Milton-Madison Bridge Project - MAASTO - 1A - Kentucky.pdf · 2013. 8. 5. · Visit the project...

Preview:

Citation preview

1

Milton-Madison Bridge Project

2013 MAASTO Conference

July 17, 2013

Kevin Hetrick, INDOT

Andy Barber, KYTC

Project Partners

Purpose and Need

• Structurally Deficient & Functionally Obsolete

• Twenty Foot out-to-out Bridge Deck

• Remaining Service Life of the structure estimated

at 10 years

Superstructure Replacement with Minimal

Approaches

• Milton Approach re-construction

• Structure No. 1 replacement

• Structure No. 2 replacement

– Scour Mitigation and Pier

Strengthening

– Superstructure Replacement

4

Milton, KY

Madison, IN

• Structure No. 3 replacement

• Construction of Structure No. 4

1 2 3

4

5

Proposed Pier

Strengthening

1) Drill holes into existing

unreinforced caisson

3) Add stem reinforcement

4) Form and cast collar and

new cap

2) Grout dowels into holes

and extend above top

of caisson

Existing Pier

and Caisson

SECTION A-A

A A

Final Scour Design Sketch

6

7

12’-0”

LANE8’-0”

SHOULDER

12’-0”

LANE5’-0”

CLEAR

8’-0”

SHOULDER

8

Ferry Service during Construction

• No Cost to Users

• Ferries would accommodate vehicles

• Special provisions for medical emergencies

• Capacity to be determined

• Hours of operation to be determined

99

Proposed

Existing

10

Design-Build Proposals

September 22, 2010Five Contractors submitted bids

Project was awarded based on

- Cost to construct project ($102-$127 million)

- Length of bridge closure (10-365 days)

- Date to open bridge to traffic (Sept 2012/May 2013)

Walsh had the lowest bid based on these factors

11

The Winning Design-Build Team

Walsh Construction, Inc (CONTRACTOR)Construction firm in La Porte, IN

www.walshgroup.com

Burgess & Niple, Inc. (DESIGNER)Engineering firm in Columbus, OH and Indianapolis, IN

www.burgessniple.com

Buckland & Taylor (DESIGNER)Bridge engineering firm in Seattle, WA

www.b-t.com

12

Proposal for Design Build Process

Innovative construction process:

Build a new truss on downstream piers while the existing bridge remains open to traffic

Strengthen existing piers

Remove old truss and slide the new truss onto the strengthened existing piers

Shortest closure periods (approx 10 days)

13

Step 1

- Existing bridge remains open to traffic

- Detour approach ramps are built on Vaughn Dr and KY 36

- Pier strengthening and widening begins

Design-Build

Process

14

15

16

Step 2

- Bridge closes to traffic for 5 days

- Approach ramps are connected to existing bridge

- Existing bridge reopens to traffic

- Pier strengthening work continues

Design-Build

Process

17

18

19

Step 3

- Downstream bridge piers are constructed

Design-Build

Process

20

21

22

Step 4

- Existing bridge remains open to traffic

- New truss superstructure is erected on downstream piers

- Permanent approaches are built

Design-Build

Process

23

24

25

26

27

28

29

30

Step 5

- Downstream bridge is connected to US 421

- Traffic is rerouted onto downstream bridge

Design-Build

Process

31

32

Step 6

- Existing bridge is demolished

Design-Build

Process

33

34

35

Step 7

- Traffic remains on downstream bridge

- Detour approach ramps are removed

- Pier strengthening and widening is completed

Design-Build

Process

36

Step 8

- Downstream bridge closed for 5 days

- Using steel rails and plates, new truss superstructure

is moved from downstream piers to its permanent place

- New Milton-Madison Bridge opens to traffic

- Downstream piers are removed

Design-Build

Process

37

For More Information

Kevin Hetrick INDOT

KHetrick@indot.in.gov

Phone 317-232-5162

Visit the project website

www.miltonmadisonbridge.com

or contact:

Andy BarberKYTC

Andy.Barber@ky.gov

Phone 502-210-5504

38

Questions?

Recommended