LCLS-II Project Overview
David Schultz LCLS-II Deputy Project Director
March 19, 2012
Outline
Slide 2
• Project priorities and status • Key features • Project overview & layout • Project schedule and path forward
LCLS-II New Instruments Workshops, March 19-22, 2012
LCLS-II Project Priorities
• Build a highly productive scientific user facility Maximize technical capabilities for the longer-
range future • Simultaneous SXR and HXR operation • Experiment hall capacity • Undulator hall length
• Control the Project Cost/Schedule DOE Guidance is $405M Total Project Cost Formal Project completion (CD-4) in 2019
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 3
• Conceptual Design (CD-1) approval 10/14/11 • Long-lead procurements approval 3/14/12
• Injector system and support facility • Fully funded for FY12 • DOE Preliminary Design (CD-2) Review as early as
August, 2012 • Establish Project baseline schedule and budget
LCLS-II Project Status
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 4
• Second 120 Hz injector and 1km LINAC section LCLS-1 and LCLS-II operate independently
• Two New Undulator sources with variable gap In a new undulator tunnel Electrons to two undulators in parallel, 60 Hz each Soft (250 - 2,000 eV) Hard (2,000 - 13,000 eV)
New underground experiment hall, two floors
Key Features of LCLS-II
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 5
Slide 6
DOE CD-3a Review of the LCLS-II Project, Dec 6-7, 2011
Linac Coherent Light Source II Injector @ 1-km point
Sectors 10-20 of Linac (1 km)
CD-0 10 April 2010, CD-1 14 October 2011
X-ray Transport Optics/Diagnostics
New Underground Experiment Hall
Bypass LCLS Linac in PEP Xport Line
New Beam Transport Hall
SXR, HXR Undulators
Electron Systems Schematic Layout
LCLS-II New Instruments Workshops, March 19-22, 2012
0
• Electron Systems largely copied from LCLS-1 • Gun, BC’s, diagnostics, e- dumps
Slide 7
LCLS-II New Construction Layout
LCLS-II New Instruments Workshops, March 19-22, 2012
Experimental Hall 2 Undulator Hall 2 Beam Transport Hall 2
Slide 8
LCLS-II Undulator Hall
• Undulator tunnel is 286 meters in length Space for baseline 114 m HXR and 66 m SXR undulators Room allocated for seeding and tapering extensions
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 9
Undulator Magnets
• LCLS-II Undulators are based on undulators designed at LBNL for the ALS.
Servo Motor
Strongbacks
Compensating Springs
Linear Encoder
Linear Slide
Magnetic Structure
LCLS-II New Instruments Workshops, March 19-22, 2012
Undulator Hall Cross Section
• Undulator tunnel is similar in cross section to the LCLS tunnel.
Slide 10
Experimental Hall 2 Layout
• Space for 4 experimental stations in an 80m long cavern. • Full size second floor for HVAC, racks, control rooms
LCLS-II New Instruments Workshops, March 19-22, 2012
Front End Systems Area for Soft X-rays Area for Hard X-rays
80m
14m
Slide 11
LCLS-II Project Schedule
Slide 12 LCLS-II New Instruments Workshops, March 19-22, 2012
First Light
Install Instruments
EH2 complete
2012 plans
• Start Injector facilities construction in July • Start Injector technical system fabrication • Complete Construction designs by the end of the
year. • Develop the Project baseline schedule and
budget for presentation to DOE in August.
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 13
Summary
• LCLS-II will add capacity and capability to the LCLS scientific program, and will provide space for expansion.
• To minimize cost and risk, electron systems rely heavily on LCLS-1 designs.
• LCLS-II will dovetail with the LUSI-II project. First light in 2018.
LCLS-II New Instruments Workshops, March 19-22, 2012 Slide 14
End of Presentation