Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

Preview:

Citation preview

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    1/28

    Detailed, Grouped by Each Number 

    Submittal Transmittal 

    LC3 (R-15-085-BF-0) Project # RUH-CP-1502

    Tel: Fax:

    Date: 3/8/2016 Reference Number: 0483

    Transmitted To: Transmitted By: Paul TeagueHadi Omar Harb

    SSEM AECOM

    P.O. Box 6341

     Al Rashid Tower, 5th Floor 

     Al Ma'athar Street

    11442 Riyadh

    Tel: 4625511

    Fax: 4627804

    P.O. Box 58806

    4 Floor, Tower 4, Tatweer Tower 

    11515 Riyadh

    Tel:

    Fax:

    Submittal Package No Description Due Date Package ActionQty

    Reviewed -

    Exceptions Noted

    Method Statement for Formworks, Rebars,

    Cast-In-Situ Concrete(Pouring, Embedments,

    Curing)

    0120 - 013300 - D1 - 11

    Transmitted For Delivered Via Tracking Number  

    Hand Action

    Notes Item ActionItems DescriptionQty

    001 Method Statement for

    Formworks, Rebars,

    Cast-In-Situ Concrete(Pouring,

    Embedments, Curing)

    Reviewed - Exceptions

    Noted

    1

    Contact Name Copies NotesCompany NameCc:

    Remarks

    Reviewed Exceptions Noted, Resubmission Required.

    1. Please see attached.

    Best Regards,

    Signature Signed Date

    Prolog Converge Printed on: 3/9/2016 Prolog KKIA Page 1

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    2/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    METHOD STATEMENT FOR

    FORMWORKS, REBARS,

    CAST-INSITU CONCRETE

    (POURING,EMBEDMENTS, CURING)

    Project Quality Manager :  Project Manager :

     

    ENGR. Amr

     Ibrahim

     Metwally

     ENGR.

     HADI

     OMAR

     HARB 

    Page 1 of 27

    1.The page header shall also include KKIA logo in the following

    sequence from left to right - GACA, KKIA, AECOM & SSEM. SSEM may

    opt to place their company logo below the first three mentioned logos.

    2.All appendices shall also show the correct (current) logos of GACA,

    KKIA and AECOM accordingly.

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    3/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    Table of Contents

    1.0 Purpose ………………………………………………………………… ………………..03

    2.0 Scope …………………………………………………………………………………….. 03

    3.0 References and Standards …………………………………………………………… 03

    4.0 Abbreviations/Defini tions …………………………………………………………….. 04

    5.0 Work Program …………………………………………………………………………...04

    6.0 Equipment ………………………………………………………………………………..04

    7.0 PPE Materials …………………………………………………………………………… 05

    8.0 Manpower Schedule …………………………………………………………………… 05

    9.0 Responsibil it ies of Key Personnel ………………………………………………….. 06

    10.0 Concreting Methodology ………………………………………………………………07

    11.0 Quali ty Requirements …………………………………………………………………. 12

    12.0 Health and Safety ………………………………………………………………………. 13

     Appendices

     Appendix 1.0- Job Risk Assessment ………………………………………………..15

     Appendix 1.1- Carpentry Works ……………………………………………………...15 Appendix 1.2- Formworks …………………………………………………………… 17

     Appendix 1.3- Steel Cut ting and Bending …………………………………………. 19

     Appendix 1.4- Concrete Works ……………………………………………………….21

     Appendix 2.0- Related ITP ……………………………………………………………. 23

     Appendix 3.0- Check li st ………………………………………………………………. 25

     Appendix 4.0- Proforma Work Permit ……………………………………………….27

    Page 2 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    4/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    1.0 PURPOSE

    The purpose of this method statement is to provide description of procedure and method for theexecution of for construction of reinforced concrete structure, the LC-3 Building and relatedstructures. This include the fabrication/installation of formworks and reinforcing bars, the pouringof cast in situ concrete, and repair of newly casted concrete. As well as the necessary materials toensure health and safety of employees with the requirement stipulated in the ContractDocuments, as well as those in Saudi Construction Specifications (ASTM and SASO-ISO)

    2.0 SCOPE

    This method statement covers the task related to construction of reinforced concrete building.This include but is not limited to : raft or strip foundations, retaining walls, columns, girders,suspended and slab on grade, concrete duct banks, manholes, other equipment supports andfoundation.

    3.0 REFERENCES AND STANDARDS

    Construction of reinforced concrete building will be in accordance with the following standards:

    3.1 Saudi Arabia Construction Specification. 

    3.2 Employers requirements, Materials Specification 

    3.3  Approved with Comments (AWC) design and construction drawings. 

    3.4  ACI-117 

    3.5  ACI-318 

    3.6  ACI-347R

    3.7  ACI-304R 

    3.8  ACI-305R 

    3.9  ASTM-C39 

    3.10 SASO SSA2 

    3.11 SASO SA 224 

    Page 3 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    5/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    4.0 ABBREVIATION/DEFINITION

    PM Project Manager

    PQP Project Quality Plan

    QIP Quality Inspection Plan

    QA&QC Quality Assurance & Quality control

    MS Method Statement

    PPE Personal Protective Equipment

    HSE Health, Safety & Environment

    PPE Personal Protective Equipment

    ECO Environmental Control Officer

    CR Construction Regulation

    EMP Environmental Management Plan

    OHSA Occupational Health and Safety Act

    SO Safety Officer

    EO Environmental Officer

    5.0 WORK PROGRAM

    Construction of the building comprise of:

    5.1 Two level building with floor area approximately 5,500 sq. m. 

    5.2 Construction of generator room, 1500 sq. m. with individual support for the equipment.  

    5.3 Control room area with provision for LV and MV- panel controls. 

    5.4 Construction of duct banks for the associated power, communication, waterlines and

    plumbing lines.

    6.0 EQUIPMENT

    The contractor (SSEM) will provide the following equipment throughout the project, quantities willbe determined by actual site demand. Equipment will be inspected prior to mobilization and shallhold valid insurance certificates, as well as certified/competent operators.

    Page 4 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    6/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    Type of Equipment Units (No.)

    Concrete Transit mixers Depend on conc. volume

    Concrete Pumps 1

    Portable Concrete Vibrator 2

    Boom trucks 1

    Water Truck 1

    Bar Benders 2

    Bar Cutters 2

    Circular Saw (Table Type) 2

    Portable electric grinders 4

    Portable electric jigsaws 4

    Misc. hand tools 1 lot

    Table I. Equipment Intended for Concrete construction works.

    7.0 PPE MATERIALS

    Personal Protective Equipment (PPE) should be provided in order to perform all works inaccordance with the safety procedures and taking into consideration the importance of properpreventive measures to ensure safety in the performance of work.

    Type of Equipment

    Safety Helmet

    Safety Boots/Shoes

    Safety Glasses

    Safety Masks

    Coveralls

    High Visibility Vests

    Hand Gloves

    Fall Arrester

    Safety Harness

    Table II. Personal Protect ive Equipment Intended for Concrete Construction Works.

    8.0 MANPOWER

    The workforce including foremen, operators, and technicians shall be well qualified with third partycertificates wherever applicable/relevant.

    Subcontractors for different trades shall be deployed depending on demand, to cover up shortfallsand to cope up with the construction schedule.

    Page 5 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    7/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    CONTRACTOR

    (SSEM)

    Construction Manager

    Site Engineer

    QC- Engineers

    Surveyor

    Safety Engineers

    Civil Foreman

    CarpentersSteel fixers

    Mason

    Scaffolders

    Equipment Operators

    Safety officers

    Flagmen

    First Aider

    Laborers

    Table III. Manpower for Concrete Construction Works. 

    9.0 RESPONSIBILITIES OF KEY PERSONNEL

    9.1 Construction Manager

    The Construction Manager will plan and expedite for the continuous supply of resources tocope up with the project demand and schedule. The construction manager will keep recordof the progress of work. He will report to the project manager on matters affectingcompletion of project. He will give direct orders to the site engineer for the effectiveimplementation of work program.

    9.2 Site Engineer

    The Site Engineer will be in charge for the supervision and implementation of all concreteconstruction works as required in the specifications and drawing, especially in giving ordersto Site foremen. Site engineer is also in charge for the preparation of daily, weekly andmonthly reports. He will coordinate with the QC-engineer on matters concerning Inspectionrequest and attend to final inspection together with SSEM QC-engineer and the owners’Engineer.

    Page 6 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    8/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    9.3 Quality Contro l Engineer

    The QC Engineer will be responsible for compliance of work to the reference contractdrawings, specifications and other QA/QC conditions required by The Engineer. He willmonitor daily activities and notify concerned parties when works deviates from the standard.He will issue proactive notification when needed to prevent non-compliance works.

    9.4 Site Foreman

    The Site Foreman will be in charge for the supervision and implementation of various stagesof concrete construction works, as instructed by the Site engineer. He will be responsible for

    the execution of works in compliance to approved drawing and contract specifications.Foreman shall also keep record of all work schedules, work production and daily safetyissues.

    9.5 Site Surveyor

    The Site Surveyor will be in charge for the setting out for building corners, elevation andmake the vertical/horizontal reference at site. He will stake out for lines and elevations ofunderground utilities construction and will prepare reports for excavation and backfillingworks.

    10.0 CONCRETING METHODOLOGY

    10.1 Sequence of Work

    The following are the sequence of work in the construction of Cast-in Situ Concrete:

    10.1.1 Fabrication and installation of form works.

    10.1.2 Fabrication and installation of steel reinforcements.

    10.1.3 Installation of anchor bolts, block-outs and other embedment to concrete whenneeded.

    10.1.4 Form closure and installation of supports

    10.1.5 Pouring of ready mix concrete.

    10.1.6 Preparation of concrete sample specimen for testing purposes.

    10.1.7 Finishing and curing of concrete.

    10.1.8 Stripping of formworks.

    10.1.9 Repair of minor concrete imperfection.

    Page 7 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    9/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    10.2 Formworks

    10.2.1 Forms shall be substantial and sufficiently tight to prevent leakage ofmortar from the concrete. Contractor shall use sufficient nailing,bolting, welding, shoring, whalers, form clamps and forming ofadequate strength to contain the fluid concrete without noticeabledeflection, leaning or bulging

    10.2.2 Forms shall be properly braced or tied together to maintain positionand shape. Forms shall be built to resist the pressures to which theywill be subjected and to limit deflections to a practicable minimumwithin the specified tolerance.

    10.2.3 Formwork shall be anchored to the shores below so that movement ofany part of the formwork system will be prevented during concreting

    10.2.4 Block outs, inserts, sleeves, anchors, water stops and other embeddeditems shall be properly identified, positioned and secured in the formsto resist all forces while concrete is being placed and hardens.

    10.2.5 Old forms shall be thoroughly cleaned of all dirt, mortar and foreign matter and

    coated with a release agent before each use.

    10.2.6 A polyethylene sheet shall be placed beneath and around the sides of concrete

    that is placed against soil where bitumen or coal tar epoxy cannot be applied.

    10.2.7 A polyethylene sheet, minimum 0.15mm thick, shall be placed beneath slabs on

    grade and other concrete structure when shown in the drawing.

    10.2.8 Water stops shall be provided in joints where watertight construction is required.

    Location and type of water stops shall be as shown on construction drawing.

    10.2.9 Expansion joint filler strips shall be made from fiber board securely bound together

    by a suitable asphaltic binder.

    10.2.10 Well trained manpower shall be deployed as the height of formworks increases.

    10.2.11 Erecting formwork frames should be erected in a progressive manner to ensure

    both the installers safety and the stability of the overall structure.

    10.2.12 Braces should be attached to the frames as soon as practical. As erecting the

    frames continues, designated access ways should be indicated by using bunting or

    by other means.

    10.2.13 Provide the side bracing or other edge protection is installed progressively and as

    soon as enough material has been raised up.

    Page 8 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    10/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    10.2.14 Framing is carried out in accordance with on-site design documentation andmanufacturers’ instructions.

    10.3 Steel Reinforcements

    10.3.1 Forms shall be inspected and checked before the reinforcing steel is placed to the

    dimensions and locations on the structural plans.

    10.3.2 The minimum concrete cover shall be measured from the outer most rebar (tie

    bar), that shall be provided for reinforcement of cast-in-place concrete structures

    as indicated in the drawings.

    10.3.3 Reinforcing steel rebar shall be correct in size, quantity, layout, spacing, positionas per the contract drawing

    10.3.4 Reinforcing Steel lap splice lengths for each bar size shall be as detailed for each

    size as shown on the Contract Drawings.

    10.3.5 Welding of reinforcement shall not be allowed unless authorized by The Engineer

    or called for specifically on the Contract Drawings.

    10.3.6 Provide necessary and safe scaffolding / platform as the height increases for steel

    reinforcement installation.

    10.3.7 Dowel bars and anchorage shall be as per approved drawing and specificationsand be maintained whenever necessary.

    10.3.8 All reinforcement must be cleared to ensure that it is free from oil, dust and

    deleterious materials.

    10.4 Anchor bolts and Embedded Items

    10.4.1 Anchor bolts and embedded items shall be set accurately, using templates.

    10.4.2 Anchor bolt projection above the top of concrete is computed as follows:

    Single Nuts:

    Thickness of grout + thickness of base plate (or height of anchor bolt chair above

    the top of grout) + 1.5 x diameter of anchor bolt.

    Double Nuts:

    Thickness of grout + thickness of base plate (or height of anchor bolt chair above

    the top of grout) + 2.5 x diameter of anchor bolt.

    Page 9 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    11/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    10.5 Form Closure Inspection

    10.5.1 Reference markers shall be installed on the formwork shores to detect formwork

    movements during concreting

    10.5.2 Wedges used for final alignment before concrete placement shall be secured

    before placing concrete.

    10.5.3 Formwork shall be anchored to shoring to prevent any movement of any part of the

    formwork during concreting.

    10.5.4 Closure of form joints, settlement of blinding slabs, shrinkage of lumber, elastic

    shortening and deflections of form members shall all be countered prior to concrete

    placement.

    10.6 Concrete Pouring

    10.6.1 Concrete pouring shall be done after pre-placement inspection and authorization to

    proceed by The Engineer.

    10.6.2 Temperature, slump of ready mix concrete shall be checked upon arrival at site.

    10.6.3 Experienced form watchers shall be provided during concrete placement to detect

    form displacement or the beginning of failure.

    10.6.4 Re-tempering of concrete after initial setting is prohibited.

    10.6.5 Concrete that has partially hardened or been contaminated by foreign materials

    shall not be deposited in the structure.

    10.6.6 Concrete shall not be dropped freely where reinforcing will cause segregation nor

    where it would fall freely from a height not allowed by the specifications.

    10.6.7 Concrete shall be discharged as near as possible to its final position to avoid

    segregation due to re-handling or flowing.

    10.6.8 Placed concrete shall be consolidated by mechanical vibration equipment

    supplemented by hand spading, rodding or tamping.

    10.6.9 After completing placing and finishing operations, efforts must continue to protect

    concrete from high temperatures, direct sunlight, low humidity, and drying winds.

    10.6.10 Concrete paving shall have control joints or construction joints located shown in

    the contract drawing.

    Page 10 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    12/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    10.6.11 Paving or slab construction joints not specified on the Contract Drawings, shall belocated at column centerlines and at intermediate intervals approved by The

    Engineer.

    10.6.12 Paving or slab construction joints not specified on the drawings, shall meet all

    requirements for architectural concrete matching the grade and type of finish

    present in the adjacent concrete.

    10.6.13 Contraction or isolation joints shall be provided to divide structurally plain concrete

    members into flexural discontinuous elements. (ACI 318M, Sec. 2.2.3.1).

    10.7 Concrete Finishing and Curing Inspection

    10.7.1 Initial floating shall be completed after concrete placement.

    10.7.2 The second floating operation shall take place after initial set but before final set

    has occurred (usually performed using a power trowel with float shoes or a pan

    attached).

    10.7.3 The use of any floating or troweling machine that has a water attachment for

    wetting the concrete surface during finishing shall be prohibited.

    10.7.4 Maximum total dissolved solids in water used for moist curing shall not exceed

    1000 parts per million.

    10.7.5 Water curing shall be continuous until the compressive strength has reached 70%

    of the specified strength, but not less than 7 days after placement.

    10.7.6 Continuous water cure can be provided by covering with wet burlap and plastic; the

    saturated burlap shall be covered with a polyethylene sheet vapor barrier,

    minimum 0.15 mm (150 microns) in thickness.

    10.7.7 Where appearance is important, concrete curing by 0.15 mm polyethylene film

    shall be avoided; film over damp burlap may be used (ACI 308, Sec. 2.4.2.1)

    10.8 Stripping of Formworks

    10.8.1 Unless otherwise specified in the project specifications, formwork and shoring shall

    be left in place to support the mass of concrete in beams, slabs and in-place

    structural members until the specified concrete strength f'c is attained. (ACI 301,

    Sec. 2.3.2.5) Note: The preferred method of determining stripping time is by testing

    test cylinders that are cured on-site or testing concrete strength in the field.

    10.8.2 When finishing is required, remove forms as soon as removal operations will not

    damage concrete. (ACI 301, Sec. 2.3.2.1)

    Page 11 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    13/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    10.8.3 Repairs and treatment on minor concrete damage shall be started immediately.(ACI 301, Sec. 2.3.2.5).

    10.8.4 Forms removal (stripping) shall be based on concrete's achieving minimum

    strength requirements as set forth by the design engineer as verified by sample

    cylinders compressive strength results.

    10.9 Cast-In-Place Concrete Final Acceptance

    10.9.1 All concrete surfaces in direct contact with earth shall be coated with two coats of

    coal tar or bitumen coating consisting of two coats coal tar epoxy coating system

    for Immersion Service or Bituminous Paint for Moderate Temperatures in Buried or

    Immersion Service. Overall dry coating thickness shall be from 325μm to 605μm.

    10.9.2 All surface defects such as cracks or honey-combing shall be filled with mortar

    consisting of 1 part Portland Cement of the type specified for the job and 2.5 parts

    fine sand and ground in smooth with a trowel or carborundum grind stone float.

    (ACI 515.1R, Sec. 3.2.1) Note: Proprietary compounds may be used in lieu of

    mortar in accordance with the manufacturer's recommendations and with prior

    approval of The Engineer.

    10.9.3 Finns, protrusions or similar irregularities projecting from the concrete shall be

    removed back to the surface by chipping, brush hammering, needle gunning or

    wire brushing. (ACI 515.1R, Sec. 3.2.4)

    10.9.4 Sharp offsets in the concrete caused by formwork misalignment, shall be

    mechanically abraded to provide gradual and smooth transitions between offset

    surfaces. (ACI 515.1R, Sec. 3.4.2)

    10.9.5 After finishing and curing operations all exposed construction joints, control joints,

    expansion-contraction joints or other types shall blend into and match with the

    existing adjacent concrete finishes (ACI 301, Sec. 5.3.3)

    11.0 QUALITY REQUIREMENTS

    To ensure the quality control of reinforced concrete construction works, a third party laboratory

    technician will be at site to check the following:

    11.1 Temperature of ready mix concrete upon arrival at site. 

    11.2 Concrete workability by checking concrete slump. 

    11.3 Preparation and proper curing/preservation of concrete sample specimen. 

    11.4 Check proper mixing proportion and procedure for application of proprietary compounds

    for concrete repairs and surfacing.

    Page 12 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    14/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    METHOD STATEMENT FOR FORMWORKS, REBARS,

    CAST-IN-SITU CONCRETE (POURING, EMBEDMENTS,

    CURING)

    First Rev. A B CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.16  DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    11.5 Check for surface preparation and thickness of coating application.

    12.0 HEALTH AND SAFETY

    During the progress of works, the necessary welfare facilities shall be provided at the project site.

    The workers shall be provided with safe drinking water, toilets, place to eat their food and place to

    store their clothes.

    Tower lights will be used during night time works and is essential for the safety of workers, the

    equipment and the proper execution of work. Barriers around construction area shall be installed.

    12.1 ISSUES

    12.1.1 The HSE engineer has the responsibility for providing help advice to the

    supervisor who is responsible for the work safety.

    12.1.2 No one shall be allowed to enter the construction site without wearing the proper

    PPE’s.

    12.1.3 Ensure that there is sufficient scaffolding/platforms and safety harness/fall

    protection when working in heights.

    12.1.4 Beware of slipping when using ladders in wet conditions.

    12.1.5 Provide protective barriers, shield systems complying with applicable standards.

    12.2 RESPONSIBILITIES

    12.2.1 Safety Engineer

    12.2.1.1 Conduct the safety induction course to all personnel involved in the

    work.

    12.2.1.2 Monitor and supervise the risk assessment.

    12.2.1.3 Ensure that necessary Permit to Work is available.

    Page 13 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    15/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONC RETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.2016 DOCUMENTNUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    12.2.1.4 Ensure that the project’s method statement and risk assessment are

    understood, complied and applied in the worksite.

    12.2.1.5 Ensure that all workers are provided with sufficient information regarding

    workplace hazards and planned control measures.

    12.2.1.6 Ensure that necessary equipment (e.g. PPE, tools) is provided prior to start

    of works.

    12.2.1.7 Ensure that all tools, equipment are certified and serviceable in accordance

    with the standard industry practice prior to use.

    12.2.1.8 Ensure that adequate level of welfare arrangements are available in the

    worksite.

    12.2.1.9 Daily inspection of health, safety and environmental compliance is carried

    out.

    12.2.2 Safety Officer

    12.2.2.1 Supervision of equipment handling, transportation and disposal of

    construction debris.

    12.2.2.2 Ensure that relevant work permit is secured prior to start of work.

    12.2.2.3 Ensure that equipment is operational and certified.12.2.2.4 Ensure that all drivers/operators are qualified to operate the

    machines/equipment.

    12.2.2.5 Regular inspection and maintenance of the equipment.

    12.2.2.6 Perform other duties as instructed by the safety engineer.

    Page 14 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    16/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONC RETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

     APPENDICES

     Appendix 1.0 Job Risk Assessment

     Appendix 1.1 Carpentry Works

    Page 15 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    17/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD C ENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONC RETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.02.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    Page 16 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    18/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

     Appendix 1.2 Formworks

    Page 17 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    19/28

     KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #: R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0021-B 

    Page 18 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    20/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

     Appendix 1.3- Steel Cu tt ing and Bending

    Page 19 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    21/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    Page 20 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    22/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

     Appendix 1.4 Concrete Works

    Page 21 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    23/28

     

    KINGDOM OF SAUDI ARABIA

    GENERAL AUTHORITY OF CIVIL AVIATION 

    CONSTRUCTION OF LOAD CENTER -3 

    FORMWORKS, REBARS, CAST-IN-SITU CONCRETE

    (POURING, EMBEDMENTS, CURING)

    First Rev. A B  CONTRACT #:R-15-085-BF-0 

    Issue Date: 17.01.16 18.2.2016 DOCUMENT NUMBER: LC3.KKIA‐UN‐MSM‐GEN‐CV‐0021‐B 

    Page 22 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    24/28

     

    CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA) 

    INSPECTION TEST PLAN FOR CIVIL WORKS  CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) (Close Joint Stock Company)   ITP Ref. No.:  ISSUANCE: 01 

    CONTRACT NO.: R-15-085-BF-0 Sec No.: REVISION: 00

    TITLE: CIVIL WORKS Sec Title.: Date: October 2015

    Activity

    No.Activity Description

    Inspection / Test Requirements Reference DocumentationMethod of

    Verification Demonstrated Evidence

    Report/ChecklistTest or Inspection Performed  Stage / Frequency  Test Required  Code/Spec/Etc.  Acceptance Criteria  SSEM AECOM

     ABBREVIATIONS:N/A  – NOT

     APPLICABLEW- WITNESS PONT S  –  SURVEILLANCE AECOM- Consultant

    Note: H  –  HOLD POINT RR  – REVI EW OF REPORTSSEM-

    Contractor

    Page 1 of 2 

    7STRUCTURAL CEMENT CONCRETECONSTRUCTION  

    7.1 FORMWORK 

    7.1.1Check dimension of formwork for conformity tothe drawings 

    Check Visual/Survey Inspection After installation offormworks

    SSEM CHECKTechnical Specification

    Civil Works Approved Construction

    DrawingsRR W Checklist Form IC-C-007

    7.1.2 Check elevation and level Check survey design date  After installation offormworks

    SSEM CHECK Technical SpecificationCivil Works

     Approved ConstructionDrawings

    RR W Checklist Form IC-C-007

    7.1.3Check stability of bracing , trying, shoring, falsework and supports

    Visual Inspection After installation of

    formworksSSEM CHECK

    Technical SpecificationCivil Works

    Project Specification RR S Checklist Form IC-C-007

    7.1.4Check of cleanliness, surface smoothness andform oil coating

    Visual Inspection After installation of

    formworksSSEM CHECK

    Technical SpecificationCivil Works

    Project Specification H S Checklist Form IC-C-007

    7.1.5 Corner chamfering as per drawing requirements Visual Inspection After installation of

    formworksSSEM CHECK

    Technical SpecificationCivil Works

    Project Specification H S Checklist Form IC-C-007

    7.1.6 Check stability and position of control joints Visual Inspection After installation of

    formworksSSEM CHECK

    Technical SpecificationCivil Works

     Approved ConstructionDrawings

    H S Checklist Form IC-C-007

    7.2  LAYING OF REBAR AND EMBEDDED ITEMS

    7.2.1 Re-bar Quality

    Check Rebar ChemicalComposition, Tensile and

    Bending Compliance w/ (ASTM A 615)

    Every 300tons/per sizedia.

    FactoryTest/Third Party

    Test

    Technical SpecificationCivil Works

    ProjectSpecification/Approved

    Material SubmittalRR RR Mill Certificate/Test report

    7.2.2Check size and spacing of re-bar and concretecover as applicable and also ensure that airblowing is made to ensure clean surface

    Visual inspection After assembly of Re-

    barSSEM CHECK

    Technical SpecificationCivil Works

     Approved ConstructionDrawings/Bar bending

    ScheduleH W Checklist Form IC-C-007

    7.2.3 Check embedded item for and free from damage Visual inspection After assembly of Re-

    barSSEM CHECK

    Technical SpecificationCivil Works

    Project Specification H W Checklist Form IC-C-007

    7.2.4Check installation of embedded items and propersupport

    Visual inspection After assembly of Re-

    barSSEM CHECK

    Technical SpecificationCivil Works

     Approved ConstructionDrawings

    H W Checklist Form IC-C-007

    7.3 CONCRETE PLACEMENT

    7.3.1 Concrete mix designCheck Approved Concrete Mix

    DesignPrior to actual

    production get startedThird Party Test

    Technical SpecificationCivil Works

    Project Specification RR RR Materials Submittal Report

    7.3.2 Concrete material qualityCheck Coarse/Fine Aggregate

    comply w/ (ASTM C 33)daily Third Party Test

    Technical SpecificationCivil Works

    Project Specification S S Checklist Form IC-C-007

    7.3.3Check Concrete delivery for correct mix as perspecification

    Check Approved Concrete MixDesign

    Every Batch Ticket Third Party TestTechnical Specification

    Civil WorksProject Specification S S Checklist Form IC-C-007

    7.3.4 Concrete slump Test Witness checking of Slump(ASTM C 143)

    Every Truck Mixer Third Party Test Technical SpecificationCivil Works

    Test Result Compliance w/Project Specification

    W W Checklist Form IC-C-007

    7.3.5 Concrete Yield, Air ContentWitness checking of Yield, Air

    Content (ASTM C 138)Control Mix Twice

    WeeklyThird Party Test

    Technical SpecificationCivil Works

    Test Result Compliance w/Project Specification

    W W Checklist Form IC-C-007

    7.3.6 Concrete making specimen in the field Witness checking of sample

    cylinder (ASTM C31

    Six test cylinder each

    day used for 28 days

    test additional test

    cylinder may be

    prepared for 7 days test

    (per 200cu.m.)

    THIRD PARTY

    TEST

    Technical Specification

    Civil Works

    Test Result Compliance w/

    Project SpecificationW W Checklist Form IC-C-007

    7.3.7 Check movement and free dropping of concrete Visual InspectionDuring Concrete

    PlacementSSEM CHECK

    Technical Specification

    Civil WorksProject Specification S S Checklist Form IC-C-007

    7.3.8 Check for proper vibration while placing concrete Visual InspectionDuring Concrete

    PlacementSSEM CHECK

    Technical Specification

    Civil WorksProject Specification S S Checklist Form IC-C-007

    7.3.9 Compressive Strength TestCheck result compressive

    strength (ASTM C39)

    Six test cylinder each

    day used for 28 days

    THIRD PARTY

    TEST

    Technical Specification

    Civil Works

    Test Result of 6 tests

    cylinder at 28 days shall beRR/W RR Material Test Report

     Appendix 2.0- Related ITP

    Page 23 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    25/28

     

    CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA) 

    INSPECTION TEST PLAN FOR CIVIL WORKS  CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) (Close Joint Stock Company)   ITP Ref. No.:  ISSUANCE: 01 

    CONTRACT NO.: R-15-085-BF-0 Sec No.: REVISION: 00

    TITLE: CIVIL WORKS Sec Title.: Date: October 2015

    Activity

    No.Activity Description

    Inspection / Test Requirements Reference DocumentationMethod of

    Verification Demonstrated Evidence

    Report/ChecklistTest or Inspection Performed  Stage / Frequency  Test Required  Code/Spec/Etc.  Acceptance Criteria  SSEM AECOM

     ABBREVIATIONS:N/A  – NOT

     APPLICABLEW- WITNESS PONT S  –  SURVEILLANCE AECOM- Consultant

    Note: H  –  HOLD POINT RR  – REVI EW OF REPORTSSEM-

    Contractor

    Page 2 of 2 

    test additional test

    cylinder may be

    prepared for 7 days test

    at least 25.0 N/mm2

    (Average of 6 Cylinder

    7.4 FINISHING AND CURING 

    7.4.1 Check for Curing as per specificationrequirements

    Check Approved Materials forcuring

     After placement ofConcrete

    SSEM CHECK Technical SpecificationCivil Works

     Approved Materials

    compliance w/Project

    Specification

    S S Checklist Form IC-C-007

    7.4.2 Check formed surfaces for finish Visual Inspection After Dismantling of

    Concrete FormsSSEM CHECK

    Technical Specification

    Civil WorksProject Specification S S Checklist Form IC-C-007

    7.4.3Repair surface defects as per approved

    procedure

     As per Approved Material

    supplier procedure for Repair

     After Dismantling of

    Concrete FormsSSEM CHECK

    Technical Specification

    Civil Works

     Approved Materials

    compliance Method

    Statement /Project

    Specification

    H W Checklist Form IC-C-007

    7.4.4 Check joints and application of filler and sealant Visual Inspection After Dismantling of

    Concrete FormsSSEM CHECK

    Technical Specification

    Civil WorksProject Specification H S Checklist Form IC-C-007

     Appendix 2.0- Related ITP

    Page 24 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    26/28

     

       

    CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

    AIRPORT 

    STRUCTURAL CEMENT CONCRETE CONSTRUCTION

    Project: Construction of New Load Center-3 IC Checklist No.: 085-IC-C-007

    Contract No.: R-15-085-BF-O ITP Ref. No.: 085-ITP-C-8.0

    Facility Name: Sec:

    Drwg. No. / Line No.: Area/Location:

    Work / item for Inspection:

    Item Activity SSEMEngr.

    SSEMQC

    GACA/AECOMRepresentative

    Corr.Sign

    Off

    Remarks

     A R N/A1 Formworks dimensions and

    elevation conforming to thedrawing 

    2 Check stability of bracing ,trying, shoring, false work andsupports 

    3 Check of cleanliness, surfacesmoothness and form oilcoating 

    4 Corner chamfering as perdrawing requirements 

    5 Check Compaction density ofCTB 

    6 Check stability and position ofcontrol joints

    7 Check Re-bar Quality8 Check size and spacing of re-

    bar and concrete cover asapplicable and also ensure thatair blowing is made to ensureclean surface

    9 Check quality and installation ofembedded materials

    10 Check Concrete delivery forcorrect mix as per specification

    11 Visual inspection of finishedCTB 

    12 Concrete slump Test

    13 Concrete making specimen inthe field

    14 Check movement and free

     Appendix 3.0- Checklist

    Page 25 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    27/28

     

       

    CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

    AIRPORT 

    dropping of concrete15 Check for proper vibration ofconcrete

    16 Check for compressive strengthof concrete

    17 Check for proper curing ofconcrete

    18 Repair of surface defects asper approved procedure

    19 Check joints and application offiller and sealant

    GACA/AECOM Representative Remarks: Legend: A=Acceptable; R=Rejected; N/A=Not

     Applicable

    SSEM QC Representative GACA / AECOM Representative

    Sign: Sign:Name: Name:

    Date: Date:

     Appendix 3.0- Checklist

    Page 26 of 27

  • 8/18/2019 Method Statement for Formworks, Rebars, Cast-In-Situ Concrete

    28/28

    SSEM-HSE/PERMIT/002/M07-11, Rev0.1, July2011 

    FORMWORKS, REBARS & CAST-IN-SITU CONCRETE WORK PERMIT

    DATE: ______________________PERIOD: __________________TO:__________________PERMIT NO.:_______________

    EQUIPMENTS: _______________________________________________________WORK AREA: ______________________

    DESCRIPTION OF WORK:_________________________________________________________________________________

    NAME OF THE ORIGINATOR:

    COMPANY: DEPARTMENT: SIGNATURE:

    PERFORMING AUTHORITYNAME:

    SIGNATURE & DATE:

    CONTACT NO:

    COMPLEMENTARY PERMITS YES NO N/A

    DRIVING IN UNAUTHORISED AREAS

    CLEARANCE FROM YERP AUTHORITY

    CLEARANCE FROM ROYAL COMMISSION

    CLEARANCE FROM OTHER DEPARTMENTS

    RISK ASSESSMENT SAFETY PRECAUTUONSYES NO N/A

    ELECTRICAL ISOLATION

    METHOD STATEMENT / JSA

    ENOUGH ACCESS/EGRESS

    SUFFICIENT

    SCAFFOLDING/PLATFORMS

    AREA CLEAR FROM COMBUSTIBLE

    SUBSTANCES

    ANY OTHER WORKS ADJACENT

    ISOLATION FROM OTHER WORKS

    AREA CLEAR FROM TOXIC GASES

    EXISTING TEMPORARY OR

    PERMANENT UTILITIES

    SUITABLE EQUIPMENT AND TOOLS

    AVAILABLE

    YES NO N/A

    PERSONAL PROTECTIVE EQUIPMENT (P.P.E)BARRICADES AND WARNING SIGNS

    AREA IS SUITABLE FOR CONCRETE REPAIR WORK

    ADDITIONAL ILLUMINATION

    PROPER ACCESS

    ACCESS/EGRESS CLEAR FROM OBSTACLES

    FIRE EXTINGUISER / FIRE WATCHMAN

    LIFE LINES/ SAFETY HARNESS

    BREATHING EQUIPMENT

    EMERGENCY RESCUE TEAM AVAILABLE.

    SLOPING OR SHIELDLING PROVIDED

    NO MATERIAL KEPT NEAR THE EXCAVATION

    GAS CYLINDERS KEPT OUT FROM THIS AREA

    WORKERS AWARE OF HAZARDS AND PRECAUTUONS

    TO BE TAKEN 

    OTHER REQUIREMENTS (IF NECESSARY)

    DECLARATION (to be filled by Performing Authority) And Competent Person

    I, UNDERSIGNED HAVE CHECKED THE AREA AND COMPLIED TO ALL SAFETY PRECAUTIONS AND RISK ASSESSMENT AND WILL CARRY OUT ACTIVITY WITH

    APPROVED METHOD STATEMENTNAME: SIGN: NAME: SIGN:

    PERMIT VALIDITY (to be filled by Site Manager/Engineer) THE ABOVE WORK HAS BEEN APPROVED AND SHALL BE CARRIED OUT SAFELY. IT HAS TO BE ENSURED THAT THE EMPLOYEE EXECUTING THE JOB HAS A COPY

    OF THE PERMIT AT ALL TIMES DURING THE WORK.

    NAME: SIGNATURE: DATE:

    PERMIT CLEARANCE (to be filled by HSE/Safety Representative)I DECLARE THAT ALL WORK UNDER MY CONTROL HAS NOW BEEN COMPLETED AND THE AREA HAS BEEN CLEARED AND THAT ALL TOOLS AND OTHER

    EQUIPMENT HAVE BEEN REMOVED

    NAME: SIGNATURE: DATE:

    PERMIT CLOSED (to be filled by Performing Authority) THE ABOVE WORK WAS COMPLETED SAFELY AND THE WORK PERMIT SHALL BE CANCELLED

    NAME: SIGNATURE : DATE:

    SAFETY DEPARTMENT:

     Appendix 4.0- Proforma Work Permit

Recommended