Mile Dželalija, UNISTAhmet Mehić, UPBHaris M U H I Ć, SUSBiH

1ST CONSORTIUM, KICK-OFF MEETING

PADERBORN, JANUARY 29TH – FEBRUARY 1ST 2014

544464-TEMPUS-1-2013-1-DE-TEMPUS-SMHES

PRESENTATION OF THE PROJECTWORK PACKAGES

TEMPUS IV – 6th Call for proposals

The project “BiH Qualifications Framework for Higher Education”

(BHQFHE)

will be implemented within 36 months.

TOTAL PROJECT FINANCE

1.112.125,90 €

Structural Measures

Haris Muhic

TARGET GROUPS

HEI’sPolicy-making public

bodies, HE

Students

Association of Employers

Labour and Employment

Agency of BiH

Haris Muhic

21 Project partnerCoordinator: University of Paderborn, Germany, Prof. Dr. Schaefer WilhelmPartners: • BiH University of Mostar, Zenica, Bihac, I. Sarajevo, Tuzla and “Dzemal Bijedic”- Mostar• Foundation for Higher Education World University Service BiH (SUSBiH)• Association of Employers of BiH• Labour and Employment Agency of Bosnia and Herzegovina• Centre for Information and Recognition of Qualifications in HE (BiH)• Ministry of Science, Education and Sports of Croatia• University of Split (Croatia)• University of Northampton (United Kingdom)• University of Limerick (Ireland)• University of Lleida (Spain)• Agency for Development of Higher Education and Quality Assurance (BiH)• Ministry of Education and Culture of Republic of Srpska• Ministry of Education, Science and Youth of Canton Sarajevo• Central and Eastern EU Network of Quality Assurance Agencies HE (Germany)• Ministry of education, science, culture and sport of WH canton

Haris Muhic

The main objective of the project

Supporting the structural reform of higher education system in BiH

Supporting the development of the BiH Qualifications Framework for Higher Education

The project shall provide models for full formal implementation of the BHQFHE at institutional levels

Based on all criteria and procedures of the European Qualifications Framework for Lifelong Learning (EQF-LLL) and the European Qualifications for European Qualifications Framework Area (QF-EHEA).

Haris Muhic

Specific project objectives

A• Creating the BHQFHE model and developing statements at sectorial

level

B• HEIs capacity building to write and assess LOs linked with sectorial

descriptors

C• Development of the BHQFHE implementation model at the level of

study programs and piloting at HEIs

D • Self-certification of the BHQFHE

STRENGTHENING AND SUPPORTING INSTITUTIONAL CAPACITIES

Haris Muhic

Summary of Work Packages

WP.1

• Expert groups’ capacities building

WP.2

• Development of BHQFHE

WP.3

• Capacity building of HEIs

WP.4

• BHQFHE implementation at HEIs Haris Muhic

Summary of Work Packages

WP.5

• BHQFHE Self-certification

WP.6

• Quality control and monitoring

WP.7

• Dissemination

WP.8

• Project management Haris Muhic

WP.1

• Expert groups’ capacities building

Mile Dželalija

1.1

• Mapping of the existing BH qualifications practice.

1.2

• Establishing of Expert groups.

1.3

• Collecting and analysing of the Best EU practice.

1.4

• Training of expert groups members

Start month

End month

1 11

WP Leader UNTZ

Task leader UNTZ

Task leader HEA

Task leader SUSBiH

Task leader SUSBiH

WP.1

• Expert groups’ capacities building

Mile Dželalija

1.1

• Mapping of the existing BH qualifications practice

1.2

• Establishing of Expert groups

1.3

• Collecting and analysing of the Best EU practice

1.4

• Training of expert groups members

WP.1

• Expert groups’ capacities building

Mile Dželalija

1.1

• Mapping of the existing BH qualifications practice.

1.2

• Establishing of Expert groups.

1.3

• Collecting and analysing of the Best EU practice.

1.4

• Training of expert groups members

WP.1

• Expert groups’ capacities building

Mile Dželalija

1.1

• Mapping of the existing BH qualifications practice.

1.2

• Establishing of Expert groups.

1.3

• Collecting and analysing of the Best EU practice.

1.4

• Training of expert groups members

WP.1

• Expert groups’ capacities building

Mile Dželalija

1.1

• Mapping of the existing BH qualifications practice

1.2

• Establishing of Expert groups

1.3

• Collecting and analysing of the Best EU practice

1.4

• Training of expert groups members

WP.2

• Development of BHQFHE

Mile Dželalija

2.1

• Developing and creating Guidelines for BHQFHE&LLL.

2.2

• Drafting of Sectorial statements.

2.3

• Consultation process on sectorial statements

2.4

• Creating of Sectorial statements

Start month

End month

9 35

WP Leader HEA

Task leader HEA

Task leader HEA

Task leader HEA

Task leader HEA

WP.2

• Development of BHQFHE

Mile Dželalija

2.1

• Developing and creating Guidelines for BHQFHE&LLL

2.2

• Drafting of Sectorial statements.

2.3

• Consultation process on sectorial statements

2.4

• Creating of Sectorial statements

WP.2

• Development of BHQFHE

Mile Dželalija

2.1

• Developing and creating Guidelines for BHQFHE&LLL

2.2

• Drafting of Sectorial statements

2.3

• Consultation process on sectorial statements

2.4

• Creating of Sectorial statements

WP.2

• Development of BHQFHE

Mile Dželalija

2.1

• Developing and creating Guidelines for BHQFHE&LLL

2.2

• Drafting of Sectorial statements

2.3

• Consultation process on sectorial statements

2.4

• Creating of Sectorial statements

WP.2

• Development of BHQFHE

Mile Dželalija

2.1

• Developing and creating Guidelines for BHQFHE&LLL

2.2

• Drafting of Sectorial statements

2.3

• Consultation process on sectorial statements

2.4

• Creating of Sectorial statements

WP.3

• Capacity building of HEIs

Mile Dželalija

3.1

• Establishing of Working groups at HEIs

3.2

• Creating Handbook for writing LOs

3.3

• Training of working groups members

Start month

End month

21 28

WP Leader UNTZ

Task leader UNTZ

Task leader UNTZ

Task leader UNIST

WP.3

• Capacity building of HEIs

Mile Dželalija

3.1

• Establishing of Working groups at HEIs

3.2

• Creating Handbook for writing LOs

3.3

• Training of working groups members

WP.3

• Capacity building of HEIs

Mile Dželalija

3.1

• Establishing of Working groups at HEIs

3.2

• Creating Handbook for writing LOs

3.3

• Training of working groups members

WP.3

• Capacity building of HEIs

Mile Dželalija

3.1

• Establishing of Working groups at HEIs

3.2

• Creating Handbook for writing LOs

3.3

• Training of working groups members

WP.4

• BHQFHE implementation at HEIs

Mile Dželalija

4.1

• Creating and developing of Implementation model

4.2

• Pilot study programs reviewing

4.3

• Conducting QA mechanisms

Start month

End month

25 33

WP Leader UL

Task leader UL

Task leader HEA

Task leader UL

WP.4

• BHQFHE implementation at HEIs

Mile Dželalija

4.1

• Creating and developing of Implementation model

4.2

• Pilot study programs reviewing

4.3

• Conducting QA mechanisms

WP.4

• BHQFHE implementation at HEIs

Mile Dželalija

4.1

• Creating and developing of Implementation model

4.2

• Pilot study programs reviewing

4.3

• Conducting QA mechanisms

WP.4

• BHQFHE implementation at HEIs

Mile Dželalija

4.1

• Creating and developing of Implementation model

4.2

• Pilot study programs reviewing

4.3

• Conducting QA mechanisms

WP.5

• BHQFHE Self-certification

Mile Dželalija

5.1

• Establishing Self-certification panel

5.2

• Publishing Self-certification Report.

Start month

End month

26 33

WP Leader UNIST

Task leader UNIST

Task leader UNIST

WP.5

• BHQFHE Self-certification

Mile Dželalija

5.1

• Establishing Self-certification panel

5.2

• Publishing Self-certification Report.

WP.5

• BHQFHE Self-certification

Mile Dželalija

5.1

• Establishing Self-certification panel

5.2

• Publishing Self-certification Report.

WP.6

• Quality control and monitoring

Haris Muhic

6.1

• On-going internal quality control and monitoring

6.2

• Organizing annual monitoring cycle

Start month

End month

1 36

WP Leader UDL

Task leader UdL

Task leader SUSBIH

WP.6

• Quality control and monitoring

Haris Muhic

6.1

• On-going internal quality control and monitoring

6.2

• Organizing annual monitoring cycle

WP.6

• Quality control and monitoring

Haris Muhic

6.1

• On-going internal quality control and monitoring

6.2

• Organizing annual monitoring cycle

WP.7

• Dissemination

Haris Muhic

7.1

• Organizing open day at each PCU

7.2

• Developing external communication plan, promotion

7.3

• Web based information portal -stakeholder network

7.4

• Dissemination conference

Start month

End month

2 36

WP Leader SUSBIH

Task leader SUSBIH

Task leader SUSBIH

Task leader SUSBIH

Task leader UPB

www.bhqehe.ba

WP.7

• Dissemination

Haris Muhic

7.1

• Organizing open day at each PCU

7.2

• Developing external communication plan, promotion

7.3

• Web based information portal -stakeholder network

7.4

• Dissemination conference

WP.7

• Dissemination

Haris Muhic

7.1

• Organizing open day at each PCU

7.2

• Developing external communication plan, promotion

7.3

• Web based information portal -stakeholder network

7.4

• Dissemination conference

WP.7

• Dissemination

Haris Muhic

7.1

• Organizing open day at each PCU

7.2

• Developing external communication plan, promotion

7.3

• Web based information portal -stakeholder network

7.4

• Dissemination conference

WP.7

• Dissemination

Haris Muhic

7.1

• Organizing open day at each PCU

7.2

• Developing external communication plan, promotion

7.3

• Web based information portal -stakeholder network

7.4

• Dissemination conference

WP.8

• Project management

Ahmet Mehic

8.1

• Kick-off and project coordination meetings

8.2

• Financial and administrative management

8.3

• Developing of internal communication plan

8.4

• Mid-term and final project reports

Start month

End month

1 36

WP Leader UPB

Task leader UPB

Task leader UPB

Task leader UPB

Task leader UPB

WP.8

• Project management

Ahmet Mehic

8.1

• Kick-off and project coordination meetings

8.2

• Financial and administrative management

8.3

• Developing of internal communication plan

8.4

• Mid-term and final project reports

WP.8

• Project management

Ahmet Mehic

8.1

• Kick-off and project coordination meetings

8.2

• Financial and administrative management

8.3

• Developing of internal communication plan

8.4

• Mid-term and final project reports

WP.8

• Project management

Ahmet Mehic

8.1

• Kick-off and project coordination meetings

8.2

• Financial and administrative management

8.3

• Developing of internal communication plan

8.4

• Mid-term and final project reports

WP.8

• Project management

Ahmet Mehic

8.1

• Kick-off and project coordination meetings

8.2

• Financial and administrative management

8.3

• Developing of internal communication plan

8.4

• Mid-term and final project reports

www.bhqfhe.ba (TBA)

Prof.dr. Mile Dželalija, UNIST

Ahmet Mehić, UPB

Haris M U H I Ć, SUSBiH,