Cement 0.50 Bag 785.00 392.50
sand 0.01 Cube 5,500.00 55.00 447.50
Wastage 10% 44.75
Labour
Un/sk for excavation 0.25 Day 650.00 162.50
Skill 0.50 Day 950.00 475.00
Un Skill 1.00 Day 650.00 650.00 1,287.50
Tools 3% 19.50 669.50
5,861.75
Per L.ft 586.18
B4 Concrete 1:2:4 (3/4") grade 20 1 Cube 53,247.30 1 m3 18,815.30
RCC semi circular open drain size 18" wide x 12" deep
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
MIXING Cost
Materials
Cement 42.00 bags 740.00 31,080.00
Sand 0.50 Cube 7,000.00 3,500.00
Metal 0.50 Cube 3,500.00 1,750.00
Water 125.00 gal 0.50 62.50
36,392.50
Labour
Mixer operator 0.33 day 950.00 313.50
Un / skilled Labour 2.00 day 650.00 1,300.00
1,613.50
Plant & Equipment
Concrete mixture 0.33 day 2,300.00 766.67
Cost for one Cube (mixing only) 38,772.67
LAYING Cost
Mason 0.75 day 950.00 712.50
Vibrator operator 0.75 day 950.00 712.50
6 Un / skilled Labour 4.50 day 650.00 2,925.00
4,350.00
Plant & Equipment
Vibrator operator 0.75 day 1,850.00 1,387.50
Add
3% of labour Cost for tools for tool 130.50
217.50
348.00
Curing
5% of labour Cost for scaffolding for scafolding
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount O/H
& profit
Water 100.00 gal. 0.50 50.00
Un / skilled Labour 0.33 day 650.00 216.67
266.67
45,124.83
O/H and profit 8,122.47
Cost for 1 Cube with Preliminaries 53,247.30
5546.59398
TERMITE TRETMENT / WATER PROOPING
Item Description Qty Unit Rate Amount Amount Remarks
15%
A1 Anti termite tretment 1 Sqr
Sub Contrctor's price 1.00 Sqr 1,975.00 1,975.00
Add
Attendance
7% of price 138.25
2,113.25 316.99 2,430.24 Sqr
Add 261.49 m2
Preliminaries 21.13
Cost per one sqr wth preliminaries 2,134.38 320.16 2,454.54 Sqr
A1 Water proofing 1 m2
Sub Contrctor's price 1.00 m2 875.00 875.00
Add
Attendance
O/H & Profit
Amount O/H & profit
Main Index
7% of price 61.25
936.25 140.44 1,076.69
Add
Preliminaries 9.36
Cost per one sqr wth preliminaries 945.61 141.84 1,087.45
Add
Protective Screed 1.00 m2 533.00 533.00 533.00
1,609.69 1m2
PLUMBING GAUGE 600
Item Description Qty Unit Rate Amount Amount Remarks
15%
1
Consider 50 L.ft
Materials
32mm pipe 50.00 L.ft 20.92 1,046.15
Clipe & nails 160.00
Solvent cement 75.00 Grms 2.28 171.00
Others 1,280.00
2,657.15
Labour
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
3,953.15
79.06 11.86 90.92
Preliminaries 10% 395.32
Cost per 50 L.ft 4,348.47
Cost per 1 L.ft 86.97 13.05 100.01
O/H & Profit
Amount with profit
32mm diameter pvc pipe fixed to wall
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
2
Consider 50 L.ft
Materials
32mm pipe 50.00 L.ft 20.92 1,046.15
Solvent cement 75.00 Grms 2.28 171.00
Others 1,280.00
2,497.15
Labour
U/sk labour 0.75 Day 650.00 487.50
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
4,319.65
86.39 12.96 99.35
Preliminaries 10% 431.97
Cost per 50 L.ft 4,751.62
Cost per 1 L.ft 95.03 14.25 109.29
3 40mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
40mm pipe 50.00 L.ft 51.00 2,550.00
Clipe & nails 300.00
Solvent cement 100.00 Grms 2.28 228.00
Others 2,045.00
32mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
5,123.00
Labour
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
6,419.00
128.38 19.26 147.64
Preliminaries 10% 641.90
Cost per 50 L.ft 7,060.90
Cost per 1 L.ft 141.22 21.18 162.40
4
Consider 50 L.ft
Materials
40mm pipe 50.00 L.ft 51.00 2,550.00
Solvent cement 100.00 Grms 2.28 228.00
Others 2,045.00
4,823.00
Labour
U/sk labour 0.75 Day 650.00 487.50
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
40mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
6,645.50
132.91 19.94 152.85
Preliminaries 10% 664.55
Cost per 50 L.ft 7,310.05
Cost per 1 L.ft 146.20 21.93 168.13
5 50mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
50mm pipe 50.00 L.ft 68.15 3,407.69
Clipe & nails 300.00
Solvent cement 100.00 Grms 2.28 228.00
Others 3,190.00
7,125.69
Labour
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
8,421.69
168.43 25.27 193.70
Preliminaries 10% 842.17
Cost per 50 L.ft 9,263.86
Cost per 1 L.ft 185.28 27.79 213.07
6 50mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Consider 50 L.ft
Materials
50mm pipe 50.00 L.ft 68.15 3,407.69
Solvent cement 100.00 Grms 2.28 228.00
Others 3,190.00
6,825.69
Labour
U/sk labour 0.75 Day 650.00 487.50
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
8,648.19
172.96 25.94 198.91
Preliminaries 10% 864.82
Cost per 50 L.ft 9,513.01
Cost per 1 L.ft 190.26 28.54 218.80
7 63mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
63mm pipe 50.00 L.ft 112.92 5,646.15
Clipe & nails 360.00
Solvent cement 100.00 Grms 2.28 228.00
Others 4,980.00
11,214.15
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Labour
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
12,510.15
250.20 37.53 287.73
Preliminaries 10% 1,251.02
Cost per 50 L.ft 13,761.17
Cost per 1 L.ft 275.22 41.28 316.51
8
Consider 50 L.ft
Materials
63mm pipe 50.00 L.ft 112.92 5,646.15
Solvent cement 100.00 Grms 2.28 228.00
Others 4,980.00
10,854.15
Labour
U/sk labour 0.75 Day 650.00 487.50
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
12,676.65
63mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
253.53 38.03 291.56
Preliminaries 10% 1,267.67
Cost per 50 L.ft 13,944.32
Cost per 1 L.ft 278.89 41.83 320.72
9 75mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
75mm pipe 50.00 L.ft 222.92 11,146.15
Clipe & nails 360.00
Solvent cement 100.00 Grms 2.28 228.00
Other 8,916.92
20,651.08
Labour
Plumber 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
21,947.08
438.94 65.84 504.78
Preliminaries 10% 2,194.71
Cost per 50 L.ft 24,141.78
Cost per 1 L.ft 482.84 72.43 555.26
10 75mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Consider 50 L.ft
Materials
75mm pipe 50.00 L.ft 222.92 11,146.15
Solvent cement 100.00 Grms 2.28 228.00
Other 8,916.92
20,291.08
Labour
Excavation 0.75 Day 650.00 487.50
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
22,113.58
442.27 66.34 508.61
Preliminaries 10% 2,211.36
Cost per 50 L.ft 24,324.93
Cost per 1 L.ft 486.50 72.97 559.47
11 90mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
90mm pipe 50.00 L.ft 274.65 13,732.50
Clipe & nails 390.00
Solvent cement 150.00 Grms 2.28 342.00
Other 9,500.00
23,964.50
Labour
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
25,260.50
505.21 75.78 580.99
Preliminaries 10% 2,526.05
Cost per 50 L.ft 27,786.55
Cost per 1 L.ft 555.73 83.36 639.09
12
Consider 50 L.ft
Materials
90mm pipe 50.00 L.ft 274.65 13,732.50
Solvent cement 150.00 Grms 2.28 342.00
Other 9,500.00
23,574.50
Labour
Excavation 0.75 Day 650.00 487.50
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
25,397.00
507.94 76.19 584.13
90mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Preliminaries 10% 2,539.70
Cost per 50 L.ft 27,936.70
Cost per 1 L.ft 558.73 83.81 642.54
13 110mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
110mm pipe 50.00 L.ft 402.30 20,115.00
Clipe & nails 390.00
Solvent cement 150.00 Grms 2.28 342.00
Other 19,000.00
39,847.00
Labour
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
41,143.00
822.86 123.43 946.29
Preliminaries 10% 4,114.30
Cost per 50 L.ft 45,257.30
Cost per 1 L.ft 905.15 135.77 1,040.92
14
Consider 50 L.ft
110mm diameter pvc pipe laying trench
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Materials
110mm pipe 50.00 L.ft 402.30 20,115.00
Solvent cement 150.00 Grms 2.28 342.00
Other 19,000.00
39,457.00
Labour
Excavation 0.75 Day 650.00 487.50
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
41,279.50
825.59 123.84 949.43
Preliminaries 10% 4,127.95
Cost per 50 L.ft 45,407.45
Cost per 1 L.ft 908.15 136.22 1,044.37
361/775
ELECTRICAL INSTALLATION
Description Unit Qty Rate Remarks
Wire
1/1.13 mm Cu/PVC/PVC 1mm2 m 100.00 1,850.00 Kalani cable
7/0.67 mm Cu/PVC earth 1.5mm2 m 100.00 5,540.00
Conduit
PCV conduit pipe 1" Lft 13.00 167.00 S-Lon
PCV conduit pipe 3/4"" L.ft 13.00 121.00
Bend
1" Nr 1.00 24.00 S-Lon
3/4" Nr 1.00 20.00
Ceiling rose
Holders
Switches
one gang one way Nr 1.00 109.09 Orange
two gang one way Nr 1.00 184.07
three gang one way Nr 1.00 263.94
four gang one way Nr 1.00 349.64
Main Index
362/775
Switch box
Round block
Socket outlet Orange
5A switched socket outlet Nr 1.00 303.87
13A switched socket outlet Nr 1.00 321.40
15A switched socket outlet Nr 1.00 373.02
Nr
Item Description Qty Unit Rate Amount Amount Remarks
15%
1
Rate for 4 Nos points
Materials
1mm2 Live 0.45 coil 1,850.00 832.50
O/H & Profit
Amount with profit
Wiring and installation (including supply of all materials) of the light points using approved type PVC insulated PVC sheathed 1 mm2 copper cable and 2.5mm2 Earth cable drawn through securely fixed concealed PVC conduit. (Switches shall be ABB / Clipsal / Orange / Tenby or equivalent)
Earth cable is not required if fitting is not Metal
363/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
1mm2 Nutral 0.35 coil 1,850.00 647.50
2.5mm Earth wire 0.25 coil 5,540.00 1,385.00
PCV conduit pipe 1" 50.00 l.ft 12.85 642.31
PCV conduit pipe 3/4"" 20.00 l.ft 9.31 186.15
Bend 4.00 no 25.00 100.00
Ceiling rose 4.00 no 35.00 140.00
Holders 4.00 no 65.00 260.00
Switches -four gang one way 1.00 no 349.64 349.64
Switch box 1.00 no 40.00 40.00
Round block 4.00 no 20.00 80.00
Brass screws 1" 4.00 no 10.00 40.00
Brass screws 1/2" 8.00 no 5.00 40.00
Flexible wire 2 core 24.00 no 25.00 600.00 5,343.10
15% sum 801.47
6% sum 320.59
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 1.50 day 950.00 1,425.00
un skilled labour 1.50 day 650.00 975.00
Mason for prepare surface 1.00 day 950.00 950.00
4,000.00
Add for Tools
3% of labour cost 3% 120.00
5% of labourer cost 5% 200.00
10,785.15
For 1 Point 2,696.29 404.44 3,100.73
cement lime and sand 15% from meterial cost
clips and wire nails 6% from meterial cost
364/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
3
Rate for 4 Nos points
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 5/8" 80.00 l.ft 10.00 800.00
5 amp socket outlets 1.00 no 303.87 303.87
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00 3,411.37
15% sum 511.71
6% sum 204.68
Labour
Un skilled labour for chasing wall1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
Un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00
4,800.00
Supply & installation of 5A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal, Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely fixed concealed PVC conduit in a ring circuit.
Cement lime and sand 15% from meterial cost
Clips and wire nails 6% from meterial cost
365/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
9,311.76
For 1 Point 2,327.94 349.19 2,677.13
4
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 1" 65.00
Conduit pipe 3/4" 25.00 l.ft 10.00 250.00
13 amp socket outlets 4.00 no 345.00 1,380.00
Bend 4.00 no 25.00 100.00
Switch box 4.00 no 40.00 160.00 1,890.00
15% sum 283.50
6% sum 113.40
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Supply & installation of 13A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal, Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely fixed concealed PVC conduit in a ring circuit.
Cement lime and sand 15% from meterial cost
Clips and wire nails 6% from meterial cost
366/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
7,470.90
For 1 Point 1,867.73 280.16 2,147.88
4
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 5/8" 80.00 l.ft 10.00 800.00
15 amp socket outlets 1.00 no 345.00 345.00
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00 1,235.00
15% sum 185.25
6% sum 74.10
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Supply & installation of 15A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal, Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely fixed concealed PVC conduit in a ring circuit.
Cement lime and sand 15% from meterial cost
Clips and wire nails 6% from meterial cost
367/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
6,678.35
For 1 Point 1,669.59 250.44 1,920.03
5
Materials
1mm2 Live 0.45 coil - -
1mm2 Nutral 0.35 coil - -
2.5mm Earth wire 0.25 coil - -
PCV conduit pipe 1" 50.00 l.ft 10.00 500.00
PCV conduit pipe 3/4"" 20.00 l.ft
1 Gang switch 1.00 no 100.00 100.00
Wiring & installation (including supply of all material, earth wire & switch) for ceiling / wall mounted fans using approved type 1 mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely fixed PVC conduits.
368/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00
Fan hook 1.00 no 250.00 250.00 440.00
15% sum 66.00
6% sum 26.40
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
5,716.40
For 1 Point 1,429.10 214.36 1,643.47
cement lime and sand 15% from meterial cost
clips and wire nails 6% from meterial cost
Supply & installation of TV socket outlet to comply with relevant BS standard (Crabtree/ Tenby/Clipsal/Orange or equivalent). Wring (including all material required ) of above socket outlet using approved type two core PVC/PVC copper cable drawn through securely fixed concealed PVC conduit.
369/775
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Supply & installation of telephone socket outlet to comply with relevant BS standard (Crabtree/ Tenby/Clipsal/Orange or equivalent). Wring (including all material required ) of above socket outlet using approved type two core PVC/PVC copper cable drawn through securely fixed concealed PVC conduit.
DOORS AND WINDOWS
Specification:
Materil
Frame -Teak
Frame 6" x4" 1.00 L.ft 1,100.00
4" x3" 1.00 L.ft 550.00
Sash -Teak
Sash 11/2" thick 1.00 Sq.ft 1,200.00
11/4" thick 1.00 Sq.ft 1,000.00
1" thick 1.00 Sq.ft 575.00
Louver
1/2" louver blade 1.00 Sq.ft 400.00
Glass - clear
6mm thick 1.00 Sq.ft 100.00
3mm thick 1.00 Sq.ft
Glazing beads 1.00 L.ft 5.00
Iron mongery -Stainless steel
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Window Fasterners 1.00 Nos 325.00
Window Rings 1.00 Nos 35.00
Main Index
Wood Seasion
6" x4" 1.00 L.ft 43.00
4' x3" 1.00 L.ft 22.00
11/2" sash 1.00 Sq.ft
11/4" sash 1.00 Sq.ft 27.00
1'-0" x 1'-0" x 1'-0" 1.00 Cu.ft 263.00
Wood Painting
Wood treatment 1.00 Sq.ft 20.00
Water base 1.00 Sq.ft 88.00
Spray paint 1.00 Sq.ft 88.00
Labour
Frame Planking 1.00 L.ft 10.00
Sash Planking 1.00 Sq.ft 10.00
Frame making 6" x 4" 1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber "v" grove panel 1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
Frame fixing to wall -small 1.00 Nos 750.00
Frame fixing to wall -big 1.00 Nos 1,000.00
Description
Qty Unit Rate Amount Amount Remarks
15%
1
O/H & Profit
Amount with profit
0-4" x 0'-3" frame with 1 1/4" thick sash local teak door
Overall size ,3' -0" x 7'- 0" , type D3 21.00 Sq.ft
Material
4"x3" frame. 19.00 L.ft 550.00 10,450.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 16.88 sq.ft 1,000.00 16,875.00
27,325.00
Wastage 10% 2,732.50
Transport 7% 1,912.75
Wood Season 19.00 l.ft 22.00 418.00
Wood Season 16.88 sq.ft 27.00 455.63
873.63
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
6"x4" Hinges 4.00 Nr 550.00 2,200.00
1 1/4" screws 32.00 Nr 8.35 267.20
1' 6" High brass barolt bolt 1.00 Nr 2,300.00 2,300.00
6" High brass barolt bolt 1.00 Nr 380.00 380.00
Union Lock Good quality 1.00 Nr 6,900.00 6,900.00
12,047.20
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 0.75 Days 1,000.00 750.00
Un/Sk 0.75 Days 675.00 506.25
Making sash
Carpenter 2.5 Days 1,000.00 2,500.00
Un/Sk 2.5 Days 675.00 1,687.50
Sash fixing to frame with iron mongery
Carpenter 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
9,631.25
Overall size 3'-0" x 7'-0" Single sash with Horizontal vertical timber battens with "V" groove as per detail drawing
Tools 3% 288.94
56,311.26
O/H and profit 18% 10,136.03
Total cost 66,447.29
Total cost for 1 Sq.ft 3,164.16
Add water base painting ( both side ) 247.50
Sq.ft Rate with water base paint 3,411.66
2
Overall size ,12' -0" x 7'- 0" , type SD1 84.00 Sq.ft
Material
4"x3" frame. 42.00 L.ft 550.00 23,100.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 33.12 sq.ft 1,000.00 33,120.00
6mm glass 46.50 sq.ft 100.00 4,650.00
104,188.24
Wastage 10% 10,418.82
Transport 7% 7,293.18
Wood Season 42.00 l.ft 22.00 924.00
Wood Season 33.12 sq.ft 27.00 894.24
1,818.24
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
Sliding gear 1.00 Item 40,000.00 40,000.00
6" High brass barolt bolt 1.00 Nos 380.00 380.00
40,380.00
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
0-4" x 0'-3" frame with 1 1/4" thick sash local teak and 6mm glass
Overall size 12'-0" x 7'-0" Timber glazed sliding door as per detail drawing
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 1.25 Days 1,000.00 1,250.00
Un/Sk 1.25 Days 675.00 843.75
Making sash
Carpenter 6 Days 1,000.00 6,000.00
Un/Sk 6 Days 675.00 4,050.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
18,006.25
Tools 3% 540.19
184,144.92
O/H and profit 18% 33,146.09
Total cost 217,291.00
Total cost for 1 Sq.ft 2,586.80
Add water base painting 110.00
Sq.ft Rate with water base paint 2,696.80
3
3 Overall size ,10' -0" x 8'- 0" , type FW 80.00 Sq.ft
Material
4"x3" frame. 29.00 L.ft 550.00 15,950.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 32.24 sq.ft 1,000.00 32,240.00
6mm glass 41.38 sq.ft 100.00 4,138.00
52,328.00
Wastage 10% 5,232.80
0-4" x 0'-3" frame with 1 1/4" thick sash local teak and 6mm glass
Overall size 10'-0" x 8'-0" Timber glazed french windoor as per detail drawing
Transport 7% 3,662.96
Wood Season 29.00 l.ft 22.00 638.00
Wood Season 32.24 sq.ft 27.00 870.48
1,508.48
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Labour
Making frame
Carpenter 1.75 Days 1,000.00 1,750.00
Un/Sk 1.75 Days 675.00 1,181.25
frame fixing to wall
Mason 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
Making sash
Carpenter 6 Days 1,000.00 6,000.00
Un/Sk 6 Days 675.00 4,050.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
18,006.25
Tools 3% 540.19
82,778.68
O/H and profit 18% 14,900.16
Total cost 97,678.84
Total cost for 1 Sq.ft 1,220.99
Add water base painting 110.00
Sq.ft Rate with water base paint 1,330.99
7
Overall size ,8' -0" x 5'- 0" , type W1 40.00 Sq.ft
0-4" x 0'-3" frame with 1 1/4" thick sash local teak and 6mm glass
Overall size 8'-0" x 5'-0" Timber glazed openable door as per detail drawing
Material
4"x3" frame. 26.00 L.ft 550.00 14,300.00
1 1/4" thick Teak timber sash 16.83 sq.ft 1,000.00 16,830.00
6mm glass 24.42 sq.ft 100.00 2,442.00
33,572.00
Wastage 10% 3,357.20
Transport 7% 2,350.04
Wood Season 26.00 l.ft 22.00 572.00
Wood Season 16.83 sq.ft 27.00 454.41
1,026.41
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
6"x4" Hinges
4"x3" Hinges
1 1/4" screws
1' 6" High brass barolt bolt
6" High brass barolt bolt
Union Lock Good quality
Union Lock Normal
Casement stay
Window Fasterners
Window Rings
Labour
Making frame
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
frame fixing to wall
Mason 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
Making sash
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
11,725.00
Tools 3% 351.75
53,882.40
O/H and profit 18% 9,698.83
Total cost 63,581.23
Total cost for 1 Sq.ft 1,589.53
Add water base painting - Area consider single side 110.00
Sq.ft Rate with water base paint 1,699.53
8
26.00 Sq.ft
Material
5"x4" frame. 22.00 L.ft 1,100.00 24,200.00
1 1/4" thick Teak timber sash 20.00 sq.ft 1,000.00 20,000.00
6mm glass 17.18 sq.ft 100.00 1,718.00
45,918.00
Wastage 10% 4,591.80
Transport 7% 3,214.26
Wood Season 22.00 l.ft 43.00 946.00
Wood Season 20.00 sq.ft 27.00 540.00
1,486.00
Holdpast ( flat iron / concrete / formwors) 4.00 Nr 250.00 1,000.00 1,000.00
Iron mongery -Stainless steel
6"x4" Hinges
4"x3" Hinges
0-5" x 0'-4" frame with 1 1/4" thick sash local teak louver sash panel and fixed glass panel with 6mm glass
Overall size ,3' -0" x 6'- 6" , type W1
1 1/4" screws
1' 6" High brass barolt bolt
6" High brass barolt bolt
Union Lock Good quality
Union Lock Normal
Casement stay
Window Fasterners
Window Rings
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 1.25 Days 1,000.00 1,250.00
Un/Sk 1.25 Days 675.00 843.75
Making sash
Carpenter 3 Days 1,000.00 3,000.00
Un/Sk 3 Days 675.00 2,025.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
12,981.25
Tools 3% 389.44
69,580.75
O/H and profit 18% 12,524.53
Total cost 82,105.28
Total cost for 1 Sq.ft 3,157.90
Add water base painting 220.00
Sq.ft Rate with water base paint 3,377.90
1
Overall size ,6' 0" x 9' 4" , type D1 6.00 9.33 55.98 Sq.ft
0.5 0.33
5.33 9.00
Material
6"x4" frame. 24.66 L.ft 1,100.00 27,126.00
1 1/2" thick Teak timber sash 47.98 sq.ft 1,200.00 57,578.67
Wood presavative 8.87 Cu.ft 263.00 2,332.05
Wood treatment 124.57 sq.ft 20.00 2,491.40
89,528.12
Wastage 10% 8,952.81
Transport 7% 6,266.97
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 110.00 2,712.60
Frame fixing to wall 1 Item 1,000.00 1,000.00
Sash planking 47.98 sq.ft 10.00 479.82
Timber Sash making 47.98 sq.ft 450.00 21,592.00
0-6" x 0'-4" frame with 1 1/2" thick sash local teak
Overall size 6'-0" x 9'-4" Double sash 0'-5" width timber stile with vertical timber battens with "V" groove as per detail drawing
Water base paint 167.94 sq.ft 88.00 14,778.72
Locks & ironmongary fixing 2,500.00 43,309.74
Tools 3% 1,299.29
Total cost 149,356.94
Total cost for 1 Sq.ft 2,668.04
2
Overall size ,3' 0" x 9' 4" , type D2 3.00 9.33 27.99 Sq.ft
frame 0.33 0.25
sash 2.50 8.83 22.08
glass 2.50 1.17 2.93
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 19.15 sq.ft 1,000.00 19,150.00
Wood presavative 3.95 Cu.ft 263.00 1,038.71
Wood treatment 60.74 sq.ft 20.00 1,214.81
34,966.52
Wastage 10% 3,496.65
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
38,499.87
Transport 7% 2,694.99
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
0-4" x 0'-3" frame with 1 1/4" thick sash local teak
Overall size 3'-0" x 9'-4", 3'-0" x 8'-0" Side hung, Single sash 0'-4" width timber stile with vertical timber battens with "V" groove with 3'-0" x 1'-2" fixed glass above as per detail drawing
Sash planking 22.08 sq.ft 10.00 220.75
Timber Sash making 22.08 sq.ft 225.00 4,966.88
Water base paint 162.09 sq.ft 88.00 14,263.92
Locks & ironmongary fixing 2,500.00 25,414.15
Tools 3% 762.42
Total cost 67,371.43
Total cost for 1 Sq.ft 2,406.98
3
Overall size ,3' 0" x 9' 4" , type D3 3.00 9.33 27.99 Sq.ft
frame 0.33 0.25
sash 2.50 8.83 22.08
glass 2.50 1.17 2.93
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 19.15 sq.ft 1,000.00 19,150.00
Wood presavative 3.95 Cu.ft 263.00 1,038.71
Wood treatment 60.74 sq.ft 20.00 1,214.81 34,966.52
Wastage 10% 3,496.65
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
38,499.87
Transport 7% 2,694.99
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Overall size 3'-0" x 9'-4", 3'-0" x 8'-0" Side hung, Single sash 'flush panel sash with 3'-0" x 1'-2" fixed glass above as per detail drawing
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 22.08 sq.ft 10.00 220.75
Timber Sash making 19.15 sq.ft 225.00 4,308.75
Water base paint 162.09 sq.ft 88.00 14,263.92
Locks & ironmongary fixing 2,500.00 24,756.02
Tools 3% 742.68
Total cost 66,693.56
Total cost for 1 Sq.ft 2,382.76
4 Overall size ,4' 0" x 9' 4" , type D4 / D5 4.00 9.33 37.32 Sq.ft
frame 0.33 0.25
sash 3.50 8.83 30.91
glass 3.50 1.17 4.10
Material
4"x3" frame. 26.66 L.ft 550.00 14,663.00
1 1/4" thick Teak timber sash 26.81 sq.ft 1,000.00 26,810.00
Wood presavative 4.88 Cu.ft 263.00 1,283.56
Wood treatment 77.88 sq.ft 20.00 1,557.61 44,314.17
Wastage 10% 4,431.42
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 9.34 L.ft 5.00 46.70 46.70
48,792.29
Transport 7% 3,415.46
Labour
Overall size 4'-0" x 9'-4", 4'-0" x 8'-0" Side hung, double sash 0'-4" width timber stile with vertical timber battens with "V" groove with 4'-0" x 1'-2" fixed glass above as per detail drawing
Frame Planking 26.66 L.ft 10.00 266.60
Frame making 26.66 L.ft 100.00 2,666.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 30.91 sq.ft 10.00 309.05
Timber Sash making 26.81 sq.ft 225.00 6,032.25
Water base paint 215.73 sq.ft 88.00 18,984.24
Locks & ironmongary fixing 2,500.00 31,508.14
Tools 3% 945.24
Total cost 84,661.13
Total cost for 1 Sq.ft 2,268.52
1 1/2" thick Frame
1 1/4" thick sash local teak
5 Overall size ,12' 3" x 9' 4" 12.25 9.33 114.29 Sq.ft
glass 9.25 7.83 72.43
Material
9" timber plank 23.18 sq.ft 1,200.00 27,819.00 16.28
1 1/4" thick Teak timber sash 51.20 sq.ft 1,000.00 51,195.00 8.62
Wood presavative 7.21 Cu.ft 263.00 1,895.16
Wood treatment 125.34 sq.ft 20.00 2,506.81 83,415.97
Wastage 10% 8,341.60
6mm Glass arae 72.43 sq.ft 100.00 7,242.75 7,242.75
Glazing beads 99.60 L.ft 5.00 498.00 498.00
Sliding gears 24.50 L.ft - -
99498.31895
Overall size 12'-3" x 9'-4", Four sash, two sashes sliding and two sash fixed on either side
SD1, SD2, SD5,SD6,SD8,SD9,SD11,SD12,SD13,SD14,SD15
Transport 7% 6,964.88
Labour
9" thk plak Planking 23.18 Sq.ft 10.00 231.83
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 51.20 sq.ft 10.00 511.95
Timber Sash making 114.29 sq.ft 225.00 25,715.81
Water base paint 102.39 sq.ft 88.00 9,010.32
Locks & ironmongary fixing 2,500.00 38,719.91
Tools 3% 1,161.60
Total cost 146,344.71
Total cost for 1 Sq.ft 1,280.44
1 1/4" thick sash local teak
SD3, SD4, SD7,SD10,SD16
6 Overall size ,6' 0" x 9' 4" 6.00 9.33 55.98 Sq.ft
glass 4.50 7.83 35.24
Material 16.16
9" timber plank 18.50 sq.ft 1,200.00 22,194.00 8.50
1 1/4" thick Teak timber sash 25.41 sq.ft 1,000.00 25,410.00
Wood presavative 4.21 Cu.ft 263.00 1,106.06
Wood treatment 69.13 sq.ft 20.00 1,382.60 50,092.66
Wastage 10% 5,009.27
6mm Glass arae 35.24 sq.ft 100.00 3,523.50 3,523.50
Glazing beads 49.32 L.ft 5.00 246.60 246.60
Sliding gears 12.00 L.ft - -
58872.02672
Transport 7% 4,121.04
Overall size 6'-0" x 9'-4", Two sash, glass sliding and two sash fixed on either side
Labour
9" thk plak Planking 18.50 Sq.ft 10.00 184.95
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 50.82 sq.ft 10.00 508.20
Timber Sash making 55.98 sq.ft 225.00 12,595.50
Water base paint 50.82 sq.ft 88.00 4,472.16
Locks & ironmongary fixing 2,500.00 21,010.81
Tools 3% 630.32
Total cost 84,634.20
Total cost for 1 Sq.ft 1,511.87
1 1/4" thick sash local teak
SD3a, SD17
7 Overall size ,6' 0" x 9' 4" 6.00 9.33 55.98 Sq.ft
glass 5.00 7.83 39.15
Material 21.66
9" timber plank 18.50 sq.ft 1,200.00 22,194.00 14.00
1 1/4" thick Teak timber sash 16.83 sq.ft 1,000.00 16,830.00
Wood presavative 3.35 Cu.ft 263.00 880.41
Wood treatment 51.97 sq.ft 20.00 1,039.40 40,943.81
Wastage 10% 4,094.38
6mm Glass arae 39.15 sq.ft 100.00 3,915.00 3,915.00
Glazing beads 35.66 L.ft 5.00 178.30 178.30
Sliding gears 12.00 L.ft - -
49131.48732
Transport 7% 3,439.20
Labour
9" thk plak Planking 18.50 Sq.ft 10.00 184.95
Overall size 6'-0" x 9'-4", single sash, glass sliding door
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 33.66 sq.ft 10.00 336.60
Timber Sash making 55.98 sq.ft 225.00 12,595.50
Water base paint 33.66 sq.ft 88.00 2,962.08
Locks & ironmongary fixing 2,500.00 19,329.13
Tools 3% 579.87
Total cost 72,479.70
Total cost for 1 Sq.ft 1,294.74
8 Overall size ,3' 0" x 6' 4" , type W1 3.00 6.33 18.99 Sq.ft
frame 0.33 0.25
sash 2.50 5.58 13.95
glass 3mm 2.50 1.17 2.93
Louver 1.50 4.58 6.87
Material
4"x3" frame. 21.66 L.ft 550.00 11,913.00
1 1/4" thick Teak timber sash 11.02 sq.ft 1,000.00 11,025.00
12.5mm louver 6.87 sq.ft 400.00 2,748.00
Wood presavative 3.16 Cu.ft 263.00 832.20
Wood treatment 53.77 sq.ft 20.00 1,075.36 27,593.55
Wastage 10% 2,759.36
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
30,389.61
Transport 7% 2,127.27
0-4" x 0'-3" frame with 1 1/4" thick sash local teak stile with timber louver and fixed glass above
Overall size 3'-0" x 6'-4", 3'-0" x 4'-0" single sash glazed window with 3'-0" x 1'-2" fixed glass above as per detail drawing
Labour
Frame Planking 21.66 L.ft 10.00 216.60
Frame making 21.66 L.ft 100.00 2,166.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 22.05 sq.ft 10.00 220.50
Timber Sash making 13.95 sq.ft 225.00 3,138.75
Water base paint 37.98 sq.ft 88.00 3,342.24
Locks & ironmongary fixing 2,500.00 12,334.09
Tools 3% 370.02
Total cost 45,220.99
Total cost for 1 Sq.ft 2,381.31
9 Overall size ,4' 0" x 6' 4" , type W2 4.00 6.33 25.32 Sq.ft
frame 0.33 0.25
sash 3.50 5.58 19.53
glass 3mm 3.50 1.17 4.10
Louver 1.50 4.58 6.87
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 15.44 sq.ft 1,000.00 15,435.00
12.5mm louver 6.87 sq.ft 400.00 2,748.00
Wood presavative 3.85 Cu.ft 263.00 1,013.27
Wood treatment 65.08 sq.ft 20.00 1,301.56 34,060.83
Wastage 10% 3,406.08
0-4" x 0'-3" frame with 1 1/4" thick sash local teak stile with timber louver and fixed glass above
Overall size 4'-0" x 6'-4", 4'-0" x 4'-0" double sash glazed window with 4'-0" x 1'-2" fixed glass above as per detail drawing
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 9.34 L.ft 5.00 46.70 46.70
37,513.61
Transport 7% 2,625.95
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 30.87 sq.ft 10.00 308.70
Timber Sash making 19.53 sq.ft 225.00 4,394.25
Water base paint 50.64 sq.ft 88.00 4,456.32
Locks & ironmongary fixing 2,500.00 15,121.87
Tools 3% 453.66
Total cost 55,715.09
Total cost for 1 Sq.ft 2,200.44
10 Overall size ,4' 0" x 6' 4" , type W3 4.00 6.33 25.32 Sq.ft
frame 0.33 0.25
sash 3.50 5.58 19.53
glass 3mm 3.50 1.17 4.10
glass 6mm 1.50 4.58 6.87
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
0-4" x 0'-3" frame with 1 1/4" thick sash local teak stile with timber louver and fixed glass above
Overall size 4'-0" x 6'-4", 4'-0" x 4'-0" ,4" width timber stile with two sash glazed window with 4'-0" x 1'-2" fixed glass above as per detail drawing
1 1/4" thick Teak timber sash 8.57 sq.ft 1,000.00 8,565.00
Wood presavative 2.89 Cu.ft 263.00 760.32
Wood treatment 37.60 sq.ft 20.00 751.96 23,640.28
Wastage 10% 2,364.03
6mm Glass arae 6.87 sq.ft 100.00 687.00 687.00
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 30.66 L.ft 5.00 153.30 153.30
26,844.60
Transport 7% 1,879.12
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 8.57 sq.ft 10.00 85.65
Timber Sash making 19.53 sq.ft 225.00 4,394.25
Water base paint 50.64 sq.ft 88.00 4,456.32
Locks & ironmongary fixing 2,500.00 14,898.82
Tools 3% 446.96
Total cost 44,069.51
Total cost for 1 Sq.ft 1,740.50
Timber Felmet
L2.55 Queens
Assume 10 L.ft
Materials
1" thick, 8" height timber felmet 10.00 L.ft 575.00 5,750.00
Nut & bolts 5.00 No 10.00 50.00
5,800.00
1" thick, 8" height timber felmet fixed with nut & bolts to RCC beam and finished with applying with 2 coat of water based lacquer.(Spray paint)
Transport 7% 406.00
Labour
Skilled Labour 1.00 day 950.00 950.00
Un / skilled Labour 1.00 day 650.00 650.00
1,600.00
Paint
Tmber planking 10.00 L.ft 10.00 100.00
Tmber painting ( water base spry) 13.40 Sq.ft 115.00 1,541.00
1,641.00
9,447.00
Total cost for 1 L.ft 944.70
DOORS AND WINDOWS
Specification:
Materil
Frame -Red Balaw
Frame 6" x4" 1.00 L.ft 458.00
4" x3" 1.00 L.ft 214.00
Sash -Mahoganie
Sash 1 1/2" thick 1.00 Sq.ft 420.00
1 1/4" thick 1.00 Sq.ft 350.00
1 3/4" thick 1.00 Sq.ft 400.00
3' 0" x 7' 0" plywood door 1.00 Nos 3,600.00
Glass - clear
6mm thick 1.00 Sq.ft 100.00
3mm thick 1.00 Sq.ft
Iron mongery -Brass
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Main Index
Window Fasterners 1.00 Nos 325.00
Window Rings 1.00 Nos 35.00
Wood Seasion
1' 0" x 1' 0" x 1' 0" 1.00 Cu.ft 263.20
Labour
1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber "v" grove panel 1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
frame planking 1.00 L.ft 10.00
Sash planking 1.00 Sq.ft 10.00
Frame fixing to wall -small 1.00 Nos 750.00
Frame fixing to wall -big 1.00 Nos 1,000.00
Lock and ironmongary fixing 2,500.00
Item Discreption No No No No Qty Unit Rate Amount
15%
D1
Size of door 4'-0" x 9'-0" 1 4.00 9.00 36.00
Material
Timber
1 1/4" thick timber sash 3.50 8.75 30.63 Sq.ft 350.00 10,718.75
Frame making 6" x 4"
Length
Width
Height
Total Amount
O/H & Profit
Double sash timber battened door -4" x3" frame and 11/4" thick sash ( finish size )
(3.5 x 10718.75
Wastage 10% 0.1 1071.88
4"x3" frame 22.00 L.ft 214.00 4,708.00
Ironmongary
6"x4" Hinges 4 4.00 Nr 550.00 2,200.00
1 1/4" screws 3 2 8 48 48.00 Nr 8.35 400.80
1' 6" High brass barolt bolt 1 1.00 Nr 2,900.00 2,900.00
6" High brass latch 1 1.00 Nr 380.00 380.00
Union Lock 1 1.00 Nr 380.00 380.00
Flat iron Item 1,500.00
24,259.43
Transport 5% 0.05 1,212.97
Labour
Frame making 22 22.00 L.ft 100.00 2,200.00
Frame fixing to wall 1.00 Item 750.00 750.00
Sash making & fixing 30.63 30.63 Sq.ft 450.00 13,781.25
Frame planking 22 22.00 l.ft 10.00 220.00
Sash planking 30.63 30.63 Sq.ft 10.00 306.25
All iron mongary fixing including locks 1.00 Per Unit 2,500.00 2,500.00
17,257.50
42,729.90
Sq.ft. Rate 1,186.94 178.04
D2 Double sash panelleded door
Size of door 1 5.00 10.00 50.00
Size of frame 0.33 0.50
Sash 0.50 0.15
Material
6"x4" door frame 2 10 20
1 6 6
26
26.00 458.00 11,908.00
1 1/4" thick timber sash 4.33 9.67 41.90 350.00 14,663.87
26571.87
Wastage 10% 0.1 2657.19
6"x4" Hinges 3 3.00 550.00 1,650.00
1 1/4" screws 3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch 1 1.00 2300.00 2,300.00
6" High brass latch 1 1.00 380.00 380.00
Union Lock 1 1.00 2900.00 2,900.00
Flat iron item 1,500.00
38,359.86
Transport 5% 0.05 1,917.99
Labour
Frame making 26.00 26.00 110.00 2,860.00
Frame fixing to wall item 1.00 750.00 750.00
Sash making & fixing 41.90 41.90 450.00 18,853.55
Locks fixing item 1.00 2500.00 2,500.00
Frame planking 26.00 26.00 10.00 260.00
Sash planking 41.90 41.90 10.00 418.97
25,642.52
65,920.37
Sq.ft. Rate 1,318.41 197.76
D 3 Single sash panelleded door
Size of door 1 4.66 8.83 41.15
Size of frame 0.33 0.41
Sash 0.41 0.13
Material
6"x4" door frame 2 8.83 17.66
2 3.84 7.68
25.34
25.34 458.00 11,605.72
1 3/4" thick timber sash 3.99 8.50 33.94 400.00 13,574.81
25180.53
Wastage 10% 0.1 2518.05
6"x4" Hinges 3 3.00 550.00 1,650.00
1 1/4" screws 3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch 1 1.00 2300.00 2,300.00
6" High brass latch 1 1.00 380.00 380.00
Union Lock 1 1.00 2900.00 2,900.00
Flat iron item 1,500.00
36,829.38
Transport 5% 0.05 1,841.47
Labour
Frame making 25.34 25.34 110.00 2,787.40
Frame fixing to wall item 1.00 750.00 750.00
Sash making & fixing 33.94 33.94 450.00 15,271.66
Locks fixing item 1.00 2500.00 2,500.00
Frame planking 25.34 25.34 10.00 253.40
Sash planking 33.94 33.94 10.00 339.37
21,901.83
60,572.68
Sq.ft. Rate 1,472.08 220.81
W 1 Sliding glazed window
Size of window 1 ### 10.16 159.11
Size of frame 0.33 0.50
Sash 0.50 0.16
Material
6"x4" window frame 2 ### 20.32
1 ### 14.66
2 9.16 18.32
53.30
53.30 458.00 24,411.40
1 3/4" thick timber sash 4 3.67 9.83 144.11 400.00 57,643.12
6mm thick plan glass 4 2.67 8.83 94.13 100.00 9,412.78
91467.30
Wastage 10% 0.1 9146.73
3"x4" Hinges 12 12.00 350.00 4,200.00
1 1/4" screws 12 2 8 192 192.00 8.35 1,603.20
1' 6" High brass latch 3 3.00 2300.00 6,900.00
6" High brass latch 3 3.00 380.00 1,140.00
Flat iron item 1,500.00
115,957.23
Transport 5% 0.05 5,797.86
Labour
Frame making 53.30 53.30 110.00 5,863.00
Frame fixing to wall item 1.00 750.00 750.00
Sash making & fixing ### 144.11 450.00 64,848.51
Locks fixing item 1.00 2500.00 2,500.00
Frame planking 53.30 53.30 10.00 533.00
Sash planking ### 144.11 10.00 1,441.08
74,494.51
196,249.60
Sq.ft. Rate 1,233.46 185.02
D 4 Single sash plywood door
Size of door 1 3.00 7.00 21.00
Size of frame 0.25 0.50
Sash 0.50 0.13
Material
3"x4" door frame 2 7.00 14.00
1 2.00 2.00
16.00
16.00 214.00 3,424.00
Plywood door 3,600.00 3,600.00
7024.00
Wastage 10% 0.1 702.40
6"x4" Hinges 3 3.00 550.00 1,650.00
1 1/4" screws 3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch 1 1.00 2300.00 2,300.00
Union Lock 1 1.00 2900.00 2,900.00
Flat iron item 1,500.00
16,477.20
Transport 5% 0.05 823.86
Labour
Frame making 16.00 16.00 100.00 1,600.00
Frame fixing to wall item 1.00 750.00 750.00
Locks fixing item 1.00 2500.00 2,500.00
Frame planking 16.00 16.00 10.00 160.00
5,010.00
22,311.06
Sq.ft. Rate 1,062.43 159.36
W 1 Glazed timber window
Size of window 1 6.75 8.50 57.38
Size of frame 0.25 0.33
Sash 0.33 0.16
Material
4"x3" window frame 3 6.75 20.25
4 8.50 34.00
54.25
54.25 205.00 11,121.25
1 1/4" thick timber sash 1 5.75 6.50 37.38
11.50 150.00 1,725.00
6mm thick plan glass 3 1.50 3.67 16.52
3 1.50 2.08 9.36
25.88 100.00 2,587.50
Beading 12 1.50 18.00
6 3.67 22.02
6 2.08 12.48
52.50 1.00 52.50
15486.25
Wastage 10% 0.1 1548.63
Steel gril 27 1.5 40.50 30 1,215.00
3"x4" Hinges 6 6.00 350.00 2,100.00
1 1/4" screws 6 2 4 48 48.00 8.35 400.80
1' 6" High brass latch 3 3.00
6" High brass latch 3 3.00 380.00 1,140.00
Casement stay 3 3.00 380.00 1,140.00
Window Fasterners 3 3.00 325.00 975.00
Window Rings 3 3.00 35.00 105.00
Flat iron item 1,500.00
25,610.68
Transport 5% 0.05 1,280.53
Labour
Frame making 54.25 54.25 100.00 5,425.00
Frame fixing to wall item 1.00 1000.00 1,000.00
Sash making & fixing 11.50 11.50 225.00 2,587.50
Locks fixing item 1.00 2500.00 2,500.00
Frame planking 54.25 54.25 10.00 542.50
Sash planking 11.50 11.50 10.00 115.00
12,170.00
39,061.21
Sq.ft. Rate 680.81 102.12
Paimting 88.00
768.81
OH 18% 907.19
Amount with profit
1,364.98
1,516.17
1,692.89
1,418.47
1,221.80
782.93
Doors Windows
408/775
Item Discription Qty Unit Rate Amount Amount
Specification:
Materil
Frame -Teak
Frame 6" x4" 1.00 L.ft 1,100.00
4" x3" 1.00 L.ft 720.00
Sash -Mahoganie
1.00 Sq.ft 1,200.00
1.00 Sq.ft 1,000.00
1 3/4" thick 1.00 Sq.ft
3' 0" x 7' 0" plywood door 1.00 Nos 3,600.00
Glass - clear
6mm thick Sand blast glass 1.00 Sq.ft 215.00
3mm thick 1.00 Sq.ft
Iron mongery -Brass
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Window Fasterners 1.00 Nos 325.00
Window Rings 1.00 Nos 35.00
Sash 1 1/2" thick
1 1/4" thick
Doors Windows
409/775
Item Discription Qty Unit Rate Amount Amount
Hold past 1.00 Item 1,500.00
Wood Seasion
1' 0" x 1' 0" x 1' 0" 1.00 Cu.ft 263.20
Wood Painting
Wood treatment 1.00 Sq.ft 20.00
Water base 1.00 Sq.ft 88.00
Spray paint 1.00 Sq.ft 88.00
Labour
1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber With louver
1.00 Sq.ft 500.00
1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
frame planking 1.00 L.ft 10.00
Sash planking 1.00 Sq.ft 10.00
1.00 Nos 750.00
Frame fixing to wall -big
1.00 Nos 1,000.00
2,500.00
D1 Timber panel door
Size of door 4.00 8.50 34.00 Sq ft
Size of frame 0.44 0.25
Sash 0.33 0.15
Material
5"x3" door frame 1 5.50 5.50
3 8.50 ###
### 31.00 L.ft 1,100.00 34,100.00
3.00 8.25 24.75 24.75 Sq.ft 1,000.00 24,750.00 58,850.00
Wastage 10% 5,885.00
Wood treatment 10% 2,942.50
Transport 10% 5,885.00
Frame making 6" x 4"
Solid timber "v" grove panel
Frame fixing to wall -small
Lock and ironmongary fixing
Sash area 1 1/4" Timber panel
Doors Windows
410/775
Item Discription Qty Unit Rate Amount Amount
3"x4" Hinges 5 5.00 Nos 350.00 1,750.00
1 1/4" screws 5 2 8 80 80.00 Nos 8.35 668.00
Hold past 1,500.00
3,918.00
Labour
Labour
Frame Planking 31.00 L.ft 10.00 310.00
Sash Planking 24.75 Sq.ft 10.00 247.50
Frame making 31.00 L.ft 100.00 3,100.00
Sash making 24.75 Sq.ft 450.00 11,137.50
Frame fixing to wall 1.00 Nos 1,000.00 1,000.00
Locks & ironmongary fixing item 2,500.00 18,295.00
Tools 3% 548.85
Water base paint
Total cost 96,324.35
Total cost for 1 Sq.ft 2,833.07
D2 Timber panel door
Size of door 3.00 7.00 21.00 Sq ft
Size of frame 0.44 0.25
Sash 0.33 0.15
Material
4"x3" door frame 1 4.50 4.50
2 7.00 ###
### 18.50 L.ft 720.00 13,320.00
3.00 6.75 20.25 20.25 Sq.ft 1,000.00 20,250.00
33,570.00
Wastage 10% 3,357.00
Wood treatment 5% 1,678.50
Transport 10% 3,357.00
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Sash area 1 1/4" Timber panel
Doors Windows
411/775
Item Discription Qty Unit Rate Amount Amount
Hold past 1,500.00
3,434.40
Labour
Frame Planking 18.50 L.ft 10.00 185.00
Sash Planking 20.25 Sq.ft 10.00 202.50
Frame making 18.50 L.ft 100.00 1,850.00
Sash making 20.25 Sq.ft 450.00 9,112.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 14,600.00
Tools 3% 438.00
Water base paint
Total cost 60,434.90
Total cost for 1 Sq.ft 2,877.85
D3
Size of door 3.00 7.00 21.00 Sq ft
Size of frame 0.33 0.25
Sash 0.33 0.15
Size of Fixed glass 3.00 1.50
Size of frame 0.33 0.25
Material
4"x3" door frame 1 4.50 4.50
2 7.00 ###
4"x3" Fixed glass frame 2 4.50 9.00
2 1.50 3.00
### 30.50 L.ft 720.00 21,960.00
Sash area 2.50 6.75 16.88
Timber for sash 2 6.5 0.25 3.25
1 2.5 0.25 0.63
1 2.5 0.75 1.88 5.75 Sq.ft 1,000.00 5,750.00
### ### 0.83 0.17 14.67 Sq.ft 1,000.00 14,674.40
6mm thick Sand blast glass 2.50 1.00 2.50 2.50 Sq.ft 215.00 537.50
42,921.90
Wastage 10% 4,292.19
Wood treatment 5.% 2,146.10
Transport 10% 4,292.19
Louver door with Timber Frame & Fixed Glass above
2" x 1/2" timber horizontals fixed to sash (on both sides)
Doors Windows
412/775
Item Discription Qty Unit Rate Amount Amount
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past 1,500.00
3,434.40
Labour
Frame Planking 30.50 L.ft 10.00 305.00
Sash Planking 20.42 Sq.ft 10.00 204.24
Frame making 30.50 L.ft 100.00 3,050.00
Sash making 16.88 Sq.ft 500.00 8,437.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 15,246.74
Tools 3% 457.40
Water base paint
Total cost 72,790.92
Total cost for 1 Sq.ft 3,466.23
D4
Size of door 2.75 7.00 19.25 Sq ft
Size of frame 0.44 0.25
Sash 0.33 0.15
Size of Fixed glass 2.75 1.50
Size of frame 0.33 0.25
Material
4"x3" door frame 1 4.25 4.25
2 7.00 ###
4"x3" Fixed glass frame 2 4.25 8.50
2 1.50 3.00
### 29.75 L.ft 720.00 21,420.00
3.00 6.75 20.25 20.25 Sq.ft 1,000.00 20,250.00
6mm thick Sand blast glass 2.25 1.00 2.25 2.25 Sq.ft 215.00 483.75 42,153.75
Wastage 10% 4,215.38
Wood treatment 5% 2,107.69
Transport 10% 4,215.38
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
Timber panel door with Timber Frame & Fixed
Glass above
Sash area 1 1/4" Timber panel
Doors Windows
413/775
Item Discription Qty Unit Rate Amount Amount
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past 1,500.00
3,434.40
Labour
Frame Planking 29.75 L.ft 10.00 297.50
Sash Planking 20.25 Sq.ft 10.00 202.50
Frame making 29.75 L.ft 100.00 2,975.00
Sash making 20.25 Sq.ft 450.00 9,112.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 15,837.50
Tools 3% 475.13
Water base paint
Total cost 72,439.21
Total cost for 1 Sq.ft 3,763.08
D5
Size of door 3.00 10.00 30.00 Sq ft
Size of frame 0.42 0.25
Sash 0.33 0.15
Material
5"x3" door frame 1 4.50 4.50
2 ### ###
### 24.50 L.ft 720.00 17,640.00
Sash area 2.50 9.75 24.38
Glass Area 4 1.84 1.92 14.13
Timber for sash 10.24 Sq.ft 1,000.00 10,243.80
6mm thick Sand blast glass 14.13 Sq.ft 215.00 3,038.21 30,922.01
Wastage 10% 3,092.20
Wood treatment 5% 1,546.10
Transport 10% 3,092.20
3"x4" Hinges 5 5.00 Nos 350.00 1,750.00
1 1/4" screws 5 2 8 80 80.00 Nos 8.35 668.00
Door with Milky White fixed glass
Doors Windows
414/775
Item Discription Qty Unit Rate Amount Amount
Hold past 1,500.00
3,918.00
Labour
Frame Planking 24.50 L.ft 10.00 245.00
Sash Planking 10.24 Sq.ft 10.00 102.44
Frame making 24.50 L.ft 100.00 2,450.00
Sash making 10.24 Sq.ft 450.00 4,609.71
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 10,657.15
Tools 3% 319.71
Water base paint
Total cost 53,547.37
Total cost for 1 Sq.ft 1,784.91
W1
Size of window 3.00 3.00 9.00 Sq ft
Size of frame 0.33 0.25
Sash 0.33 0.15
Material
4"x3" window frame 2 4.50 9.00
2 3.00 6.00
### 15.00 L.ft 720.00 10,800.00
Sash area 2.50 2.50 6.25
Louver Area 1.18 1.84 2.17
Timber for sash 4.08 Sq.ft 1,000.00 4,078.80
2 2.17 4.34 Sq.ft 1,000.00 4,342.40 19,221.20
Wastage 10% 0.1 1,922.12
Wood treatment 5% 0.05 961.06
Transport 10% 1,922.12
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Louver window with timber frame
2" x 1/2" timber horizontals fixed to sash (on both sides)
Doors Windows
415/775
Item Discription Qty Unit Rate Amount Amount
Hold past 1,500.00
3,434.40
Labour
Labour
Frame Planking 15.00 L.ft 10.00 150.00
Sash Planking 8.42 Sq.ft 10.00 84.21
Frame making 15.00 L.ft 100.00 1,500.00
Sash making 8.42 Sq.ft 450.00 3,789.54
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 8,773.75
Tools 3% 263.21
Water base paint
Total cost 36,497.86
Total cost for 1 Sq.ft 4,055.32
W1
Size of window 2.75 4.25 11.69 Sq ft
Size of frame 0.33 0.25
Sash 0.33 0.15
Size of Fixed glass 2.75 1.50
Size of frame 0.33 0.25
Material
4"x3" window frame 2 4.25 8.50
2 4.25 8.50
4"x3" Fixed glass frame 2 4.25 8.50
2 1.50 3.00
### 28.50 L.ft 720.00 20,520.00
Sash area 2.25 3.75 8.44
Timber for sash 2 1.75 0.25 0.88
3 3.25 0.25 2.44 3.31 Sq.ft 1,000.00 3,312.50
4 ### 0.67 0.18 7.72 Sq.ft 1,000.00 7,718.40
6mm thick Sand blast glass 2.25 1.00 2.25 2.25 Sq.ft 215.00 483.75 32,034.65
Wastage 10% 0.1 3,203.47
Wood treatment 5% 0.05 1,601.73
Transport 10% 3,203.47
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
Louver window with timber frame & Fixed Glass above
2" x 1/2" timber horizontals fixed to sash (on both sides)
Doors Windows
416/775
Item Discription Qty Unit Rate Amount Amount
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past 1,500.00 3,434.40
Labour
Frame Planking 28.50 L.ft 10.00 285.00
Sash Planking 11.03 Sq.ft 10.00 110.31
Frame making 28.50 L.ft 100.00 2,850.00
Sash making 9.97 Sq.ft 450.00 4,485.78
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 10,981.09
Tools 3% 329.43
Water base paint
Total cost 54,788.23
Total cost for 1 Sq.ft 4,687.76
Size of window 2.83 2.58 7.30 Sq ft
Size of frame 0.33 0.25
Sash 0.33 0.15
Material
4"x3" window frame 2 4.33 8.66
2 2.58 5.16
### 13.82 L.ft 720.00 9,950.40
Sash area 2.33 2.08 4.85
Louver Area 1.01 1.42 1.43
Timber for sash 1.98 Sq.ft 1,000.00 1,978.00
2 1.43 2.87 Sq.ft 1,000.00 2,868.40
14,796.80
Wastage 10% 0.1 1,479.68
Wood treatment 5% 0.05 739.84
Transport 10% 1,479.68
Louver window with timber frame (Water tank room door)
2" x 1/2" timber horizontals fixed to sash (on both sides)
Doors Windows
417/775
Item Discription Qty Unit Rate Amount Amount
3"x4" Hinges 2 2.00 Nos 350.00 700.00
1 1/4" screws 2 2 8 32 32.00 Nos 8.35 267.20
Hold past 1,500.00
2,467.20
Labour
Labour
Frame Planking 13.82 L.ft 10.00 138.20
Sash Planking 4.85 Sq.ft 10.00 48.46
Frame making 13.82 L.ft 100.00 1,382.00
Sash making 4.85 Sq.ft 450.00 2,180.88
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00 6,999.54
Tools 3% 209.99
Water base paint
Total cost 28,172.73
Total cost for 1 Sq.ft 3,858.54
Doors Windows
418/775
15%
O/H & Profit
Amount with profit
Doors Windows
419/775
O/H & Profit
Amount with profit
3'-0"
10'-0
"
Doors Windows
420/775
O/H & Profit
Amount with profit
424.96 ###
3'-0"
7'-0
"
10'-0
"
Doors Windows
421/775
O/H & Profit
Amount with profit
431.68 ###
3'-0"
7'-0
"
Doors Windows
422/775
O/H & Profit
Amount with profit
519.94 ###
3'-0"
7'-0
"
Doors Windows
423/775
O/H & Profit
Amount with profit
564.46 ###
3'-0"
10'-0
"
Doors Windows
424/775
O/H & Profit
Amount with profit
267.74 ###
4'-6"
3'-0
"
Doors Windows
425/775
O/H & Profit
Amount with profit
608.30 ###
2.752'-9"
4'-3
"
Doors Windows
426/775
O/H & Profit
Amount with profit
703.16 ###
2.752'-9"
4'-3
"
Doors Windows
427/775
O/H & Profit
Amount with profit
578.78 ###
TYPE OF ROOF / ROOF PLUMBING / CANOPIES
Item Description Qty Unit Rate Amount Amount
15%
1 TIMBER ROOF
1
Consider 15.34 Sqr
Materials
Frame work
Red balaw timber
4''x8'' Ridge plate 48.00 L.ft 665.00 31,920.00
4''X6'' Purling 213.50 L.ft 458.00 97,783.00
3''X6'' Rafter 962.51 L.ft 285.00 274,315.35
2''X2'' Runers 501.50 L.ft 55.00 27,582.50
431,600.85
Wastage 10% of timber 10% 43,160.09
Wood preservative 181 Cu.ft 263.00 47,510.27
Nails & screws 15 kg 160.00 2,400.00
49,910.27
O/H & Profit
Amount with profit
Asbestos roof with exposed rafters and lunumiddala ceiling. Rate include to tar sheet and insulation
( Roof timber is bigger than in normal size )
Main Index
Roof Covering
Asbestors Roof covering 15.34 Sqr 3,510.42 53,849.79
Wastage 10% of roof covering 10% 5,384.98
J bolts 300 No 5.00 1,500.00
60,734.77
Timber ceiling
6" thick Lunumidella plank 15.34 Sqr 5,600.00 85,904.00
Wastage 20% of timber ceiling 20% 17,180.80
Wood preservative 767 Cu.ft 263.00 201,721.00
304,805.80
Tar sheet 15.34 Sqr 1,000.00 15,340.00
Mackfoil 5mm double side 15.34 Sqr 1,775.09 27,229.93 42,569.93
Wastage 10% 10% 4,256.99
937,038.69
Transport 10% 10% 93,703.87
Labour
Planking charges for frame work 1,726 L.ft 10.00 17,255.10
Planking charges for timber ceiling 1534 Sqr 10.00 15,340.00
labour 15.34 Sqr 15,000.00 230,100.00
262,695.10
Add for tools 3% of labour 3% 6,903.00
Add for scaffolding 5% of labour 5% 11,505.00
1,311,845.66
85,517.97 12,827.70 98,345.67
Preliminaries 10% 131,184.57
Cost per 15.34 Sqs 1,443,030.23
Cost per 1 Sqs 94,069.77 14,110.47 108,180.23
2
Red balaw timber
Materials
Frame work
3''x 6'' Ridge plate 35.00 L.ft 285.00 9,975.00
3''x 6'' wall plate 70.00 L.ft 285.00 19,950.00
3" x 5" beam 42.00 L.ft 290.00 12,180.00
2" x 6" support 7.50 L.ft 214.00 1,605.00
2 ''x 4'' Rafter 369 L.ft 135.50 49,999.50
2''x 2'' Runers 210.00 L.ft 55.00 11,550.00
105,259.50
Wastage 10% of timber 10% 10,525.95
Wood preservative 45 Cu.ft 263.00 11,819.85
Nails & screws 10 kg 160.00 1,600.00
13,419.85
Roof Covering
Asbestors Roof covering 7.21 Sqr 3,510.42 25,310.10
Wastage 10% of roof covering 10% 2,531.01
J bolts 300 No 5.00 1,500.00
29,341.11
Timber ceiling
6" thick Lunumidella plank 7.21 Sqr 5,600.00 40,376.00
Wastage 20% of timber ceiling 20% 8,075.20
Wood preservative 360.50 Cu.ft 263.00 94,811.50
143,262.70
Asbestos roof with exposed rafters and lunumiddala ceiling.
Labour
Planking charges for frame work 733.50 L.ft 10.00 7,335.00
labour 7.21 Sqr 11,000.00 79,310.00
86,645.00
ADD
Add for tools 3% of labour 3% 2,379.30
Add for scaffolding 5% of labour 5% 3,965.50
394,798.92
54,757.13 8,213.57 62,970.70
Preliminaries 10% 39,479.89
Cost for 7.21 Sqr 434,278.81
Cost per 1 Sqs 60,232.84 9,034.93 69,267.77
3
( Small structure timber roof )
Tholang timber Consider 600 Sq ft
Material
Frame work
3" x 4" wall plate 52.00 L ft 183.00 9,516.00
2" x 7" ridge plate 25.00 L ft 215.00 5,375.00
2" x 4" Rafters 360.00 L ft 123.50 44,460.00
2" x 2" reepers 150.00 L ft 49.00 7,350.00
66,701.00
ADD 5% wastage 5% 3,335.05
Asbestos roof with exposed rafters and lunumiddala ceiling.
Wood preservative 31.29 Cu.ft 263.00 8,228.22
48.00 Cu.ft 263.00 12,624.00
Nails & screws 8 kg 160.00 1,280.00
22,132.22
ADD 5% wastage 5% 1,106.61
Roof Covering
Asbestos sheet (12' 0" long) 600.00 Sq ft 35.10 21,062.50
J bolts 120.00 no 5.00 600.00
Tar sheet 600.00 Sq ft 10.00 6,000.00
27,662.50
ADD 5% wastage 5% 1,383.13
Timber ceiling
6" thick Lunumidella plank 600.00 Sq ft 56.00 33,600.00 33,600.00
Wastage 20% of timber ceiling 20% 6,720.00
Labour
Labour charges 600.00 Sq ft 110.00 66,000.00
66,000.00
Add for tools 3% of labour 3% 1,980.00
Add for scaffolding 5% of labour 5% 3,300.00
233,920.50
38,986.75 5,848.01 44,834.76
Preliminaries 10% 23,392.05
Cost for 6 Sqr 257,312.55
Cost for 1 Sqr 42,885.43 6,432.81 49,318.24
4
Tholang timber Consider 270 Sq ft
Material
Frame work
3" x 4" Wall plate 36.00 L.ft 183.00 6,588.00
2" x 5" Ridge Plate 18.00 L.ft 163.50 2,943.00
2" x 4" rafters 300.00 L.ft 123.50 37,050.00
46,581.00
Wastage 5% 5% 2,329.05
Slooping Ceiling
Asbestos sheet 270.00 Sq.ft 34.38 9,281.25 9,281.25
Wastage 5% 5% 464.06
Roof covering
Plywood sheet (9mm) 9.00 No 2,675.00 24,075.00
Nails and screws 5.00 Kg 160.00 800.00
24,875.00
Wastage 5% 5% 1,243.75
Half round tile covering
Half round tile 1,215 No 18.00 21,870.00 21,870.00
Wastage 5% 5% 1,093.50
Asbestos sheet roof with exposed rafters, plywood sloping ceiling and asbestos sheet covered by half round tile
Labour
Carpenter 2.00 Day 950.00 1,900.00
For tile cover 2.00 Day 650.00 1,300.00
3,200.00
Add for tools 3% of labour 3% 96.00
Add for scaffolding 5% of labour 5% 160.00
111,193.61
41,182.82 6,177.42 47,360.24
Preliminaries 10% 11,119.36
122,312.97
Cost for 1 sqr 45,301.10 6,795.17 52,096.27
5 Asbestos roof with frame work.
Tholang timber
Consider 13.43 Sqr (49.5' x 27')
Materal
Frame work
4" X 2" Rafters 810.00 L.ft 123.50 100,035.00
4" x 3" wall plate 97.50 L.ft 183.00 17,842.50
6" x 3" purlin 146.25 L.ft 260.00 38,025.00
5" x 5" props 25.40 L.ft 410.00 10,414.00
2" x 2" reepers 250.00 L.ft 49.00 12,250.00
178,566.50
wastage 10% 5% 8,928.33
Transport 7% 7% 12,499.66
Wood Presavative 86.45 Cu.ft 263.00 22,736.97
Nails & screws 14.00 Kg 160.00 2,240.00
Roof covering 72,607.83
Asbestos sheet 1,316.25 Sq.ft 35.10 46,205.86
J bolts 285.00 No 5.00 1,425.00
Labour
Planing charges 1,079.15 L.ft 10.00 10,791.50
Skilled labour 8.00 Day 950.00 7,600.00
Un / sk labour 15.00 Day 650.00 9,750.00
17,350.00
Add for tools 3% of labour 3% 520.50
Add for scaffolding 5% of labour 5% 867.50
302,131.81
22,496.78 3,374.52 25,871.30
Preliminaries 10% 30,213.18
332,345.00
Cost for 1 Sqr (without polish) 24,746.46 3,711.97 28,458.43
6
137.81
( for two layer )
Half round tile laying on asbestos roof
Consider 1 Sqr
Material
Half round tile 450 Nos 20.00 9,000.00
Wastage 10% 10% 900.00
Transport 10% 10% 900.00
10,800.00
Labour
Skilled labour 1 Day 950.00 950.00
Unskilled labour 1 Day 650.00 650.00
1,600.00
Add for tools 3% of labour 3% 48.00
Add for scaffolding 5% of labour 5% 80.00
12,528.00 1,879.20 14,407.20
Preliminaries 10% 1,252.80
Cost for 1 Sqr 13,780.80 2,067.12 15,847.92
7
For 10 L.ft
Materials
Half round tile (Double layer) 50 Nos 18.00 900.00
Transport 7% 63.00 963.00
Labour
Un/sk labour 0.1 Day 650.00 65.00
Add 3% Tools 1.95
Two layers on either side of ridge
add 5% Scaffolding 3.25 70.20
1,033.20
103.32 15.50 118.82
Priliminary 10% 103.32
1,136.52
Cost for 1 L.ft 113.65 17.05 130.70
8
Consider 102.4Sqr
Materal
Asbestos sheet 10,240 Sq.ft 35.10 359,466.67
Wastage 10% 10% 35,946.67
Transport 7% 7% 25,162.67 420,576.00
Nails & screws 106 Kg 160.00 16,960.00
J bolts 2,173 No 5.00 10,865.00
27,825.00
Labour
Labour 20% 89,680.20
Add for tools 3% of labour 3% 2,690.41
Add for scaffolding 5% of labour 5% 4,484.01
96,854.62
Total Cost for 102.4 Sqr 545,255.62
5,324.76 798.71 6,123.48
Priliminary 10% 54,525.56
599,781.18
Asbestos roof without frame work
Cost for 1 Sqr 5,857.24 878.59 6,735.82
9
Materials
Ridge 4.00 pair 45.00 180.00
Roofing screws 16.00 no 15.00 240.00
420.00
Labour
S/k labourer 0.25 day 950.00 237.50
Un/skilled Labour 0.25 day 650.00 162.50
400.00
Tools 3% 12.00
Scaffolding 5% 20.00
852.00
85.20 12.78 97.98
Priliminary 10% 85.20
937.20
Cost for 1 L.ft 93.72 14.06 107.78
Tholang timber
Consider 10.60 Sqr (44.2' x 12')*2
Materal
Asbastos ajestable close fitting ridge fixed complete with roofing screws or bolts
Frame work
4" X 2" Rafters 744.00 L.ft 123.50 91,884.00
4" x 3" wall plate 80.00 L.ft 183.00 14,640.00
4" x 2" colour tile 36.00 L.ft 260.00 9,360.00
2" x 2" reepers 1,408.00 L.ft 55.00 77,440.00
193,324.00
wastage 10% 5% 9,666.20
Transport 7% 7% 13,532.68
Wood Presavative 63.03 Cu.ft 263.00 16,576.00
Nails & screws 14.00 Kg 160.00 2,240.00
18,816.00
Roof covering
Asbestos sheet 742.00 Sq.ft 90.00 66,780.00
J bolts No 5.00 -
66,780.00
Timber ceiling
6" thick Lunumidella plank 1060.00 Sq ft 56.00 59,360.00 59,360.00
Wastage 20% of timber ceiling 30% 17,808.00
Labour
Planing charges 860.00 L.ft 10.00 8,600.00
Skilled labour Day -
Un / sk labour 1,060.00 Day 120.00 127,200.00
127,200.00
Add for tools 3% of labour 3% 3,816.00
Add for scaffolding 5% of labour 5% 6,360.00
525,262.88
49,553.10 7,432.97 56,986.07
Preliminaries 20% 105,052.58
630,315.45
Cost for 1 Sqr (without polish) 59,463.72 8,919.56 68,383.28
4
Tholang timber Consider 270 Sq ft
Material
Frame work
3" x 4" Wall plate 36.00 L.ft 183.00 6,588.00
2" x 5" Ridge Plate 18.00 L.ft 163.50 2,943.00
2" x 4" rafters 300.00 L.ft 123.50 37,050.00
46,581.00
Wastage 5% 5% 2,329.05
Slooping Ceiling
Asbestos sheet 270.00 Sq.ft 34.38 9,281.25 9,281.25
Wastage 5% 5% 464.06
Roof covering
Asbestos sheet 17.00 No 380.00 6,460.00
Nails and screws 5.00 Kg 160.00 800.00
7,260.00
Wastage 5% 5% 363.00
Asbestos sheet roof with exposed rafters, plywood sloping ceiling and asbestos sheet covered by half round tile
Half round tile covering
Half round tile 1,215 No - - -
Wastage 5% 5% -
Labour
Playing charges 300.00 L.ft 10.00 3,000.00
Carpenter 5.00 Day 950.00 4,750.00
For tile cover 5.00 Day 650.00 3,250.00
11,000.00
Add for tools 3% of labour 3% 330.00
Add for scaffolding 5% of labour 5% 550.00
78,158.36
28,947.54 4,342.13 33,289.67
Preliminaries 20% 15,631.67
93,790.04
Cost for 1 sqr 34,737.05 5,210.56 39,947.61
2 ZN / AL ROOF
1
Consider 1 m2
Materials
Zn/Al sheet 1.00 m2 970.31 970.31
Add - Lap and wastage 3% 29.11
Zn/Al roof fix to "c" purlin ( Purlin measured separatly )
97.03
Allow sum for serwes 3.00 Nos 8.35 25.05
Allow sum for bolt & nuts 1.00 Nos 50.00 50.00
1,171.50
Labour
Sk labour 0.25 day 950.00 237.50
U/sk labour 0.25 day 650.00 162.50
400.00
Add
3% of labour cost for tool 12.00
5% of labour cost for scafolding 20.00
32.00
1,603.50 240.53 1,844.03
Preliminaries 160.35
Cost for one 1m2 with preliminaries 1,763.85 264.58 2,028.43
11 Grangular coated Zn/ Al roof
Consider 15 Sqr
Materal
Zn/ Al Sheet 1,500 Sq.ft 106.00 159,000.00
Wastage 10% 10% 15,900.00
Transport 7% 7% 11,130.00 186,030.00
Nails & screws 15.00 Kg 160.00 2,400.00
Bolt 200 No 50.00 10,000.00 12,400.00
Add - 10% trance port
Labour
Labour 20% 39,686.00
Add for tools 3% of labour 3% 1,190.58
Add for scaffolding 5% of labour 5% 1,984.30 42,860.88
241,290.88
Total Cost for 1 Sqr 16,086.06 2,412.91 18,498.97
Priliminary 10% 24,129.09
265,419.97
Cost for 1 L.ft 17,694.66 2,654.20 20,348.86
12
Consider 1 L.ft
Materials
Ridge 1.00 L.ft 135.00 135.00
Roofing screws 16.00 no 15.00 240.00
375.00
Labour
S/k labourer 0.125 day 950.00 118.75
Un/skilled Labour 0.125 day 650.00 81.25
200.00
Tools 3% 6.00
Scaffolding 5% 10.00
591.00 88.65 679.65
Preliminaries 59.10
Cost for one 1m2 with preliminaries 650.10 97.52 747.62
Granguler coated Zn/Al Ridge caps
3 ROOF PLUMBING
1 Upvc Gutter
Assume 40 m
Material
Pvc Guter 40 m 221.64 8,865.75
Running joint 10 no 233.00 2,330.00
Pvc Bracket 89 no 44.00 3,916.00
Nail 360 no 8.35 3,006.00
Solvent Cement 100 grm 2.28 228.00
18,345.75
Wastage 5% 917.29
Labur
Sk labour 1.25 Day 950.00 1,187.50
UnSk labour 1.25 Day 650.00 812.50
2,000.00
Scaffolding 5% 100.00
Tools 3% 60.00
21,423.04
535.58 80.34 615.91
Priliminary 10% 2,142.30
23,565.35
Cost per 1 m 589.13 88.37 677.50
2 Upvc Gutter Out let
Material
Upvc Gutter Out let 1 No 554.00 554.00
Pvc Bracket 2 no 44.00 88.00
Nail 30 no 8.35 250.50
Solvent Cement 12 grm 2.28 27.36
919.86
Wastage 5% 45.99
Labur
Sk labour 0.125 Day 950.00 118.75
UnSk labour 0.125 Day 650.00 81.25 200.00
Scaffolding 5% 10.00
Tools 3% 6.00
1,181.85 177.28 1,359.13
Priliminary 10% 118.19
1,300.04 195.01 1,495.04
3 Upvc Down pipe
Assume 40 m
Material
Pvc Down pipe 40 m 215.89 8,635.62
Running joint 10 no 233.00 2,330.00
Pvc Bracket 89 no 44.00 3,916.00
Nail 360 no 8.35 3,006.00
Solvent Cement 100 grm 2.28 228.00
18,115.62
Wastage 5% 905.78
Labur
Sk labour 1.25 Day 950.00 1,187.50
UnSk labour 1.25 Day 650.00 812.50 2,000.00
Scaffolding 5% 100.00
Tools 3% 60.00
21,181.40
529.53 79.43 608.97
Priliminary 10% 2,118.14
23,299.54
582.49 87.37 669.86
4 Rain water gutter (Cupper)
Assume 40 L.ft
Material
Copper Gutter 40.00 L ft 4,500.00 180,000.00
Wastage 5% 5% 9,000.00
189,000.00
Labour
Skilled 0.25 day 950.00 237.50
Un skilled 0.25 day 650.00 162.50
400.00
Tools 3% 3% 12.00
Scaffolding 5% 5% 20.00
189,432.00
4,735.80 710.37 5,446.17
Priliminary 10% 18,943.20
208,375.20
5,209.38 781.41 5,990.79
5
Assume 10 L.ft
Material
Flashing ( 2'- 2" ) 10.00 L.ft 180.00 1,800.00
Screws 100.00 1,900.00
Wastage 5% 190.00
Labour
Sklled 0.30 Hrs 118.75 35.63
Un skilled 0.30 Hrs 81.25 24.38
60.00
Tools 3% 3% 1.80
Scaffolding 5% 5% 3.00
2,154.80
215.48 32.32 247.80
Priliminary 10% 215.48
2,370.28
Zn/Al flashing for roof end ( front side )
237.03 35.55 272.58
5 Zn/Al gutter
Assume 10 L.ft
Material
Flashing ( 2'- 2" ) 10.00 L.ft 157.00 1,570.00
Gutter bracket 6.00 Nr 10.00
Screws 100.00 1,670.00
Wastage 5% 167.00
Transport 3% 50.10
Labour
Sklled 0.30 Hrs 118.75 35.63
Un skilled 0.30 Hrs 81.25 24.38
60.00
Tools 3% 3% 1.80
Scaffolding 5% 5% 3.00
1,951.90
195.19 29.28 224.47
Priliminary 10% 195.19
2,147.09
214.71 32.21 246.92
4 HEAT SOLUTION
1 Sisalation domestic 100
Assume 1 Sqr
Material
Sisilation domestic 100 1 sqr 1,288.00 1,288.00
Wastage 5% 64.40
Transport 7% 90.16 1,442.56
Labour
Un skilled 1 Day 650.00 650.00
Tools 3% 19.50
Scaffolding 5% 32.50 702.00
Cost for 1 Sqr 2,144.56 321.68 2,466.24
Priliminary 10% 214.46
2,359.02 353.85 2,712.87
Cost for 1 L.ft
4
Consider 5.0 Sqr 5 Sqr
Materal
5mm thick double side Macfoil 500 Sq.ft 26.50 13,250.00
18 GI mesh 500 Sq.ft 6.70 3,350.00
Nail 3 Kg 160.00 480.00
17,080.00
Labour
Skilled labour 2.00 Day 950.00 1,900.00
Un / sk labour 2.50 Day 650.00 1,625.00
5mm thick double side Macfoil (double side Al foil with 18 GI mesh laid over 50x50mm battens )
3,525.00
Add for tools 3% of labour 3% 105.75
Add for scaffolding 5% of labour 5% 176.25
20,887.00
Total Cost for 1 Sqr 4,177.40 626.61 4,804.01
Priliminary 10% 2,088.70
22,975.70
Cost for 1 L.ft 4,595.14 689.27 5,284.41
Tempered Glass Canopy
Consider 13'-0" x 8'-6" (110.5 Sq.ft)
Material
"U' chanel 2 Length 7,000.00 14,000.00
11/2" x11/2" box bars 7 Nos 1,825.00 12,775.00
Tempered glass 113 Sq.ft 700.00 79,100.00
Weding rods 1 Item 1,500.00
Plate 1.34 Sq.ft 325.00 435.50
Anchor bolt 16 Nos 350.00 5,600.00
Silican gum 8 Nos 250.00 2,000.00
Flashing 33 L.ft 275.00 9,075.00
124,485.50
Transport 5% 6,224.28
Labour
Sk 2 Days 950.00 1,900.00
Un/sk 2 Days 650.00 1,300.00
3,200.00
Small tools 3% 3% 96.00
Scafolding 5% 5% 160.00
134,165.78
O/H and profit 25% 25% 33,541.44
Cost without paint 167,707.22
Allow sum for anticorosive paint 5,000.00
Cost with paint 172,707.22
Ex.38 Placing Acrylic Sheet above Pergolas
Material
45.00 Sqft 150.00 6,750.00
3" x 2" Timber Pergolas -Teak 33.75 L.ft 175.00 5,906.25 12,656.25
Transport 10% 1,265.63
Wastage 10% 1,265.63
Labour
skilled 2.00 day 950.00 1,900.00
Un skilled 1.00 day 650.00 650.00 2,550.00
Tools 3% 76.50
17,814.00
O/H & Profit 25% 4,453.50
Acrylic sheet (Polycarbonate) 3mm thick
Total Cost 22,267.50
1 Sqr 43,873.32
Materials
Class 1 Timber 5.55 c.ft 3,240.00 17,982.00
Wastage 5% 899.10
Reepers 2" x 2" 110.00 l.ft 55.00 6,050.00
Wire nails 1.50 kg 160.00 240.00
Calicut tiles 70.00 no 95.00 6,650.00
Woodpreservitive 1.50 liter 388.00 582.00
32,403.10
Labour
Mason 2.00 day 950.00 1,900.00
Un/skilled Labour 3.00 day 650.00 1,950.00
3,850.00
Add
Tools 3% of labour Cost for tools 115.50
192.50
36,561.10
Preliminaries 7,312.22
Cost for 1 Sqr with Preliminaries 43,873.32
Calicut pattern tile hip roof in single storey building consisting of wall plate ridge plate beam struct rafters & reepers.
Scaffolding 5% of labour Cost for scaffolding
ROOF TIMBER COST SEPERATLY
Item Description Qty Unit Rate Amount Amount Remarks
15%
TIMBER ROOF FRAME WORK
1 Treated "Kempas" 2"x2" battens
Assumed 3806 L.ft
Material
2"x2" Battens 3,806.00 L.ft 65.00 247,390.00
Wastage 5% 12,369.50
Transport 10% 24,739.00
Wood treatment 3,806.00 L.ft 7.09 26,984.54 311,483.04
Labour
Planking charges 3,806.00 L.ft 10.00 38,060.00
Labour 18% 56,066.95 94,126.95
405,609.99
106.57 15.99 122.56
Priliminary 10% 40,561.00
446,170.99
Cost for 1 L.ft 117.23 17.58 134.81
O/H & Profit
Amount with profit
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
2 Treated "Kempas" 2"x1" battens
Assumed 547L.ft
Material
2"x1" Battens 547.00 L.ft 28.00 15,316.00
Wastage 5% 765.80
Transport 10% 1,531.60
Wood treatment 547.00 L.ft 3.54 1,936.38 19,549.78
Labour
Planking charges 547.00 L.ft 10.00 5,470.00
Labour 18% 3,518.96 8,988.96
28,538.74
52.17 7.83 60.00
Priliminary 10% 2,853.87
31,392.61
Cost for 1 L.ft 57.39 8.61 66.00
3 Treated "Balaw" 1 1/4"x2 1/2" sealing member
Assumed 651 L.ft
Material
1 1/4"x2 1/2" sealing member 651.00 L.ft 135.50 88,210.50
Wastage 5% 4,410.53
Transport 10% 8,821.05
Wood treatment 651.00 L.ft 10.63 6,920.13 108,362.21
Labour
Planking charges 651.00 L.ft 10.00 6,510.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Labour 18% 19,505.20 26,015.20
134,377.40
206.42 30.96 237.38
Priliminary 10% 13,437.74
147,815.14
Cost for 1 L.ft 227.06 34.06 261.12
4 Treated "Balaw" 4" x 2" collers
Assumed 590 L.ft
Material
4" x 2" collers 590.00 L.ft 135.50 79,945.00
Wastage 5% 3,997.25
Transport 10% 7,994.50
Wood treatment 590.00 L.ft 14.17 8,360.30 100,297.05
Labour
Planking charges 590.00 L.ft 10.00 5,900.00
Labour 18% 18,053.47 23,953.47
124,250.52
210.59 31.59 242.18
Priliminary 10% 12,425.05
136,675.57
Cost for 1 L.ft 231.65 34.75 266.40
5 Treated "Balaw"4" x 3" wall plate / ridge plate
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Assumed 509 L.ft
Material
4" x 3" wall plate 509.00 L.ft 214.00 108,926.00
Wastage 5% 5,446.30
Transport 10% 10,892.60
Wood treatment 509.00 L.ft 21.26 10,821.34 136,086.24
Labour
Planking charges 509.00 L.ft 10.00 5,090.00
Labour 18% 24,495.52 29,585.52
165,671.76
325.48 48.82 374.31
Priliminary 10% 16,567.18
182,238.94
Cost for 1 L.ft 358.03 53.70 411.74
6 Treated "Balaw 5" x 2" rafters
Assumed 5820 L.ft
Material
5" x 2" rafters 5,820.00 L.ft 171.50 998,130.00
Wastage 5% 49,906.50
Transport 10% 99,813.00
Wood treatment 5,820.00 L.ft 17.72 103,130.40 1,250,979.90
Labour
Planking charges 5,820.00 L.ft 10.00 58,200.00
Labour 18% 225,176.38 283,376.38
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
1,534,356.28
263.64 39.55 303.18
Priliminary 10% 153,435.63
###
Cost for 1 L.ft 290.00 43.50 333.50
7 Treated "Balaw 5" x 4" corble plates
Assumed 110 L.ft
Material
5" x 4" corble plates 110.00 L.ft 458.00 50,380.00
Wastage 5% 2,519.00
Transport 10% 5,038.00
Wood treatment 110.00 L.ft 35.43 3,897.30 61,834.30
Labour
Planking charges 110.00 L.ft 10.00 1,100.00
Labour 18% 11,130.17 12,230.17
74,064.47
673.31 101.00 774.31
Priliminary 10% 7,406.45
81,470.92
Cost for 1 L.ft 740.64 111.10 851.74
8 Treated "Balaw 6" x 4" pole plates
Assumed 335 L.ft
Material
6" x 4" pole plates 335.00 L.ft 458.00 153,430.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Wastage 5% 7,671.50
Transport 10% 15,343.00
Wood treatment 335.00 L.ft 42.52 14,244.20 190,688.70
Labour
Planking charges 335.00 L.ft 10.00 3,350.00
Labour 18% 34,323.97 37,673.97
228,362.67
681.68 102.25 783.93
Priliminary 10% 22,836.27
251,198.93
Cost for 1 L.ft 749.85 112.48 862.32
9 Treated "Balaw 7" x 2" hip rafters / Valley rafters
Assumed 145 L.ft
Material
7" x 2" hip rafters 145.00 L.ft 350.00 50,750.00
Wastage 5% 2,537.50
Transport 10% 5,075.00
Wood treatment 145.00 L.ft 24.80 3,596.00 61,958.50
Labour
Planking charges 145.00 L.ft 10.00 1,450.00
Labour 18% 11,152.53 12,602.53
74,561.03
514.21 77.13 591.35
Priliminary 10% 7,456.10
82,017.13
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Cost for 1 L.ft 565.64 84.85 650.48
10 Treated "Balaw 8" x 2" ridge plate
Assumed 218 L.ft
Material
8" x 2" ridge plate 218.00 L.ft 350.00 76,300.00
Wastage 5% 3,815.00
Transport 10% 7,630.00
Wood treatment 218.00 L.ft 28.34 6,178.12 93,923.12
Labour
Planking charges 218.00 L.ft 10.00 2,180.00
Labour 18% 16,906.16 19,086.16
113,009.28
518.39 77.76 596.15
Priliminary 10% 11,300.93
124,310.21
Cost for 1 L.ft 570.23 85.53 655.76
11.0 Treated "Thulan" 7" x 2" ridge plate
Assume 40L.ft
Material
7" x 2" ridge plate 40.00 L.ft 215.00 8,600.00
Wastage 5% 430.00
Transport 10% 860.00
Wood treatment 40.00 L.ft 24.80 992.00 10,882.00
Labour
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Planking charges 40.00 L.ft 10.00 400.00
Labour 18% 1,958.76 2,358.76
13,240.76
331.02 49.65 380.67
Priliminary 10% 1,324.08
14,564.84
Cost for 1 L.ft 364.12 54.62 418.74
12.0 Treated "Thulan" 4" x 3" Wall plate
Assume 80L.ft
Material
4" x 3" wall plate 80.00 L.ft 183.00 14,640.00
Wastage 5% 732.00
Transport 10% 1,464.00
Wood treatment 80.00 L.ft 21.26 1,700.80 18,536.80
Labour
Planking charges 80.00 L.ft 10.00 800.00
Labour 18% 3,336.62 4,136.62
22,673.42
283.42 42.51 325.93
Priliminary 10% 2,267.34
24,940.77
Cost for 1 L.ft 311.76 46.76 358.52
13.0 Treated "Thulan" 2" x 6" Exposed rafter
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Assume 800L.ft
Material
2" x 6" exposed rafter 800.00 L.ft 198.00 158,400.00
Wastage 5% 7,920.00
Transport 10% 15,840.00
Wood treatment 800.00 L.ft 21.26 17,008.00 199,168.00
Labour
Planking charges 800.00 L.ft 10.00 8,000.00
Labour 18% 35,850.24 43,850.24
243,018.24
303.77 45.57 349.34
Priliminary 10% 24,301.82
267,320.06
Cost for 1 L.ft 334.15 50.12 384.27
14.0 Treated "Thulan" 2" x 2" Battens
Assume 1300L.ft
Material
2" x 2" battens 1,300.00 L.ft 49.00 63,700.00
Wastage 5% 3,185.00
Transport 10% 6,370.00
Wood treatment 1,300.00 L.ft 7.09 9,217.00 82,472.00
Labour
Planking charges 1,300.00 L.ft 10.00 13,000.00
Labour 18% 14,844.96 27,844.96
110,316.96
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
84.86 12.73 97.59
Priliminary 10% 11,031.70
121,348.66
Cost for 1 L.ft 93.35 14.00 107.35
SPECIAL FLOOR FINISHES
Item Description Qty Unit Rate Amount Amount Remarks
15%
Mansoor
Considering 1 Sqr
Material
Brick 360 Nos 7.00 2,520.00
Cement 2.00 bag 740.00 1,480.00
Lime 30.00 kg 14.50 435.00
Sand 0.18 cube 7,500.00 1,350.00
Water 25.00 gal 0.50 12.50
5,797.50
Labour
Skilled 1.50 Day 950.00 1,425.00
Un skilled 1.75 Day 650.00 1,137.50
2,562.50
Add 3% for tools 3% 76.88
8,436.88 1,265.53 9,702.41
Preliminaries 10% 843.69
O/H & Profit
Amount with profit
Supply and lay brick paving on compacted earth with cement sand motar.
Main Index
Cost for 1 Sqr 9,280.56 1,392.08 10,672.65
1 Terrazo floor Mansoor
Consider 1 Sqr
Material
Terrazzo chips 4.50 cwt 950.00 4,275.00
Cement 3.75 Bags 740.00 2,775.00
Bedding
Cement 1.25 Bags 740.00 925.00
Sand 0.04 Cube 7,500.00 300.00
8,275.00
Transport 10% 10% 827.50
Machine hire 0.50 Day 3,200.00 1,600.00 1,600.00
Labour
Sepicial mason 1.50 Day 950.00 1,425.00
Un skilled 1.50 Day 650.00 975.00
Bedding
Skilled 1.00 Day 950.00 950.00
Un skilled 1.00 Day 650.00 650.00
4,000.00
Add for tools 3% of labour 3% 120.00
Terrazzo mix (6:5)
14,822.50 2,223.38 17,045.88
Preliminaries 10% 1,482.25
Cost per 1 Sqr 16,304.75 2,445.71 18,750.46
2 Titanium floor Mansoor
Consider 1 Sqr
Maretial
Cement 6.00 Bags 740.00 4,440.00
White cement 3.00 Bags 1,300.00 3,900.00
Sand 0.30 Cube 7,500.00 2,250.00
Titanium 1.50 kg 525.00 787.50
Wax 1.00 Ltr -
Cotton waste 1.00 kg -
11,377.50
Transport 5% 5% 568.88
Machine hire 0.50 Day 3,200.00 1,600.00 1,600.00
Labour
Skilled 2.00 Day 950.00 1,900.00
Un skilled 4.00 Day 650.00 2,600.00
4,500.00
Add for tools 3% of labour 3% 135.00
18,181.38 2,727.21 20,908.58
Preliminaries 10% 1,818.14
Cost for 1 Sqr 19,999.51 2,999.93 22,999.44
CERAMIC TILE / MARBKE FINISH FLOOR
Porcelain Tile
1'-0" x 1'-0" porcelain tile
P.C Sum per sq.ft Rs. 300/=
Materials
1'-0" x 1'-0" porcelain tile ### Sq.ft 150.00 15,000.00
waste 5% 750.00
Cement bedding ### Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
22,531.00
Labour
### Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
26,136.00 3,920.40 30,056.40
Preliminaries 10% 2,613.60
Cost for 1 Sqr 28,749.60 4,312.44 33,062.04
Labour for fixing tile with cement sluarry
P.C Sum per sq.ft Rs.185/=
Materials
1'-0" x 1'-0" granite tile ### Sq.ft 185.00 18,500.00
waste 5% 925.00
Cement bedding ### Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
29,188.38
Labour
### Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 32,793.38 4,919.01 37,712.38
Preliminaries 10% 3,279.34
Cost for 1 Sqr 36,072.71 5,410.91 41,483.62
1,047.51
Consider 1 Sqr
Materials
Mosaic tile 100.00 Sq.ft 750.00 75,000.00
Cement 5.00 Bag 740.00 3,700.00
Sand 0.20 Cube 7,500.00 1,500.00
0'-8" x 0'-8" non slip Hemogenous
Labour for fixing tile with cement sluarry
Supply and lay mosaic tile with cement sand bedding.
80,200.00
Wastage 5% 4,010.00
Transport 7% for tile 5,250.00
Labour
Mason 3.50 Day 950.00 3,325.00
U/sk labour 3.50 Day 650.00 2,275.00
5,600.00
Add for tools 3% of labour cost 3% 168.00
95,228.00 14,284.20 109,512.20
Preliminaries 10% 9,522.80
Cost for 1 Sqr ### 15,712.62 120,463.42
1 M2 11,271.19
Homogenious tile 4"x4"
Considering 1 Sqr
Tile 900.00 no 17.00 15,300.00
Cement slurry 1.25 Bag 700.00 875.00
Tile grout 0.75 kg 155.00 116.25 16,291.25
Wastage 5% 814.56
Transport 7% 1,140.39
Water 10.00 gal 0.50 5.00
Labour
Skill 1.25 day 950.00 1,187.50
Un Skill 1.25 day 650.00 812.50 2,000.00
3% of labour Cost for tools 60.00
Cost per Sqr 20,311.20 3,046.68 23,357.88
Preliminaries 10% 2,031.12
Cost for 1 Sqr 22,342.32 3,351.35 25,693.67
Marble Queens
1 Sqr
( P.C Sum per sq.ft Rs. 2200/=)
Materials
Marble ### Sq.ft 2,200.00 220,000.00
waste 15% 33,000.00
Cement bedding ### Sq.ft 59.65 5,964.75
adhesive glue ### Sq.ft 100.00 10,000.00
268,964.75
Labour
### Sq.ft 125.00 12,500.00
12,500.00
3% of labour cost Tools 375.00
Cost per Sqr ### 42,275.96 324,115.71
Preliminaries 10% 28,183.98
Cost for 1 Sqr ### 46,503.56 356,527.28
3/4" thk 1:3 cement sand mix, finished smooth cement rendering, 2'-0" x 2'-0" Marble with approved colour and Quality, fixed with specific adhesive glue very neatly
Labour for fixing marble with adhensive
ROUGH TILE FINISH FLOOR
Scorched Granite
P.C Sum per sq.ft Rs. 1350/=
Materials
1'-0" x 1'-0" granite tile ### Sq.ft 1,350.00 135,000.00
waste 5% 6,750.00
Cement bedding ### Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25 148,531.00
Labour
### Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
### 22,820.40 174,956.40
Preliminaries 10% 15,213.60
Cost for 1 Sqr ### 25,102.44 192,452.04
Mansoor
1'-0" x 1'-0" non slip Hemogenous floor granite tile
Labour for fixing tile with cement sluarry
Hand cut granite laying with cement sand bedding " Mirisgal "
Considering 1 Sqr
Materials
Hand cut granite 1' 0"x 1' 0" ### Nos 350.00 35,000.00
Cement 5.00 bag 740.00 3,700.00
Sand 0.20 Cube 7,500.00 1,500.00
40,200.00
Transport 10% 10% 4,020.00
Labour
Skilled 3.50 day 950.00 3,325.00
U/sk labour 3.50 day 650.00 2,275.00
5,600.00
For tools 3% of labour cost 3% 168.00
49,988.00 7,498.20 57,486.20
Preliminaries 10% 4,998.80
Cost for 1 Sqr 54,986.80 8,248.02 63,234.82
Dressed stone
P.C Sum per sq.ft Rs.375
Materials
1'-0" x 1'-0" granite tile ### Sq.ft 375.00 37,500.00
waste 5% 1,875.00
Cement bedding ### Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
1'-0" x 1'-0" x 0'-2" Assorted dressed stone
49,138.38
Labour
### Sq.ft 40.00 4,000.00
4,000.00
3% of labour cost Tools 120.00
Cost per Sqr 53,258.38 7,988.76 61,247.13
Preliminaries 10% 5,325.84
Cost for 1 Sqr 58,584.21 8,787.63 67,371.84
Consider 1 Sqr
Materials
1'-0" x 1'-0" granite tile ### Sq.ft 2,500.00 250,000.00
waste 5% 12,500.00
Cement bedding ### Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
272,263.38
Labour
### Sq.ft 125.00 12,500.00
12,500.00
Add for tools 3% of labour cost 3% 375.00
Labour for fixing tile with cement sluarry
Supply and lay 1'-0" x 1'-0" granite tile
Labour for fixing marble with adhensive
Cost per Sqr ### 42,770.76 327,909.13
Preliminaries 10% 28,513.84
Cost for 1 Sqr ### 47,047.83 360,700.04
Pressed Cement Tile
1'-0" x 1'-0" Cement tile
P.C Sum per sq.ft Rs. 165/=
Materials
1'-0" x 1'-0" granite tile ### Sq.ft 165.00 16,500.00
waste 5% 825.00
Cement bedding ### Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
24,106.00
Labour
### Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 27,711.00 4,156.65 31,867.65
Preliminaries 10% 2,771.10
Cost for 1 Sqr 30,482.10 4,572.32 35,054.42
Pressed cement tile 16"x16"
Labour for fixing tile with cement sluarry
Tile 57.00 no 250.00 14,250.00
Cement slurry 1.25 Bag 700.00 875.00
Tile grout 0.75 kg 155.00 116.25 15,241.25
Wastage 5% 762.06
Transport 7% 1,066.89
Water 10.00 gal 0.50 5.00
Labour
Skill 1.25 day 950.00 1,187.50
Un Skill 1.25 day 650.00 812.50
2,000.00
3% of labour Cost for tools 60.00
Cost per Sqr 19,135.20 2,870.28 22,005.48
Preliminaries 10% 1,913.52
Cost for 1 Sqr 21,048.72 3,157.31 24,206.03
Mirrissa
Assume 1 Sqr
Material
12"x12"x1 1/2" paving stone ### No 85.00 8,500.00 8,500.00
Transport 5% 425.00
1 1/2" Cement & Sand Bed
Cement 6.00 Bag 700.00 4,200.00
Sand 0.16 Cube 7,500.00 1,200.00 5,400.00
Wastage 10% 10% 540.00
Labour
Grade 20 concrete 12"x12"x1 1/2" paving stone
Skill 4.00 Day 950.00 3,800.00
Un Skill 4.00 Day 650.00 2,600.00 6,400.00
Tools 3% 192.00
Cost per Sqr 21,457.00 3,218.55 24,675.55
Preliminaries 10% 2,145.70
Cost for 1 Sqr 23,602.70 3,540.41 27,143.11
3
648.65 Mansoor
Consider 1 Sqr
Materials
Coble stone 9" x 5" 240.00 Nos 200.00 48,000.00
Cement 5.00 Bag 740.00 3,700.00
Sand 0.20 Cube 7,500.00 1,500.00
53,200.00
Labour
Mason 3.50 Day 950.00 3,325.00
U/sk labour 3.50 Day 650.00 2,275.00
5,600.00
Add for tools 3% of labour cost 3% 168.00
58,968.00 8,845.20 67,813.20
Preliminaries 10% 5,896.80
Cost for 1 Sqr 64,864.80 9,729.72 74,594.52
Coble Stone Paving with cement sand bedding
Mansoor
Considering 1 Sqr
Material
Rubble stone (1'0"x1'0" ) ### Sq.ft 3,000.00 300,000.00
Cement 2.00 Bag 740.00 1,480.00
Lime 30.00 Kg 14.50 435.00
Sand 0.18 Cube 7,500.00 1,350.00
Water 25.00 Gal 0.50 12.50
303,277.50
Labour
Skilled 1.00 Day 950.00 950.00
Un skilled 1.50 Day 650.00 975.00
1,925.00
Add 3% for tools 3% 57.75
### 45,789.04 351,049.29
Preliminaries 10% 30,526.03
Cost for 1 Sqr ### 50,367.94 386,154.22
TIMBER FLOOR
Timber Bordered floor
Rubble Stone paving with cement sand bedding (Antique Type )
1 Sqr 80 L.ft
Materials
1" thick 1'-3" width "Teak" plank ### Sq.ft 600.00 60,000.00
3/4" x2" battens ### L.ft 55.00 6,050.00
Cemifix 5.00 Kg 880.00 4,400.00
brass screws ### no 8.35 835.00
Cement bedding ### Sq.ft 89.47 8,947.13
80,232.13
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
Labour for timber work
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00 3,200.00
Add 3% of labour cost tools 96.00
Paint
Timber Planking ### Sq.ft 10.00 1,000.00
### L.ft 10.00 1,100.00
wood preservative 11.18 Cu.ft 263.00 2,940.08
3/4" thick 1:3 cement sand levelled floor with 2" x2" battens embedded on levelled rough cement floor & fixed 1" thick 1'-3" width timber plank "Teak" using brass screws and well standed to receive smooth surface and apply wood preservative, stain and approved polish
wood Treatment ### sq.ft 20.00
5,040.08
Labour for painting
skilled labourer 1.00 day 950.00 950.00 950.00
Polishing ### Sq.ft 95.00 9,500.00 9,500.00
99,018.20 14,852.73 113,870.93
Preliminaries 10% 9,901.82
Cost for 1 Sqr ### 16,338.00 125,258.03
Timber Skirting
8" high "Teak" Skirting 1 Sqr 150 L.ft
Materials
8" thick Teak Plank ### Sq.ft 600.00 60,000.00
brass screws ### no 8.35 1,252.50
61,252.50
Labour for timber fixing
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00 800.00
Add 3% of labour cost tools 24.00
Paint
Timber Planking ### Sq.ft 10.00 1,000.00
wood preservative 8.00 Cu.ft 263.00 2,104.00
wood Treatment ### l.ft 14.17 2,125.50
5,229.50
Labour for painting
skilled labourer 1.00 day 950.00 950.00 950.00
Plishing ### Sq.ft 35.00 3,500.00 3,500.00
Cost per Sqr 71,756.00
Cost per L.ft 478.37 71.76 550.13
Preliminaries 10% 47.84
Cost for 1 L.ft 526.21 78.93 605.14
SPECIAL WALL FINISHES
Item Description Qty Unit Rate Amount Amount Remarks
15%
plaster rough plaster
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
2,400.00
3% of labour cost Tools 72.00
5% of labour cost Scaffolding 120.00
3,647.00 547.05 4,194.05
Preliminaries 10% 364.70
Cost for 1 Sqr 4,131.70 619.76 4,751.46
O/H & Profit Amount with
profit
3/4" thick 1:5 rough plaster ( without Lime )
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
EX Isolated Colunm & beam
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Wastage 10% 105.50
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
2,400.00
3% of labour cost Tools 72.00
5% of labour cost Scaffolding 120.00
Cost per Sqr 3,752.50 562.88 4,315.38
Preliminaries 10% 375.25
Cost for 1 Sqr 4,247.75 637.16 4,884.91
EX Reveals & Jamb
Consider 3" reveals 400.00 L.ft
Materials
cement 0.85 bags 700.00 595.00
3/4" thick 1:5 rough plaster ( without Lime )
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Wastage 15% 158.25
Labour
skilled labourer 4.00 day 950.00 3,800.00
un /skilled labourer 4.00 day 650.00 2,600.00
6,400.00
3% of labour cost Tools 192.00
5% of labour cost Scaffolding 320.00
8,125.25
Cost for one L ft 20.31 3.05 23.36
Preliminaries 10% 812.53
Cost for 8.45 Sqr 8,937.78
22.34 3.35 25.70
INT Reveals & Jamb
Consider 3" reveals 400.00 L.ft
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Wastage 15% 158.25
Labour
skilled labourer 4.30 day 950.00 4,085.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
un /skilled labourer 4.30 day 650.00 2,795.00
6,880.00
3% of labour cost Tools 206.40
5% of labour cost Scaffolding 344.00
8,643.65
Cost for one L ft 21.61 3.24 24.85
Preliminaries 10% 864.37
Cost for 8.45 Sqr 9,508.02
23.77 3.57 27.34
1
112.05 Mansoor
Consider 1 Sqr
Material
Cement 0.85 Bag 740.00 629.00
Lime 60.00 kg 14.50 870.00
Sand 0.06 Cube 7,500.00 450.00
Water 20.00 Gal 0.50 10.00
Chicken Mesh 100.00 Sq ft 40.00 4,000.00
5,959.00
Wastage 10% 595.90
Labour
Skilled 2.00 Day 950.00 1,900.00
plaster rough plaster with chiken mesh
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi rough in external wall in ground floor including
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Un skilled 2.25 Day 650.00 1,462.50
3,362.50
3% of Labour cost 3% 100.88
5% of Labour cost 5% 168.13
10,186.40 1,527.96 11,714.36
Preliminaries 10% 1,018.64
Cost for 1 Sqr 11,205.04 1,680.76 12,885.80
1 Sqr Queens
Materials
Bedding
cement 1.88 bags 700.00 1,312.50
sand 0.06 cube 7,500.00 450.00
water 37.50 gal 0.50 18.75
Slurry
cement 1.25 bags 700.00 875.00
water 25.00 bags 0.50 12.50
2,668.75
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
Extra Labour for slurry
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00
3,200.00
15mm (3/4") thk plinth plaster in 1:3 cement sand screed finish smooth with gray cement floorting.
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Add 3% of labour cost tools 96.00
Cost per Sqr 5,964.75 894.71 6,859.46
Preliminaries 10% 596.48
Cost for 1 Sqr 6,561.23 984.18 7,545.41
2
Mansoor
Consider 12" width layer (10ft)
Material
Cement 0.85 Bag 740.00 629.00
Lime 60.00 kg 14.50 870.00
Sand 0.06 cube 7,500.00 450.00
Water 20.00 gal 0.50 10.00 1,959.00
Material Cost for 10 L ft 195.90
Labour
Skilled 1.50 Day 950.00 1,425.00
Un skilled 2.00 Day 650.00 1,300.00
2,725.00
3% of Labour cost 3% 81.75
5% of Labour cost 5% 136.25
3,138.90
313.89 47.08 360.97
Preliminaries 10% 313.89
PLASTERING IN STARICASE EDGE
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Cost for 10 L.ft 3,766.68
Cost for 1 L.ft 376.67 56.50 433.17
4
Mansoor
Consider 1 Sqr
Material
Total coat 1.50 Bucket 2,800.00 4,200.00
Fillet 0.75 Bucket 3,189.00 2,391.75
Cement 6 Kg 14.80 88.80
Paint 5 Ltr 550.00 2,750.00
Sand paper 10 Nos 42.50 425.00
Bruss 0.1 Nos 595.00 59.50
9,915.05
Add: 5% transport 5% 495.75
Labour
Painter 2 Days 950.00 1,900.00
1,900.00
Add: 3% tools 3% 57.00
Add: 5% Scafolding 5% 95.00
12,462.80 1,869.42 14,332.22
Preliminaries 10% 1,246.28
Cost for 1 Sqr 13,709.08 2,056.36 15,765.45
WATER BASE PLASTER ( HIGH MALL)
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
3 SUPPLY & FIX GLASS BOXES Mansoor
Consider 1 Sqr
Material
1'-0"x 1'-0" glass blocks 100.00 Nos 1,700.00 170,000.00
Cement 2.00 bag 740.00 1,480.00
Lime 30.00 kg 14.50 435.00
Sand 0.18 cube 7,500.00 1,350.00
Water 25.00 gal 0.50 12.50
173,277.50
Labour
Skilled 1.50 Day 950.00 1,425.00
Un skilled 1.75 Day 650.00 1,137.50
2,562.50
Add 3% for tools 3% 76.88
175,916.88 26,387.53 202,304.41
Preliminaries 10% 17,591.69
Cost for 1 Sqr 193,508.56 29,026.28 222,534.85
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
1'-0" x 1'-0" GLASS MOSAIC Tile
P.C Sum per sq.ft Rs. 683/=
Materials
1'-0" x 1'-0" GLASS MOSAIC 100.00 Sq.ft 683.00 68,300.00
waste 5% 3,415.00
cement 3.00 bag 700.00 2,100.00
sand 0.08 cube 7,500.00 600.00
adhesive glue 100.00 Sq.ft 100.00 10,000.00
tile grout 0.75 kg 155.00 116.25
water 25.00 gal 0.50 12.50
84,543.75
Labour
skilled labourer 3.00 day 950.00 2,850.00
un /skilled labourer 3.00 day 650.00 1,950.00
4,800.00
3% of labour cost Tools 144.00
Cost per Sqr 89,487.75 13,423.16 102,910.91
Preliminaries 10% 8,948.78
Cost for 1 Sqr 98,436.53 14,765.48 113,202.00
1'-0" x1'-0" Glass mosaic
(P.C.sum per Sqft Rs.1600/=)
Materials
1'-0" x 1'-0" GLASS MOSAIC 100.00 Sq.ft 1,600.00 160,000.00
waste 5% 8,000.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Cement bedding 100.00 Sq.ft 59.65 5,964.75
tile grout 0.75 kg 155.00 116.25
adhesive glue 100.00 Sq.ft 100.00 10,000.00
184,081.00
Labour
100.00 Sq.ft 50.00 5,000.00
5,000.00
3% of labour cost Tools 150.00
Cost per Sqr 189,231.00 28,384.65 217,615.65
Preliminaries 10% 18,923.10
Cost for 1 Sqr 208,154.10 31,223.11 239,377.22
Ceramic Tile
P.C Sum per sq.ft Rs. 215
Materials
tile 100.00 Sq.ft 215.00 21,500.00
waste 5% 1,075.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
29,356.00
Labour
Labour for fixing tile with cement sluarry
1'-0" x 1'-0" non slip Hemogenous wall tile
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
100.00 Sq.ft 35.00 3,500.00
3,500.00
Tools
3% of labour cost 105.00
32,961.00 4,944.15 37,905.15
Preliminaries 10% 3,296.10
Cost for 1 Sqr 36,257.10 5,438.57 41,695.67
P.C Sum per sq.ft Rs.185
Materials
tile 100.00 Sq.ft 185.00 18,500.00
waste 5% 925.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
26,206.00
Labour
100.00 Sq.ft 35.00 3,500.00
3,500.00
Tools
3% of labour cost 105.00
Cost per Sqr 29,811.00 4,471.65 34,282.65
Preliminaries 10% 2,981.10
Labour for fixing tile with cement sluarry
0'-8" x 0'-8" non slip Hemogenous wall tile
Labour for fixing tile with cement sluarry
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Cost for 1 Sqr 32,792.10 4,918.82 37,710.92
Scorched Granite
(P.C.sum per Sqft Rs.1350/=)
Materials
2'-0" x1'-0" Non slip granite tile 100.00 Sq.ft 1,350.00 135,000.00
waste 5% 6,750.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
148,531.00
Labour
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 152,136.00 22,820.40 174,956.40
Preliminaries 10% 15,213.60
Cost for 1 Sqr 167,349.60 25,102.44 192,452.04
Dressed Stone
(P.C.sum per Sqft Rs.1600/=)
2'-0" x1'-0" Non slip Homogenous floor granite tile
Labour for fixing tile with cement sluarry
1'-0" x 1'-0" x 0'-2" Assorted dressed stone
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Materials
1'-0" x 1'-0" granite tile 100.00 Sq.ft 375.00 37,500.00
waste 5% 1,875.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
46,156.00
Labour
100.00 Sq.ft 40.00 4,000.00
4,000.00
3% of labour cost Tools 120.00
Cost per Sqr 50,276.00 7,541.40 57,817.40
Preliminaries 10% 5,027.60
Cost for 1 Sqr 55,303.60 8,295.54 63,599.14
10 4" thick Skirting
Consider 300 L.ft
Materials
Cement 1.25 Bags 740.00 925.00
Sand 0.04 Cube 7,500.00 300.00
Water 25.00 Gal 0.50 12.50
Cement slurry 1.25 Bags 740.00 925.00
2,162.50
Wastage 10% 0.10 216.25
Labour for fixing tile with cement sluarry
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Labour
Skilled labourer 1.00 Day 950.00 950.00
Un skilled labourer 1.00 Day 650.00 650.00
Extra labour
Skilled labourer 5.00 Day 950.00 4,750.00
Un skilled labourer 3.00 Day 650.00 1,950.00
8,300.00
Add: 3% tools 3% 249.00
Cost for 1 Sqr 10,927.75
36.43 5.46 41.89
Preliminaries 10% 1,092.78
12,020.53
Cost per 1 L.ft 40.07 6.01 46.08
11 3" thick External Revels
Consider 400 L.ft
Materials
Cement 0.85 Bags 740.00 629.00
Lime 30.00 Kg 14.50 435.00
Sand 0.06 Cube 7,500.00 450.00
Water 20.00 Gal 0.50 10.00
1,524.00
Wastage 10% 0.10 152.40
Labour
Skilled labourer 1.33 Day 950.00 1,263.50
Un skilled labourer 1.33 Day 650.00 864.50
Extra labour
Skilled labourer 4.00 Day 950.00 3,800.00
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Un skilled labourer 2.00 Day 650.00 1,300.00
7,228.00
Add: 3% tools 3% 216.84
Add: 3% tools 5% 361.40
Cost per 1 Sqr 9,482.64
23.71 3.56 27.26
Preliminaries 10% 948.26
10,430.90
Cost per 1 L.ft 26.08 3.91 29.99
Mansoor
Consider 187 Sq.ft
Materials
Pebbles (50 Kg) 35.00 Bag 7,500.00 262,500.00
Cement 4.00 Bag 740.00 2,960.00
265,460.00
Labour
Mason 20.00 Day 950.00 19,000.00
U/sk labour 5.00 Day 650.00 3,250.00
22,250.00
For tools 3% of labour cost 3% 667.50
288,377.50
154,212.57 23,131.89 177,344.45
Preliminaries 10% 28,837.75
Laying pebbles in wall with cement slurry.
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit Amount with
profit
Cost for 187 Sq.ft 317,215.25
Cost for 1 Sqr 169,633.82 25,445.07 195,078.90
SPECIAL CEILING FINISHES
Item Description Qty Unit Rate Amount Amount Remarks
15%
1 Mansoor
Consider 3.3 sqr
Materials
Balaw timber
4"x 2" Joists 199.10 L ft. 135.50 26,978.05
2"x 2" Joists 82.72 L ft. 55.00 4,549.60
2"x 2" Joists 21.00 L ft. 55.00 1,155.00
32,682.65
Wastage 5% of timber 5% 1,634.13
8.00 Nos 1,840.00 14,720.00
Wire nails 4.13 kg 160.00 660.00
Sand peper 2.00 Nos 42.50 85.00
Wood preservative 14.17 Cu.ft 263.00 3,725.93
19,190.93
Labour
Painter 1.25 days 950.00 1,187.50
Carpenter 2.25 days 950.00 2,137.50
Un skilled labour 2.00 days 650.00 1,300.00
4,625.00
Add for tools 3% of labour 3% 138.75
O/H & Profit
Amount with profit
Supper flex ceiling with timber fram work
Superflex ceiling sheet 6mm thick 8'-0" 4'-0"
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Add for scaffolding 5% of labour 5% 231.25
58,502.71
17,728.09 2,659.21 20,387.31
Preliminaries 10% 5,850.27
Cost for 3.3 Sqr 64,352.98
Cost for 1 Sqr 19,500.90 2,925.14 22,426.04
Sloping Ceiling
9mm thick gypsum board 4 Nos 1,175.00 4,700.00
Nails 1 kg 160.00 160.00 4,860.00
Transport 10% 486.00
Labour
Skilled labour 1.00 day 950.00 950.00
Un skilled labour 1.00 day 650.00 650.00 1,600.00
Tools 3% 48.00
Cost for 1 Sqr 6,994.00 1,049.10 8,043.10
Preliminaries 10% 699.40
Total Cost 7,693.40 1,154.01 8,847.41
10mm thick superflex ceiling boards fixed to exposed rafter
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
2
Consider 156 Sq ft
Material
Tholang timber
2" x 4" timber 112.00 L ft 123.50 13,832.00
2" x 2" joists 96.00 L ft 49.00 4,704.00
Asbestos ceiling sheet 156.00 Sq.ft 23.75 3,705.00 201.394052
Nails & screws 3.00 kg 160.00 480.00
22,721.00
Wastage 5% 5% 1,136.05
Labour
Carpenter 1.00 Day 950.00 950.00
Un skilled 2.00 Day 650.00 1,300.00
2,250.00
Add for tools 3% of labour 3% 67.50
Add for scaffolding 5% of labour 5% 112.50
26,287.05
16,850.67 2,527.60 19,378.27 2085.102
Preliminaries 10% 2,628.71
Cost for 1.56 Sqr 28,915.75
Cost for 1 Sqr 18,535.74 2,780.36 21,316.10
3
Consider 120 Sq ft 10.00 12.00 120.00
Flat asbestos ceiling with timber fram work.
Flat "tuna" ceiling with timber fram work
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Material
Tholang timber
2" x 4" timber 84.00 L ft 123.50 10,374.00
Tuna timber 120.00 Sq.ft 95.00 11,400.00
Wastage 10% 10% 1,140.00
Nails & screws 3.00 kg 160.00 480.00
23,394.00
Wastage 5% 5% 1,169.70
Labour
Carpenter 2.00 Day 950.00 1,900.00
Un skilled 4.00 Day 650.00 2,600.00
4,500.00
Add for tools 3% of labour 3% 135.00
Add for scaffolding 5% of labour 5% 225.00
29,423.70
24,519.75 3,677.96 28,197.71
Preliminaries 10% 2,942.37 281.98
Cost for 1.2 Sqr 32,366.07
Cost for 1 Sqr 26,971.73 4,045.76 31,017.48
Cost for 1 Sq.ft 269.72
Consider 102.4 Sqr
Materials
Timber ceiling 6"x 3/4" finished size TUNA tonuged & grooved planks fixed over rafters
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Timber ceiling
102.40 Sqr 9,500.00 972,800.00
Wastage 10% of timber ceiling 10% 97,280.00
Wood preservative 614.40 Cube 263.00 161,587.20 1,231,667.20
Transport 5% 5% 61,583.36
Labour
labour 35% 431,083.52
Add for tools 3% of labour 3% 12,932.51
Add for scaffolding 5% of labour 5% 21,554.18
Cost per 102.4 Sqr 1,758,820.76
17,175.98 2,576.40 19,752.38
Preliminaries 10% 1,717.60
Total Cost 18,893.58 2,834.04 21,727.62
4
Subcontractor's rate 1 Sqr ### 17,500.00
Add: only Attendance 8% 1,400.00
Total for 1 sqr 18,900.00 2,835.00 21,735.00
Preliminaries 10% 1,890.00
Cost for 1.2 Sqr 20,790.00 3,118.50 23,908.50
4'-0" x 4'-0 " Super flex ceiling with aluminium frame work
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
A.6
1 sqr
4'-0" x4'-0" asbestos ceiling sheet 7 Nos 380.00 2,660.00
Nails 150.00
2,810.00
Transport 10%
Labour
skilled 1.00 day 950.00 950.00
Un skilled 1.00 day 650.00 650.00 1,600.00
Add for tools 3% of labour 3% 48.00
Add for scaffolding 5% of labour 5% 80.00
4,538.00 680.70 5,218.70
Preliminaries 10% 453.80
Total Cost 4,991.80 748.77 5,740.57
Consider 156 Sq ft
Material
Tholang timber
2" x 4" timber 112.00 L ft 123.50 13,832.00
2" x 2" joists 96.00 L ft 49.00 4,704.00
Cement fiber board 156.00 Sq.ft 200.00 31,200.00
Nails & screws 3.00 kg 160.00 480.00
Asbestos ceiling sheet fix to frame work ( frame work measured seperatly )
Cement fiber board ceiling with timber frame
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
50,216.00
Wastage 5% 0.05 2,510.80
Labour
Carpenter 1.00 Day 950.00 950.00
Un skilled 2.00 Day 650.00 1,300.00
2,250.00
Add for tools 3% of labour 0.03 67.50
Add for scaffolding 5% of labour 0.05 112.50
Cost for 156 sq.ft 55,156.80
35,356.92 5,303.54 40,660.46
Preliminaries 10% 3,535.69
Total Cost 38,892.62 5,833.89 44,726.51
5 Operation Theatre Ceiling
Unit Rate
M² 4,625.00 *
Supply and installation of ceiling system for operation Theatre at Emergency Trauma Centre Building, Teaching Hospital, Karapitiya.
'Eurometalic' ceiling system comprising of DuPontAlesta AM powder coated metal ceiling tiles installed on a concealed suspension system
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
plain surface (not perforated)
* Notes:
Rate exclusive of 15% VAT
Mode of Payment
Advance 75%
On progress 20%
At Completion 5%
Valid for 30 days from 19.01.09
modular 'eurometalic' 600x600mm concealed panels of 0.5mm thick steel sheet accurately pressed to guarantee diamentional precision
powder coated to 80 microns thickness in white colour using 'DuPont Alesta AM' developed to provide an active hygienic coating system with excellent anti-bacterial properties
edges are specially shaped to be close mounted
vertical edges pressed to form a shape that will lock into a special spring clip with steel conduit
the complete system is suspended from the soffit above using adjusting clips and 4mm diameter galvanised hanger rods
the panels are individually demountable to ensure access to any part of the ceiling void
the perimeter manels can easily be cut when necessary and are fitted to the edge trim (quoted below)
holes for light fixtures and other shall be cut.
MANHOLES / SEPTIC TANKS
Item Description No Depth Qty
8'-0" x6'-0" x 5'-0" concrete septic tank
1 Excavation 8 8 5.5 352
2 2" Lean concrete 8 8 64
3 6" thick base concrete 8 8 0.5 32
4 9" thick brick wall 2 8 5
2 6 5
5 Concrete for cover slab 8 8 0.42 26.88
6 Formwork for cover slab 8 6 48
7 Reinforcement for base & wall 12 2.4 28.8
16 1.8 28.8
8 Reinforcement 12 2.4 28.8
16 1.8 28.8
9 Plastering 8 6 48
2 8 5 80
2 6 5 60
MANEHOLE
Length
Breath
975
75
Main Index
Area 3.00 3.00 2.50
9.84 9.84 8.20
Concrete Bed hight 0.15
Excavation 3.00 3.00 2.50
Screed 2" tk 3.00 3.00
Concrete Bed 3.00 3.00 0.49
Brick work 9" 36.36 2.46
Benching 2.46 2.46
Plastering 9.84 1.61
Plastering in benching 2.46 2.46
Conc. In benching 2.46 2.46 0.39
Copping Beam 36.36 0.74 0.25
14.268 0.36 0.25
750
15075
200
Form work to beam 36.36 0.23
0.984 0.23
15.744 0.23
Form work to Slab 36.36 0.23
Concrete cover 36.36 ### 0.23
600x 600 x 600 mm Manhole
Area 0.60 0.60 0.60
Excavation 0.60 0.60 0.60
Screed 2" tk 0.60 0.60
Concrete Bed 0.60 0.60 0.33
brick walls 2.4 0.27
Formwork 4 0.60 0.27
Reinforcement 8 0.60 0.90
8 0.60 0.90
Benching 0.58 0.58
Plastering 4 0.58 0.27
Plastering in benching 0.58 0.58
Cast iron lid
1500mm dia x 1500mm height sockage pit
Area 3.14 0.75 0.75 1.50
Excavation 3.14 0.75 0.75 1.50
brick walls 3.14 1.5 1.00
Plastering 3.14 1.5 1.00
Cover slab 3.14 0.75 0.75
1500mm dia x 2000mm height sockage pit
Area 3.14 0.75 0.75 2.00
Excavation 3.14 0.75 0.75 2.00
brick walls 3.14 1.5 1.00
Plastering 3.14 1.5 1.00
Cover slab 3.14 0.75 0.75
Q 19
Area 7.00 6.00 5.50
Excavation 7.00 6.00 5.50
Screed 2" tk 7.00 6.00
Concrete Bed 7.00 6.00 0.33
Concrete walls 26.00 5.17 0.33
Formwork 4 7.00 5.17
Reinforcement 80 5.50 ###
18 26.00 ###
22 6.00 ###
19 7.00 ###
Benching 6.34 5.34
Waterproofing 2 6.34 5.17 ###
Construction of under ground RC water sump capacity 6000 Ltr. ( Internal size 7'-0" x 6'-0" x 5'-6" ) double seal CI heavy duty access cover
2 5.34 5.17 ###
1 6.34 5.34 ###
Plastering 2 6.34 5.17 ###
2 5.34 5.17 ###
Plastering in benching 6.34 5.34
Form work to Slab 4 6.34 0.33
Concrete cover 7.00 6.00 0.33
DDT for CI cover 6.29 1.00 0.33
Reinforcement 8 7.00 ###
63mm dia swan neck ventilation pipe
Foot valve
Ball valve
Additional labour
W 11
Area 2.00 2.00 3.00
Excavation 2.00 2.00 3.00
Screed 2" tk 2.00 2.00
Concrete Bed 2.00 2.00 0.33
Concrete walls 8.00 2.67 0.42
2' 0" dia double seal CI heavy duty access cover
Sewer manhole size internally 2'-0" x 2'-0" & depth not exceeding 3'-0" with CI Cover
Formwork 4 2.00 2.67
Reinforcement 13 3.00 7.40
Benching 1.34 1.34
Plastering 4 1.34 2.67
Plastering in benching 1.34 1.34
Form work to Slab 4 1.34 0.33
Cast Iron cover
Additional labour
W 14
Area 2.66 3.16 1.50
Excavation 2.66 3.16 1.50
Screed 2" tk 2.66 3.16
Concrete Bed 2.66 3.16 0.33
Concrete walls 11.64 1.17 0.33
Formwork 4 2.66 1.17
Reinforcement 19 1.50 5.26
Plastering 4 2.00 1.17
Construction of RC grease trap internaly 2'-0" x1'-6" built in 6" thick RC walls(stainles steel grease removal tray)
Plastering in benching 2.00 2.50
Form work to Slab 4 2.00 0.33
Checked plate cover
Stainless steel stainer bucket
Stainless steel lifting handle
Additional labour
W15
Area 1.00 1.00 2.00
Excavation 1.00 1.00 2.00
Screed 2" tk 1.00 1.00
Concrete Bed 1.00 1.00 0.33
Concrete walls 4.00 1.67 0.33
Formwork 4 1.00 1.67
Reinforcement 7 2.00 2.66
Benching 0.34 0.34
Plastering 4 0.34 1.67
Plastering in benching 0.34 0.34
Form work to Slab 4 0.34 0.33
M.S. grating and frame
Anticorrosive paint
Construction of CI Storm water manhole internaly 1'-0" x1'-0" built in 4" thick RC walls
Additional labour
Unit Rate Amount
352.00 Cu.ft 11.72 4,124.12
64.00 Sq.ft 48.53 3,105.82
32.00 Cu.ft 337.43 10,797.77
80.00 Sq.ft 158.74 12,699.20
60.00 Sq.ft 158.74 9,524.40
26.88 Cu.ft 337.43 9,070.12
48.00 Sq.ft 98.81 4,742.68
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
48.00 Sq.ft 37.88 1,818.36
80.00 Sq.ft 37.88 3,030.59
60.00 Sq.ft 37.88 2,272.94
64,483.21
Total Qty
112.5
10.5 m3
90.53 Cu.ft
0.49 L.ft
22.50 Cu.ft 11.72 263.62
9.00 Sqr 48.53 436.76
4.43 Cu.ft 337.43 1,494.14
89.45 Sq.ft 158.74 14,198.59
6.05 Sq.ft 37.88 229.25
15.81 Sq.ft 37.88 599.10
6.05 Sq.ft 37.88 229.25
2.38 Cu.ft 337.43 803.73
6.60
1.27
7.87 Cu.ft 337.43 2,654.72
900
150
8.35
0.23
3.61
12.19 Sq.ft 98.81 1,204.34
8.35 Sq.ft 98.81 824.86
328.59 Cu.ft 337.43 110,875.30
###
0.96 Cu.ft
0.22 m3 625.00 135.00
0.36 m2 566.00 203.76
0.12 m3 ### 1,618.65
0.65 m1 2,200.00 1,425.60
0.65 m2 1,300.00 842.40
1.81 kg 225.00 406.32
0.34 m2 678.00 228.08
0.63 m2 678.00 424.70
0.34 m2 678.00 228.08
1 No ### 11,696.00
17,208.58
3.48 Cu.ft
2.65 m3 625.00 1,657.37
4.71 m2 2,200.00 10,371.43
4.71 m2 678.00 3,196.29
1.77 No ### 24,087.05
39,312.13
3.86 m3
3.54 m3 625.00 2,209.82
4.71 m2 2,200.00 10,371.43
4.71 m2 678.00 3,196.29
1.77 No ### 24,087.05
39,864.59
231.00 Cu.ft
231.00 cu.ft 15.00 3,465.00
42.00 sq.ft 51.27 2,153.34
13.86 cu.ft 358.89 4,974.22
44.36 cu.ft 358.89 15,919.86
144.76 sq.ft 90.00 13,028.40
219.28 kg 140.00 30,699.46
33.86 sq.ft 37.28 1,262.14
154.63 sq.ft 160.00 24,740.29
120.77 sq.ft 37.28 4,502.35
33.86 sq.ft 37.28 1,262.14
8.37 sq.ft 90.00 753.19
13.86
(2.07)
11.79 cu.ft 358.89 4,229.78
10.53 kg 140.00 1,474.78
1,475.00
2,773.00
2,500.00
19,000.00
134,212.93
2,500.00
###
12.00 Cu.ft
12.00 cu.ft 15.00 180.00
4.00 sq.ft 51.27 205.08
1.32 cu.ft 358.89 473.73
8.97 cu.ft 358.89 3,219.67
21.36 sq.ft 90.00 1,922.40
7.40 kg 140.00 1,036.66
1.80 sq.ft 37.28 66.94
14.31 sq.ft 37.28 533.52
1.80 sq.ft 37.28 66.94
1.77 sq.ft 90.00 159.19
11,600.00
19,464.14
2,500.00
21,964.14
12.61 Cu.ft
12.61 cu.ft 15.00 189.13
8.41 sq.ft 51.27 430.96
2.77 cu.ft 358.89 995.51
4.49 cu.ft 358.89 1,612.92
12.45 sq.ft 90.00 1,120.39
5.26 kg 140.00 736.19
9.36 sq.ft 37.28 348.94
5.00 sq.ft 37.28 186.40
2.64 sq.ft 90.00 237.60
5,000.00
10,858.04
2,500.00
13,358.04
2.00 Cu.ft
2.00 cu.ft 15.00 30.00
1.00 sq.ft 51.27 51.27
0.33 cu.ft 358.89 118.43
2.20 cu.ft 358.89 791.14
6.68 sq.ft 90.00 601.20
2.66 kg 140.00 371.89
0.12 sq.ft 37.28 4.31
2.27 sq.ft 37.28 84.67
0.12 sq.ft 37.28 4.31
0.45 sq.ft 90.00 40.39
2,097.61
2,500.00
4,597.61
SANITARY FITTING AND ACCESSORIES
Rate Rs. Date
New Eurosmart basin mixer Grohe Nr 14,960.00 6/2/2010
New Eurosmart concealed bath mixer Grohe Nr 12,950.00 6/2/2010
Concealed body bath Grohe Nr 12,320.00 6/2/2010
Relaxa head shower buo Grohe Nr 22,810.00 6/2/2010
Lineare basin mixer Grohe Nr 34,510.00 6/2/2010
Lineare bidet mixer Grohe Nr 34,510.00 6/2/2010
Silver metalic bidet spray Grohe Nr 9,130.00 6/2/2010
Coasta sink mixer Grohe Nr 10,570.00 6/2/2010
New Eurostyle sink mixer Grohe Nr 21,340.00 6/2/2010
mintaa sink mixer Grohe Nr 58,400.00 6/2/2010
Angle valve Grohe Nr 1,850.00 6/2/2010
Angle valve Grohe Nr 1,650.00 6/2/2010
Item Description Qty Unit Rate Amount Amount Remarks
15%
O/H & Profit
Amount with profit
Fixing of Sanitary fittings with necessary accessories
Main Index
Material
Flexible hose 1 Nos 325.00 325.00
"S" or "P" trap 1 Nos 500.00 500.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,325.00
13.01 Water closet
Material
Pedestal type Water closet 1 Nos 18,725.00 18,725.00
Add 15% 2,808.75
Flexible hose 1 Nos 325.00 325.00
"S" or "P" trap 1 Nos 500.00 500.00
Angle valve 1 Nos 750.00 750.00
Transport 2% 462.18
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 26,320.93
Add O/H 18% 4737.7665
31,058.69
13.02 Pedestal wash basin
Material
Pedestal wash basin 1 Nos 10,750.00 10,750.00
Add 15% 1,612.50
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 1,350.00 1,350.00
Angle valve 1 Nos 750.00 750.00
Mixer tap 1 Nos 3,000.00 3,000.00
Transport 2% 362.25
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 21,224.75
Add O/H 18% 3820.455
25,045.21
2 Vanity wash basin
Material
Flexible hose 2 Nos 325.00 650.00
Bottle trap 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Vanity basin tap 1 Nos 250.00 250.00
Total basic cost 6,500.00
13.03 Vanity wash basin
Material
Vanity wash basin 1 Nos 6,365.00 6,365.00
Add 15% 954.75
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 1,350.00 1,350.00
Angle valve 1 Nos 750.00 750.00
Mixer tap 1 Nos 3,000.00 3,000.00
Transport 2% 261.40
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 16,081.15
Add O/H 18% 2,894.61
18,975.75
3 Flexible showers
Material
Flexible hose 2 Nos 325.00 650.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,900.00
4 Bidet spry
Material
Flexible hose 1 Nos 325.00 325.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 3,825.00
13.06 Bidet spry
Material
Bidet spry 1 Nos 2,700.00 2,700.00
Flexible hose 1 Nos 325.00 325.00
Angle valve 1 Nos 750.00 750.00
Transport 2% 75.50
Labour
Fixing charges 1 Item 750.00 750.00
Total basic cost 4,600.50
Add O/H 18% 828.09
5,428.59
SUPPLY & FIX MIRRORS Mansoor
Consider 20 Sq.ft
Material
Mirror 20.00 Sq.ft 845.00 16,900.00
Screws & bolts 4.00 Nos 8.35 33.40
16,933.40
Transport 10% 1,693.34
Labour
Skilled 0.25 day 950.00 237.50
Un skilled 0.25 day 650.00 162.50
400.00
19,026.74
Add O/H & profit 25% 25% 4,756.69
Cost for 20 Sq.ft 23,783.43
Cost for 1 Sq.ft 1,189.17
5 1/2" bib tap
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 250.00
13.04 Jacuzzi bath
Material
Jacuzzi bath 1 Nos ### 130,000.00
Add 15% 19,500.00
Flexible hose 2 Nos 325.00 650.00
Angle valve 3 Nos 750.00 2,250.00
Mixer tap 1 Nos 3,000.00 3,000.00
Transport 2% 3,108.00
Labour
Fixing charges 1 Item 3,500.00 3,500.00
Total basic cost 162,008.00
Add O/H 18% 29,161.44
191,169.44
6 Bath tub
Material
Flexible hose 2 Nos 325.00 650.00
Conceal value 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 3,500.00 3,500.00
Total basic cost 7,000.00
13.05 mirror Size 700 x 1100 0.77 m2 3,766.00 2,899.82
Pencil 3.6 L.m 148.00 532.80
Punching 4 Nos 50.00 200.00
Nuts 4 Nos 25.00 100.00
Transport 2% 74.65
Labour
Fixing charges 1 Item 500.00 500.00
Total basic cost 4,307.27
Add O/H 18% 775.31
5,082.58
7 Accessories
Labour
Fixing charges
Paper holder 200.00
Soap holder 200.00
towel rail 200.00
tooth brush holder 200.00
cloth pegs 200.00
1,000.00
8 Builder's work
Excavation 10 Cu.ft 14.00 140.00
Back filling 10 Cu.ft 15.00 150.00
mass concrete 3.3 Cu.ft 285.00 940.50
1,230.50
123.05
13.07 shower mixer spray
Material
shower mixer spray 1 Nos 6,000.00 6,000.00
Flexible hose 2 Nos 325.00 650.00
wall mounted tap 1 Nos 750.00 750.00
Transport 2% 148.00
Labour
Fixing charges 1 Item 1,200.00 1,200.00
Total basic cost 8,748.00
Add O/H 18% 1,574.64
10,322.64
13.08 towel rail
32 dia 600mtr towel rail 1 no 2,000.00 2,000.00
Nuts 4 no 25.00 100.00
Transport 2% 42.00
Labour
Fixing charges 1 Item 300.00 300.00
Total basic cost 2,442.00
Add O/H 18% 439.56
2,881.56
13.09 sigle bowl stainless steel sink
Material
sigle bowl stainless steel sink 1 Nos 8,500.00 8,500.00
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 2,750.00 2,750.00
Angle valve 1 Nos 750.00 750.00
Swell type piller tap 1 Nos 2,500.00 2,500.00
Mixer tap 1 Nos 3,000.00 3,000.00
Transport 2% 363.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 21,263.00
Add O/H 18% 3,827.34
25,090.34
13.1 Double bowl stainless steel sink
Material
Double bowl stainless steel sink 1 Nos 15,000.00 15,000.00
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 2,750.00 2,750.00
Angle valve 1 Nos 750.00 750.00
Swell type piller tap 1 Nos 2,500.00 2,500.00
Mixer tap 1 Nos 3,000.00 3,000.00
Transport 2% 493.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 27,893.00
Add O/H 18% 5,020.74
32,913.74
13.12 Soap tray
Soap tray 1 No 1,500.00 1,500.00
Screws 2 No 25.00 50.00
Transport 2% 31.00
Labour
Fixing charges 1 Item 200.00 200.00
Total basic cost 1,781.00
Add O/H 18% 320.58
2,101.58
13.13 1/2" Garden tap
1/2" Garden tap 1 No 750.00 750.00
Transport 2% 15.00
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 1,015.00
Add O/H 18% 182.70
1,197.70
Water pump 1 15,720.00 15,720.00
Gate valve 3 1,650.00 4,950.00
Non retern valve 1 2,000.00 2,000.00
Transport 2% 453.40
Labour
Fixing charges 1 Item 2,000.00 2,000.00
Total basic cost 25,123.40
Add O/H 18% 4,522.21
29,645.61
Water pump 1 44,000.00 44,000.00
Gate valve 3 1,650.00 4,950.00
Non retern valve 1 2,000.00 2,000.00
Transport 2% 1,019.00
Labour
Fixing charges 1 Item 2,000.00 2,000.00
Total basic cost 53,969.00
Add O/H 18% 9,714.42
63,683.42
Water pump 1 32,500.00 32,500.00
Gate valve 3 1,650.00 4,950.00
Non retern valve 1 2,000.00 2,000.00
Transport 2% 789.00
Labour
Fixing charges 1 Item 2,000.00 2,000.00
Total basic cost 42,239.00
Add O/H 18% 7,603.02
49,842.02
Q16
Materials
1 No 28,543.00 28,543.00
Gate valve 2 No 1,650.00 3,300.00
Non-Return valve 1 No 2,000.00 2,000.00
Balancing valve 1 No 2,000.00 2,000.00
Stainer 1 No 2,000.00 2,000.00
Float switch panel 1 No 650.00 650.00
Control panel 1 No 75,000.00 75,000.00
Tarter 1 No 10,300.00 10,300.00
solvent cement 75.00 grms 2.28 171.00
Supply & install centrifugal electric water pump
Electric water pump (Delivery 2000gl/hr@ 12Mtr
Other Item 1,000.00 1,000.00
GI Pipe 1 No -
Transport 2% 2,499.28
Labour
Fixing charges 1 Item 2,000.00 2,000.00
129,463.28
Q17
Materials
1 No ### 125,000.00
solvent cement ### grms 2.28 228.00
Tarter 1 No 10,300.00 10,300.00
Transport 2% 2,710.56
Labour
Fixing charges 1 Item 2,000.00 2,000.00
140,238.56
Q18
Materials
1000Ltr water tank 1 No 12,000.00 12,000.00
Gate valve 2 No 1,650.00 3,300.00
Non-Return valve 1 No 2,000.00 2,000.00
solvent cement 75.00 grms 2.28 171.00
Other Item 1,000.00 1,000.00
Transport 2% 369.42
Supply & install Pressure boosting package near the over head tank
65 Ltr per per minits at 30psi. Pressure tank
Supply & install 1000 Ltr plastic water tank
Labour
Fixing charges 1 Item 2,000.00 2,000.00
20,840.42
Q20
Assume 50 L.ft
Materials
32mm pipe 50.00 l.ft 49.23 2,461.54
clipe & nails 160.00
solvent cement 75.00 grms 2.28 171.00
Others 1,280.00
4,072.54
Labour
skilled labourer 0.75 day 950.00 712.50
U/sk labour 0.75 day 650.00 487.50
1,200.00
3% for tool 36.00
5% for Scaffolding 60.00
5,368.54
107.37
Q21 Supply & fix 1" dia gate valve
Materials
1" dia gate valve 1 No 1,650.00 1,650.00
32mm dia. Pumping main to over head tank from sump
solvent cement 10.00 grms 2.28 22.80
Transport 2% 33.46
Labour
Fixing charges 1 Item 500.00 500.00
2,206.26
Q22
Assume 50 L.ft
Materials
25mm pipe 50.00 l.ft 33.00 1,650.00
clipe & nails 160.00
solvent cement 75.00 grms 2.28 171.00
Others 880.00
2,861.00
Labour
excavation 0.75 day 950.00 712.50
skilled labourer 0.75 day 950.00 712.50
U/sk labour 0.75 day 650.00 487.50
1,912.50
3% Tools 57.38
5% Scaffolding 95.63
4,926.50
98.53
Q31
Materials 287
20mm hot water pipe ### l.ft 87.50 8,750.00
20mm ' T ' joint 5.00 No 145.00 725.00
Laying of 25mm supply main from the road & to the sump as shown in drawing
20mm polypropylene pipe or equivalent hot water
20mm Elbow 3.00 No 100.00 300.00
20mm Lugged Elbow 8.00 No 240.00 1,920.00
20mm Clip 67.00 No 19.14 1,282.38
Concrete nail with roll plug ### No 5.00 665.00 13,642.38
Transport 2% 272.85
Wastage 5% 682.12
LabourPlumber 10.50 day 950.00 9,975.00
U/sk labour 10.50 day 650.00 6,825.00
16,800.00
3% of Tools 504.00
5% of Scaffolding 840.00
32,741.35
327.41
Q32
100 L.ft
Materials
15mm hot water pipe ### l.ft 70.12 7,012.20
15mm ' T ' joint 5.00 No 65.00 325.00
15mm Elbow 3.00 No 60.00 180.00
15mm Lugged Elbow 8.00 No 195.00 1,560.00
15mm Clip 67.00 No 19.14 1,282.38
Concrete nail with roll plug ### No 5.00 665.00 11,024.58
Transport 2% 220.49
Wastage 5% 551.23
15mm polypropylene pipe or equivalent hot water
LabourPlumber 10.50 day 950.00 9,975.00
U/sk labour 10.50 day 650.00 6,825.00
16,800.00
3% of Tools 504.00
5% of Scaffolding 840.00
29,940.30
299.40
Q33
Materials
10mm hot water pipe ### l.ft 60.98 6,097.56
10mm ' T ' joint 8.00 No 65.00 520.00
10mm Elbow 7.00 No 60.00 420.00
10mm Lugged Elbow 11.00 No 195.00 2,145.00
10mm Clip ### No 19.14 1,914.00
Concrete nail with roll plug ### No 5.00 1,000.00 12,096.56
Transport 2% 241.93
Wastage 5% 604.83
LabourPlumber 10.50 day 950.00 9,975.00
U/sk labour 10.50 day 650.00 6,825.00
16,800.00
3% of Tools 504.00
5% of Scaffolding 840.00
31,087.32
10mm polypropylene pipe or equivalent hot water
310.87
Q34
Materials
solar hot water panel 300 Ltr 1 No ### 198,000.00
Others 2,000.00 2,000.00
200,000.00
Q36 1 1/2" dia gate valve
Materials
1 1/2" dia gate valve 1 No 4,800.00 4,800.00
solvent cement 5.00 grms 2.28 11.40
Transport 2% 96.23
Labour
Fixing charges 1 Item 200.00 200.00
5,107.63
Q37 1 1/4" dia gate valve
Materials
1 1/4" dia gate valve 1 No 3,600.00 3,600.00
solvent cement 5.00 grms 2.28 11.40
Transport 2% 72.23
Supply & fix solar hot water panel 300 Ltr
Labour
Fixing charges 1 Item 200.00 200.00
3,883.63
Q38 1" dia gate valve
Materials
1" dia gate valve 1 No 2,450.00 2,450.00
solvent cement 5.00 grms 2.28 11.40
Transport 2% 49.23
Labour
Fixing charges 1 Item 200.00 200.00
2,710.63
Q39 3/4" dia gate valve
Materials
3/4" dia gate valve 1 No 1,950.00 1,950.00
solvent cement 5.00 grms 2.28 11.40
Transport 2% 39.23
Labour
Fixing charges 1 Item 200.00 200.00
2,200.63
Q40 1/2" dia gate valve
Materials
1/2" dia gate valve 1 No 1,475.00 1,475.00
solvent cement 5.00 grms 2.28 11.40
Transport 2% 29.73
Labour
Fixing charges 1 Item 200.00 200.00
1,716.13
Sanitary fittings
Q42
Material
Flexible hose 1 Nos 325.00 325.00
"S" or "P" trap 1 Nos 500.00 500.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,325.00
Q43 Fixing of Vanity wash basin
Material
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Fixing of pedestal type of water closet
Total basic cost 6,250.00
Q44
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 1,350.00 1,350.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 5,500.00
Q45
Material
Flexible hose 2 Nos 325.00 650.00
Bottel trap 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 6,250.00
Q46
Fixing of Stainless steel sink double bowl sigle drain (Mixer tap)
Fixing of Stainless steel sink double bowl sigle drain (single tap)
Fixing of Mirror (pencil edge Size 2'-6" x 2'-0"
Pencil 9 L.ft 45.00 405.00
holl making 4 Nos 50.00 200.00
Nuts 4 Nos 25.00 100.00
Labour
Fixing charges 1 Item 500.00 500.00
Total basic cost 1,205.00
Q47
Material
1 Nos -
Flexible hose 2 Nos 325.00 650.00
Angle valve 1 Nos 750.00 750.00
Mixer tap 1 Nos -
Transport 2% 28.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,178.00
Q48
Material
Flexible hose 2 Nos 325.00 650.00
Supply & fix chromium plated telephon head shower spray with concealed type shower (Mixer tap)
chromium plated telephon head shower
Fix chromium plated telephon head shower spray with control type shower (Mixer tap)
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,150.00
Q49
Material
Flexible hose 1 Nos 325.00 325.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 3,825.00
Q50
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 250.00
Q51
Fixing of approved quality hand spray bidet comprising
Fixing of stainless steel towel rail 32 dia.
Fixing of stainless steel brass pegs with double hanging hooks fixed to doors
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 250.00
Q52 Fixing of stainless steel soap tray
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 250.00
Q50
1/2" dia. C.P Garden tap 1 Nos 365.00 365.00
solvent cement 5.00 grms 2.28 11.40
Labour
Fixing charges 1 Item 200.00 200.00
576.40
W17
Consider 50 L.ft
Materials
Supply & fix 1/2" dia. C.P Garden tap
Supply & fix 110 dia. uPVC (Type400)
110mm pipe 50.00 L.ft 195.60 9,780.00
Solvent cement ### Grms 2.28 342.00
Other 15,000.00
25,122.00
Labour
Excavation 0.75 Day 650.00 487.50
Skilled labourer 0.75 Day 950.00 712.50
U/sk labour 0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
26,944.50
538.89
C
Materia
Supplu of motar pump 1 Nos 15,000.00 15,000.00
cement 0.25 Cement 740.00 185.00
Sand 0.01 Cube 7,500.00 75.00
Allum for pipe 1 Item 500.00 500.00
15,760.00
Transport 10% 1,576.00
Labour
Mason 0.50 day 950.00 475.00
Un skilled 0.50 day 650.00 325.00
Plumber 0.50 day 950.00 475.00 475.00
Supply and Fix water pump including valve
Tools 3% 14.25
17,825.25
O/H & Profit 25% 4,456.31
Total Cost 22,281.56
Water Geyser
Material
30L Water geyser 1.00 Nos 16,500.00 16,500.00
Angle valve 2.00 Nos 750.00 1,500.00
Flexible hoses 2.00 Nos 325.00 650.00 18,650.00
Labour
Skilled 1.00 Day 950.00 950.00
Un skilled 1.00 Day 650.00 650.00 1,600.00
Tools 3% 48.00
Cost for 1 Nos 20,298.00
Supply & Fix Squatting fan
Material
Squatting pan 1 No 549.00 549.00
Cement bedding 200.00
Labour
Fixing charges 1 Item 750.00 750.00
Total basic cost 1,499.00
Supply & Fix Shower
Material
Shower head 1 Nos 150.00 150.00
Solvent cement 50.00
Labour
Fixing charges 1 Item 200.00 200.00
Total basic cost 400.00
TIMBER WORKS
Item Description Qty Unit Rate Amount Amount
15%
1
785.57
Consider 10' 0"x10' 0" area
Material ( balaw)
2"x 4" timber 60.00 L ft 135.50 8,130.00
2"x 2" timber 60.00 L ft 55.00 3,300.00
3/4" thick timber plank (Kmbuk) 100.00 Sq ft 450.00 45,000.00
Nails 5 kg 160.00 800.00
57,230.00
Wastage 5% 0.05 2,861.50
Timber plaking
Labour
Carpenter 2 days 950.00 1,900.00
Un skilled 1 day 650.00 650.00
2,550.00
Add for tools 3% of labour 0.03 76.50
Add for scaffolding 5% of labour 0.05 127.50
62,845.50
O/H & Profit
Amount with profit
Timber deck with 2" x4 ", 2"x 2" fram and 3/4" thick kubuk plank
Main Index
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Add O/H & profit 0.25 15,711.38
Cost for 1 Sqr 78,556.88
Assume 1'-4" wide 75 L.ft long 6.25 1 sqr
Materials
1" thick, 6" width yellow Balue 91.44 Sq.ft 292.00 26,699.75
Nut & bolts 550.00 No 10.00 5,500.00
sand paper 5.00 no 40.00 200.00
brush 0.10 no 595.00 59.50
32,459.25
Transport 7% 2,272.15
Labour
skilled labourer 1.00 day 950.00 950.00
un /skilled labourer 1.00 day 650.00 650.00
1,600.00
3% of labour cost 48.00
Paint
Timber Planking 91.44 Sq.ft 10.00 914.38
wood preservative 7.32 Cu.ft 263.00 1,923.85
wood Treatment 91.44 sq.ft 20.00 1,828.75
Water base lacqer 182.88 sq.ft 88.00 16,093.00
1" thick, 6" width yellow Balue timber plank fixed on RCC beams with 1/2" gap finished with two coats of water based lacqer
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
20,759.97
57,139.37
3 6" high kubuk skirting Mansoor
Consider 10 L.ft
Material
Kumbuk Plank 10.00 L ft 175.00 1,750.00
Wastage 10% 10% 175.00
Nails 20.00 8.35 167.00
Wood presevative 250.00
2,342.00
Labour
Skilled 1 day 950.00 950.00
Un skilled 1 day 650.00 650.00
1,600.00
Add 3% for tools 3% 48.00
3,990.00
Add O/H & profit 25% 25% 997.50
4,987.50
Cost for one L ft 498.75
4
Mansoor
Staircase hand rail including copper posr.
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Consider 12 L.ft
Material
2"x4" teak hand rail 12.00 L.ft 625.00 7,500.00
S/S Cable 48.00 L.ft 250.00 12,000.00
Copper post (1"x2 1/4"x2'9") 4.00 Nos 3,000.00 12,000.00
31,500.00
Labour
Skilled 7.00 day 900.00 6,300.00
Un skilled 4.00 day 650.00 2,600.00
8,900.00
Add 3% for tools 3% 267.00
40,667.00
Add O/H & profit 25% 25% 10,166.75
50,833.75
Cost for 1 L.ft 4,236.15
Assume 10 L.ft
Materials
3" x 2" Teak 10.00 L.ft 700.00 7,000.00
2" Flat iron 10.00 L.ft 68.42 684.20
3" x 2" teak timber member fixed to 2" thick flat iron wiyh welded to 5/8" dia mild steel round bar spaces fixed to wall all complete as per detail drawing
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
5/8" mild steel round bar 72.00 L.ft 22.03 1,585.96
Bolt & Nuts 15.00 No 10.00 150.00
Welding rod 5.00 No 10.00 50.00
sand paper 5.00 No 35.00 175.00
Anchor bolt etc 360.00
10,005.16
Transport 7% 700.36
Welding plant 1.00 hour 312.50 312.50
Labour
Skilled Labour 3.00 day 950.00 2,850.00
Un / skilled Labour 2.00 day 650.00 1,300.00
4,150.00
Paint
Tmber planking 10.00 L.ft 10.00 100.00
Tmber painting (spry) 11.60 Sq.ft 115.00 1,334.00
Iron paint
Anti corosive 1.50 Ltr 586.00 879.00
Steel primer 1.00 Ltr 973.00 973.00
Black eggshell paint 1.50 Ltr 542.00 813.00
Tinner 2.00 Ltr 338.00 676.00
Brush 1/2" 1.00 no 100.00 20.00
4,795.00
19,963.03
1,996.30 299.45 2,295.75
prilimineries 10% 0.10 1,996.30
21,959.33
Cost per L.ft 2,195.93 329.39 2,525.32
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
5
Material
1' 0" width "U" Iron 22.33 L.ft 2,600.00 58,058.00
"L" Iron 84.00 L.ft 125.00 10,500.00
25mm Tor steel rod 7.06 kg 260.00 1,834.90
1 1/2" thick Kumbuk timber 90.00 Sq.ft 450.00 40,500.00
1:2:4 Concrete 0.20 Cube 38,400.00 7,587.84
3/4" Screws 100.00 Nos 5.58 558.00
Glue 4.00 Ltr 175.00 700.00
119,738.74
Add 10% for wastage 10% 11,973.87
Add 5% for transport 5% 5,986.94
Labour
Skilled Labour 5.00 day 950.00 4,750.00
Un Skilled Labour 5.00 day 650.00 3,250.00
8,000.00
Add 3% for tools 3% 240.00
Add 5% for scaffolding 5% 400.00
146,339.55
Add O/H & profit 25% 25% 36,584.89
Cost for Staircase 182,924.44
6 TIMBER LATTIS 676.82 Kiri
Consider 3.41 Sqr (48.75' x 7')
Timber staircas support with "U" Iron
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Material
2" x 2" battens 500.00 L.ft 45.00 22,500.00
2" x 1" reepers 3,920.00 L.ft 27.00 105,840.00
128,340.00
Wastage 10% 10% 12,834.00
Transport 7% 7% 8,983.80
Nails & screws 14.00 160.00 2,240.00
2,240.00
Labour
Planing charges 3,920.00 L.ft 7.00 27,440.00
Skilled 3.00 Day 950.00 2,850.00
Un skilled 3.00 Day 650.00 1,950.00
4,800.00
Basic cost 184,637.80
Add O/H & profit 25% 25% 46,159.45
Cost per 3.41 Sqr 230,797.25
Cost per Sqr (without polish) 67,682.48
Material
8" dia app 9' 6" high columns 1.00 Nos 6,000.00 6,000.00
Transport 5% 300.00 6,300.00
Pressure impregnated,mature coconut, sealed 8"x8" square ends finished smooth
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
labour
Planking charges
Post making & Fixing charges 650.00 650.00
Tools 3% 19.50
Cost for one Post 6,969.50
Galvanized iron angle iron
For 1 pair
Material
100x 75x 8mm angle iron 1.33 L.ft 750.00 1,000.00
12mm bolts 2.00 nos 300.00 600.00 1,600.00
Labour
Un skilled 0.25 Day 650.00 162.50 162.50
Cost for one pair 1,762.50
Concrete encasing to anchor bolts
For 1 No 2' 0"x8"x6"
Material
Concrete (grade 20) 0.66 Cu.ft 297.00 196.02
Wastage 5% 9.80 205.82
Labour
Skilled 0.1 Day 950.00 95.00
Un skilled 0.1 Day 650.00 65.00 160.00
Tools 3% 4.80
Cost for 1 nos 370.62
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
0.33
19.71
For 8" dia 9' 6" high column
Material
Water based Sandind sealer 0.83 Ltr 820.00 680.60
Wood stain 0.83 Ltr 656.25 544.69
Wood finishing 1.25 Ltr 805.00 1,006.25
Sand paper 10.00 Nos 40.00 400.00
Canvas 10.00 l.ft 65.00 650.00
Brush 0.25 Nos 595.00 148.75 3,430.29
Wastage 5% 171.51
Labour
Skilled 1.00 Day 950.00 950.00
Unskilled 2.00 Day 650.00 1,300.00 2,250.00
Add 3% for tools 67.50
Cost for 1 Sqr 5,919.30
Cost for 1 Sq.ft 59.19
1,166.69
Skirting moulded top edge
4" x 1/2" high straight timber
Prepair and apply two coats water based sanding sealer, stain and two finishing coats on Coconut.
Cost for 8" dia 9' 6" high column (19.71 Sq.ft)
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Consider 10 L.ft
Material
4" x 1/2" high straight timber 10.00 L ft 200.00 2,000.00
Wastage 10% 10% 200.00
Transport 10% 200.00
Nails 20.00 8.35 167.00
Wood presevative
2,567.00
Labour
Skilled 0.5 day 950.00 475.00
Un skilled 0.5 day 650.00 325.00
800.00
Add 3% for tools 3% 24.00
Cost for 10 L ft 3,391.00
Cost for 1 L ft 339.10
B Teak panneled door
D 4 (1200x3000)
Material
Door sash 38.74 Sq ft 650.00 25,178.40
Wastage 10% 25,178.40
2,517.84
Labour 38.74 Sq ft 350.00 13,557.60
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Tools 3% 406.73
Cost for Door sash 41,660.57
F Antique Door
(1200x2100)
Material
Door sash 27.12 Sq ft 450.00 12,201.84 12,201.84
Cost for Door sash 12,201.84
Ex 03 2" x 1" Lattis area For 3.41 Sqr
48'- 9" x 7'- 0"
Material
2" x 2" reepers 92.00 L.ft 45.00 4,140.00
2" x 1" reepers 2,341.43 L.ft 27.00 63,218.57
67,358.57
Wastage 15% 10,103.79
Transport 10% 6,735.86
Wood Preservative 5,500.00
Nails & screws 14.00 160.00 2,240.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Labour
Planing charges 2,433.43 L.ft 7.00 17,034.00
Skilled 3.00 Day 950.00 2,850.00
Un skilled 3.00 Day 650.00 1,950.00 4,800.00
Basic cost 113,772.21
Add O/H & profit 25% 28,443.05
142,215.27
Cost per Sqr (without polish) 41,705.36
Mansoor
Consider 32 Sq.ft
Material
1" thick kubuk plank 32.00 Sq ft 450.00 14,400.00
Wastage 10% 10% 1,440.00
Wood preservative 150.00
15,990.00
Labour
Skilled 0.50 days 950.00 475.00
Un skilled 0.50 days 650.00 325.00
800.00
Tools 3% 3% 24.00
Planning charges 340.00
340.00
17,154.00
SUPPLY & FIX KUMBUK PLANK TO VENITY TOP
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with profit
Add O/H & profit 25% 25% 4,288.50
Cost for 1 Sqr 21,442.50
Cost for 1 Sq.ft 670.08
Pantry Cupboard
L.ft 15,000.00
L.ft 20,000.00
L.ft 18,500.00
L.ft 9,200.00
Complete mahogany pantry cupboard ( Bottom and upper )
Complete Teak pantry cupboard ( Bottom and upper )
Mahogany cacase and surface teak pantry cupboard ( Bottom and upper )
Complete MDF pantry cupboard ( Bottom and upper )
Remarks
Remarks
Buller's
Remarks
134
Remarks
3.14285714285714
STEEL WORKS
Item Description Qty Unit Rate Amount Amount
15%
1 STEEL DOOR
Supply and fixing of steel door
9' 2" x 6' 10" (0.6 sqr)
Material
50 x 50 x 6 mm box iron 3.00 Nos 1,346.09 4,038.27
25 x 25 x 3 mm box iron 10.00 Nos - -
Door lock 1.00 Nos 6,900.00 6,900.00
Hinges 4.00 Nos 1,100.00 4,400.00
Welding rods 5.00 kg -
Cutting disks 6.00 Nos -
Oil primer 4.00 Liters -
Enamal paint 4.00 Liters 553.00 2,212.00
17,550.27
Labour
For fabricating and fixing
Skilled lobour 3.00 days - -
O/H & Profit
Amount with profit
Main Index
Un skilled 4.00 days 123.50 494.00
For painting
Skilled lobour 1.00 days - -
494.00
ADD 3% for tools 3% 14.82
18,059.09
30,098.48 4,514.77 34,613.26
prilimineries 10% 0.1 1,805.91
Cost for 0.6 sqr 19,865.00
Cost for 1 sqr 33,108.33 4,966.25 38,074.58
2 HAND RAIL
Fixing of wall hand rail (10 L.ft)
Material
50mm dia G.I pipe 10.00 L.ft 1,900.00 19,000.00
12mm M.S rods 40.00 L.ft -
6mm M.S plates 4.00 nos -
16mm dia ancher bolts 16.00 nos -
Welding rods 2.00 kg -
Primer 0.50 lts -
Auto colour paint 0.50 lts -
Additional promote 0.50 lts -
19,000.00
Labour
For fabricating and fixing
Skilled lobour 2.00 days - -
Un skilled 3.00 days 123.50 370.50
370.50
ADD 3% for tools 0.03 11.12
Cost for 1 sqr without prilimineries 19,381.62
1,938.16 290.72 2,228.89
prilimineries 10% 0.10 1,938.16
Cost for10 L.ft 21,319.78
Cost for 1 L.ft 2,131.98 319.80 2,451.77
3 SUPPLY & FIX " H" BEAM
Material
" H" beam 350x175x41.5kg 1 Nos 47,300.00 47,300.00
Bolt 8 Nos 150.00 1,200.00
10mm plate 2 sq.ft 1,100.00 2,200.00
50,700.00
Transport 3,500.00
Labour
Sk 1 Days 950.00 950.00
Un/sk 1 Days 650.00 650.00
1,600.00
Small tools 3% 3% 48.00
Scafolding 5% 5% 80.00
55,928.00 8,389.20 64,317.20
prilimineries 10% 0.10 5,592.80
Cost for above Item 61,520.80 9,228.12 70,748.92
3 G.I LADDER
Assume 35 L.ft
Material
4/3" G.I. pipe 70.00 L.ft 64.21 4,494.74
35.00 L.ft 62.11 2,173.68
10% wastage 666.84
Welding rods Item 600.00
Welding plant 1.00 Day 2,500.00 2,500.00
Grinding Item 900.00
11,335.26
Transport 10% 1,133.53
Labour
Skillded 4.00 Day 950.00 3,800.00
Un/skilled 4.00 Day 650.00 2,600.00
6,400.00
Tools 3% 192.00
Scafallding 5% 320.00
1/2" G.I. pipe solied
19,380.79
553.74 83.06 636.80
prilimineries 10% 0.10 1,938.08
21,318.87
Cost per 1 L.ft 609.11 91.37 700.48
Roller Shutter
Morter 1.00 No 35,000.00 35,000.00
Roller Shutter 200.00 Sq.ft 700.00 140,000.00
175,000.00 26,250.00 201,250.00
875.00 131.25 1,006.25
prilimineries 10% 0.10 17,500.00
192,500.00 28,875.00 221,375.00
Cost per Sq.ft 962.50 144.38 1,106.88
Balcony Terrace Railling
Assume 10 L.ft
Over size 20'-0" x 10'-0" (type RD1 200Sq.ft)
2" Diameter galvanized iron (Horizontzl) with 1" dia m/s rood (Vertical @ 8" centers) fixed to horizontzl galvanized bar & fixed to wall
Materials
2" Diameter galvanized iron 10.00 L.ft 222.11 2,221.10
1" dia m/s 4.00 L.ft 52.63 210.52
Achobolt 1.00 Item 100.00 100.00
Welding rod 5.00 No 10.00 50.00
sand paper 3.00 No 35.00 105.00
2,686.62
Transport 7% 188.06
Welding plant 1.00 hour 312.50 312.50
Labour
Skilled Labour 2.00 day 950.00 1,900.00
Un / skilled Labour 2.00 day 650.00 1,300.00
3,200.00
Iron paint
Anti corosive 0.75 Ltr 586.00 439.50
Steel primer 1.00 Ltr 973.00 973.00
Black eggshell paint 0.50 Ltr 542.00 271.00
Tinner 1.00 Ltr 338.00 338.00
Brush 1/2" 1.00 no 100.00 20.00
2,041.50
8,428.68
842.87 126.43 969.30
prilimineries 10% 0.10 842.87
9,271.55
Cost per L.ft 927.16 139.07 1,066.23
Weld mesh Galvanized iron
Assume 1 Sqr
100.00 Sq.ft 45.00 4,500.00
Wastage 5% 225.00
Wastage 5% 225.00
Allow for galvanizing 1,000.00
Labour
Skill 0.20 Day 950.00 190.00
Un Skill 0.20 Day 650.00 130.00
Per Sqr 6,270.00
62.70
Railing
Consider 10 L.ft
Weld mesh Galvanized iron (3.15mm)
1 1/2" primer & painted G I hand rail with fixing bracket 12mm G I painted rods with timber railing @ 2' 0" c/c as detail
Material
1 1/2" G I hand rail 10.00 L.ft 100.00 1,000.00
12mm GI rods @ 2' 0" c/c 6.00 l.ft 32.00 192.00
fixing brackets 600.00
Allow sum for galvanized 500.00 2,292.00
Wastage 10% 229.20
Labour
Skilled 1.00 day 950.00 950.00
Un skilled 2.00 day 650.00 1,300.00 2,250.00
Add 3% for tools 67.50
Cost for 10 L ft 4,838.70
Cost for 1 L ft 483.87
1,750.00
Ex.40 Supply And fix Cast Iron lids for manhols and gullys.
Material
12" x 12" Rainwater Gully cover 12.00 Nos 4,980.00 59,760.00
18" x 18" Gully cover 5.00 Nos 10,800.00 54,000.00
30" x 20" Gully cover 2.00 Nos 14,900.00 29,800.00
26" x 24" Gully cover 2.00 Nos 11,696.00 23,392.00
24" x 24" Gully cover 1.00 Nos 11,696.00 11,696.00
12" x 12" Dranage cover 1.00 Nos 3,950.00 3,950.00
20" x 25" Gully cover 1.00 Nos 11,696.00 11,696.00
14" x 14" Gully cover 1.00 Nos 6,780.00 6,780.00
21" x 21" Gully cover 1.00 Nos 11,696.00 11,696.00
Cement 1.00 bag 780.00 780.00
Sand 0.09 cube 7,500.00 675.00
Water 12.00 gal 0.50 6.00
Transport 10% 214,231.00
21,423.10
Labour
Skilled 6.00 Day 950.00 5,700.00
Un skilled 6.00 650.00 3,900.00 9,600.00
Tools 3% 288.00
-
O/H & Profit 25% 0
Total Cost -
Remarks
Buller's
Nishani
Queens
Queens
TYPE OF BOUNDARY WALL
Item Description Qty Unit Rate Amount Amount
15%
1 BOUNDRY WALL
Consider 10' 0" long
Consider 10' 0" long, 7'-0" high
Excavation 10.00 1.18 1.25 14.75 Cu ft 13.39 197.50
Rubble 10.00 1.18 1.25 14.75 Cu ft 1.54 22.68
10.00 0.75 0.50 3.75 Cu ft 1.54 5.77
4" block work 10.00 7.00 70.00 Sq ft 1.20 84.00
concrete in 4"x4" columns 2 2.00 2.00 0.50 4.00 Cu ft 328.94 1,315.74
2 0.34 0.34 8.00 1.85 Cu ft 328.94 608.40
Formwork in 4"x4" columns 2 1.68 8.00 26.88 Sq ft 14.78 397.16
O/H & Profit
Amount with
profit
4" block wall
1' 0"
Main Index
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Reinforcement in 4"x4" columns 4 9.00 6.78 kg - -
32 0.50 1.08 kg - -
Rough plaster 2.00 10.00 7.00 ### Sq ft - -
Painting 2.00 10.00 7.00 ### Sq ft 0.60 84.00
Copping 10.00 10.00 Lft 80.00 800.00
3,515.25
351.52 52.73 404.25
Preliminaries 0.10 351.52
Cost for 10 l ft 3,866.77
Cost for 1 l ft 386.68 58.00 444.68
Chain Link Fencing
18.75 Concrete volume
Assume 50 L.ft
Material
Cement 2.5 Bag 740.00 1,850.00
Sand -rough 0.08 Cube 7,000.00 560.00
Metail 0.14 Cube 4,800.00 672.00
PVC coated 2"x2" square,guage 10 chainlink fence,with 9' 0" high reinforced concrete posts equilent to as manufactured by SEC, buried in 18"x18"x24" deep concrete at 8' 0" c/c as detail,with 3 stands staining wire the bottom encased in 13"x6" concrete.
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
6 Nr 1,211.28 7,267.68
50.00 L.ft 385.71 19,285.71
Tensin wire 150.00 l.ft 10.00 1,500.00
31,135.39
Transport 5% 5% 1,556.77
Wastage 10% 10% 3,113.54
Labour
Skilled 2.00 day 950.00 1,900.00
Un skilled 4.00 day 650.00 2,600.00 4,500.00
3% of labour Cost for tools 135.00
Cost for 50 L.ft 40,440.70
Cost for 1 L.ft 808.81
Concrete precast fence post 7'-7" high
PVC coated 2"x2" square chainlink fence -Fence hight 8'-0"
MISSALLANIOUS
Item Description Qty Unit Rate Amount Amount Remarks
15%
Concrete Arch Demolish A11
Machine & equipment hiried
Time for demolosh work - 15 Days
Jacks 100 Nos 750.00 75,000.00
Jack hire for 1 day 50/= 15 days @ 75/=
Concrete braker 15 Days 5,000.00 75,000.00
Oxigen cutter 1 Days 6,000.00 6,000.00
156,000.00
Labour
Skilled -braker opretor 15 Days 1,200.00 18,000.00
For demolish
Un/sk 75 Days 675.00 50,625.00
( 15 days 5 un/sk )
75
Remove to tactor
Un/sk 25 Days 675.00 16,875.00
O/H & Profit
Amount with profit
Main Index
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
( 15 days 5 un/sk )
85,500.00
Tractor loard remove from site 5 load 1,500.00 7,500.00
7,500.00
Small tools 3% 2,565.00
Scafolding 5% 4,275.00
Basik cost 255,840.00
O/H and profit 25% 63,960.00
Cost for above 319,800.00
Demolish Concrete Slab & Beam Buller's
Machine & equipment hiried
Jacks ( 5 days) 40 Nos 250.00 10,000.00
Jack hire for 1 day 50/= 5 days @ 50/=
Concrete braker 5 Days 5,000.00 25,000.00
Oxigen cutter 0.5 Days 6,000.00 3,000.00
38,000.00
Labour
Skilled -braker opretor 5 Days 1,200.00 6,000.00
Un Skille laber for demolish 15 Days 675.00 10,125.00
( 5 days 3 un/sk )
Un Skille laber for remove 4 Days 675.00 2,700.00
( 2 days 2 un/sk ) 18,825.00
Small tools 3% 3% 564.75
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Scafolding 5% 5% 941.25
Tractor loard remove from site 2 load 1,500.00 3,000.00
3,000.00
61,331.00
O/H and profit 25% 25% 15,332.75
Cost for above 76,663.75
For one box
Material
1 Nos 4,560.00 4,560.00
6"x 9" random rubble 0.27 Cube 2,300.00 621.00 5,181.00
Transport 7% 362.67
Labour
For excavation Unskilled 0.5 day 650.00 325.00
skilled 0.5 day 950.00 475.00
Un skilled 0.75 day 650.00 487.50 1,287.50
Tools 3% 38.63
Cost for one Box (.27 Cube) 6,869.80
3' 0"x3' 0"x3' 0" PVC coated GI gabion basckets filleed with 6"x 9" random rubble and buried 3' 0" deep and 3' 0" above ground level.
3' 0"x3' 0"x3' 0" PVC coated GI gabion basckets
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Cost for one Cube 25,443.69
Fixing Concret stain posts in fence.For one post
Material
Concrete post 1 Nos 475.00 475.00
Transport 5% 23.75 498.75
Labour
Skilled 0.25 Day 950.00 237.50
Un skilled 0.50 Day 650.00 325.00 562.50
Tools 3% 16.88
Cost for one Post 1,078.13
F Remove roof Galle
For 1 Sqr
Labour
Skilled 1.00 day 950.00 950.00
Unskilled 2.00 day 750.00 1,500.00 2,450.00
Tools 3% 73.50
2,523.50
O/H & profit 25% 630.88
Total 3,154.38
For 28.19 Sqr 88,921.83
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Ex.49 Garden tap with Brick wall sink 4'-0" x 2'-0" 0'-5"
Material
4" Thick concrete 3.25 Cu.ft 412.00 1,338.53
6" brick work
12.48 Sq.ft 125.00 1,559.65
Water proofing
16.99 Sq.ft 110.00 1,869.14
Tilling
16.99 Sq.ft 140.00 2,378.91 7,146.23
Labour
Skilled Labour 4.00 Day 1,000.00 4,000.00
Un skilled Labour 3.00 day 750.00 2,250.00 6,250.00
Tools 3% 187.50
Total Cost 13,583.73
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
3 Built up Temperary huts for workers
Consider 12'-0" x 10'-0"
Floor & wall
Excavation top soil 168.00 Sq.ft 8.37 1,405.95
2" thick screed 120.00 Sq.ft 48.53 5,823.41
Cement rendering 120.00 Sq.ft 28.36 3,402.60
Covering GI sheets 72.00
60.00
132.00 Sq.ft 12.75 1,683.00
2" x2" Timber frame 45.00
48.00
40.00
133.00 L.ft 28.00 3,724.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Roof
GI sheets 120.00 Sq.ft 12.75 1,530.00
Frame 36.00
20.00
56.00 Sq.ft 28.00 1,568.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
20,106.96
Cost per 1 Sqr 16,755.80
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
4
Consider 5'-0" x 4'-0"
Excavation top soil 30.00 Sq.ft 8.37 251.06
2" thick screed 20.00 Sq.ft 48.53 970.57
Cement rendering 20.00 Sq.ft 28.36 567.10
Covering GI sheets 70.00
56.00
126.00 Sq.ft 12.75 1,606.50
2" x2" Timber frame 35.00
20.00
16.00
71.00 L.ft 28.00 1,988.00
Hinges 2.00 no 49.00 98.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Roof
GI sheets 20.00 Sq.ft 12.75 255.00
Frame 10.00
8.00
18.00 Sq.ft 28.00 504.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Supply & Fix Squatting fan 1.00 No 1,499.00 1,499.00
Supply & Fix Angle Valve 2.00 No 576.40 1,152.80
Built up Temperary toilet for workers including temperary pit
Item Description Qty Unit Rate Amount Amount Remarks O/H & Profit
Amount with profit
Supply & Fix Shower 1.00 No 400.00 400.00
63mm pipe 3.00 L.ft 253.53 760.60
32mm pipe 5.00 L.ft 107.37 536.85
25mm pipe 3.00 L.ft 83.14 249.42
Supply & Fix Pit 1.00 No 5,000.00 5,000.00
Excavation for pit 48.00 C.ft 13.39 642.72
PAINTING
Item Description Qty Unit Rate
INTERNAL PAINT APPLICATION
5 APPLY TWO COAT OF TOTAL COAT
Consider 8.45 Sqr
Material
Total coat 28kg bucket 3.50 Bucket 2,800.00
Sand paper 10 Nos 42.50
Bruss 0.1 Nos 595.00
Add: 5% transport 5%
Labour
Painter 4 Days 950.00
Add: 3% tools 3%
Add: 5% Scafolding 5%
Preliminaries 10%
Cost for 8.45 Sqr
Main Index
Consider 8.45 Sqr
Material
Total coat 3.50 Bucket 2,800.00
One coat of acralic filler 7.00 Ltr 337.00
Two coats of emulsion 11.27 Ltr 550.00
Sand paper 40.00 Nos 42.50
Roller Bruss 3.00 Nos 400.00
Add: 5% transport 0.05
Labour
Painter for Totalcoat apply 4.00 Days 950.00
Painter 15.00 Days 950.00
Add: 3% tools 0.03
Add: 5% Scafolding 0.05
Cost per Sqr
Preliminaries 10%
Cost for 1 Sqr
Painting & alkail Resistant Primer -CIC
Wall putty -Asian Paint
Emulsion 02 coats to internal walls including primer
Materials
Emulsion paint 2.00 Ltr 550.00
Wall putty @ Rs. 2100 per 28kg bag 7.50 Kg 75.00
Two coat of Total coat & cut the surface using sand paper (No 120,No 100,No 80,No 60) & apply one coat of acralic filler and two coats of interior emulsion paint of approved colour Internaly
sand paper 2.00 no 42.50
roller brush 0.08 no 595.00
Transpor 5%
Labour
skilled labourer 1.75 day 950.00
3% of labour cost for tools 0.03
3% of labourer cost scaffolding 0.03
Slab & Soffit Painting(Ceiling)
Consider 8.45 Sqr
Material
One coat of acralic filler 8.45 Ltr 337.00
Two coats of interior emulsion 12.67 Ltr 550.00
Sand paper 40.00 Nos 42.50
Bruss 6.00 Nos 400.00
Add: 5% transport 0.05
Labour
Sk labour 8.45 Days 950.00
unSk labour 8.45 Days 650.00
Add: 3% tools 0.03
Add: 5% Scafolding 0.05
Cost per Sqr
Preliminaries 10%
Cost for 1 Sqr
Prepare and apply one coat of interior emulsion white paint to internal soffit slab.
EXTERNAL PAINT APPLICATION
Weathershield 02 coats to external walls including primer
Materials
Weathershield paint 1.50 Ltr 750.00
Alkali resistance plaster primer 1.00 Kg 805.00
brush 0.08 no 555.00
Transpor 5%
Labour
skilled labourer 1.50 day 950.00
3% of labour cost for tools 0.03
3% of labourer cost scaffolding 0.03
TIMBER SURFACE FINISHING APPLICATION
2 SPRAY PAINT
Consider Door size 3' 0" x 7' 0" 75.00 Sq.ft
Material
First coat
Die 1.25 Ltr 1,810.00
Second coat
Base coat 1.25 Ltr 1,916.67
Third coat
Laquare 1.25 Ltr 1,916.67
Wastage 10% 10%
Labour
For cutting Unskilled 2.00 day 650.00
For spraying Skilled 1.50 day 950.00
Add 3% for tools 3%
For 75 Sq ft
For 1 Sqr
For 1 Sqr
Material
Sandind sealer 0.83 Ltr 820.00
Wood stain 0.83 Ltr 656.25
Matt lacqer 1.25 Ltr 805.00
Thinner 7.00 Ltr 599.00
Sand paper 10.00 Nos 40.00
Canvas 10.00 l.ft 65.00
Brush 0.25 Nos 595.00
Wastage 5%
Labour
Skilled 1.00 Day 950.00
Unskilled 2.00 Day 650.00
Add 3% for tools
Cost for 1 Sqr
Cost for 1 L.ft (4" thick)
Material
Enamal paint 1.25 Ltr 857.00
Prepair and apply two coats of sanding sealer, stain and two coats colourless matt lacqer on Timber.
Prepair and apply sanding sealer system on timber frame and enamel paint system on ms rods.
Thinner 7.00 Ltr 599.00
Sand paper 10.00 Nos 40.00
Brush 0.25 Nos 595.00
Wastage 5%
Labour
Skilled 1.00 Day 950.00
Unskilled 2.00 Day 650.00
Add 3% for tools
Cost for 1 Sqr
Cost for 1 Sq.ft
Amount Amount Remarks
15%
INTERNAL PAINT APPLICATION
Mansoor
1 Sqr
9,800.00
425.00
59.50
10,284.50
514.23
3,800.00
3,800.00
114.00
190.00
14,902.73
1,763.64 264.55 2,028.18
1,490.27
16,393.00
1,940.00 291.00 2,231.00
O/H & Profit
Amount with profit
9,800.00
2,359.00
6,198.50
1,700.00
1,200.00
21,257.50
1,062.88
3,800.00
14,250.00
18,050.00
541.50
902.50
4,948.45 742.27 5,690.71
494.84
5,443.29 816.49 6,259.79
1,100.00
562.50
85.00
47.60
1,795.10
89.76
1,884.86
1,662.50
1,662.50
49.88
49.88
3,647.11 547.07 4,194.17
2,847.65
6,971.25
1,700.00
2,400.00
13,918.90
695.94
8,027.50
5,492.50
13,520.00
405.60
676.00
3,457.57 518.64 3,976.20
345.76
3,803.32 570.50 4,373.82
EXTERNAL PAINT APPLICATION
1,125.00
805.00
44.40
1,974.40
98.72
2,073.12
1,425.00
1,425.00
42.75
42.75
3,583.62 537.54 4,121.16
TIMBER SURFACE FINISHING APPLICATION
140.88 Mansoor
2,262.50
2,395.84
2,395.84
7,054.18
705.42
1,300.00
1,425.00
2,725.00
81.75
10,566.34
10,566.34
14,088.46 2,113.27 16,201.73
680.60
544.69
1,006.25
4,193.00
400.00
650.00
148.75 7,623.29
381.16
950.00
1,300.00 2,250.00
67.50
10,321.95
34.41
1,071.25
4,193.00
400.00
148.75 5,813.00
290.65
950.00
1,300.00 2,250.00
67.50
8,421.15
84.21
MATERIAL PRICES
1 Steel
2 Masonry
3 Roofing Materials
4 Electrical
5 Doors & Windows -glass, hingers etc.
6 Painting
7 Waterproofing
8 Floor / Wall / Ceiling Finishes
9 Plumbing / Sanitary fittings
10 Ready Mix Concrete
11 Timber
12 Tools & Equipment
13 Miscellaneous Materials
14 Labour / Hire Charges
15 Orange Electrical price list
16 Habour
17 Micro Partition
18 Labour Rate
Main Index
Code Category Description Remarks Unit
Steel Material
S Steel Tor steel 10,12,16,20,25 Mton
S Steel M.S rounds 10,12 Mton
S Steel M.S rounds 16,21 Mton
B Bunding wire G18 Kg
A Angle iron Size 1"x1"1/8" 6mts
A Angle iron Size 2"x2"x3mm 6mts
A Angle iron Size 2"x2"x5mm 6mts
A Angle iron Size 3"x3"x 6mm 6mts
A Angle iron Size 4"x4"x6mm 6mts
A Angle iron Size 11/2"x11/2"x3mm 6mts
Angle iron Size 50x50x6mm 5.8mts
A Aluminium flat Size 1"x3mm 12L.ft
A Aluminium box Size 2"x1" 12L.ft
A Aluminium box Size 2"x2"x3mm 6mts
A Aluminium box 4" Flat iron -6mm 6mts
A Aluminium box 3"x3" 6mts
A Channel 100x50 "C" Chanel
A Channel 150x75 "C" Chanel
A Channel 200x100 "C" Chanel 6mts
A Channel 150x65x20mm 2.3mm thick Lm
A Channel 100x50x20mm 2.0mm thick Lm
G G.I pipe 1/2" dia meadium duty 6mtr
G G.I pipe 1/2" pipe 6mtr
G G.I pipe 3/4" pipe Pakistan 6mtr
G G.I pipe 1" dia meadium duty 6mtr
G G.I pipe 1.5" dia meadium duty 6mtr
G G.I pipe 1 1/2" pipe 6mtr
G G.I pipe 1 1/4" pipe heavy 6mtr
G G.I pipe 2" dia meadium duty 6mtr
G G.I pipe 2" dia Pakistan 6mtr
G G.I pipe 3" dia meadium duty 6mtr
G G.I pipe 4" dia meadium duty 6mtr
Index
G G.I pipe 4" dia 6mtr
G G.I plain sheet G 18 8'x4' Sheet
G G.I plain sheet G 22 8'x3' Sheet
G G.I plain sheet G 30 8'x3' Sheet
G G.I welding mesh G10 2"x2" (12'x7') Sheet
B Box iron 1/2"x 1/2" x 6 mm box iron
B Box iron 1" x 1" x 6 mm box iron
B Box iron 25 x 25 x 3 mm box iron
F Flat iron Size 3/4"x1/4" 6mtr
F Flat iron Size 1/2"x1/4" 6mtr
F Flat iron Size 1"x1/4" 6mtr
F Flat iron Size 1 1/2"x1/4" 6mtr
F Flat iron Size 2"x1/4" 6mtr
F Flat iron Size 4"x1/4" 6mtr
M M.S sheet Size 8'x4'x1/16" Sheet
M M.S sheet Size 8'x4'x1/8" Sheet
M M.S sheet Size 8'x4'x1/4" Sheet
M M.S sheet Size 8'x4'x 10mm Sheet
M M.S sheet Size 8'x4'x 1/2" Sheet
M M.S sheet Size 8'x4'x 15mm Sheet
M M.S sheet Size 8'x4'x 9mm Sheet
S Steel plate MS plate 8'-x4' 3mm Nos
S Steel plate MS plate 8'-x4' 6mm Nos
S Steel plate MS plate 8'-x4' 8mm Nos
S Steel plate MS plate 8'-x4' 10mm Nos
S Stainless steel plate 8'-0" x4'-0" 1.5mm thick type 304 Nos
N Nail wire nail 5-to 8G Nos
N Nail wire nail 10G Nos
N Nail wire nail 12G Nos
N Nail wire nail 14G Nos
W Wire nail 5 to 8G Kg
W Wire nail 10G Kg
W Wire nail 12G Kg
W Wire nail 14G Kg
B Bolts 16mm bolt Nos
B
S Steel "H" beam 8"x4"x7mm thick (22 kg per mtr ) 6m
S Steel "H" beam 8"x8"x11mm thick (50 kg per mtr ) 6m
S Steel "H" beam 10"x5"x8mm thick (26 kg per mtr ) 6m
S Steel "H" beam 14"x7"x6mm thick (41.5 kg per mtr ) 6m
SBRC mesh
Sheet
SBRC mesh
Sheet
SBRC mesh
Sheet
SBRC mesh
Sheet
SBRC mesh
Sheet
SBRC mesh
Sheet
SBRC mesh
Sheet
S wire rod wire rods 6mm Mton
S Barbed wire Barbed wire 25Kg 25kg
C Chicken mesh Sq.ft
C Chequred plate 6mm thick, 8' x 4' sheet Nos
C Sheet pil 450mm width, 6m long Nos
B.R.C fabrick 12'x7" sheets 6mm 8"x8'
B.R.C fabrick 12'x7" sheets 5mm 8"x8'
B.R.C fabrick 12'x7" sheets 6mm 6"x6"
B.R.C fabrick 12'x7" sheets 5mm 6"x6"
B.R.C fabrick 12'x7" sheets 6mm 8"x8'
B.R.C fabrick 12'x7" sheets 3.15mm 2"x2"
B.R.C fabrick 12'x7" sheets 6mm 4"x4''
Currencet price Date Other Remark Telephone Price Date Price
Steel Material
106,400.00 14/8/2009 With VAT ### 3/3/2009 165,000.00
106,400.00 14/8/2009 With VAT ### 3/3/2009 65,700.00
59,000.00
100.00
325.00
810.00 11/4/2009
2,400.00 11/4/2009 875.00
1,600.00
3,000.00
775.00
2,400.00 27/5/2009
230.00
898.00 24/09/2008 480.00
2,400.00
3,000.00
4,394.00 10/10/2008
5,200.00
9,500.00
21,000.00
1,000.00 30/01/2009
740.00 30/01/2009
750.00 575.00
1,180.00 24/09/2008
1,220.00 11/4/2009 1,475.00
4,400.00 11/7/2008 950.00
1,900.00 1,400.00
3,150.00 24/09/2008
2,050.00 11/4/2009
8,850.00 11/7/2008 1,900.00
4,220.00 11/4/2009
3,300.00
4,300.00
1,050.00 24/09/2007
2,250.00
1,375.00
475.00
3,800.00 9/2/2009 1,375.00
2,200.00
850.00 11/4/2009
700.00 11/4/2009
650.00 27/4/2009 300.00
390.00 27/4/2009
495.00 27/4/2009 350.00
800.00 27/4/2009
575.00
1,300.00
1,800.00
2,700.00
5,300.00
35,000.00 6/5/2008 8,500.00
10,500.00
14,000.00
31,500.00 6/5/2008
6,900.00
14,000.00
18,500.00
34,000.00 12/8/2008
17,000.00 3/3/2009 Nawaloka 0115-323023
82.80
82.80
86.30
88.50
160.00 5/8/2008
170.00 5/8/2008
170.00 5/8/2008
170.00 5/8/2008
50.00
22,500.00 6/5/2008
52,000.00 6/5/2008
26,500.00 6/5/2008
47,300.00 12/8/2008
2,555.00 1,212.17
888.30
3,130.00 1,586.96
1,212.17
1,212.17
3,800.00 12/4/2009 1,332.17
4,500.00 2,380.00
4,818.00 12/8/2008
40.00
15,500.00 27/5/2009
70,000.00 28/09/2010
Date
11/5/2004
11/5/2004
11/5/2004
24/09/2008
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
Code Category Description Remarks Unit
Masonary meterial
C Cement Holcim 50kg bag
C Cement Sevana 50kg bag
C Cement 50kg bag
R Rubble Rubble 6"x 9" Cube
R Rubble Rubble 6"x 4" Cube
B Brick 9"x41/2"x 3" Nos
S Sand Smooth sand Cube
S Sand Rough sand Cube
S Sand Sea sand Cube
M Metal Cube
M Metal 1" metal
M Metal
M Chip metal Cube
L Lime Kg
B Hollow blocks 390x100x190mm (4") SMA holdings Nos
B Hollow blocks 390x150x190mm (6") Nos
B Hollow blocks 390x200x190mm (8") Nos
B Solid blocks 390x100x190m (4") Nos
B Solid blocks 390x150x190mm (6") Nos
B Solid blocks 390x200x190mm (8") Nos
R Regiform sheet 2" thick Nos
P Pergolas 2" x6" L.ft
P Pergolas
P Pergolas
F Fence post 5'-9" Middle post No
F Fence post 7'-7" bend type No
¾" metal
½" metal
Index
F Fence post 8' No
F Fence post 9' No
F Fence post 10' No
F Fence post 8 height 1'6" bent type No
Path edge 50x150x600mm No
Curbe 125x255x915 Nr
Half curbe 125x255x450mm Nr
C Chemefix Kg
E Earth with transport imported 1 cube
Fwk Formwork Formwork Sanken M2
Fwk Formwork Maga M2
Fwk Formwork DG5 M2
Fwk Formwork Mould oill Ltr
Fwk Formwork Base plate No
Fwk Formwork Grease Kg
W Water bars 6" high l.ft
W Water bars 8" high l.ft
W Water bars 9" high l.ft
Q Quarry dust 1 cube
Currencet price Date Other Remark Telephone Price
Masonary meterial
700.00 14/8/2009 785.00
50kg bag
740.00 12/4/2009 630.00
785.00
4,200.00 1/6/2009
3,400.00 23/05/2008
7.00 12/4/2009
7,500.00
7,000.00 12/4/2009
4,900.00 8/3/2009
4,800.00 12/4/2009
3,750.00 12/4/2009
14.50 11/10/2007
42.55 15/02/2010 With out VAT
62.67 15/02/2010
83.05 15/02/2010
59.86 15/02/2010 36.50
82.82 15/02/2010 57.50
115.83 15/02/2010 73.56
330.00
90.00 08.07.2008 With out VAT price
784.00 15/02/2010 Including VAT. SEC 2236279 303.00
1,211.28 15/02/2010 Including VAT 366.00
510.00
693.00
960.00
1,140.00
153.00 15/02/2010
580.00 15/02/2010
297.25 15/02/2010
880.00 17.04.2009 80.00
2,200.00 21/3/2009 1,750.00
1,129.00
1,150.00
20.00
175.00 12/8/2008
460.00 12/9/2009
300.00 12/8/2008
400.00 12/8/2008
400.00 12/8/2008
4,500.00 10/10/2008
Date
12/4/2009
12/4/2009
16/11/07
16/11/07
Code Category Description Remarks Unit
Roofing material
C
R Roofing sheet Zn/Al sheet .47 m²
R Roofing sheet Zn/Al sheet 4.7 2'-6" x 1'-0"=265/= Sq ft
Acrylic Sheet Sq ft
A Asbestos roofing sheet 12 ft (3500 x 1090mm) 4' Nos
A Asbestos roofing sheet 10 ft (3000 x 1090mm) 4' Nos
A Asbestos roofing sheet 8 ft (2500 x 1090mm) 4' Nos
A Asbestos roofing sheet 6 ft (1750 x 1090mm) 4' Nos
G GI roofing sheet 10 ft (3000 x 1090mm) 4' Nos
H Half round tile ( Sinhala Ulu) 420 per sqr Nos
R Calicut tile Flat tile 125 per sqr Nos
R Asbestos covering tile covering tile 450 per sqr Nos
R DSI Tile covering tile 138 per sqr Nos
T Ridge tile Ridge tile Nos
T Ridge tile Zn/Al G18 L.ft
T Ridge tile Asbastos ajestable Pair
R Roofing screws Nos
R
T Tar sheet Tar sheet Sq ft
J J bolt J bolt Nos
S Screws 1 1/4" Nos
J
P Polycorbanete sheet 4mm thick 6'-11" x 19'-0" Nos
P 6mm thick 6'-11" x 19'-0" Nos
Polycorbanete sheet Roller 4'-0" width 4mm thcik L.ft
4'-0" width 1mm thcik L.ft
7'-0" width 2mm thcik L.ft
P
R Insulation Mcfoil sheet Sq.m
R Insulation 50mm ,double side Sq ft
R Insulation mesh Sq ft
Index
R
R Macfoil 5mm double side m2
R 10mm double side m2
R
R Sq ft
R
Sisilation domestic 100
Currencet price Date Other Remark Telephone
Roofing material
970.31 7/7/2008 With VAT
106.00 25/03/2009
150.00
1,685.00 15/2/2010 440 per sq. m Mascons -2325561
1,375.00 15/2/2010
1,165.00 15/2/2010
825.00 15/2/2010
510.00 2/6/2009
20.00 25/03/2009 3600 of one lorry load Randatha Ulu 060-2150285
28.00 25/03/2009
18.00 25/03/2009
150.00 25/03/2009
45.00 11/3/2005
135.00 25/03/2009
45.00
15.00
10.00
5.00 5/8/2008 195/= per 1 kg ( 38 Nos per kg)
8.35
9,000.00 31/2/2010
13,100.00 31/2/2010
560.00 31/2/2010
3,000.00 31/2/2010
1,600.00 31/2/2010
90.00 8/3/2009 077-7772857 /50 /56
26.50 8/3/2009 Roofmart 037-5260269
6.70 8/3/2009 Bor-0112519804
191.00 22/04/2009
338.00 22/04/2009
12.88
Price Date Price Date
Roofing material
1,680.00 5/8/2008 975.00 5/2/2005
1,370.00 5/8/2008 825.00 5/3/2005
1,160.00 5/8/2008 690.00 5/4/2005
820.00 5/8/2008 485.00 5/5/2005
Randatha Ulu 060-2150285
Code Category Description Remarks
Electrical Items
E Switches ( White series ) One gang one way
E Switches ( White series ) One gang two way
E Switches ( White series ) Two gang one way
E Switches ( White series ) Three gang one way
E Switches ( White series ) Four gang one way
E Switches ( White series ) Five gang one way
E Switches ( White series ) Six gang one way
E Switches ( White series ) 20A double pole W/ neon
S Socket outlet 5A switched Socket outlet
S Socket outlet 15A switched Socket with neon
S Socket outlet 15A switched Socket outlet
S Socket outlet 15A switched Socket with neon
S Socket outlet 13A switched Socket outlet
S Socket outlet 13A switched Socket with neon
S Socket outlet TV socket
S Socket outlet Twin TV socket
S Socket outlet Telephone socket outlet 4 line
S Socket outlet Telephone socket outlet 4 line
S Socket outlet Twin Telephone socket outlet 4 line
S Socket outlet Twin Telephone socket with shutter
S Socket outlet
S Socket outlet
S Socket outlet Combine TV & Tel socket
S Socket outlet Data socket with shutter
S Socket outlet Tiwn Data socket with shutter
S Socket outlet 110V shaver socket
C Controllers Hum free fan controller
C Controllers Fan controller with swith 1 gang
C Controllers Light dimmer with swith 1 gang
C Controllers Bell press
Telephone socket shutter ( fast rapid connection)
TwinTelephone socket shutter ( fast rapid connection)
Index
C Controllers Bell push
C Controllers Bell push whether prrof W/indicator
C Controllers Weather proof cover transparent
C Controllers Weather proof cover mat
C Controllers Two way mechanisim dolly only
C Controllers Key switch
C Controllers 45A/ 13A cooker switch
C Controllers Fan controller with 21 gang
C Controllers Light dimmer with 2 gang
C Controllers Tumbler box
C Controllers Sun box
C Controllers Junction box
M MCB 6A ,10A , 16A, 20A, 25A, 32A Single pole 4.5A
M MCB 40A
M MCB 63A
M MCB 6A ,10A , 16A, 20A, 25A, 32A ,40ATwo pole
M MCB 63A
M MCB
M MCB 63A
M MCB 100A
M MCB 6A ,10A , 16A, 20A, 25A, 32A ,40A Four pole
M MCB 63A
M MCB 100A
I Isolater 2P/40A
I Isolater 2P/63A
I Isolater 4P/40A
I Isolater 4P/63A
I Isolater 4P/100A
C Changing over Switches 2P/40A
C Changing over Switches 4P/40A
B Cables- CU/PVC/PVC 2 Core 1.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 1.5mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 4 Core 1.5mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 2 Core 2.5mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 3 Core 2.5mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 4 Core 2.5mm2 Cu/PVC/PVC
6A ,10A , 16A, 20A, 25A, 32A ,40ATheree pole
B Cables- CU/PVC/PVC 2 Core 4mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 4mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 4 Core 4mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 6mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 6mm2 Cu/PVC/PVCB Cables- CU/PVC/PVC 4 Core 6mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 25mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 35mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 50mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 70mm2 Cu/PVC/PVC
B Cables- Cu/XLPE/PVC 2Core 4mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 4mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 6mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 6mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 10mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 10mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 16mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 16mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 3Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 3Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 50mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 70mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 95mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 120mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 150mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 185mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 240mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 300mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 400mm2 Cu/XLPE/PVC
B Cables- CU/PVC/PVC 1 Core x 1 mm² Cu/PVC / PVC earth
B Cables- CU/PVC/PVC 1 Core x 1.5 mm² Cu/PVC /PVC earth
B Cables- CU/PVC/PVC 1 Core x 2.5 mm² Cu/PVC / PVC earth
B Cables- CU/PVC/PVC 1 Core x 4 mm² Cu/PVC /PVC earth
B Cables- CU/PVC/PVC 1 Core x 6 mm² Cu/PVC /PVC earth
B Cables- CU/PVC/PVC 1 Core x 10 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 16 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 25 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 35 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 50 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 70 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 95 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 120 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 150 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 185 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 240 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC 1 Core x 300 mm² Cu/PVC/PVC earth
B Cables- CU/PVC/PVC earth
B Cables- CU/PVC/PVC earth
B Cables- XLPE/SWA/PVC 2 Core x 1 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 1 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 1 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 2.5 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 2.5 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 2.5 mm² Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 4 mm² Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 4 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 4 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 6 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 6 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 6 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 10 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 10 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 10 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 16 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 16 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 16 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 25 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 25 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 25 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 2 Core x 35 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 3 Core x 35 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 35 mm² Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 50 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 70 mm²Cu/ XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 95 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 120 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 150 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 185 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 240 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 300 mm² Cu/XLPE/SWA/PVC armouredB Cables- XLPE/SWA/PVC 4 Core x 400 mm² Cu/XLPE/SWA/PVC armoured
Cables single core - Cu/PVC/PVC
Cables single core - Cu/PVC/PVC
Cables single core - Cu/PVC/PVC 1/1.13 mm Cu/PVC/PVC 1mm2
Cables single core - Cu/PVC/PVC 1/1.38 mm Cu/PVC/PVC 1.5mm2
Cables single core - Cu/PVC/PVC 7/0.53 mm Cu/PVC/PVC - S 1.5mm2
Cables single core - Cu/PVC/PVC 7/0.53 mm Cu/PVC/PVC - T 1.5mm2
Cables single core - Cu/PVC/PVC 7/0.67 mm Cu/PVC/PVC - S 2.5mm2
Cables single core - Cu/PVC/PVC 7/0.67 mm Cu/PVC/PVC - T 2.5mm3
Cables single core - Cu/PVC/PVC 7/0.85 mm Cu/PVC/PVC - S 4mm2
Cables single core - Cu/PVC/PVC 7/0.85 mm Cu/PVC/PVC - T 4mm2
Cables single core - Cu/PVC/PVC 7/1.04 mm Cu/PVC/PVC - S 6mm2
Cables single core - Cu/PVC/PVC 7/1.04 mm Cu/PVC/PVC - T 6mm2
Cables single core - Cu/PVC/PVC 7/1.35 mm Cu/PVC/PVC - S 10mm2
Cables single core - Cu/PVC/PVC 7/1.35 mm Cu/PVC/PVC - T 10mm2
Cables single core - Cu/PVC/PVC 7/1.70 mm Cu/PVC/PVC - S 16mm2
Cables single core - Cu/PVC/PVC 7/1.70 mm Cu/PVC/PVC - T 16mm2
Cables single core - Cu/PVC/PVC 7/2.14 mm Cu/PVC/PVC 25mm2
Cables single core - Cu/PVC/PVC 19/1.35 mm Cu/PVC/PVC - S 25mm2
Cables single core - Cu/PVC/PVC 19/1.53 mm Cu/PVC/PVC - S 35mm2
Cables single core - Cu/XLPC/PVC
Cables single core - Cu/XLPC/PVC 19/1.78 mm Cu/XLPC/PVC - S 50mm2
Cables single core - Cu/XLPC/PVC 19/2.14 mm Cu/XLPC/PVC - S 70mm2
Cables single core - Cu/XLPC/PVC 19/2.52 mm Cu/XLPC/PVC - S 95mm2
Cables single core - Cu/XLPC/PVC 37/1.78 mm Cu/XLPC/PVC - S 95mm2
Cables single core - Cu/XLPC/PVC 37/2.03 mm Cu/XLPC/PVC - S 120mm2
Cables single core - Cu/XLPC/PVC 37/2.25 mm Cu/XLPC/PVC - S 150mm2
Cables single core - Cu/XLPC/PVC 37/2.52 mm Cu/XLPC/PVC - S 185mm2
Cables single core - Cu/XLPC/PVC 61/2.25 mm Cu/XLPC/PVC - S 240mm2
Cables single core - Cu/XLPC/PVC 61/2.52 mm Cu/XLPC/PVC - S 300mm2
Cables single core - Cu/XLPC/PVC 61/2.85 mm Cu/XLPC/PVC - S 400mm2
Cables single core - Cu/XLPC/PVC 61/3.20 mm Cu/XLPC/PVC - S 500mm2
Cables single core - Cu/XLPC/PVC 91/3.00 mm Cu/XLPC/PVC - S 630mm2
D
C Ceiling Rose
H Holders
R Round block
B Brass screws 1"
B Brass screws 1 1/2"
W Flexible wire
W
Steel condute pipe 50mm dia , Length - 12' 6"
Ceiling mounted sprit AC unit 18000 Btu/hr
24000 Btu/hr
48000 Btu/hr
Unit Currencet price Date Other Remark Telephone Price
Electrical Items
Nos 108.00 8/3/2009 84.00
Nos 172.00 8/3/2009 131.00
Nos 184.00 8/3/2009 144.00
Nos 265.00 8/3/2009 218.00
Nos 355.00 8/3/2009 291.00
Nos 442.00 8/3/2009 364.00
Nos 470.00 8/3/2009 440.00
8/3/2009
Nos 758.00 8/3/2009 617.00
8/3/2009
Nos 307.00 8/3/2009 249.00
Nos 354.00 8/3/2009 271.00
Nos 378.00 8/3/2009 304.00
Nos 451.00 8/3/2009 331.00
Nos 325.00 8/3/2009 257.00
Nos 8/3/2009
Nos 507.00 8/3/2009 400.00
Nos 642.00 8/3/2009 Kevilton 600.00
Nos 507.00 8/3/2009 400.00
Nos 470.00 8/3/2009 440.00
Nos 642.00 8/3/2009 600.00
Nos 631.00 8/3/2009 590.00
Nos 406.00 8/3/2009 380.00
Nos 610.00 8/3/2009 570.00
Nos 589.00 8/3/2009 550.00
Nos 1,077.00 8/3/2009 915.00
Nos 1,252.00 8/3/2009 1,170.00
Nos 3,210.00 8/3/2009 3,000.00
8/3/2009
Nos 819.00 8/3/2009 700.00
Nos 760.00 8/3/2009 587.00
Nos 760.00 8/3/2009 587.00
Nos 260.00 8/3/2009 195.00
Nos 260.00 8/3/2009 195.00
Nos 500.00 8/3/2009 400.00
Nos 230.00 8/3/2009 185.00
Nos 230.00 8/3/2009 185.00
Nos 78.00 8/3/2009 73.00
Nos 3,010.00 8/3/2009 2,800.00
Nos 1,290.00 8/3/2009 1,200.00
Nos 667.00 8/3/2009 60.00
Nos 667.00 8/3/2009 620.00
Nos 102.00 8/3/2009 70.00
Nos 32.00 8/3/2009 30.00
Nos 29.00 8/3/2009 27.00
Nos 529.00 9/8/2008 With VAT -Kalani cable 0112-2574511-5
Nos 1,035.00 9/8/2008
Nos 1,610.00 9/8/2008
Nos 1,955.00 9/8/2008
Nos 4,025.00 9/8/2008
Nos 2,875.00 9/8/2008
Nos 5,750.00 9/8/2008
Nos 19,550.00 9/8/2008
Nos 7,130.00 9/8/2008
Nos 9,775.00 9/8/2008
Nos 21,850.00 9/8/2008
Nos 1,322.50 9/8/2008
Nos 1,955.00 9/8/2008
Nos 5,750.00 9/8/2008
Nos 6,325.00 9/8/2008
Nos 8,050.00 9/8/2008
Nos 3,680.00 9/8/2008
Nos 4,600.00 9/8/2008
1m 280.00 ACL CABLE1m 340.001m 410.001m 380.001m 500.001m 560.00
1m 760.001m 820.00
1m 840.00
1m 950.001m 1080.00
1m 1140.00
1m 1190.00
1m 1590.00
1m 1830.00
1m 1700.00
1m 2060.00
1m 2400.00
1m
1m
1m
1m
1m 2280.00
1m 2750.00
1m 3160.00
1m 3050.00
1m 3390.00
1m 3840.00
1m 5240.00
1m 7020.00
1m 9660.00
1m 11370.00
1m 14200.00
1m 19040.00
1m 22230.00
1m 28740.00
1m 38220.00
100m 1,810.00 3/3/2009 1750.00
100m 3760.00100m 5540.00100m 8650.00100m 12570.00100m 20710.00100m 31590.00100m 54500.00100m 70410.00100m 86700.00100m 143010.00100m 179510.00100m 248650.00100m 282570.00100m 353100.00100m 522580.00100m 668040.00
1m 290.00
1m 350.00
1m 430.001m 390.001m 520.001m 580.00
1m 800.001m 860.001m 880.001m 1000.001m 1130.001m 1190.001m 1250.001m 1670.001m 1920.001m 1780.001m 2160.001m 2520.001m 2400.001m 2890.001m 3320.001m 3210.001m 3560.001m 4040.00
1m 5510.001m 7380.001m 10160.001m 11960.001m 14940.001m 20040.001m 23400.001m 30250.001m 40230.00
100m 1850.00100m 3830.00100m 4160.00100m 7920.00100m 6150.00100m 11540.00100m 9610.00100m 18170.00100m 13960.00100m 24930.00100m 23010.00100m 41340.00
100m 35090.00
100m 62420.00
100m 56940.00
100m 60550.00
100m 78230.00
100m 96330.00
100m 158890.00
100m 199450.00
100m 205450.00
100m 276270.00
100m 313960.00
100m 392330.00
100m 580640.00
100m 742260.00
100m 908330.00
100m 1173420.00
100m 1468140.00
Nos 35.00
Nos 65.00
Nos 20.00
Nos 10.00
Nos 5.00
Nos 25.00
3,500.00
99,900.00 LG brand
127,900.00
429,000.00
Date
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
Code Category Description
Doors windows materila
E Iron mongery
B Brass screws 1"
B Brass screws 3/4"
B Brass screws 1/2"
B 4"
B Barrel bolt 6"
B 8"
B Barrel bolt 12"
B Barrel bolt 1' 6"
24"
B
B 4"
B 6"
B 8"
B 10"
B 12"
B 18"
B 2"
T 2 1/2"
T 3"
T 4"
T 5"
T 6"
T 12"
T 14"
T 16"
B Butt hinges 6"x 4"
B Butt hinges 6"x 6"
B Butt hinges 3"x 4"
B Butt hinges 2 1/2"x 4"
Barrel bolt Brass
Barrel bolt Brass
Barrel bolt Brass
Barrel bolt stinless steel
Barrel bolt stinless steel
Barrel bolt stinless steel
Barrel bolt stinless steel
Barrel bolt stinless steel
Barrel bolt stinless steel
Barrel bolt stinless steel
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Tower Bolts Metal
Index
B 3"x 4"
H 2" x 2"
H 3" x 2"
H 3" x 3"
H 4" x 2"
H 4" x 2 1/2"
H 4" x 3"
H 4" x 4"
H 5" x 3"
H 5" x 4"
H 5" x 5"
H 6" x 4"
H 6" x 6"
H 4"
H 5"
H 6"
H 8"
H 10"
H 12"
H 14"
H 16"
B Brass barrel nipple 1/2" diameter
B Brass barrel nipple
B Brass barrel nipple
C Casement fastner
C Casement fastner
C Casement fastner
C 10"
C Casement stay
C Casement stay
C Casement stay
M Mortice lock
M Mortice lock
M Mortice lock
U Union lock
Butt hinges Brass
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Butt Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Heavy Tee Hinges Metal
Casement stays Metal
H 2 1/2"
H 3"
H 4"
H 5"
H 6"
W Left
W Right
W
S Sliding gear
S Sliding gear
S Sliding gear
G Glass Tempeted glass 12'-0" x 8'-0'
G Glass 5mm thick clear glass
Glass 6mm thick clear glass
G Glass 6.3mm thick laminated clear glass
G Glass Sand blast glass 6mm thick one side
G Glass Pencil edgge
P Plywood doors Ordinary/MR 2'-3"
P Plywood doors Ordinary/BR 2'-3'
P Plywood doors Teak one side MR 2'-3"
P Plywood doors Teak one side BR 2'-3"
P Plywood doors Teak two side MR 2'-3"
P Plywood doors Teak two side BR 2'-3'
P Plywood doors
P Plywood doors Ordinary/MR 2'-6"
P Plywood doors Ordinary/BR 2'-6'
P Plywood doors Teak one side MR 2'-6"
P Plywood doors Teak one side BR 2'-6"
P Plywood doors Teak two side MR 2'-6"
P Plywood doors Teak two side BR 2'-6'
P Plywood doors
Hasps & Staples Metal
Hasps & Staples Metal
Hasps & Staples Metal
Hasps & Staples Metal
Hasps & Staples Metal
Window Fasterners Metal
Window Fasterners Metal
Window Rings Metal
P Plywood doors Ordinary/MR 2'-9"
P Plywood doors Ordinary/BR 2'-9'
P Plywood doors Teak one side MR 2'-9"
P Plywood doors Teak one side BR 2'-9"
P Plywood doors Teak two side MR 2'-9"
P Plywood doors Teak two side BR 2'-9'
P Plywood doors
P Plywood doors Ordinary/MR 3'-0"
P Plywood doors Ordinary/BR 3'-0'
P Plywood doors Teak one side MR 3'-0"
P Plywood doors Teak one side BR 3'-0"
P Plywood doors Teak two side MR 3'-0"
P Plywood doors Teak two side BR 3'-0'
P Plywood doors
P Plywood doors Ordinary/MR 3'-6"
P Plywood doors Ordinary/BR 3'-6'
P Plywood doors Teak one side MR 3'-6"
P Plywood doors Teak one side BR 3'-6"
P Plywood doors Teak two side MR 3'-6"
P Plywood doors Teak two side BR 3'-6'
F Fibre Window
D Finish dooor 3'-6" x 7'-0" Jack
D Finish dooor 3'-6" x 7'-0" Mahogani
D
D Roller door Zn/Al
D Roller door
D Roller door Moter
D
Remarks Unit Currencet price DateOther Remark
Doors windows materila
No 8.35
No 5.58
No
No 250.00 29/12/2008
No 490.00 13/10/2008
No 435.00 29/12/2008
No 550.00
No 2,600.00 13/10/2008
No 1,800.00 29/12/2008
No 185.00 4/3/2009
No 195.00 4/3/2009
No 305.00 4/3/2009
No 415.00 4/3/2009
No 520.00 4/3/2009
No 550.00 4/3/2009
No 52.00 4/3/2009
Powder coated finish-Metco Gold 1 No 104.00 8/3/2009
1 No 138.25 8/3/2009
1 No 152.75 8/3/2009
1 No 168.75 8/3/2009
1 No 180.25 8/3/2009
1 No 325.50 8/3/2009
1 No 364.00 8/3/2009
1 No 410.00 8/3/2009
pair 1,100.00
pair
pair 360.00
pair 275.00
Indian No 180.00 29/12/2008
Powder coated finish-Metco Gold 1 No 49.00 8/3/2009
1 No 65.00 8/3/2009
1 No 77.75 8/3/2009
1 No 93.25 8/3/2009
1 No 101.00 8/3/2009
1 No 126.75 8/3/2009
1 No 181.75 8/3/2009
1 No 190.75 8/3/2009
1 No 227.75 8/3/2009
1 No 271.25 8/3/2009
1 No 286.75 8/3/2009
1 No 358.50 8/3/2009
Powder coated finish-Metco Gold 1 No 109.50 8/3/2009
1 No 126.50 8/3/2009
1 No 165.25 8/3/2009
1 No 248.00 8/3/2009
1 No 274.50 8/3/2009
1 No 309.00 8/3/2009
1 No 523.75 8/3/2009
1 No 571.50 8/3/2009
No
Powder coated finish-Metco Gold 1 No 190.75 8/3/2009
1 No 2,910.00
2,900.00
Powder coated finish-Metco Gold 1 No 50.75 8/3/2009
1 No 58.50 8/3/2009
1 No 109.00 8/3/2009
1 No 119.00 8/3/2009
1 No 216.00 8/3/2009
Powder coated finish-Metco Gold 1 No 102.00 8/3/2009
1 No 102.00 8/3/2009
Powder coated finish-Metco Gold 1 No 69.00 8/3/2009
11 3,360.00 15/10/2008
11 2,670.00 15/10/2008
8 2,170.00 15/10/2008
Sq.ft 450.00 4842
without VAT Sq.ft 75.00 3/3/2009 Asoka glass
with VAT Sq.ft 100.00 27/4/2009
without VAT Sq.ft 280.00 3/3/2009 Asoka glass
Sand blast glass 6mm thick one side Sq.ft 215.00 11/12/2008
L.ft 70.00 11/12/2008
Nos 3,950.00 8/3/2009
Nos 4,100.00 8/3/2009
Nos 4,100.00 15/02/2007
Nos 4,250.00 15/02/2007
Nos 5,100.00 15/02/2007
Nos 5,250.00 15/02/2007
Nos 4,000.00 8/3/2009
Nos 4,150.00 8/3/2009
Nos 4,250.00 15/02/2007
Nos 4,400.00 15/02/2007
Nos 5,200.00 15/02/2007
Nos 5,350.00 15/02/2007
Nos 4,125.00 8/3/2009
Nos 4,275.00 8/3/2009
Nos 4,350.00 15/02/2007
Nos 4,500.00 15/02/2007
Nos 5,250.00 15/02/2007
Nos 5,400.00 15/02/2007
Nos 4,725.00 8/3/2009
Nos 4,875.00 8/3/2009
Nos 4,700.00 15/02/2007
Nos 4,850.00 15/02/2007
Nos 5,650.00 15/02/2007
Nos 5,800.00 15/02/2007
Nos 4,850.00 8/3/2009
Nos 5,000.00 8/3/2009
Nos 4,800.00 15/02/2007
Nos 4,950.00 15/02/2007
Nos 5,750.00 15/02/2007
Nos 5,900.00 15/02/2007
1 Sq.ft 1200.00-3000.00 8/3/2009
Nos 20,000.00 8/3/2009
Nos 14,500.00 8/3/2009
Sq.ft 700.00 21/04/2009
16' 0" x 8' 0" Nos 30,000.00 21/04/2009
Nos 35,000.00 21/04/2009
Telephone Price Date
Doors windows materila
190.00 13/10/2008
20.00
0112-314820-2
90.00 3/3/2009
0112-314820-2
2,800.00 15/02/2007
2,950.00 15/02/2007
2,900.00 15/02/2007
3,050.00 15/02/2007
3,100.00 15/02/2007
3,250.00 15/02/2007
3,600.00 15/02/2007
3,750.00 15/02/2007
3,850.00 15/02/2007
4,050.00 15/02/2007
Code Category Description
Painting Items
Pentalite Emulsion Paints
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Emulsion paint -CIC
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Eanemal paint
P Painting Items wood paint
P Painting Items Aluminium paint
P Painting Items Roof paint
P Painting Items Aluminium sealer
P Painting Items Alkali Resistant plaster primer
P Painting Items G.I. Adhession promoter
P Painting Items Q/D Zinc phosphate red primer
P Painting Items Q/D MIO paint silver Grey
P Painting Items Q/D Metal primer Zinc phospate yellow / block
P Painting Items crack bridging wall primer
P Painting Items Colour enhancing wall primer
Painting Items Q/D P/U floor paint
Painting Items Epoxy paint white
Painting Items Blackboard paint
Painting Items Epoxy floor paint
Painting Items Bathroom paint
Painting Items Heat resistance paint
Painting Items Masonary sealer
Painting Items Weathersshield texture base
Painting Items Interior texture base
Painting Items Acrylic wall filler
Painting Items Acrylic wall putty
Painting Items Flexible filler
Painting Items Masonary water repellant
Painting Items Super grip filler
Painting Items Master palette emulsion ( dark colours)
Painting Items Master palette emulsion ( light colours)
Index
Painting Items Master palette weathershield ( dark colours)
Painting Items Master palette weathershield ( light colours)
Painting Items Master palette gloss ( dark colours)
Painting Items Master palette gloss ( light colours)
Painting Items Anicorrsive paint
Painting Items Anicorrsive paint
Painting Items Polyurethane varnish -Gloss
Painting Items Polyurethane varnish -Matt
Painting Items Coach finish varnish - gloss
Painting Items Coach finish varnish - matt
Painting Items Exterior varnish - gloss
Painting Items Exterior varnish - matt
Painting Items Parquet varnish
Painting Items Teak oil
Painting Items Woodfinish gloss lacquer
Painting Items Woodfinish stain
Painting Items Sanding sealer concentrate
Painting Items Sanding sealer rosewood
Painting Items woodfiller ( clear)
Painting Items Wood sheen ( Mshogany , Teak , Walnut, Ebony, Pine)
Painting Items Woodstain ( Mshogany , Teak , Walnut, Jackwood )
Painting Items Thinner 850-8
Painting Items Epoxy thinner 850-761
Painting Items Mineral turpentine
Painting Items Parquet varnish thinner
Painting Items Enamel paint
Painting Items sand paper
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Roller Brush
Painting Items Oil primer
Painting Items Oil primer
Painting Items Oil primer
Painting Items Oil primer
Painting Items Filler
Painting Items Filler
Painting Items Filler
Painting Items Filler
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Thinner (Autocare N/C Super)
Painting Items Thinner (Autocare N/C GP)
Painting Items Thinner (Autocare GP)
Painting Items Thinner (Asian Paint Epoxy)
Painting Items Thinner (Asian Paint Mineral Turpentine)
Painting Items Thinner (Metacare Stoving Thinner 050)
Painting Items Thinner (Metacare Stoving Thinner CCS)
Painting Items Thinner (Autocare Acrylic Thinner)
Wood preservitive
Wood preservitive
Wood primer
Wood primer
Wood primer
Wall primer
Wall primer
Wood stain
Wood stain
Wood stain
Wood finish stain
Wood finish stain
Wood finish stain
Wood finish stainSteel primer
Totalcoat
Painting Water base
Painting Spray paint
Wall putty 28Kg bag
Painting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting ItemsPainting Items
Remarks Unit Currencet price Date Other Remark
Painting Items
11/8/2008 CIC price list -11th Aug 2008
White & all colours Ltr 550.00 16/02/2010
Brilllian white Ltr 700.00
weathershield all colour Ltr 750.00 16/02/2010
Dulux gloss finish Ltr
White & all colours Ltr 768.00
Brilllian white Ltr 780.00
Dulux egshell finish ( Blac Ltr 857.00
Stain wood Ltr 1,029.00
bright aluminium Ltr 844.00
Roofshied (water base ) all Ltr 879.00
Aluminium paint Ltr 723.00
Ltr 805.00
Ltr 494.00
Ltr 928.00
Ltr 1,074.00
Ltr
Ltr 955.00
Ltr 851.00
Ltr 884.00
Ltr
Ltr
Ltr 1,085.00
Ltr 892.00
Ltr 1,619.00
Ltr 560.00
Ltr 339.00
Ltr 328.25
Ltr 416.00
Ltr 631.00
Ltr 758.00
Ltr 564.50
400 gram 182.00
Ltr 705.00
Ltr 648.00
Ltr 1,077.00
Ltr 1,017.00
Ltr 916.00
Ltr 818.00
Black, red, Oxide, Brown Ltr 586.00
Grey , Green Ltr 601.00
Ltr 797.00
Ltr 879.00
Ltr 697.00
Ltr 767.00
Ltr 895.00
Ltr 1,191.00
Ltr 867.00
Ltr 472.75
Ltr 980.00
Ltr 980.00
Ltr 1,069.00
Ltr 1,156.00
Ltr
Wood sheen ( Mshogany , Teak , Walnut, Ebony, Pine) Ltr 781.00
Ltr 845.00
Ltr
Ltr 260.00
Ltr 432.75
Ltr 262.75
Ltr 351.00
Enamel paint Ltr 622.00
Nos 42.50
1/2" 100.00 8/3/2009
3/4" 115.00 8/3/2009
1" 145.00 8/3/2009
1 1/2" 185.00 8/3/2009
2" 280.00 8/3/2009
2 1/2" 325.00 8/3/2009
3" 400.00 8/3/2009
6" 595.00 8/3/2009
9" 595.00 8/4/2009
10 Ltr Bucut 2,844.00
4 Ltr Bucut 1,138.00
1 Ltr Ltr 337.00
Ltr 525.00
Permoglaze Enamel
Eggshell Finish 4 Ltr 2,168.00
Matt Finish 4 Ltr 2,071.00
1 Ltr 553.00
4 Ltr 2,184.00 8/3/2009
4 Ltr 1,511.00 8/3/2009
4 Ltr 1,280.80 8/3/2009
4 Ltr 2,499.00 8/3/2009
4 Ltr 1,607.00 8/3/2009
4 Ltr 1,468.00 8/3/2009
Normal 4 Ltr 1,352.00 8/3/2009
4 Ltr 2,268.00 8/3/2009
1 Ltr 242.50 5/8/2008
Asian paints Aluminium wo 4 Ltr 2,077.00
1 Ltr 555.00
0.5 Ltr 301.00
1 312.75
4 Ltr 2,300.00 575
300 ml 230.00
4 Ltr 2,906.00
1 Ltr 795.00
500 ml 432.00
1 Ltr 973.00 8/3/2009
Bucut 28 kg 2,800.00 8/3/2009
Sq.ft 88.00 8/3/2009
Sq.ft 88.00 8/3/2009
bag 2,100.00
Telephone Price Date
Painting Items
450.00
167.50 9/2/2005
Code Category Description Remarks Unit Currencet price
Waterproofing material
Waterproofing material Febmix iLtr
Waterproofing material M.C. 31 1Ltr
Waterproofing material DPC tar bitumen gal 530.00
Waterproofing material shell fintkote type 3 Ltr 231.00
Waterproofing material shell fintkote type 5 Ltr 242.00
W Water Proofing 875.00
W Water Proofing Barralastic Without Screed 1Sq.ft 96.00
1 m2
Index
Date Other RemarkTelephone Price Date
Waterproofing material
###
27.25
26/04/2009
Code Category Description Remarks
Floor / wall / Ceiling finishing material
Colour cement Red super dark
Colour cement Dark brown
Colour cement Black special
Colour cement Briliant blue extra
Colour cement Green tennis court
Colour cement White cement
Colour cement White cement
T Tile 6" x 6"T Tile 8" x 8"T Tile 12" x 12"T wall tile 6" x 6"T wall tile 8" x12"T wall tile 8" x 8"T wall tile 12" x 12"T
T wall tile 200mm wide Boder tileT
T
T Tile Slate tile 1'-0' 1'-0"T
T Concrete paving slab 12" x12"T Concrete paving slab 6" x 6"T Concrete paving slab 16" x16"T Concrete paving slab 300x300x50mm Natural
Colour
Natural ( with R/F )
T Tile Mosaic tileT
T Tile Terracota tile 8" x 8"T Tile Terracota tile 1'-0" x 1'-0"T
T Tile Cement Tile 1'-0" x 1'-0"Tile 16"x16"
Index
Tile 12" x12" StaircaseTile 16" x16"Tile 12" x12" bathroom floor
T Tile 12" x12" Bathroom wallTile
G Granite Blue fal
G Granite Shiva Gold
G Granite Green Galaxy
G Granite Natural stone 4" x8"
G Granite Natural stone 12" x6"
G
Rough granite "Mirisgal" 1'-0" x1'-0"
Rough granite Coble stone 9" x 5"Rough granite Rubble stone (1'0"x1'0" )
Rough granite Pebbles (50 Kg)
T Tile grout
Terrazzo chips
Titanium
C Construction grout 25Kg sack
P External Paving tile Including labour cost
Adhesive glue
Interlocking Paving With Quary Dust
C Ceiling sheet 3.2mm superflex sheet 4'-0" x 4'-0"
C Ceiling sheet 6mm superflex sheet 8'-0" x 4'-0"
C
C Ceiling sheet 9mm Gypsum sheet 4'-0" x 4'-0"
C Ceiling sheet 12mm Gypsum sheet 4'-0" x 4'-0"
C Ceiling sheet Asbestos sheet 4'-0" x4'-0"
C
C Ceiling sheet 1 1/2"x1 1/2" cove moulding
C Ceiling sheet 1/2"x1/2" beading
C
T Lumumidella plank 6" thick width ( with planing )
Ceiling finishes
Ceiling finishes15mm thick
Ceiling finishes4.5mm thick
Concealed ceiling with bulk head system using " Euro frame" suspended fames work
Mineral fiber ceiling system with 600x600mm frame work
Cement finber board / Moisture resistant 600x600x4.5mm thick
Unit Currencet price Date Other Remark Telephone Price
Floor / wall / Ceiling finishing material
kg 456.00 9/8/2008 Mascons Ltd 2325561-3
kg 589.25 9/8/2008 Mascons Ltd
kg 493.25 9/8/2008 Mascons Ltd
kg 640.50 9/8/2008 Mascons Ltd
kg 547.25 9/8/2008 Mascons Ltd
kg 33.80 9/8/2008 Mascons Ltd
bag 1,300.00
80.00 1/6/2009
150.00 1/6/2009 138/= to 173/=
Nos 210.00
Nos 78.75 9/8/2008 Mascons Ltd with VAT
Nos 37.00
Nos 250.00 12/12/2008
Nr 88.00 15/102/2010 SMA holdings
Nr 123.00 15/102/2010
Nr 147.00 15/102/2010
Sq.ft 750.00
nos 28.00 25/03/2009
nos 60.00 25/03/2009
nos 180.00 1/6/2009
Sq.ft 160.00 40,277.00
Sq.ft 145.00 40,277.00
Sq.ft 132.00 40,277.00
Sq.ft 140.00 40,277.00
Sq.ft 104.00
Sq.ft 2,650.00 12/8/2008
Sq.ft 975.00 12/8/2008
Sq.ft 1,700.00 12/8/2008
Nos 83.00 12/8/2008
Nos 274.00 12/8/2008
Nos 350.00 20/03/2009
Nos 200.00
Sq.ft 3,000.00
50 kg 7,500.00
kg 155.00
Cwt 950.00
kg 525.00 12/4/2009
25Kg sack ###
Sq.ft 185.00 8/3/2009
Sq.ft 100.00 8/4/2009
Sq.ft 165.00 9/11/2009 011-2796003
Pavex(Pvt)Ltd
Sheet 400.00 24/10/2008
Sheet 1,840.00 12/4/2009
Sheet 1,175.00 26/4/2009
Sheet 1,350.00 26/4/2009
Nos 380.00 15/2/2010 255.55
Sq.ft 56.00 5/8/2008 NAM timber Tel 2818800
m2 3,775.00 3/11/2008 Access ( Rate without VAT)
m2 2,000.00 3/11/2008 Access ( Rate without VAT)
m2 2,167.00 3/11/2008 Access ( Rate without VAT)
Date
Code Category Description Remarks
Plumbing material
P PVC pipe 20mm -1/2" Type 1000
P PVC pipe 25mm - 3/4" Type 1000
P PVC pipe 32mm - 1" Type 1000
P PVC pipe 40mm - 11/4" Type 1000
P PVC pipe 50mm - 11/2" Type 1000
P PVC pipe 63mm - 2" Type 1000
P PVC pipe 75mm - 2 1/2" Type 1000
P PVC pipe 90mm - 3" Type1000
P PVC pipe 110mm - 4" Type1000
P PVC pipe 140mm - 5" Type1000
P PVC pipe 160mm - 6" Type1000
P PVC pipe 225mm - 8" Type1000
P PVC pipe 280mm - 10" Type 1000
P PVC pipe 315mm - 12" Type 1000
P PVC pipe 32mm - 1" Type 600
P PVC pipe 40mm - 11/4" Type 600
P PVC pipe 50mm - 11/2" Type 600
P PVC pipe 63mm - 2" Type 600
P PVC pipe 75mm - 2 1/2" Type 600
P PVC pipe 90mm - 3" Type 600
P PVC pipe 110mm - 4" Type 600
P PVC pipe 140mm - 5" Type 600
P PVC pipe 160mm - 6" Type 600
P PVC pipe 225mm - 8" Type 600
P PVC pipe 280mm - 10" Type 600
P PVC pipe 315mm - 12" Type 600
P PVC pipe 50mm - 11/2" Type 400
P PVC pipe 63mm - 2" Type 400
P PVC pipe 75mm - 2 1/2" Type 400
P PVC pipe 90mm - 3" Type 400
P PVC pipe 160mm - 6" Type 400
P PVC pipe 225mm - 8" Type 400
P PVC pipe 280mm - 10" Type 400
P PVC pipe 315mm - 12" Type 400
Index
P PVC fittings - clip 20mm -1/2"
P PVC fittings - clip 25mm - 3/4"
P PVC fittings - clip 32mm - 1"
P PVC fittings - clip 40mm - 11/4"
P PVC fittings - clip 50mm - 11/2"
P PVC fittings - clip 63mm - 2"
P PVC fittings - clip 75mm - 2 1/2"
P PVC fittings - clip 90mm - 3"
P PVC fittings - clip 110mm - 4"
P PVC fittings - cap 20mm -1/2"
P PVC fittings - cap 25mm - 3/4"
P PVC fittings - cap 32mm - 1"
P PVC fittings - cap 40mm - 11/4"
P PVC fittings - cap 50mm - 11/2"
P PVC fittings - cap 63mm - 2"
P PVC fittings - cap 75mm - 2 1/2"
P PVC fittings - cap 90mm - 3"
P PVC fittings - cap 110mm - 4"
P PVC fittings - elbow 20mm -1/2"
P PVC fittings - elbow 25mm - 3/4"
P PVC fittings - elbow 32mm - 1"
P PVC fittings - elbow 40mm - 11/4"
P PVC fittings - elbow 50mm - 11/2"
P PVC fittings - elbow 63mm - 2"
P PVC fittings - elbow 75mm - 2 1/2"
P PVC fittings - elbow 90mm - 3"
P PVC fittings - elbow 110mm - 4"
P PVC fittings - equal tee 20mm -1/2"
P PVC fittings - equal tee 25mm - 3/4"
P PVC fittings - equal tee 32mm - 1"
P PVC fittings - equal tee 40mm - 11/4"
P PVC fittings - equal tee 50mm - 11/2"
P PVC fittings - equal tee 63mm - 2"
P PVC fittings - equal tee 75mm - 2 1/2"
P PVC fittings - equal tee 90mm - 3"
P PVC fittings - equal tee 110mm - 4"
P PVC fittings - faucet socket 20mm -1/2"
P PVC fittings - faucet socket 25mm - 3/4"
P PVC fittings - faucet socket 32mm - 1"
P PVC fittings - faucet socket 40mm - 11/4"
P PVC fittings - faucet socket 50mm - 11/2"
P PVC fittings - faucet socket 63mm - 2"
P PVC fittings - faucet socket 75mm - 2 1/2"
P PVC fittings - faucet socket 90mm - 3"
P PVC fittings - faucet socket 110mm - 4"
P PVC fittings - bend 20mm -1/2"
P PVC fittings - bend 25mm - 3/4"
P PVC fittings - bend 32mm - 1"
P PVC fittings - bend 40mm - 11/4"
P PVC fittings - bend 50mm - 11/2"
P PVC fittings - bend 63mm - 2"
P PVC fittings - bend 75mm - 2 1/2"
P PVC fittings - bend 90mm - 3"
P PVC fittings - bend 110mm - 4"
P PVC fittings - socket 20mm -1/2"
P PVC fittings - socket 25mm - 3/4"
P PVC fittings - socket 32mm - 1"
P PVC fittings - socket 40mm - 11/4"
P PVC fittings - socket 50mm - 11/2"
P PVC fittings - socket 63mm - 2"
P PVC fittings - socket 75mm - 2 1/2"
P PVC fittings - socket 90mm - 3"
P PVC fittings - socket 110mm - 4"
P PVC fittings - valve socket 20mm -1/2"
P PVC fittings - valve socket 25mm - 3/4"
P PVC fittings - valve socket 32mm - 1"
P PVC fittings - valve socket 40mm - 11/4"
P PVC fittings - valve socket 50mm - 11/2"
P PVC fittings - valve socket 63mm - 2"
P PVC fittings - valve socket 75mm - 2 1/2"
P PVC fittings - valve socket 90mm - 3"
P PVC fittings - valve socket 110mm - 4"
P PVC conduit pipe 18mm 5/8"
P PVC conduit pipe 20mm 3/4"
P PVC conduit pipe 25mm 1"
P PVC conduit pipe 30mm 1 1/4"
P PVC conduit pipe 40mm 11/2"
P PVC conduit pipe 50mm 2"
P PVC conduit pipe 90mm T 1000
P PVC conduit pipe 110mm T 1000
PVC conduit fittings - bend 18 mm
PVC conduit fittings - bend 20 mm
PVC conduit fittings - bend 25 mm
PVC conduit fittings - bend 30 mm
PVC conduit fittings - bend 40 mm
PVC conduit fittings - bend 50 mm
PVC conduit fittings - socket 18 mm
PVC conduit fittings - socket 20 mm
PVC conduit fittings - socket 25 mm
PVC conduit fittings - socket 30 mm
PVC conduit fittings - socket 40 mm
PVC conduit fittings - socket 50 mm
PVC conduit fittings - saddle 18 mm
PVC conduit fittings - saddle 20 mm
PVC conduit fittings - saddle 25 mm
PVC conduit fittings - saddle 30 mm
PVC conduit fittings - saddle 40 mm
PVC conduit fittings - saddle 50 mm
Roof plumbing - gutter Square Gutter
Roof plumbing - gutter Half Round Gutter
Roof plumbing - gutter fittings Running Head
Roof plumbing - gutter fittings Gutter Joiner
Roof plumbing - gutter fittings Mitre Joiner
Roof plumbing - gutter fittings End Cap
Roof plumbing - gutter fittings Gutter Box
Roof plumbing - gutter fittings Gutter Bracket-A
Roof plumbing - gutter fittings Gutter Bracket-B
Roof plumbing - down pipe Down Pipe
Roof plumbing - down pipe fittings Down Spout Elbow
Roof plumbing - down pipe fittings Down Spout Joiner
Roof plumbing - down pipe fittings Down Spout Clip
New Rain Water Gutter System
Roof plumbing - gutter Square Gutter (Brown)
Roof plumbing - gutter Half Round Gutter (Brown)
Gutter & Down Spout Fittings
Roof plumbing - gutter fittings Running Head
Roof plumbing - gutter fittings Gutter Joiner
Roof plumbing - gutter fittings Mitre Joiner (Outer)
Roof plumbing - gutter fittings Mitre Joiner (Inner)
Roof plumbing - gutter fittings End Cap
Roof plumbing - gutter fittings Gutter Box (200x200x200mm)
Roof plumbing - gutter fittings Gutter Bracket (Inner)
Roof plumbing - gutter fittings Gutter Bracket (Outer)
Roof plumbing - gutter fittings DP Elbow
Roof plumbing - gutter fittings DP Angle Elbow
Roof plumbing - gutter fittings DP Joiner
Roof plumbing - gutter fittings DP Clip
Roof plumbing - gutter fittings DP Conveyor
Roof plumbing - gutter fittings DP "Y"
Roof plumbing - gutter fittings DP Tee
Roof plumbing - gutter fittings Gutter Box Connector
Reducing fittings - reducing socket 25x20mm
Reducing fittings - reducing socket 32x20mm
Reducing fittings - reducing socket 32x25mm
Reducing fittings - reducing socket 40x20mm
Reducing fittings - reducing socket 40x25mm
Reducing fittings - reducing socket 40x32mm
Reducing fittings - reducing socket 50x20mm
Reducing fittings - reducing socket 50x25mm
Reducing fittings - reducing socket 50x32mm
Reducing fittings - reducing socket 50x40mm
Reducing fittings - reducing socket 63x20mm
Reducing fittings - reducing socket 63x25mm
Reducing fittings - reducing socket 63x32mm
Reducing fittings - reducing socket 63x40mm
Reducing fittings - reducing socket 63x50mm
Reducing fittings - reducing tee 25x20mm
Reducing fittings - reducing tee 32x20mm
Reducing fittings - reducing tee 32x25mm
Reducing fittings - reducing tee 40x20mm
Reducing fittings - reducing tee 40x25mm
Reducing fittings - reducing tee 40x32mm
Reducing fittings - reducing tee 50x20mm
Reducing fittings - reducing tee 50x25mm
Reducing fittings - reducing tee 50x32mm
Reducing fittings - reducing tee 50x40mm
Reducing fittings - reducing tee 63x20mm
Reducing fittings - reducing tee 63x25mm
Reducing fittings - reducing tee 63x32mm
Reducing fittings - reducing tee 63x40mm
Reducing fittings - reducing tee 63x50mm
H Hot water pipes CPVC Pipe 1/4" ( 10mm)
H Hot water pipes CPVC Pipe 1/2" ( 15mm)
H Hot water pipes CPVC Pipe 3/4" ( 20mm)
Fittings
Hot water - fittings CPVC Coupling 1/2" (15mm)
Hot water - fittings CPVC Coupling 3/4" (20mm)
Hot water - fittings CPVC Threded Male Adaptor 1/2" (15mm)
Hot water - fittings CPVC Threded Male Adaptor 3/4" (20mm)
Hot water - fittings CPVC Threded Female Adaptor 1/2" (15mm)
Hot water - fittings CPVC Threded Female Adaptor 3/4" (20mm)
Hot water - fittings Brass Threded Male Adaptor 1/2" (15mm)
Hot water - fittings Brass Threded Male Adaptor 3/4" (20mm)
Hot water - fittings Brass Threded Female Adaptor 1/2" (15mm)
Hot water - fittings Brass Threded Female Adaptor 3/4" (20mm)
Hot water - fittings Brass EPT Elbow 1/2" (15mm)
Hot water - fittings Brass EPT Elbow 3/4" (20mm)
Hot water - fittings Brass EPT Tee 3/4"x1/2" (20x15mm)
Hot water - fittings Brass Coupling 3/4"x1/2" (20x15mm)
Hot water - fittings CPVC Reducer Coupling 3/4"x1/2" (20x15mm
Hot water - fittings CPVC Union 1/2" (15mm)
Hot water - fittings CPVC Union 3/4" (20mm)
Hot water - fittings CPVC Elbow 1/2" 45D (15mm)
Hot water - fittings CPVC Elbow 3/4" 45D (20mm)
Hot water - fittings CPVC Cap 1/2" (15mm)
Hot water - fittings CPVC Cap 3/4" (20mm)
Hot water - fittings CPVC Elbow 1/2" (15mm)
Hot water - fittings CPVC Elbow 3/4" (20mm)
Hot water - fittings CPVC Tee 1/2" (15mm)
Hot water - fittings CPVC Tee 3/4" (20mm)
Hot water - fittings CPVC Reducer Bush 3/4"x1/2" (20x15mm)
Hot water - fittings CPVC Reducer Tee 3/4"x1/2" (20x15mm)
Adhesive Solution Adhesive Solution - 50ml
Adhesive Solution Adhesive Solution - 118ml
P Compact Ball Valve 20 mm diameterP Compact Ball Valve 25 mm diameterP Compact Ball Valve 32 mm diameterP Compact Ball Valve 40 mm diameterP Compact Ball Valve 50 mm diameterP Compact Ball Valve 63 mm diameter
National PVC water tank
P Water tank 350Ltr
P Water tank 500Ltr
P Water tank 1000Ltr
P Water tank 2000Ltr
P S-Lon Water Tank (vertical)
P Water tank 300Ltr Watermaate
P Water tank 500Ltr Watermaate
P Water tank 1000Ltr Watermaate
P Water tank 2000Ltr Watermaate
P Water tank 350Ltr PE Plus
P Water tank 500Ltr PE Plus
P Water tank 750Ltr PE Plus
P Water tank 1000Ltr PE Plus
P Water tank 1500Ltr PE Plus
P Water tank 2000Ltr PE Plus
P Water tank 5000Ltr PE Plus
P Water tank 500Ltr White Layer
P Water tank 750Ltr White Layer
P Water tank 1000Ltr White Layer
P Water tank 1500Ltr White Layer
P Water tank 2000Ltr White Layer
P Water tank 10000Ltr Solco
P ANTON Water Tank (Vertical)
P Water tank 300Ltr
P Water tank 500Ltr
P Water tank 1000Ltr
P Water tank 1500Ltr
P Water tank 2000Ltr
Stainless steel water tank
P Water tank - Stainless steel 500Ltr
P Water tank - Stainless steel 850Ltr
P Water tank - Stainless steel 1250Ltr
S Water tank - Stainless steel 75LS Water tank - Stainless steel 100LS Water tank - Stainless steel 150LS Water tank - Stainless steel 200LS Water tank - Stainless steel 300LS Water tank - Stainless steel 450L
Solar panel 75L
100L
150L
200L
300L
450L
H Hume pipe 3" dia 8' long
H Hume pipe 3" dia 8' long
H Hume pipe 4" dia 6' long
H Hume pipe 4" dia 8' long
H Hume pipe 9" dia 8' long
H Hume pipe 9" dia 4' long
H Hume pipe 12'' dia 8' long
H Hume pipe 12" dia 4' long
H Hume pipe 15" dia 8' long
H Hume pipe 15" dia 4' long
H Hume pipe 18' dia 8' long
H Hume pipe 18" dia 4' long
H Hume pipe 24" dia 8' long
H Hume pipe 24" dia 4' long
H Hume pipe 30" dia 8' long
H Hume pipe 30" dia 4' long
H Hume pipe 36" dia 8' long
H Hume pipe 36" dia 4' long
H Hume pipe 48" dia 8' long
H Hume pipe 48" dia 4' long
H Hume pipe 60" dia 8' long
S Septic tanks 10 Person 24'
S Septic tanks 15 Person 30"
S Septic tanks 25 person 36'
S Septic tanks 35 person 42"
S Septic tanks 50 person 48"
S Septic tanks 60 person 54'
S Septic tanks 75 person 60"
S Septic tanks 125 person 72'
S 10 Person 4'-0" x 8'-0"
S
S Septic tanks 4' 6" dia 8' 0" long
S
S
S Soakage pit 24" x4'
S Soakage pit 30" x4'
S Soakage pit 30" x4'
S Soakage pit 42" x4'
S Soakage pit 48" x4'
S Soakage pit 54" x4'
S Soakage pit 60" x4'
S Soakage pit 72" x4'
B Brass item 0.5" Brass Gate Valve -English
B Brass item 0.5" Brass stops -English
B Brass item 0.5" C/P Stop -Cobra
B Brass item 1/2" Brass bib tap English
S
S
B Ball Cock 1"spain
B
S Solvent cement 25 GramsS Solvent cement 50 GramsS Solvent cement 75 GramsS Solvent cement 90 GramsS Solvent cement 250 GramsS Solvent cement 500 GramsS Solvent cement 1000 GramsS
S Stainless steel Bottle trap
S
S
S Stainless steel Gully cover
S
S Stainless steel shower Good Quality
S
S
H Hand bidet spray
H
T Towel Rail Cromium Plated 2' 0"
T
T Toilet accessories Cromium Plated
T
M Mirrors Mirror
M Pencil Edge
M Hole making
M Screws
M
F Flexible hose 16"
F
A Angle Valve
A
B Ball valve Pegler
Ball valve 1/2" S -Lon
Ball valve 3/4"
Ball valve 1"
Ball valve 11/4"
Ball valve 11/2"
Ball valve 2"
Ball valve 3"
Ball valve
Ball valve
Cupper gutters
Sanitary fittings
S Sanitary fittings water closetS Sanitary fittings vanity basinS Sanitary fittings under counter basinS Sanitary fittings
S Sanitary fittings Urinals U.KS Sanitary fittings U.KS Sanitary fittings wash basin-Pedestal MalaysiaS Sanitary fittings Squatin panS Sanitary fittings Squatin panS Sanitary fittings Squatin panS
T Taps
T Taps
T Taps
T Taps Dual handle kitchen mixer tapT Taps
T Taps
T Taps
T Taps Garden tapT
TT Tap mixture tapT
S Shower
S Shower
Dual handle Lavatory mixer tap
Single lever Lavatory mixer tap
Single lever Lavatory mixer tap
Sigle handle kitchen mixer tapSigle handle kitchen mixer tapSigle handle kitchen mixer tap
Wall mounted single hadle bath mixer
S Shower
S New Eurosmart basin mixer Grohe
S New Eurosmart concealed bathGrohe
S Concealed body bath Grohe
S Relaxa head shower buo Grohe
S Lineare basin mixer Grohe
S Lineare bidet mixer Grohe
S Silver metalic bidet spray Grohe
S Coasta sink mixer Grohe
S New Eurostyle sink mixer Grohe
S mintaa sink mixer Grohe
S Angle valve Grohe
S Angle valve Grohe
Unit Currencet price Date Other Remark Telephone Price
Plumbing material
4m (13ft) 156.00 1.12.2008 39.00 194.00
4m (13ft) 429.00 1.12.2008 107.25 429.00
4m (13ft) 640.00 1.12.2008 160.00 640.00
4m (13ft) 948.00 1.12.2008 237.00 948.00
4m (13ft) 1,366.00 1.12.2008 341.50 1,366.00
4m (13ft) 2,305.00 1.12.2008 576.25 2,305.00
4m (13ft) 4,720.00 1.12.2008 1180.00 4,720.00
6m (20ft) 8,556.00 1.12.2008 1426.00 8,556.00
6m (20ft) 12,792.00 1.12.2008 12,792.00
6m (20ft) 21,192.00 1.12.2008 21,192.00
6m (20ft) 26,628.00 1.12.2008 26,628.00
6m (20ft) 51,957.00 1.12.2008 51,957.00
6m (20ft) 80,199.00 1.12.2008 80,199.00
6m (20ft) 101,853.00 1.12.2008 ###
4m (13ft) 272.00 1.12.2008 68.00 272.00
4m (13ft) 663.00 1.12.2008 165.75 663.00
4m (13ft) 886.00 1.12.2008 221.50 886.00
4m (13ft) 1,468.00 1.12.2008 367.00 1,468.00
4m (13ft) 2,898.00 1.12.2008 724.50 2,898.00
6m (20ft) 5,493.00 1.12.2008 915.50 5,493.00
6m (20ft) 8,046.00 1.12.2008 8,046.00
6m (20ft) 12,891.00 1.12.2008 12,891.00
6m (20ft) 16,788.00 1.12.2008 16,788.00
6m (20ft) 32,913.00 1.12.2008 32,913.00
6m (20ft) 50,619.00 1.12.2008 50,619.00
6m (20ft) 64,524.00 1.12.2008 64,524.00
4m (13ft) 628.00 1.12.2008 157.00 628.00
4m (13ft) 1,141.00 1.12.2008 285.25 1,141.00
4m (13ft) 1,836.00 1.12.2008 459.00 1,836.00
6m (20ft) 3,735.00 1.12.2008 622.50 3,735.00
6m (20ft) 11,640.00 1.12.2008 11,640.00
6m (20ft) 23,145.00 1.12.2008 23,145.00
6m (20ft) 34,896.00 1.12.2008 34,896.00
6m (20ft) 44,466.00 1.12.2008 44,466.00
Nos 16.00 1.12.2008 16.00
Nos 17.00 1.12.2008 17.00
Nos 16.00 1.12.2008 18.00
Nos 21.00 1.12.2008 21.00
Nos 26.00 1.12.2008 26.00
Nos 27.00 1.12.2008 27.00
Nos 66.00 1.12.2008 66.00
Nos 81.00 1.12.2008 81.00
Nos 139.00 1.12.2008 139.00
Nos 19.00 1.12.2008 19.00
Nos 23.00 1.12.2008 23.00
Nos 31.00 1.12.2008 31.00
Nos 43.00 1.12.2008 43.00
Nos 63.00 1.12.2008 63.00
Nos 90.00 1.12.2008 90.00
Nos 255.00 1.12.2008 255.00
Nos 359.00 1.12.2008 359.00
Nos 422.00 1.12.2008 422.00
Nos 15.00 1.12.2008 15.00
Nos 27.00 1.12.2008 27.00
Nos 40.00 1.12.2008 40.00
Nos 66.00 1.12.2008 66.00
Nos 111.00 1.12.2008 111.00
Nos 187.00 1.12.2008 187.00
Nos 404.00 1.12.2008 404.00
Nos 683.00 1.12.2008 683.00
Nos 756.00 1.12.2008 756.00
Nos 20.00 1.12.2008 20.00
Nos 36.00 1.12.2008 36.00
Nos 55.00 1.12.2008 55.00
Nos 90.00 1.12.2008 90.00
Nos 156.00 1.12.2008 156.00
Nos 238.00 1.12.2008 238.00
Nos 395.00 1.12.2008 395.00
Nos 903.00 1.12.2008 903.00
Nos 1,394.00 1.12.2008 1,394.00
Nos 20.00 1.12.2008 20.00
Nos 28.00 1.12.2008 28.00
Nos 36.00 1.12.2008 36.00
Nos 67.00 1.12.2008 67.00
Nos 92.00 1.12.2008 92.00
Nos 143.00 1.12.2008 143.00
Nos 284.00 1.12.2008 264.00
Nos 404.00 1.12.2008 404.00
Nos 906.00 1.12.2008 906.00
Nos 26.00 1.12.2008 26.00
Nos 36.00 1.12.2008 36.00
Nos 51.00 1.12.2008 51.00
Nos 111.00 1.12.2008 111.00
Nos 178.00 1.12.2008 178.00
Nos 288.00 1.12.2008 288.00
Nos 824.00 1.12.2008 824.00
Nos 1,378.00 1.12.2008 1,378.00
Nos 1,746.00 1.12.2008 1,746.00
Nos 16.00 1.12.2008 16.00
Nos 23.00 1.12.2008 23.00
Nos 34.00 1.12.2008 34.00
Nos 51.00 1.12.2008 51.00
Nos 78.00 1.12.2008 78.00
Nos 125.00 1.12.2008 125.00
Nos 308.00 1.12.2008 308.00
Nos 453.00 1.12.2008 453.00
Nos 727.00 1.12.2008 727.00
Nos 20.00 1.12.2008 20.00
Nos 28.00 1.12.2008 28.00
Nos 32.00 1.12.2008 32.00
Nos 60.00 1.12.2008 60.00
Nos 83.00 1.12.2008 83.00
Nos 138.00 1.12.2008 138.00
Nos 373.00 1.12.2008 373.00
Nos 578.00 1.12.2008 578.00
Nos 906.00 1.12.2008 906.00
4m (13ft) 81.00 1.12.2008 94.00
4m (13ft) 121.00 1.12.2008 134.00
4m (13ft) 167.00 1.12.2008 184.00
4m (13ft) 483.00 1.12.2008 483.00
4m (13ft) 686.00 1.12.2008 686.00
4m (13ft) 786.00 1.12.2008 786.00
6m (20ft)
6m (20ft)
Nos 16.00 1.12.2008 16.00
Nos 20.00 1.12.2008 20.00
Nos 24.00 1.12.2008 24.00
Nos 41.00 1.12.2008 41.00
Nos 60.00 1.12.2008 60.00
Nos 85.00 1.12.2008 85.00
Nos 6.00 1.12.2008 6.00
Nos 7.00 1.12.2008 7.00
Nos 7.00 1.12.2008 7.00
Nos 20.00 1.12.2008 20.00
Nos 24.00 1.12.2008 24.00
Nos 38.00 1.12.2008 38.00
Nos 11.00 1.12.2008 11.00
Nos 11.00 1.12.2008 11.00
Nos 11.00 1.12.2008 11.00
Nos 12.00 1.12.2008 12.00
Nos 13.00 1.12.2008 13.00
Nos 17.00 1.12.2008 17.00
3.65m (12ft) 809.00 1.12.2008 934.00
Nos 233.00 1.12.2008 233.00
Nos 101.00 1.12.2008 101.00
Nos 328.00 1.12.2008 328.00
Nos 84.00 1.12.2008 84.00
Nos 554.00 1.12.2008 554.00
Nos 44.00 1.12.2008 44.00
Nos 20.00 1.12.2008 20.00
3.65m (12ft) 788.00 1.12.2008 788.00
Nos 142.00 1.12.2008 142.00
Nos 105.00 1.12.2008 105.00
Nos 22.00 1.12.2008 22.00
1,467.00 11.08.2008
972.00 11.08.2008
Nos 233.00 1.12.2008 264.00
Nos 101.00 1.12.2008 114.00
Nos 328.00 1.12.2008 384.00
Nos 328.00 1.12.2008 384.00
Nos 84.00 1.12.2008 98.00
Nos 554.00 1.12.2008 708.00
Nos 44.00 1.12.2008 48.00
Nos 20.00 1.12.2008 60.00
Nos 168.00 11.08.2008 168.00
Nos 168.00 11.08.2008 168.00
Nos 118.00 11.08.2008 118.00
Nos 28.00 11.08.2008 28.00
Nos 64.00 11.08.2008 64.00
Nos 330.00 11.08.2008 330.00
Nos 240.00 11.08.2008 240.00
Nos 72.00 11.08.2008 72.00
Nos 22.00 1.12.2008 22.00
Nos 27.00 1.12.2008 27.00
Nos 34.00 1.12.2008 34.00
Nos 44.00 1.12.2008 44.00
Nos 50.00 1.12.2008 50.00
Nos 57.00 1.12.2008 58.00
Nos 59.00 1.12.2008 59.00
Nos 68.00 1.12.2008 68.00
Nos 81.00 1.12.2008 81.00
Nos 84.00 1.12.2008 84.00
Nos 99.00 1.12.2008 99.00
Nos 103.00 1.12.2008 103.00
Nos 107.00 1.12.2008 107.00
Nos 110.00 1.12.2008 110.00
Nos 115.00 1.12.2008 115.00
Nos 38.00 1.12.2008 38.00
Nos 50.00 1.12.2008 50.00
Nos 56.00 1.12.2008 56.00
Nos 66.00 1.12.2008 66.00
Nos 86.00 1.12.2008 86.00
Nos 90.00 1.12.2008 90.00
Nos 102.00 1.12.2008 102.00
Nos 119.00 1.12.2008 119.00
Nos 128.00 1.12.2008 128.00
Nos 146.00 1.12.2008 146.00
Nos 228.00 1.12.2008 228.00
Nos 235.00 1.12.2008 235.00
Nos 236.00 1.12.2008 236.00
Nos 238.00 1.12.2008 238.00
Nos 246.00 1.12.2008 246.00
3 m 840.00 27.04.2009
3 m 870.00 27.04.2009 690.00
3 m 861.00 11.08.2008
Nos 35.00 11.08.2008
Nos 65.00 11.08.2008
Nos 45.00 11.08.2008
Nos 80.00 11.08.2008
Nos 65.00 11.08.2008
Nos 105.00 11.08.2008
Nos 450.00 11.08.2008
Nos 580.00 11.08.2008
Nos 450.00 11.08.2008
Nos 590.00 11.08.2008
Nos 195.00 11.08.2008
Nos 240.00 11.08.2008
Nos 275.00 11.08.2008
Nos 260.00 11.08.2008
Nos 70.00 11.08.2008
Nos 540.00 11.08.2008
Nos 795.00 11.08.2008
Nos 60.00 11.08.2008
Nos 100.00 11.08.2008
Nos 30.00 11.08.2008
Nos 50.00 11.08.2008
Nos 50.00 11.08.2008
Nos 100.00 11.08.2008
Nos 65.00 11.08.2008
Nos 145.00 11.08.2008
Nos 35.00 11.08.2008
Nos 125.00 11.08.2008
kg 640.00 11.08.2008
kg 920.00 11.08.2008
Nos 122.00 1.12.2008 122.00
Nos 221.75 1.12.2008 221.00
Nos 237.00 1.12.2008 237.00
Nos 371.75 1.12.2008 371.00
Nos 494.75 1.12.2008 494.00
Nos 789.50 1.12.2008 789.00
Nos 5,065.00
Nos 7,000.00
Nos 11,300.00
Nos 20,665.00
Nos 4,775.00 11.08.2008
Nos 5,775.00 11.08.2008
Nos 10,300.00 11.08.2008
Nos 18,700.00 11.08.2008
Nos 5,125.00 11.08.2008
Nos 6,580.00 11.08.2008
Nos 9,800.00 11.08.2008
Nos 12,000.00 11.08.2008
Nos 17,000.00 11.08.2008
Nos 21,450.00 11.08.2008
Nos 50,500.00 11.08.2008
Nos 8,460.00 11.08.2008
Nos 10,900.00 11.08.2008
Nos 13,400.00 11.08.2008
Nos 19,400.00 11.08.2008
Nos 24,700.00 11.08.2008
Nos 84,000.00 11.08.2008
Nos 5,170.00 11.08.2008
Nos 6,940.00 11.08.2008
Nos 12,835.00 11.08.2008
Nos 17,975.00 11.08.2008
Nos 26,200.00 11.08.2008
Nos 19,600.00 11.08.2009
Nos 24,900.00 11.08.2009
Nos 32,900.00 11.08.2009
Nos 55,000.00 11.08.2009
Nos 69,000.00 11.08.2009
Nos 93,000.00 11.08.2009
Nos 115,000.00 11.08.2009
Nos 150,000.00 11.08.2009
Nos 225,000.00 11.08.2009
Nos 68,000.00 15/02/20210
Nos 85,000.00 15/02/20210
Nos 106,250.00 15/02/20210
Nos 127,500.00 15/02/20210
Nos 168,300.00 15/02/20210
Nos 242,250.00 15/02/20210
6lft 420.00
8lft 636.00
6lft 510.00
8lft 663.00
8lft 3,200.00 5/7/2007 978.00
4lft 1,800.00 5/7/2007
8lft 3,800.00 5/7/2007 1,275.00
4lft 1,900.00 5/7/2007
8lft 5,000.00 5/7/2007 1,275.00
4lft 2,500.00 5/7/2007
8lft 5,800.00 5/7/2007 1,950.00
4lft 2,900.00 5/7/2007
8lft 7,200.00 5/7/2007 1,950.00
4lft 3,225.00 9/1/2009 Dias concrete -2930763
8lft 8,800.00 5/7/2007 1,950.00
4lft 4,400.00 5/7/2007
8lft 10,800.00 5/7/2007 1,951.00
4lft 6,000.00 9/1/2009 Dias concrete -2930763
8lft 16,900.00 5/7/2007 9,330.00
4lft 8,450.00 5/7/2007
8lft 14,100.00
No 5,100.00
No 69,000.00
No 8,700.00
No 10,500.00
No 25,000.00 13/07/06 13,700.00
No 16,800.00
No 21,930.00
No 29,400.00
No 30,300.00 3/12/2008 Dias concrete -2930763
No 40,975.00 21/04/2009
No 2,130.00
No 2,940.00
No 3,750.00
No 4,830.00
No 6,000.00
No 7,260.00
No 8,700.00
No 13,200.00
No 350.00
No 350.00
No 750.00
No 350.00
Nos
25 Grams 57.00 1.12.2008 57.00
50 Grams 108.00 1.12.2008 108.00
75 Grams 142.00 1.12.2008 142.00
250 Grams 451.00 1.12.2008 451.00
500 Grams 874.00 1.12.2008 874.00
1000 Grams 1,720.00 1.12.2008 1,720.00
Nos 2,750.00 21/04/2009
1,350.00 20/03/2009
Nos 1,250.00 21/04/2009
Nos 8,000.00 21/04/2009
Nos 4,000.00 21/04/2009
Nos 2,700.00 21/04/2009
Nos 2,000.00 21/04/2009
Set 7,200.00 21/04/2009
Sq.ft 350.00 21/04/2009
L.ft 45.00 21/04/2009
Nos 50.00 21/04/2009
Nos 25.00 21/04/2009
Nos 325.00 20/03/2009
Nos 750.00 20/03/2009
Nos 1,475.00 20/03/2009
Nos 122.00 15/02/20010
Nos 221.00 15/02/20010
Nos 237.00 15/02/20010
Nos 371.00 15/02/20010
Nos 494.00 15/02/20010
Nos 789.00 15/02/20010
Nos 2,070.00 15/02/20010
L.ft 4,500.00
Nos 15,200.00
Nos 5,638.13
Nos 5,006.66
Nos 2,265.00 9/8/2008 Mascons Ltd 2325561-3
Nos 1,380.00
Nos 5,899.50
Nos 862.00
Nos 816.00
Nos 549.00
Nos 2,363.25 9/8/2008 Mascons Ltd
Nos 1,495.00
Nos 1,989.50
Nos 2,386.25
Nos 519.00
Nos 701.50
Nos 1,058.00
Nos 365.00
Nos 1,442.00
Nos 2,202.25 9/8/2008 Mascons Ltd
Nr 14,960.00 6/2/2010
Nr 12,950.00 6/2/2010
Nr 12,320.00 6/2/2010
Nr 22,810.00 6/2/2010
Nr 34,510.00 6/2/2010
Nr 34,510.00 6/2/2010
Nr 9,130.00 6/2/2010
Nr 10,570.00 6/2/2010
Nr 21,340.00 6/2/2010
Nr 58,400.00 6/2/2010
Nr 1,850.00 6/2/2010
Nr 1,650.00 6/2/2010
Date Price Date
Plumbing material
11.08.2008 168.00
11.08.2008 329.00
11.08.2008 491.00
11.08.2008 726.00
11.08.2008 1,046.50
11.08.2008 1,766.50
11.08.2008 3,652.00
11.08.2008 6,955.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008 308.00
11.08.2008 524.00
11.08.2008 718.00
11.08.2008 1,157.00
11.08.2008 2,278.00
11.08.2008 4,464.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008 13.00
11.08.2008 21.00
11.08.2008 34.00
11.08.2008 53.00
11.08.2008 95.00
11.08.2008 150.00
11.08.2008 326.00
11.08.2008 552.00
11.08.2008 610.00
11.08.2008 17.00
11.08.2008 29.00
11.08.2008 47.00
11.08.2008 72.00
11.08.2008 125.00
11.08.2008 192.00
11.08.2008 318.00
11.08.2008 729.00
11.08.2008 1,125.00
11.08.2008 17.00
11.08.2008 22.00
11.08.2008 31.00
11.08.2008 54.00
11.08.2008 74.00
11.08.2008 115.00
11.08.2008 213.00
11.08.2008 326.00
11.08.2008 731.00
11.08.2008 22.00
11.08.2008 29.00
11.08.2008 44.00
11.08.2008 89.00
11.08.2008 143.00
11.08.2008 232.00
11.08.2008 664.50
11.08.2008 1,112.50
11.08.2008 1,409.50
11.08.2008 14.00
11.08.2008 19.00
11.08.2008 29.00
11.08.2008 41.00
11.08.2008 62.00
11.08.2008 101.00
11.08.2008 248.50
11.08.2008 365.50
11.08.2008 585.50
11.08.2008 17.00
11.08.2008 22.00
11.08.2008 30.00
11.08.2008 48.00
11.08.2008 67.00
11.08.2008 111.00
11.08.2008 300.50
11.08.2008 466.00
11.08.2008 731.00
11.08.2008 49.00 8/4/2004
11.08.2008 74.80 8/4/2004
11.08.2008 106.00 8/4/2004
11.08.2008 269.00 8/4/2004
11.08.2008 384.00 8/4/2004
11.08.2008 440.00 8/4/2004
10,395.00
11.08.2008 13.25
11.08.2008 15.75
11.08.2008 19.50
11.08.2008 33.25
11.08.2008 48.75
11.08.2008 69.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
420.00
636.00
510.00
663.00
978.00
1,275.00
1,275.00
1,950.00
1,950.00
1,950.00
1,951.00
9,330.00
14,100.00
5,100.00
69,000.00
8,700.00
10,500.00
13,700.00
16,800.00
21,930.00
29,400.00
2,130.00
2,940.00
3,750.00
4,830.00
6,000.00
7,260.00
8,700.00
13,200.00
350.00
350.00
750.00
350.00
170.00
11.08.2008 45.50
11.08.2008 87.00
11.08.2008 136.00
11.08.2008 362.50
11.08.2008 703.50
11.08.2008 1,384.75
Code Category Description Remarks Unit
Ready Mix Concrete
Q Ready Mix Concrete G40 excl. VAT
Q Ready Mix Concrete G35 excl. VAT
Q Ready Mix Concrete G30
Q Ready Mix Concrete G25
Q Ready Mix Concrete G20
Q Ready Mix Concrete G15
Q Ready Mix Concrete G30
G25
G20
G15
Q Ready Mix Concrete G35
Q Ready Mix Concrete G30
Q Ready Mix Concrete G25
Q Ready Mix Concrete G30
G25
G20
G15
Q Ready Mix Concrete G15 excl. VAT
Q Ready Mix Concrete G40 excl. VAT
Q Ready mix concrete Ready mix concrete grade 25 with VAT 1m3
Q Pump car carging 30m3
Q Ready mix concrete Ready mix concrete grade 20 with VAT 1m3
Q Ready mix concrete Ready mix concrete grade 25 with VAT 1m3
Q Ready mix concrete Ready mix concrete grade 30 with VAT 1m3
M³
M³
excl. VAT & Pumping M³
excl. VAT & Pumping
M³
excl. VAT & Pumping
M³
excl. VAT & Pumping
M³
excl. VAT & Pumping M³
M³
M³
excl. VAT & Pumping excl. VAT & Pumping
M³
excl. VAT & Pumping excl. VAT & Pumping
M³
excl. VAT & Pumping
M³
excl. VAT & Pumping excl. VAT & Pumping
M³
excl. VAT & Pumping excl. VAT & Pumping excl. VAT & Pumping
M³
M³
Index
Currencet price Date Other Remark Telephone Price
Ready Mix Concrete
11,175.00 25.09.08 excl. pumping, max 15km transpor 2368494 Thudawe Bros.
10,725.00 25.09.08 excl. pumping, max 15km transpor 2368494 Thudawe Bros.
9,700.00 20/04/2010 2368494 Thudawe Bros.
9,000.00 20/04/2010 2368494 Thudawe Bros.
8,700.00 20/04/2010 2368494 Thudawe Bros.
8,600.00 25.09.08 2368494 Thudawe Bros.
8,950.00 20/04/2010 2522939 Sanken
8,600.00 20/04/2010
8,100.00 20/04/2010
2808835 Maga
2423085 orumix
2807808 LHP
9,650.00 20/04/2010 20m3 plumping charge 5.000.00 4400404 ICC
9,200.00 20/04/2010
8,900.00 20/04/2010
8,000.00 20/04/2010
2375500 Sunbee
2945865 Supermix
8,970.00 22/102007
14,375.00 22/10/2007
9,545.00 3/6/2008
10,005.00 3/6/2008
10,580.00 3/6/2008
30m3 plumping charge 12.000.00 after 30m3 400/= per 1m3
25m3 plumping charge 10.000.00 after 25m3 300/= per 1m3
Ready Mix Concrete
Code Category Description Remarks Unit
Timber
T Timber Teak 2"x1" timber L.ft
T Timber Teak 2" x 2" timber L.ft
T Timber Teak 2" x 3" timber L.ft
T Timber Teak 3" x 5" timber L.ft
T Timber Teak 5" x 5" timber L.ft
T Timber Teak 7" x 7" timber L.ft
T Timber Balaw 2"x1" timber L.ft
T Timber Balaw 2" x 2" timber L.ft
T Timber Balaw 2" x 4" timber L.ft
T Timber Balaw 2" x 5" timber L.ft
T Timber Balaw 2" x 6" timber L.ft
T Timber Balaw 2" x 7" timber L.ft
T Timber Balaw 2" x 8" timber L.ft
T Timber Balaw 3" x 4" timber L.ft
T Timber Balaw 3" x 5" timber L.ft
T Timber Balaw 3" x 6" timber L.ft
T Timber Balaw 4" x 6" timber L.ft
T Timber Balaw 4" x 8" timber L.ft
T Timber Balaw 1" x 8" timber L.ft
T Timber Balaw 1" x 9" timber L.ft
T Timber Balaw 1" x 10" timber L.ft
T Timber Balaw 1" x 12" timber L.ft
T Timber Balaw 11/4" x 9" timber L.ft
T Timber Balaw 11/4" x 10" timber L.ft
T Timber Balaw 3/4" timber L.ft
T
T Timber Yellow Balaw 1 1/4" thick Sq.ft
T Timber Yellow Balaw 1" thick Sq.ft
T
T Tholang 2"x1" timber L.ft
T Tholang 2" x 2" timber L.ft
T Tholang 2" x 4" timber L.ft
Index
T Tholang 2" x 5" timber L.ft
T Tholang 2" x 6" timber L.ft
T Tholang 2" x 7" timber L.ft
T Tholang 2" x 8" timber L.ft
T Tholang 3" x 4" timber L.ft
T Tholang 3" x 5" timber L.ft
T Tholang 3" x 6" timber L.ft
T Tholang 4" x 6" timber L.ft
T Tholang 4" x 8" timber L.ft
T Tholang 1" x 8" timber L.ft
T Tholang 1" x 9" timber L.ft
T Tholang 1" x 10" timber L.ft
T Tholang 1" x 12" timber L.ft
T Tholang 11/4" x 9" timber L.ft
T Tholang 11/4" x 10" timber L.ft
T Kempus 2" x 2" timber L.ft
T Kempus 2" x 3" timber L.ft
T Kempus 2" x 4" timber L.ft
T Kempus 3" x 4" timber L.ft
T Kempus 2" x 6" timber L.ft
T Kempus 3" x 6" timber L.ft
T Altoniya 2" x 2" timber L.ft
T
T Rubber plank 3/4" x7" L.ft
T
T Tuna timber 6' x 3/4" Sq.ft
T
T 1" thick kubuk plank Sq.ft
T
T 11/4" thick teak timber Local teak Sq.ft
T Sq.ft
T
T Balau Balau Cu.ft
T
T Timber Cu.ft
T
T
T Showring Plank 1' 6'' thick planks s.ft
T Showring Plank 2'' x 6'' joist l ft
11/2" thick Mahogani timber plank
T Showring Plank 12' 0'' long joist no
T Showring Plank 2'' x 4'' joist l ft
T Showring Plank 4' 0'' long props (2''x4'') no
T
P Plywood sheet 6mm 4'x8' Nos
P Plywood sheet 9mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 12mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 15mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 18mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 21mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 25mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 29mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 9mm (W.B.P) 4'x8' Nos
P Plywood sheet 12mm (W.B.P) 4'x8' Nos
P Plywood sheet 15mm (W.B.P) 4'x8' Nos
P Plywood sheet 18mm (W.B.P) 4'x8' Nos
P Plywood sheet 21mm (W.B.P) 4'x8' Nos
P Plywood sheet 25mm (W.B.P) 4'x8' Nos
P Plywood sheet 29mm (W.B.P) 4'x8' Nos
V Valance board timber 1" x9" 1 L.ft
F Finish Timber Stairscse Hand Rail 1 L.ft
F Finish Timber with metal Stairscse Hand Rail 1 L.ft
W Wood treatment 2" x 1" L.ft
W Wood treatment 4" x 1" L.ft
W Wood treatment 5" x 1" L.ft
W Wood treatment 6" x 1" L.ft
W Wood treatment 7" x 1" L.ft
W Wood treatment 8" x 1" L.ft
W Wood treatment 9" x 1" L.ft
W Wood treatment 10" x 1" L.ft
W Wood treatment 11" x 1" L.ft
W Wood treatment 12" x 1" L.ft
W Wood treatment 12" x 1 1/4" L.ft
W Wood treatment 10" x 1 1/4" L.ft
W Wood treatment 9" x 1 1/4" L.ft
W Wood treatment 8" x 1 1/4" L.ft
W Wood treatment 2" x 2" L.ft
W Wood treatment 2" x 3" L.ft
W Wood treatment 2" x 4" L.ft
W Wood treatment 2" x 5" L.ft
W Wood treatment 2" x 6" L.ft
W Wood treatment 2" x 7" L.ft
W Wood treatment 2" x 8" L.ft
W Wood treatment 2" x 10" L.ft
W Wood treatment 3" x 4" L.ft
W Wood treatment 3" x 5" L.ft
W Wood treatment 3" x 6" L.ft
W Wood treatment 3" x 7" L.ft
W Wood treatment 4" x 4" L.ft
W Wood treatment 4" x 5" L.ft
W Wood treatment 4" x 6" L.ft
W Wood treatment 4" x 8" L.ft
W
W Wood Seasion 1'-0" x 1'-0" x 1'-0" Cu.ft
P Planking charges L.ft
P Planking charges Sq.ft
Currencet price Date Other Remark Telephone Price
Timber
375.00
750.00
1,125.00
2,000.00
33.00 5/8/2008 NAM timber Tel 2818800 23.00
55.00 5/8/2008 NAM timber 45.00
135.50 5/8/2008 NAM timber 135.00
171.50 24/01/2008 100.00
214.00 24/01/2008
350.00 24/01/2008
214.00 24/01/2008 106.00
290.00 25/09/2008 NAM timber Tel 2818800 150.00
285.00
458.00 24/01/2008
665.00 24/01/2008
380.00 27/04/2009
292.00 27/04/2009
49.00 26/05/2008
123.50 24/01/2008
163.50 24/01/2008 100.00
198.00 24/01/2008
215.00
290.00 24/01/2008
183.00 26/05/2008 106.00
245.00 26/05/2008 150.00
260.00
410.00 24/01/2008
595.00 26/05/2008
150.00
168.75
187.50
225.00
195.00
217.00
28.00 28/02/2008
65.00 28/02/2009 Nadeeka
135.00 28/02/2009
195.00 28/02/2009
195.00 28/02/2009
325.00 28/02/2009
18.00 15/01/08
11.00 30/10/2004 10,646.76 per M3
95.00
450.00 12/8/2008
95.00 20/03/2009
420.00 25/02/2009
3,240.00 5/8/2008
1,980.00
100.00 125.00
165.00
780.00
165.00
160.00
725.00 12.08.2008 243.78125
2,675.00 1/1/2009 MACKPLY
3,050.00 1/1/2009 1025.5625 0114400136-137 2,055.00
3,200.00 1/1/2009 1076 mackply @sltnet.lk 2,625.00
3,550.00 1/1/2009 1193.6875 2,010.00
4,000.00 1/1/2009 1345
5,800.00 1/1/2009 1950.25
7,550.00 1/1/2009 2538.6875
2,825.00 1/1/2009
3,250.00 1/1/2009 1092.8125
3,450.00 1/1/2009 1160.0625
3,750.00 1/1/2009 1260.9375
4,125.00 1/1/2009 1387.03125
6,175.00 1/1/2009 2076.34375
8,175.00 1/1/2009 2748.84375
200.00 28/02/2009
1,950.00 8/3/2009
2,200.00 8/3/2009
3.54 8/3/2009
7.09 8/3/2009
8.86 8/3/2009
10.63 8/3/2009
12.40 8/3/2009
14.17 8/3/2009
15.94 8/3/2009
17.72 8/3/2009
19.49 8/3/2009
21.26 8/3/2009
26.57 8/3/2009
22.14 8/3/2009
19.92 8/3/2009
17.72 8/3/2009
7.09 8/3/2009
10.63 8/3/2009
14.17 8/3/2009
17.72 8/3/2009
21.26 8/3/2009
24.80 8/3/2009
28.34 8/3/2009
35.43 8/3/2009
21.26 8/3/2009
26.57 8/3/2009
31.89 8/3/2009
37.20 8/3/2009
28.34 8/3/2009
35.43 8/3/2009
42.52 8/3/2009
56.68 8/3/2009
263.00 8/3/2009
10.00 8/3/2009
10.00 8/3/2009
Date
23.00
45.00
135.00
100.00
0/01/2009
Code Category Description Remarks
Tools & Equipment
Z
D Diamond cutting wheel 7"
D 4"
Z
Z
Z
Z
Index
Unit Currencet price Date Other Remark
Tools & Equipment
Nos
Nos
Day
Telephone Price Date
Tools & Equipment
3,500.00
1,350.00
Code Category Description Remarks Unit
Miscellaneous
A Arpifoam 3'x6'x1/4" Sheet
A Arpifoam 3'x6'x1/2" Sheet
A Asphalt Hot application 1ltr
A Angle valve C/P 1/2" German type No
A A/C unit 9000BTU/hr Nos
A A/C unit 12000BTU/hr Nos
A A/C unit 18000BTU/hr Nos
A A/C unit 24000BTU/hr Nos
Staircase Nosing aluminium - natural with VAT- 12' lengths m
Staircase Nosing pvc with VAT - 2.44m lengths m
Water gal
Glass box Nos
A Anti termite tretment 1 Sqr
A Anti termite tretment 1 Sq.ft
Tube Wells For Gardens 30' 0" Nos
For drinking water 100' 0" Nos
1'-0"x 1'-0" glass blocks
Index
Currencet price DateOther RemarkTelephone Price Date
Miscellaneous
103.00
838.00
20.00
225.00
42,930.00 15/02/2007
48,800.00 15/02/2007
62,200.00 15/02/2007
82,300.00 15/02/2007
323.35 28/10/2008
350.41 28/10/2008
0.50
1,700.00
1,975.00
13.00 8/3/2009 Terminators
40000.00-35000.00 21/04/2009
130,000.00 21/04/2009
Miscellaneous
Code Category Description Remarks Unit
Labour / Hire Charges
Labour Mason
Labour Carpenter
Labour Blaksmith
Labour Painter
Labour Plumber
Labour Sk labourLabour Un/sk labourLabour Electricion
Labour Mixer operatorHire Concrete mixture Day
Hire Vibrator Day
Hire Tractor 1 load
Hire Terrazo cut Machine Hire Welding plant Day
Hire JCB Hour
Hire Bracker Day
Index
Currencet price Date Other RemarkTelephone Price Date
Labour / Hire Charges
950.00
950.00
950.00
950.00
950.00
950.00
650.00
950.00
950.00
2,300.00 12/10/2007
1,850.00 12/10/2007
850.00 22/10/2007
3,200.00
2,500.00 1/12/2008
2,000.00 30/04/2009
4,500.00 20/07/2009
Labour / Hire Charges
Orange
OREL SOLUTIONS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792100/1/100 Fax :0114792253
X-SERIES WIRING ACCESSORIES PRICE LIST
ITEM CODE DESCRIPTION NET VAT
Rs. 12%
1 X05-0110 ONE GANG ONE WAY SWITCH 97.40 11.69 X05-0120 TWO GANG ONE WAY SWITCH 164.35 19.72 X05-0130 THREE GANG ONE WAY SWITCH 235.66 28.28 X05-0140 FOUR GANG ONE WAY SWITCH 312.18 37.46 X05-0150 FIVE GANG ONE WAY SWITCH 446.09 53.53 X05-0210 ONE GANG TWO WAY SWITCH 153.99 18.48 X05-0220 TWO GANG TWO WAY SWITCH 270.44 32.45 X05-0230 THREE GANG TWO WAY SWITCH 405.22 48.63 X05-0240 FOUR GANG TWO WAY SWITCH 540.87 64.90 X05-0250 FIVE GANG TWO WAY SWITCH 607.83 72.94 X05-0260 TUMBLER SWITCH 92.18 11.06 X05-0200 BLANK PLATE W/REMOVERBLE PLUG 82.61 9.91
X05-0270 LIGHT DIMMER 665.22 79.83 X05-0280 FAN SPEED CONTROLLER 665.22 79.83 XF5-1100 X SERIES 4 STEP FAN CONTROLLER 716.52 85.98
X05-1050 5A SWITCHED SOCKET OUTLET 271.31 32.56 X05-1060 5A S/SOCKET OUTLET W/NEON 312.18 37.46 X05-1130 13A SWITCH SOCKET OUTLET 286.96 34.44 X05-1140 13A S/SOCKET OUTLET W/NEON 338.27 40.59 X05-1170 13A TWIN SOCKET OUTLET 588.70 70.64 X05-1150 15A SWITCH SOCKET OUTLET 333.05 39.97 X05-1160 15A S/SOCKET OUTLET W/NEON 399.05 47.89 XAC-2050 5A PLUG TOP 116.52 13.98 XAC-2130 13A PLUG TOP 178.26 21.39
XAC-410L LAMP HOLDER 102.61 12.31 TV / TELEPHONE OUTLETS
X05-1190 75 OHM TELEVISION OUTLET 445.22 53.43 X05-1180 ONE GANG 4 WIRE TELPHON OUTLET 445.22 53.43 X05-1200 8 CON 8WAY TEL SOCKET W/PLATE 1,249.57 149.95
MOUNTING BOX XAC-310S MOUNTING BOX (SINGLE) 35.65 4.28
SPECIAL PURPOSE FLUSH SWITCHES X05-0180 X30 1G 2WAY B/PRESS SWITCH 230.44 27.65 X05-0320 20A DOUBLE POLE SWITCH W/NEON 665.22 79.83 X07-1180 COOKER CONTROL UNIT 2,250.43 270.05
Index
X05-1183 4G TRAILING SOCKET OUTLET 1,534.79 184.17
More Details Please Contact Riskhan : 0114792241 or 0773576803. Fax 0114792253
With White or Colour Surround
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
X-2000 WIRING ACCESSORIES PRICE LIST
ITEM CODE DESCRIPTION NET VAT
Rs. 12% SINGLE POLE FLUSH SWITCHES
X07-0110 ONE GANG ONE WAY SWITCH WITH SURROUND 86.91 10.43 X07-0120 TWO GANG ONE WAY SWITCH WITH SURROUND 145.22 17.43 X07-0130 THREE GANG ONE WAY SWITCH WITH SURROUND 213.04 25.56 X07-0140 FOUR GANG ONE WAY SWITCH WITH SURROUND 282.61 33.91 X07-0150 FIVE GANG ONE WAY SWITCH WITH SURROUND 349.57 41.95 X07-0210 ONE GANG TWO WAY SWITCH WITH SURROUND 134.78 16.17 X07-0220 TWO GANG TWO WAY SWITCH WITH SURROUND 245.22 29.43 X07-0230 THREE GANG TWO WAY SWITCH WITH SURROUND 368.70 44.24 X07-0240 FOUR GANG TWO WAY SWITCH WITH SURROUND 491.30 58.96 X07-0200 BLANK PLATE WITH SURROUND 73.91 8.87
LIGHT DIMMERS & FAN SPEED CONTROLLERS
X07-0270 LIGHT DIMMER WITH SURROUND 595.65 71.48 X07-0280 FAN SPEED CONTROLLER WITH SURROUND 595.65 71.48 X07-0300 FAN SPEED CONTROLLER 4 STEP WITH SURROUND 650.43 78.05
SWITCHED SOCKET OUTLETS X07-1050 5A SWITCHED SOCKET OUTLET 245.22 29.43 X07-1130 13A SWITCHED SOCKET OUTLET 260.87 31.30 X07-1150 15A SWITCHED SOCKET OUTLET 300.87 36.10
TV / TELEPHONE OUTLETS X07-1190 TV SOCKET WITH SURROUND 405.22 48.63 X07-1184 TELEPHONE SOCKET WIYH SURROUND 405.22 48.63 X07-1200 8CON 8WAY TELEPHONE SOCKET OUTLET WITH SURROUND -
SPECIAL PURPOSE FLUSH SWITCHES X07-0180 BELL PRESS 204.35 24.52 X07-0190 10A INTERMEDIATE SWITCH 2,455.65 294.68 X07-1170 SHAVER SOCKET 3,426.96 411.24 X07-1180 COOKER CONTROL UNIT 2,250.43 270.05
X07-0915 45A DP APPLIANCE SWITCH WITH NEON 1,575.65 189.08 X07-0910 KEY TAG SWITCH 1,841.74 221.01 X07-0320 20A DOUBLE POLE SWITCH WITH NEON 595.65 71.48
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
X06 WIRING ACCESSORIES PRICE LIST-GOALD HL
ITEM COAD DISCRIPTIONNET VATRs. 12%
SINGLE POLE FLUSH SWITCHES X06-3110 1GANG 1WAY -FERROUS SILVER HL 683.04 81.96 X06-3120 2GANG 1WAY -FERROUS SILVER HL 787.50 94.50 X06-3030 3GANG 1WAY -FERROUS SILVER HL 787.50 94.50 X06-3140 4GANG 1WAY -FERROUS SILVER HL 866.07 103.93 X06-3150 5GANG 1WAY -FERROUS SILVER HL 945.54 113.46 X06-3210 1GANG 2WAY -FERROUS SILVER HL 735.71 88.29 X06-3220 2 GANG 2WAY -FERROUS SILVER HL 840.18 100.82
LIGHT DIMMERS & FAN SPEED CONTROLLERS
X06-3270 LIGHT DIMMER-FERROUS SILVER HL 1,334.82 160.18 X06-3280 FAN CONTROL-FERROUS SILVER HL 1,334.82 160.18
SWITCHED SOCKET OUTLETS
X06-3050 5A S/SOCKET -FERROUS SILVER HL 645.54 77.46 X06-3130 13A S/SOCKET -FERROUS SILVER HL 787.50 94.50
TV / TELEPHONE OUTLETS
X06-3190 TV SOCKET - FERROUS SILVER HL 1,371.43 164.57 X06-3080 X6 Telepho Skt-FERROUS SILVER HL 740.18 88.82
SPECIAL PURPOSE FLUSH SWITCHES X06-3180 BELL PRESS - FERROUS SILVER HL 566.96 68.04
X06-3320 DOUBLE POLE-FERROUS SILVER HL 840.18 100.82
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792131/100 Fax :0114792128
ORANGE ALPHA & SIGMA PRICE LIST ORANGE ALPHA
XMA-106C 6A 1POLE MCB Type C 179.14 21.50 XMA-110C 10A 1POLE MCB Type C 179.14 21.50 XMA-116C 16A 1POLE MCB Type C 179.14 21.50 XMA-120C 20A 1POLE MCB Type C 179.14 21.50 XMA-132C 32A 1POLE MCB Type C 179.14 21.50 XRA-240Y 40A 30mA 2POLE RCD 1,611.31 193.36 XIS-240A 40A 2POLE ISOLATOR 399.14 47.90
ORANGE SIGMA XMS-106C 6A 1 POLE MCB TYPE C - SIGMA (With 5Years Warraty) 302.61 36.31 XMS-110C 10A 1 POLE MCB TYPE C- SIGMA ( do) 302.61 36.31 XMS-116C 16A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31 XMS-120C 20A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31 XMS-132C 32A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31 XMS-140C 40A 1 POLE MCB TYPE C - SIGMA (do) 343.48 41.22 XMS-206C 6A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39 XMS-210C 10A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39 XMS-216C 16A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39 XMS-220C 20A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39 XMS-232C 32A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39 XMS-240C 40A 2 POLE MCB TYPE C - SIGMA (do) 660.00 79.20 XMS-263C 63A 2 POLE MCB TYPE C - SIGMA (do) 660.00 79.20
XMS-306C 6A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73 XMS-310C 10A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73 XMS-316C 16A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73 XMS-320C 20A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73 XMS-332C 32A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73 XMS-340C 40A 3 POLE MCB TYPE C - SIGMA (do) 941.74 113.01 XMS-363C 63A 3 POLE MCB TYPE C - SIGMA (do) 1,002.61 120.31 XMS-406C 6A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16 XMS-410C 10A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16 XMS-416C 16A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16 XMS-420C 20A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16 XMS-432C 32A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16 XMS-440C 40A 4 POLE MCB TYPE C - SIGMA (do) 1,213.05 145.57 XMS-463C 63A 4 POLE MCB TYPE C - SIGMA (do) 1,330.44 159.65
RCD SIGMA XRS-240Y 40A 30mA 2 POLE RCD - SIGMA ( with 5 Years warranty) 2,148.70 257.84 XRS-240Z 40A 100mA 2 POLE RCD - SIGMA ( do) 2,327.83 279.34 XRS-240Y 63A 30mA 2 POLE RCD - SIGMA ( do) 2,302.61 276.31 XRS-240Z 63A 100mA 2 POLE RCD - SIGMA ( do) 2,358.27 282.99 XRS-240Y 40A 30mA 4 POLE RCD - SIGMA ( do) 3,100.00 372.00 XRS-240Z 40A 100mA 4 POLE RCD - SIGMA ( do) 3,222.61 386.71 XRS-240Y 63A 30mA 4 POLE RCD - SIGMA ( do) 3,401.74 408.21
XIS-240A 40A 2 POLE ISOLATOR - SIGMA ( With 5 Years Warranty) 640.00 76.80 XIS-263A 63A 2POLE ISOLATER -SIGMA (do) 757.40 90.89 XIS-340A 40A 3POLE ISOLATER -SIGMA (do) 1,064.35 127.72 XIS-363A 63A 3POLE ISOLATER -SIGMA (do) 1,151.31 138.16 XIS-440A 40A 4POLE ISOLATER -SIGMA (do) 1,213.05 145.57 XIS-463A 63A 4POLE ISOLATER -SIGMA (do) 1,330.44 159.65
Prices are subjected to change without prior notice5 Years Warranty For Sigma Products & 1 Year Warranty For Alpha RCD
More Details Please Contact Lakshitha Morawaka: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
ORANGE COMPACT FLUORESCENT LAMPS (CFL.s) ZT000310 ORANGE CFL 5W (Day Light / Pin Type) 265.22 31.83 XCU-P07D ORANGE CFL 7W (Day Light / Pin Type) 265.22 31.83 XCU-P09D ORANGE CFL 9W (Day Light / Pin Type) 265.22 31.83 XCU-P11D ORANGE CFL 11W (Day Light / Pin Type) 265.22 31.83 XCU-P15D ORANGE CFL 15W (Day Light / Pin Type) 265.22 31.83 XCU-P20D ORANGE CFL 20W (Day Light / Pin Type) 321.74 38.61
XCU-P05W ORANGE CFL 5W (Warm White / Pin Type) 265.22 31.83 XCU-P09W ORANGE CFL 9W (Warm White / Pin Type) 265.22 31.83 XCU-P11W ORANGE CFL 11W (Warm White / Pin Type) 265.22 31.83 XCU-P15W ORANGE CFL 15W (Warm White / Pin Type) 265.22 31.83 XCU-P20W ORANGE CFL 20W (Warm White / Pin Type) 321.74 38.61
ZT000311 ORANGE CFL 5W (Day Light / Srew Type) 265.22 31.83 XCU-S09D ORANGE CFL 9W (Day Light / Srew Type) 265.22 31.83 XCU-S11D ORANGE CFL 11W (Day Light / Srew Type) 265.22 31.83 XCU-S15D ORANGE CFL 15W (Day Light / Srew Type) 265.22 31.83 XCU-S20D ORANGE CFL 20W (Day Light / Srew Type) 321.74 38.61
XCU-S05D ORANGE CFL 9W (Warm White / Srew Type) 265.22 31.83 XCU-S09W ORANGE CFL 9W (Warm White / Srew Type) 265.22 31.83 XCU-S11W ORANGE CFL 11W (Warm White / Srew Type) 265.22 31.83 XCU-S15W ORANGE CFL 15W (Warm White / Srew Type) 265.22 31.83 XCU-S20W ORANGE CFL 20W (Warm White / Srew Type) 321.74 38.61(Warranty : 18 Month)
ORANGE SPIRAL CFL XCS-P07D ORANGE SPIRAL CFL 7W (Day Light / Pin Type) 308.70 37.04 XCS-P11D ORANGE SPIRAL CFL 11W (Day Light / Pin Type) 308.70 37.04 XCS-P15D ORANGE SPIRAL CFL 15W (Day Light / Pin Type) 308.70 37.04 XCS-P20D ORANGE SPIRAL CFL 20W (Day Light / Pin Type) 391.70 47.00 XCS-P25D ORANGE SPIRAL CFL 25W (Day Light / Pin Type) 413.04 49.56 XCS-S07D ORANGE SPIRAL CFL 7W (Day Light / Srew Type) 308.70 37.04 XCS-S11D ORANGE SPIRAL CFL11W (Day Light / Srew Type) 308.70 37.04 XCS-S15D ORANGE SPIRAL CFL15W (Day Light /SrewType) 308.70 37.04 XCS-S20D ORANGE SPIRAL CFL 20W (Day Light / Srew Type) 391.30 46.96
XCS-S25D ORANGE SPIRAL CFL 25W (Day Light / Srew Type) 413.04 49.56XCS-P07W ORANGE SPIRAL CFL 7W (Warm White / Pin Type) 308.70 37.04XCS-P11W ORANGE SPIRAL CFL 11W ( Warm White/ Pin Type) 308.70 37.04XCS-P15W ORANGE SPIRAL CFL 15W ( Warm White/ Pin Type) 308.70 37.04XCS-P20W ORANGE SPIRAL CFL 20W ( Warm White/ Pin Type) 391.30 46.96XCS-S07W ORANGE SPIRAL CFL 7W (Warm White / Screw Type) 308.70 37.04XCS-S11W ORANGE SPIRAL CFL 11W (Warm White / Screw Type) 308.70 37.04XCS-S15W ORANGE SPIRAL CFL 15W (Warm White / Screw Type) 308.70 37.04XCS-S11W ORANGE SPIRAL CFL 20W (Warm White / Screw Type) 391.30 46.96
Warranty : 12 Month ORANGE FLOURESCENT TUBES
XTL-018D FLUORESCENT TUBE 2FEET - DAYLIGHT 73.91 8.87 XTL-036D FLUORESCENT TUBE 4FEET - DAYLIGHT 73.91 8.87
ORANGE GLS XG1-025C 25W GLS BULBS (Clear /Pin Type) 55.36 6.64 XG1-040C 40W GLS BULBS (Clear /Pin Type) 55.36 6.64 XG1-060C 60W GLS BULBS (Clear /Pin Type) 55.36 6.64 XG1-075C 75W GLS BULBS (Clear /Pin Type) 55.36 6.64 XG1-100C 100W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG2-025C 25W GLS BULBS (Clear /Screw Type) 55.36 6.64 XG2-040C 40W GLS BULBS (Clear /ScrewType) 55.36 6.64 XG2-060C 60W GLS BULBS (Clear /Screw Type) 55.36 6.64 XG2-075C 75W GLS BULBS (Clear /Screw Type) 55.36 6.64 XG2-100C 100W GLS BULBS (Clear /Pin Type) 55.36 6.64
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
OREL SOLUTIONS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133 Fax :0114792253
CABLE PRICE LIST Item Description Imp Size mm Size
PVC Cable XT-01113-B-RD-4 1/1.13mm S/C 100m Red 1/0.044 1
XT-01113-B-RD-1/1.13mmS/C 50m Red 1/0.044 1 XT-01113-B-BK-4 1/1.13mm S/C 100m Black 1/0.044 1
XT-01113-B-BK-1/1.13mmS/C 50m Red 1/0.044 1 XT-07053-B-RD-4 7/0.50mm S/C100m Red 3/0.036 1.5 XT-07053-B-BK-4 7/0.50mm S/C100m Black 3/0.036 1.5 XT-07053-C-MC-4 7/0.50mm T/ Flat 100m 3/0.036 1.5 XT-07067-B-RD-4 7/0.67mm S/C100m Red 7/0.029 2.5 XT-07067-B-BK-4 7/0.67mm S/C100m Black 7/0.029 2.5 XT-07067-C-MC-4 7/0.67mm T/ F 100m 7/0.029 2.5 XT-07067-P-MC-4 7/0.67 mm Green 100m 7/0.029 2.5 XT-07067-P-MC-2 7/0.67 mm Green 50m 7/0.029 2.5 XT-07085-B-RD-4 7/0.85 mm S/C100m Red 7/0.036 4 XT-07085-B-BK-4 7/0.85 mm S/C100m Black 7/0.036 4 XT-07085-C-MC-4 7/0.85 mm T/ F 100m 7/0.036 4 XT-07104-B-RD-4 7/1.04mm S/C 100m Red 7/0.044 6 XT-07104-B-BK-4 7/1.04mm S/C 100m Black 7/0.044 6 XT-07104-C-MC-4 7/1.04mm T/ F 100m 7/0.044 6 XT-07104-C-MC-2 7/1.04mm T/ F 50m 7/0.044 6 XT-07135-B-RD-4 7/1.35mm S/C 100m Red 7/0.052 10
XT-07135-B-BK-4 7/1.35mm S/C 100m Black 7/0.052 10 XT-07135-C-MC-4 7/1.35mm T/ F 100m 7/0.052 10 XT-07170-B-RD-4 7/1.70mmS/C 100m Red 7/0.064 16 XT-07170-B-BK-4 7/1.70mmS/C 100m Black 7/0.064 16 XT-07170-C-MC-4 7/1.70mm T/ F 100m 7/0.064 16
XLPE INSULATED CABLES (Cu/XLPE/PVC)
XT-07214-B-BK-7/2.14mm S/C 100m Red 19/0.044 25XT-07214-B-RD-7/2.14mm S/C 100m Red 19/0.044 25
XT-19135-B-BK-4 19/1.35mm S/C 100m Black 19/0.052 25 XT-19135-B-RD-4 19/1.35mm S/C 100m Red 19/0.052 25
XT-19153-B-RD-19/1.53mm S/C 100m Red 19/0.064 35XT-19153-B-BK-19/1.53mm S/C 100m Black 19/0.064 35XT-19178-B-RD-19/1.78mm S/C 100m Red 19/0.073 50XT-19178-B-BK-19/1.78mm S/C 100m Black 19/0.073 50XT-19214-B-RD-19/2.14mm S/C 100m Red 19/0.083 70XT-19214-B-BK-19/2.14mm S/C 100m Black 19/0.083 70XT-19252-B-RD-19/2.52mm S/C 100m Red 37/0.072 95XT-19252-B-BK-19/2.52mm S/C 100m Black 37/0.072 95XT-37178-B-RD-37/1.78mm S/C 100m Red 37/0.072 95XT-37178-B-BK-37/1.78mm S/C 100m Black 37/0.072 95XT-37203-B-RD-37/2.03mm S/C 100m Red 37/0.083 120XT-37203-B-BK-37/2.03mm S/C 100m Black 37/0.083 120XT-37225-B-RD-37/2.25mm S/C 100m Red 37/0.093 150XT-37225-B-BK-37/2.25mm S/C 100m Black 37/0.093 150XT-37252-B-RD-37/2.52mm S/C 100m Red 37/0.103 185XT-37252-B-BK-37/2.52mm S/C 100m Black 37/0.103 185XT-61225-B-RD-61/2.25mm S/C 100m Red 61/0.093 240XT-61225-B-BK-61/2.25mm S/C 100m Black 61/0.093 240XT-61252-B-RD-61/2.52mm S/C 100m Red 61/0.103 300XT-61252-B-BK-61/2.52mm S/C 100m Black 61/0.103 300XT-61285-B-RD-61/2.85mm S/C 100m Red 400XT-61285-B-BK-61/2.85mm S/C 100m Black 400XT-61320-B-RD-61/3.20mm S/C 100m Red 91/0.103 500XT-61320-B-BK-61/3.20mm S/C 100m Black 91/0.103 500
Orange
OREL SOLUTIONS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792100/1/100 Fax :0114792253
X-SERIES WIRING ACCESSORIES PRICE LIST GROSS
Rs.
1 109.09 184.07 263.94 349.64 499.62 172.47 302.89 453.85 605.77 680.77 103.24 92.52
745.05 745.05 802.50
303.87 349.64 321.40 378.86 659.34 373.02 446.94 130.50 199.65 114.92
TV / TELEPHONE OUTLETS 498.65 498.65 1,399.52
MOUNTING BOX 39.93
SPECIAL PURPOSE FLUSH SWITCHES 258.09 745.05 2,520.48
1,718.96
More Details Please Contact Riskhan : 0114792241 or 0773576803. Fax 0114792253
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
X-2000 WIRING ACCESSORIES PRICE LIST GROSS
Rs. SINGLE POLE FLUSH SWITCHES
97.34
162.65
238.60
316.52
391.52
150.95
274.65 412.94 550.26 82.78
LIGHT DIMMERS & FAN SPEED CONTROLLERS
667.13
667.13
728.48
SWITCHED SOCKET OUTLETS
274.65
292.17
336.97
TV / TELEPHONE OUTLETS
453.85
453.85
-
SPECIAL PURPOSE FLUSH SWITCHES 228.87
2,750.33
3,838.20
2,520.48
1,764.73
2,062.75
667.13
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
X06 WIRING ACCESSORIES PRICE LIST-GOALD HLGROSS
Rs.
SINGLE POLE FLUSH SWITCHES 765.00 882.00 882.00 970.00
### 824.00 941.00
LIGHT DIMMERS & FAN SPEED CONTROLLERS
######
SWITCHED SOCKET OUTLETS
723.00 882.00
TV / TELEPHONE OUTLETS
### 829.00
SPECIAL PURPOSE FLUSH SWITCHES 635.00 941.00
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792131/100 Fax :0114792128
ORANGE ALPHA & SIGMA PRICE LIST ORANGE ALPHA
200.64 200.64 200.64 200.64 200.64 1,804.67 447.04
ORANGE SIGMA 338.92 338.92 338.92 338.92 338.92 384.70 647.66 647.66 647.66 647.66 647.66 739.20 739.20
1,014.82 1,014.82 1,014.82 1,014.82 1,014.82 725.00 800.00 925.00 925.00 925.00 925.00 925.00 975.00 1,000.00
RCD SIGMA 2,406.54 2,607.17 2,578.92 2,641.26 3,472.00 3,609.32 3,809.95
716.80 848.29 1,192.07 1,289.47 1,358.62 1,490.09
Prices are subjected to change without prior notice5 Years Warranty For Sigma Products & 1 Year Warranty For Alpha RCD
More Details Please Contact Lakshitha Morawaka: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
ORANGE COMPACT FLUORESCENT LAMPS (CFL.s) 297.05 297.05 297.05 297.05 297.05 360.35
297.05 297.05 297.05 297.05 360.35
297.05 297.05 297.05 297.05 360.35
297.05 297.05 297.05 297.05 360.35
345.74 345.74 345.74 438.70 462.60 345.74 345.74 345.74 438.26 462.60 345.74 345.74 345.74 438.26 345.74 345.74 345.74 438.26
82.78 82.78
62.00 62.00 62.00 62.00 62.00
62.00 62.00 62.00 62.00 62.00
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
OREL SOLUTIONS (PVT) LTD No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133 Fax :0114792253
CABLE PRICE LIST Amp Net Vat Gross Price
12 1,286.96 154.44 1441.4012 643.48 77.22 720.7012 1,286.96 154.44 1441.4012 643.48 77.22 720.7014 2,803.48 336.42 3139.9014 2,803.48 336.42 3139.9014 5,337.39 640.49 5977.8817 4144.57 497.35 4641.9217 4144.57 497.35 4641.9217 7776.96 933.24 8710.2017 3733.48 448.02 4181.5017 1866.74 224.01 2090.7529 6476.30 777.16 7253.4629 6476.30 777.16 7253.4629 12245.00 1469.40 13714.4037 9407.83 1128.94 10536.7737 9407.83 1128.94 10536.7737 16800.65 2016.08 18816.7337 8400.33 1008.04 9408.3751 15506.74 1860.81 17367.55
51 15506.74 1860.81 17367.5551 27859.57 3343.15 31202.7266 23647.61 2837.71 26485.3266 23647.61 2837.71 26485.3266 42065.65 5047.88 47113.53
87 38372.61 5755.89 44128.5087 38372.61 5755.89 44128.5087 40805.43 6120.81 46926.2487 40805.43 6120.81 46926.24
106 52720.22 7908.03 60628.25106 52720.22 7908.03 60628.25125 64918.04 9737.71 74655.75125 64918.04 9737.71 74655.75160 107078.04 16061.71 123139.75160 107078.04 16061.71 123139.75195 134411.96 20161.79 154573.75195 134411.96 20161.79 154573.75195 139567.39 20935.11 160502.50195 139567.39 20935.11 160502.50220 186181.96 27927.29 214109.25220 186181.96 27927.29 214109.25260 211581.74 31737.26 243319.00260 211581.74 31737.26 243319.00295 264396.30 39659.45 304055.75295 264396.30 39659.45 304055.75360 391300.87 58695.13 449996.00360 391300.87 58695.13 449996.00410 500218.70 75032.81 575251.51410 500218.70 75032.81 575251.51457 612135.43 91820.31 703955.74457 612135.43 91820.31 703955.74520 790783.04 118617.46 909400.50520 790783.04 118617.46 909400.50
HabourFenders & Bollards
#Description Unit Qty Rate Amount
1
m 3 1,500.00 4,500.00
2 Mild steel D-shackle 12mm nr 1 175.00 175.00
3m 1.8 16,666.67 30,000.00
Mild steel chain links with 16mm wire (available in 3m lengths)
Rubber Fender (1800mm length - IRHD 65)
Index
Habour
Habour
Contact Mr. Chaminda Williams0773 667665
# Description Rate Unit
Notes:Micro partitining systemsiutable for both internal & external wallscan build with the rigiform+mesh panels to any spansupply & installation done by micro
13200 sq.ft.
2450 sq.ft.
Per unit floor area to complete including all foundation work, structure, finishing as with normal brick wall.
Per unit wall area including plaster and painted finish as with normal brick wall
Index
Habour
LABOUR RATES
Code Category Description Remarks Unit
Labour Rate
1 Labour Rate Foundation excavation Cube
2 Labour Rate Earth filling around foundation Cube
3 Labour Rate 2" thick lean concrete Sq.ft
4 Labour Rate 3" thick lean concrete Sq.ft
5 Labour Rate 4" thick lean concrete Sq.ft
6 Labour Rate Column base 3'-0" 3'-0" Nos
7 Labour Rate Column base 6" thick Sq.ft
8 Labour Rate Column base 9" thick Sq.ft
9 Labour Rate Column base 12" thick Sq.ft
10 Labour Rate Rubble foundation Cu.ft
11 Labour Rate DPC 1'-0" with (Two coat tar) L.ft
12 Labour Rate 9" thick brick wall Sq.ft
13 Labour Rate 41/2" thick brick wall Sq.ft
14 Labour Rate 8" thick block wall Sq.ft
15 Labour Rate 6" thick block wall Sq.ft
16 Labour Rate 4" thick block wall Sq.ft
17 Labour Rate Column 9" x 9" L.ft
18 Labour Rate Column 12" x 12" L.ft
19 Labour Rate Lintol 41/2" X 6" L.ft
20 Labour Rate Lintol 4" X 6" L.ft
21 Labour Rate Lintol 9" X 6" L.ft
22 Labour Rate Beam 9" x 9" L.ft
23 Labour Rate Beam 9" x 12" L.ft
24 Labour Rate Beam 9" x 15" L.ft
25 Labour Rate Beam 9" x 18" L.ft
26 Labour Rate 41/2" thick slab -Conc., R/F & formwork Sq.ft
27 Labour Rate Stair case Sq.ft
28 Labour Rate Smooth plaster Sq.ft
29 Labour Rate Rough plaster Sq.ft
30 Labour Rate Soffit plaster Sq.ft
31 Labour Rate Smooth plaster in sides of column & beam Sq.ft
32 Labour Rate Rough plaster in sides of column & beam Sq.ft
33 Labour Rate Floor concrete 3" Sqr
34 Labour Rate Cement rendering- smooth Sq.ft
35 Labour Rate Cement rendering- rough Sq.ft
36 Labour Rate Skirting - cement L.ft
Index
37 Labour Rate Floor tile 1' 6" x 1' 6" Sq.ft
38 Labour Rate Wall tile Sq.ft
39 Labour Rate Skirting - tile L.ft
40 Labour Rate Plinth plaster Sq.ft
41 Labour Rate Internal painting Sqr
42 Labour Rate External painting Sqr
43 Labour Rate Putty & paint Sqr
44 Labour Rate Door frame fix Nos
45 Labour Rate Window - large Nos
46 Labour Rate Window Nos
47 Labour Rate Polishing Sqr
48 Labour Rate weather gard L.ft
49 Labour Rate Ridge tile L.ft
50 Labour Rate Concrete drain with plastering Sq.ft
51 Labour Rate Manhole (2' x 2' x 2') Nos
52 Labour Rate Terazzo Sq.ft
53 Labour Rate Titanium - normal Sq.ft
54 Labour Rate Titanium - colour Sq.ft
55 Labour Rate Fixing marble with adhensive Sq.ft
56 Labour Rate Fixing tile 1'-0" x 1'-0" Sq.ft
57 Labour Rate Assorted dressed stone Sq.ft
58 Labour Rate Glass mosaic Tile Sq.ft
Labour Rate Mason
Labour Rate Labour
Currencet price Date Other Remark Telephon Price Date Price
Labour Rate
2,000.00 23/11/2009 1,500.00 12/1/2009
800.00 23/11/2009 1,000.00 12/1/2009
25.00 23/11/2009
30.00 23/11/2009 25.00 12/1/2009
35.00 10/11/2009
2,400.00 12/1/2009
65.00 23/11/2009
70.00 23/11/2009
75.00 23/11/2009
42.00 23/11/2009 30.00 12/1/2009
20.00 23/11/2009 15.00 12/1/2009
45.00 23/11/2009 42.00 10/11/2009 38.00
30.00 23/11/2009 35.00 10/11/2009 25.00
32.00 23/11/2009 35.00 10/11/2009
28.00 23/11/2009 30.00 10/11/2009
25.00 23/11/2009 25.00 10/11/2009
95.00 23/11/2009 85.00 12/1/2009
110.00 12/1/2009
55.00 12/1/2009
50.00 23/11/2009
55.00 23/11/2009 65.00 12/1/2009
100.00 23/11/2009 80.00 12/1/2009
110.00 23/11/2009 95.00 12/1/2009
120.00 23/11/2009
125.00 23/11/2009
70.00 23/11/2009 85.00 12/1/2009
160.00 23/11/2009
20.00 23/11/2009 20.00 8/3/2009 20.00
18.00 23/11/2009 18.00 8/3/2009 18.00
27.00 23/11/2009 28.00 8/3/2009 28.00
45.00 23/11/2009
40.00 23/11/2009
2,500.00 12/1/2009
30.00 23/11/2009 21.00 12/1/2009
20.00 23/11/2009
30.00 23/11/2009 28.00 12/1/2009
35.00 23/11/2009 37.50 8/3/2009 30.00
45.00 23/11/2009 40.00 8/3/2009 45.00
40.00 23/11/2009
30.00 23/11/2009
1,200.00 8/3/2009
1,000.00 8/3/2009
2,000.00 8/3/2009
600.00 23/11/2009 500.00 8/3/2009
850.00 23/11/2009
600.00 8/3/2009
3,500.00 8/3/2009
60.00 23/11/2009
55.00 23/11/2009
70.00 23/11/2009
3,000.00 23/11/2009
270.00 1/6/2009
220.00 1/6/2009
250.00 1/6/2009
125.00 1/6/2009
35.00 1/6/2009
40.00 1/6/2009
50.00 1/6/2009
1,250.00 8/3/2009 950.00
850.00 8/3/2009 650.00
Date Price Date
8/3/2009 28.00 12/1/2009
8/3/2009 24.00 12/1/2009
12/1/2009
12/1/2009
12/1/2009
12/1/2009
12/1/2009
HOSPITAL EQUEPMENT
Code Category Description Remarks Unit
Paitient Beds NrDelivery beds NrExamination beds NrPaitient Trolley NrDrug Trolley NrDressing Trolley NrWheel chair NrWard screen NrSaline stand NrBed side cupboard NrOxygen cylinder stand
Index
Currencet price Date Other Remark Telephone Price
25,000.00 26/05/2010 Biomed International (Pvt) Ltd 2576104 /2577226 300,000.00 26/05/2010 25,000.00 26/05/2010 25,000.00 26/05/2010 30,000.00 26/05/2010 30,000.00 26/05/2010
26/05/2010 25,000.00 26/05/2010 12,500.00 26/05/2010 15,000.00 26/05/2010 15,000.00 26/05/2010
Date Price Date Price Date
Discription Nos Length Width Height Qty
3.1.21
Assume 10 L,ft
MaterialConcrete for pergolasWastage 10%Reinforcement Y 10
Painting two coats weather shield emulsion paint
Labour
Cost for 10 L.ftO/H % Profit 18%
Cost for 1 L.ftCost for 1 m
assume 10 m2
Material6mm double sided 'Macfoil ' screws and nailswastage 5%Transport 7%
LabourunskilledTools 3%
Total cost O/H % Profit 18%
Casting and fixing in position 6"x 2 1/2" R.C pergolas reinforced with 02 nos.Y 10 bars and R6 links at 6" centres all complete Rate shall include for prepare and apply two coats weather shield emulsion paint of approved quality and colour .
Supply and lay 6mm double sided 'Macfoil ' aluminium foil as directed.
Cost for 10m2Cost for 1m2
6.10
Assume 10 L.ft
MaterialHalf round tileCementSandTransport 10%
LabourSkilledUn skilledTools 3%
Cost for 10 L.ft
O/H % Profit 18%
Cost for 1 L.ftCost for 1 m
14.02
14.03
Supply and lay two layers of half round tiles as coping over walls/boundary walls complete as per drawing .
Single sash white powder coated aluminium louvred door complete as per type D6 , Size 750x2400mm
White powder coated aluminium window with glazed and louvred panels complete as per type W2 ,Size 600x1500mm
14.03
Material
36mm dia GI frame18mm GI horizontal members GI Hinges 3" x 5"Locking divice
LabourTools 3%
Total cost
Add O/H & Profit 18%
Cost for I DoorCost for I m2
14.04
14.05
14.06
14.07
14.08
Mild steel grille door complete as per type G1 Size 1500x2400mm
Mild steel grille door complete as per type G2 Size 900x2400mm
Mild steel grille door complete as per type G3 Size 1237x1800mm
Mild steel grille door complete as per type G4 Size 4000 x 2875mm
Mild steel grille door complete as per type G5 Size 4200 x 2875mm
Mild steel grille door complete as per type G6 Size 600 x 750 mm
14.09
15.01
Material100mm thick brick wall 4 0.60 2.10 5.04 75mm thick RCC shelves 9 0.92 0.60 4.97 Formwork 18 0.92 0.60 9.94 BRC mesh 9 0.92 0.60 4.97 50 x 50mm timber frame 10 2.10 21.00
5 0.92 4.60 Plywood doors 5 5.00 Brick wall & shelves plastering 8 0.60 2.10 10.08
18 0.92 0.60 9.94 Brick wall & shelves painting 8 0.60 2.10 10.08
18 0.92 0.60 9.94 Plywood doors painting 10 0.92 2.10 19.32 Self closing hinges 10 10.00
Total costO/H % Profit 18%
15.02
Material100mm thick brick wall 2 0.30 2.40 1.44
3 0.30 1.05 0.94 75mm thick RCC shelves 22 0.30 0.70 4.62
1 3.50 0.60 2.10 Formwork 44 0.30 0.70 9.24
2 3.50 0.60 4.20 BRC mesh 22 0.30 0.70 4.62
1 3.50 0.60 2.10
Mild steel grille door complete as per type G7 Size 1500 x 1500 mm
Built in R.C.C. concrete storage unit with shelves 75mm thick 5000x600 mm and 5000x300 mm with 16mm thick plywood doors with a painted finish and self closing hinges and lock in store room complete as per drawing .
Built in R.C.C. concrete storage unit with shelves 75mm thick 5000x600 mm and 5000x300 mm with 16mm thick plywood doors with a painted finish and self closing hinges and lock in study room complete as per drawing .
50 x 50mm timber frame 8 0.75 6.00 Plywood doors 2 0.75 0.75 1.13 Brick wall & shelves plastering 4 0.30 2.40 2.88
6 0.30 1.05 1.89 44 0.30 0.70 9.24
Brick wall & shelves painting 4 0.30 2.40 2.88 6 0.30 1.05 1.89
44 0.30 0.70 9.24 Plywood doors painting 2 0.75 0.75 1.13 Cut & polish concrete 1 3.50 0.60 2.10 Self closing hinges 4 4.00
Total costO/H % Profit 18%
15.04 Material75mm thick RCC shelves 1 5.00 0.60 3.00
8 0.60 0.90 4.32 6 2.40 0.60 8.64 1 5.00 0.60 3.00 1 2.70 0.60 1.62 1 5.00 1.14 5.70
Formwork 2 5.00 0.60 6.00 16 0.60 0.90 8.64 12 2.40 0.60 17.28
2 5.00 0.60 6.00 2 2.70 0.60 3.23 2 5.00 1.14 11.40
BRC mesh 1 5.00 0.60 3.00 8 0.60 0.90 4.32 6 2.40 0.60 8.64 1 5.00 0.60 3.00 1 2.70 0.60 1.62 1 5.00 1.14 5.70
Plywood doors 5.00 0.75 3.75 5.00 2.40 12.00
10 0.90 0.60 5.40 10 0.30 0.90 2.70
Built in R.C.C Work Tops,shelves and granite slab over work top /shelves , internal shelf of timber,drawers and cupboards doors in pantry all complete as per drawing .
10 0.30 0.60 1.80
Brick wall & shelves plastering 2 5.00 0.60 6.00 16 0.60 0.90 8.64 12 2.40 0.60 17.28
2 5.00 0.60 6.00 2 2.70 0.60 3.23 2 5.00 1.14 11.40
Brick wall & shelves painting 2 5.00 0.60 6.00 16 0.60 0.90 8.64 12 2.40 0.60 17.28
2 5.00 0.60 6.00 2 2.70 0.60 3.23 2 5.00 1.14 11.40
Plywood doors painting 2 5.00 0.75 7.50 2 5.00 2.40 24.00
20 0.90 0.60 10.80 20 0.30 0.90 5.40 20 0.30 0.60 3.60
Granite 5.00 0.60 3.00 5.00 1.14 5.70 0.98 0.90 0.88
Self closing hinges 4 4.00
Total costO/H % Profit 18%
15.05
MaterialConcrete 4.90 0.95 0.30 1.40
2.40 0.25 0.70 0.42
Formwork 1 4.90 0.30 1.47 2 0.95 0.30 0.57 2 2.40 0.70 3.36 2 0.70 0.25 0.35
BRC mesh 4.90 0.95 4.66 2.40 0.25 0.60
Built in seat / table with cut & polished cement finish in living room complete as per drawing .
Cut & Polish 2 2.40 0.70 3.36 2 0.80 1.25 2.00
100mm deep cushion 2 2.40 0.70 3.36
Rough granite 2 0.30 1.25 0.75
Total costO/H % Profit 18%
15.06
75mm thick RCC shelves 5 2.58 0.60 7.73 1 0.52 0.60 0.31
13 0.90 0.60 7.02 3 0.96 0.60 1.72 2 1.13 0.60 1.36 3 2.16 0.60 3.89 5 0.90 0.60 2.70
Formwork 10 2.58 0.60 15.45 2 0.52 0.60 0.62
26 0.90 0.60 14.04 6 0.96 0.60 3.44 4 1.13 0.60 2.72 6 2.16 0.60 7.79
10 0.90 0.60 5.40
BRC mesh 5 2.58 0.60 7.73 1 0.52 0.60 0.31
13 0.90 0.60 7.02 3 0.96 0.60 1.72 2 1.13 0.60 1.36 3 2.16 0.60 3.89 5 0.90 0.60 2.70
Cut & Polish 5 2.58 0.60 7.73 1 0.52 0.60 0.31
13 0.90 0.60 7.02 3 0.96 0.60 1.72
Built in R.C.C Work Tops , shelves and cut and polished cement finished over work tops / shelves ,internal shelf of timber,drawers and cupboards doors in kitchen all complete as per drawing .
2 1.13 0.60 1.36 3 2.16 0.60 3.89 5 0.90 0.60 2.70
Plywood doors and drawers 3 0.96 0.60 1.72 6 0.96 0.15 0.86 6 0.60 0.15 0.54
Plywood doors and drawers painting 6 0.96 0.60 3.44 12 0.96 0.15 1.72 12 0.60 0.15 1.08
Total costO/H % Profit 18%
15.07 1.88 1.80
Mass Concrete 1.88 1.80 0.23 0.76 1.80 0.80 0.15 0.22
Formwork 2 1.88 0.23 0.86 2 1.80 0.23 0.83 1 1.80 0.80 1.44 2 0.80 0.15 0.24 1 1.80 0.15 0.27
BRC mesh 1.80 0.15 0.27 0.15 0.80 0.12
Total costO/H % Profit 18%
15.08
Concrete ledge 1 0.68 0.60 0.41
Formwork 1 0.68 0.60 0.41 2 0.68 0.08 0.10 2 0.60 0.08 0.09
BRC Mesh 0.68 0.60 0.00
Cut & polish 1 0.68 0.60 0.41
Built in R.C.C. concrete bed 1875x1800 mm in bed room 01 complete as per drawing .
Built in R.C.C.concrete ledge 600x675 mm in bed room 01 complete as per drawing .
2 0.68 0.08 0.10 2 0.60 0.08 0.09
Total costO/H % Profit 18%
15.09
75mm thick RCC shelves 1 1.38 0.60 0.83 4 1.20 0.60 2.88 2 0.60 0.60 0.72 3 2.40 0.60 4.32
Formwork 2 1.38 0.60 1.65 8 1.20 0.60 5.76 4 0.60 0.60 1.44 6 2.40 0.60 8.64
BRC Mesh 1 1.38 0.60 0.83 4 1.20 0.60 2.88 2 0.60 0.60 0.72 3 2.40 0.60 4.32
Cut & polish 2 1.38 0.60 1.65 8 1.20 0.60 5.76 4 0.60 0.60 1.44 6 2.40 0.60 8.64
Plywood door 2.40 1.20 2.88
Plywood door painting 2 2.40 1.20 5.76
Total costO/H % Profit 18%
15.10 1.95 1.80
Mass Concrete 1.95 1.80 0.23 0.79 1.80 0.80 0.15 0.22
Formwork 2 1.95 0.23 0.90 2 1.80 0.23 0.83
Built in R.C.C.concrete dressing table/storage 2700x600 mm with cement rendered with cupboard doors in bed room 01 complete as per drawing .
Built in R.C.C. concrete bed 1950x1800 mm in bed room 01 complete as per drawing .
1 1.80 0.80 1.44 2 0.80 0.15 0.24 1 1.80 0.15 0.27
BRC Mesh 1.80 0.15 0.27 0.15 0.80 0.12
Total costO/H % Profit 18%
15.13
75mm thick RCC shelves 8 0.68 0.68 3.68 3 1.05 0.60 1.89 4 2.40 0.60 5.76
Formwork 16 0.68 0.68 7.37 6 1.05 0.60 3.78 8 2.40 0.60 11.52
BRC mesh 8 0.68 0.68 3.68 3 1.05 0.60 1.89 4 2.40 0.60 5.76
Cut & polish 16 0.68 0.68 7.37 6 1.05 0.60 3.78 8 2.40 0.60 11.52
Ply wood doors 2 1.60 0.68 2.18
Ply wood doors painting 4 1.60 0.68 4.36
Total costO/H % Profit 18%
15.14 75mm thick RCC shelves 10 0.60 0.60 3.60
4 2.40 0.60 5.76
Built in R.C.C.concrete dressing table 2713x675 mm with cement rendered in master bed room complete as per drawing .
Built in R.C.C.concrete cupboard and open shelfs 3000x2400mm high in master bed room complete as per drawing .
2 1.44 0.60 1.73
Formwork 20 0.60 0.60 7.20 8 2.40 0.60 11.52 4 1.44 0.60 3.46
BRC Mesh 10 0.60 0.60 3.60 4 2.40 0.60 5.76 2 1.44 0.60 1.73
Cut & polish 20 0.60 0.60 7.20 8 2.40 0.60 11.52 4 1.44 0.60 3.46
Ply wood doors 2 2.40 0.68 3.27
Ply wood doors painting 4 2.40 0.68 6.55
Total costO/H % Profit 18%
15.15
75mm thick RCC shelves 5 1.70 0.60 5.09 3 2.40 0.60 4.32
Formwork 10 1.70 0.60 10.17 6 2.40 0.60 8.64
BRC Mesh 5 1.70 0.60 5.09 3 2.40 0.60 4.32
Cut & polish 10 1.70 0.60 10.17 6 2.40 0.60 8.64
Ply wood doors 2 2.40 0.81 3.89
Ply wood doors painting 4 2.40 0.81 7.78
Total costO/H % Profit 18%
Built in R.C.C.concrete cupboard 1695x600 mm with cement rendered in master bed room complete as per drawing .
15.22
75mm thick RCC shelves 1 3.00 0.60 1.80 3 0.75 0.60 1.35
Formwork 2 3.00 0.60 3.60 6 0.75 0.60 2.70
BRC Mesh 1 3.00 0.60 1.80 3 0.75 0.60 1.35
Cut & polish 2 3.00 0.60 3.60 6 0.75 0.60 2.70
Ply wood doors 2 0.75 0.80 1.20
Ply wood doors painting 4 0.75 0.80 2.40
Total costO/H % Profit 18%
15.23
75mm thick RCC shelves 5 1.16 0.60 3.49 2 2.40 0.60 2.88
Formwork 10 1.16 0.60 6.98 4 2.40 0.60 5.76
BRC Mesh 5 1.16 0.60 3.49 2 2.40 0.60 2.88
Cut & polish 10 1.16 0.60 6.98 4 2.40 0.60 5.76
Ply wood door and drawers 1 2.40 1.16 2.78 4 1.16 0.60 2.78 8 1.16 0.15 1.39 8 0.60 0.15 0.72
Ply wood doors painting 2 2.40 1.16 5.57 8 1.16 0.60 5.57
16 1.16 0.15 2.78 16 0.60 0.15 1.44
Built in R.C.C.concrete table 3000x600mm in bed room 02 complete as per drawing .
Built in R.C.C.concrete cupboard with 1163x2400mm including timber doors & drawers in bed room 02 complete as per drawing .
Total costO/H % Profit 18%
15.25
Brick base 2 1.91 0.28 1.05
75mm thick RCC concrete 1.91 0.90 1.72
Formwork 1 1.91 0.90 1.72 2 1.91 0.08 0.29 2 0.90 0.08 0.14
BRC Mesh 1.91 0.90 1.72
Cut & polish 1.91 0.90 1.72
Total costO/H % Profit 18%
15.26
75mm thick RCC concrete 2 2.71 0.60 3.25 1 1.36 0.60 0.81 5 0.90 0.60 2.70
Formwork 4 2.71 0.60 6.51 2 1.36 0.60 1.63
10 0.90 0.60 5.40
BRC Mesh 2 2.71 0.60 3.25 1 1.36 0.60 0.81 5 0.90 0.60 2.70
Cut & polish 4 2.71 0.60 6.51 2 1.36 0.60 1.63
10 0.90 0.60 5.40
Ply wood doors 2 0.90 0.68 1.22
Built in R.C.C. concrete bed 1913x600 mm in staff room complete as per drawing .
Built in R.C.C. concrete work top & open shelves 75mm thick 2712x600x900mm high , granite top and plywood doors with high gloss finish PU paint of approved colour complete as per drawing .
Ply wood doors painting 4 0.90 0.68 2.44
Granite Tile 1 2.71 0.60 1.63
Total costO/H % Profit 18%
Supply and fix cement grill 1m2
Material
1'-0" x1'-0" cement grilCementSandTranspoort
Labour
MasonUn/ Sk
Tools
O/H % Profit 18%
Total Qty Unit Rate
1.10 Cu.ft 200.00 220.00
3.76 Kg 112.00 421.56 1.02 Kg 112.00 113.82
12.50 sq.ft 50.00 625.00
280.00
1,660.38 298.87
1,959.25
195.92 642.63
10.00 m2 191.00 1,910.00 150.00 103.00 144.20
0.10 day 650.00 65.00 1.95
2,374.15 427.35
2,801.50 280.15
44.00 Nos 18.00 792.00 0.01 bag 785.00 7.85 0.02 Cube 7,000.00 140.00 939.85
93.99
0.10 Day 950.00 95.00 0.10 Day 650.00 65.00 160.00
4.80
1,198.64
215.75 1,414.39
141.44 463.92
1.00 10,760.00 1.80 19,368.00
1.00 10,760.00 0.90 9,684.00
1.50 2.40 3.60
18.90 L.ft 165.79 3,133.42 37.50 L.ft 77.63 2,911.18
4.00 Nos 510.00 2,040.00 1.00 Nos 1,500.00 1,500.00 9,584.61
2,000.00 60.00 2,060.00
11,644.61
2,096.03
13,740.63 3,816.84
0.90 2.40 2.16
8,244.38
1.24 1.80 2.23
8,498.58
4.00 2.88 11.50
43,893.69
4.20 2.88 12.08
46,088.38
0.60 0.75 0.45
1,717.58
1.50 1.50 2.25
8,587.90
5.04 m2 1,200.00 6,048.00 4.97 m2 1,100.00 5,464.80 9.94 m2 715.00 7,104.24 4.97 m2 450.00 2,235.60
25.60 m 180.00 4,608.00 5.00 Nos 4,725.00 23,625.00
20.02 m2 580.00 11,609.28
20.02 m2 340.00 6,805.44 19.32 m2 800.00 15,456.00 10.00 Nos 250.00 2,500.00
85,456.36 15,382.14
100,838.50
2.39 m2 1,200.00 2,862.00
6.72 m2 1,100.00 7,392.00
13.44 m2 715.00 9,609.60
6.72 m2 450.00 3,024.00
6.00 m 180.00 1,080.00 1.13 m2 2,500.00 2,812.50
14.01 m2 580.00 8,125.80
14.01 m2 340.00 4,763.40 1.13 m2 800.00 900.00 2.10 m2 1,350.00 2,835.00 4.00 Nos 250.00 1,000.00
44,404.30 7,992.77
52,397.07
26.28 m2 1,100.00 28,904.70
52.55 m2 715.00 37,576.11
26.28 m2 450.00 11,824.65
25.65 m2 2,500.00 64,125.00
52.55 m2 580.00 30,481.32
52.55 m2 340.00 17,868.36
51.30 m2 800.00 41,040.00
9.58 m2 8,000.00 76,620.00
4.00 Nos 250.00 1,000.00
309,440.14 55,699.23
365,139.37
1.82 m3 12,245.00 22,243.04
5.75 m2 715.00 4,111.25
5.26 m2 450.00 2,364.75
5.36 m2 1,350.00 7,236.00
3.36 m2
0.75 m2 8,000.00 6,000.00
41,955.04 7,551.91
49,506.95
24.73 m2 1,100.00 27,198.60
49.45 m2 715.00 35,358.18
24.73 m2 450.00 11,126.70
24.73 m2 1,350.00 33,380.10
3.12 m2 2,500.00 7,796.25
6.24 m2 800.00 4,989.60
119,849.43 21,572.90
141,422.33
0.98 m3 12,245.00 11,943.47
3.64 m2 715.00 2,602.96
0.39 m2 450.00 175.50
14,721.92 2,649.95
17,371.87
0.41 m2 1,100.00 445.50
0.60 m2 715.00 429.00
1.01 m2 450.00 452.25
0.60 m2 1,350.00 810.00
2,136.75 384.62
2,521.37
8.75 m2 1,100.00 9,621.48
17.49 m2 715.00 12,507.92
8.75 m2 450.00 3,936.06
17.49 m2 1,350.00 23,616.36
2.88 m2 2,500.00 7,200.00
5.76 m2 800.00 4,608.00
61,489.82 11,068.17 72,557.99
1.01 m3 12,245.00 12,315.41
3.68 m2 715.00 2,627.63
0.39 m2 450.00 175.50
15,118.53 2,721.34
17,839.87
11.33 m2 1,100.00 12,466.08
22.67 m2 715.00 16,205.90
11.33 m2 450.00 5,099.76
22.67 m2 1,350.00 30,598.56
2.18 m2 2,500.00 5,456.00
4.36 m2 800.00 3,491.84
73,318.14 13,197.27 86,515.41
11.09 m2 1,100.00 12,196.80
22.18 m2 715.00 15,855.84
11.09 m2 450.00 4,989.60
22.18 m2 1,350.00 29,937.60
3.27 m2 2,500.00 8,184.00
6.55 m2 800.00 5,237.76
76,401.60 13,752.29 90,153.89
9.41 m2 1,100.00 10,345.50
18.81 m2 715.00 13,449.15
9.41 m2 450.00 4,232.25
18.81 m2 1,350.00 25,393.50
3.89 m2 2,500.00 9,720.00
7.78 m2 800.00 6,220.80
69,361.20 12,485.02 81,846.22
3.15 m2 1,100.00 3,465.00
6.30 m2 715.00 4,504.50
3.15 m2 450.00 1,417.50
6.30 m2 1,350.00 8,505.00
1.20 m2 2,500.00 3,000.00
2.40 m2 800.00 1,920.00
22,812.00 4,106.16
26,918.16
6.37 m2 1,100.00 7,005.90
12.74 m2 715.00 9,107.67
6.37 m2 450.00 2,866.05
12.74 m2 1,350.00 17,196.30
7.68 m2 2,500.00 19,200.00
15.36 m2 800.00 12,288.00
67,663.92 12,179.51 79,843.43
1.05 m2 1,800.00 1,893.87
1.72 m2 1,100.00 1,890.90
2.14 m2 715.00 1,530.46
1.72 m2 450.00 773.55
1.72 m2 1,350.00 2,320.65
8,409.43 1,513.70 9,923.12
6.77 m2 1,100.00 7,444.80
13.54 m2 715.00 9,678.24
6.77 m2 450.00 3,045.60
13.54 m2 1,350.00 18,273.60
1.22 m2 2,500.00 3,051.00
2.44 m2 800.00 1,952.64
1.63 m2 8,000.00 13,017.60
56,463.48 10,163.43 66,626.91
11.00 Nos 75.00 825.00 0.50 Bag 785.00 392.50 0.05 Cube 7,000.00 350.00
78.38
1.00 Day 950.00 950.00 0.50 Day 650.00 325.00 1,275.00
38.25
1,391.63 250.49
1,642.12
Recommended