Ice Factory, Grimsby Appraisal of Existing Structure by ... · Ice Factory, Grimsby Appraisal of...

Preview:

Citation preview

Ice Factory, GrimsbyAppraisal of Existing Structureby Alan Baxter & Associates LLPwith Richard Griffiths Architectsand KMCS (Cost Consultant)February 2010

Alan Baxter

Ice Factory, GrimsbyAppraisal of Existing Structureby Alan Baxter & Associates LLPwith Richard Griffiths Architectsand KMCS (Cost Consultant)February 2010

Alan Baxter

Contents1.0 Summary..........................................................................................................1

2.0 Introduction....................................................................................................2

3.0 HistoryoftheBuildingandtheSite......................................................3

4.0 Geology............................................................................................................5

5.0 FormofExistingStructure........................................................................7

6.0 ObviousDefectsintheExistingStructure....................................... 13

7.0 ProposalsforRemedialWorkstotheExistingStructure........... 19

8.0 ProposedAlterationstotheStructure.............................................. 22

9.0 NextStage.................................................................................................... 23

10.0 ExistingFabric,byRichardGriffithsArchitects(RGA)................. 24

11.0 CostEstimate,byKMCS.......................................................................... 25

Appendices............................................................................................................. 27

AppendixA–InformationReceived........................................................................... 28

AppendixB–DrawingsbyABA.................................................................................... 29

AppendixC–DrawingsbyRGA.................................................................................... 30

1

1.0

Sum

mar

y

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

1.7 Thesebuildingshavenotbeenmaintainedinanyformformanyyears,probablywellinexcessofthe20yearssincetheyfellintodisuse.Rainwateriscascadingthroughthebuildingsfromtoptobottom.

1.8 Overall,andmostlyasaresultofthetotallackofmaintenance,combinedwiththeaggressiveenvironmentcreatedinthebuildingsfromthemanufactureoficeinvolvinghugevolumesofwatermovingaroundthebuildings,thestructureisnowinaverypoorstateindeed.

1.9 Intermsofanormallifecycleforbuildingsofthisnature,thesebuildingshavemissedtheirlasttwomajoroverhaulsandarenowdegradingatarapidlyincreasingrate.

1.10 Thefollowingnotesdescribetheaboveingreaterdetailtogetherwithproposalsforthelikelyremedialworksrequiredtotrytoaddresstheobviousdefectsinthestructure,allinaccordancewiththeScopeofWorkssetoutbytheNELC.

1.11 Itdoesappearasifthebasicstructuretothebuildingscanbemostlyretainedthoughthereissomeextensiverepairandimprovementsrequired.

1.12 AConservationStatementisrequiredtocomplementthisstudyandhelptounderstandwhatishistoricallyimportantaboutthesebuildings,andtoestablishaclearandproperinterpretationoftheirculturalvalue.

1.13 ReferalsotothelatersectionsonthefabricofthebuildingbytheArchitect,RichardGriffithsArchitects,andthecostestimatesforthelikelyworksbytheQuantitySurveyor,KMCS.

1.14 ThebasicestimatedcostbyKMCSofthethreeoptionsdiscussedwithNELCare:

(C) Tobringthebuildingstoare-usablestandard £4.75M

(B) Areducedversionof(C) £3.5M

(A) TemporaryProtectionwithsomeUrgentStructuralRepairs £1.5M

RefertoSection11.0forfurthercostinformation.

1.0Summary Structure

1.1 TheIceFactorycomprisestwomainbuildingsbuiltin1900/1901and1907/1910.Thereisasmall1950sextensiontothefirstbuilding.ThebuildingsareListedGradeII*.

1.2 Thestructuretothesebuildingsistypicalofindustrialbuildingsoftheirtimewithloadbearingbrickworkwallsandinternalsteelcolumnssupportingsteelandtimberroofsandfloors.

Theformofthestructure,however,isveryparticulartothepurposeofthebuildings,thatis,tomanufactureverylargepiecesoficeforthefishingindustry.

Inplacesthestructuretothebuildingformsapartofthestructuretothemachine/workingsoftheicemakingprocess.

1.3 Thebuildingsarelargeandaretypicallyaround10mhighwithsomeareasextendingalittlebelowgroundlevel.Somespaceshaveafull10mclearheightandotherscompriseofthreestoreys,e.g.twostoreysoficemakingoveranundercroftforthedistributionofservices.

1.4 Itappearsthattheoriginaldesignandconstructionofthestructurewasofareasonablequalityproducingsomerobuststructures,necessaryfortheheavydutymanufacturingprocesscarriedoutwithinthebuildings.

1.5 Thefoundationsgenerallyappeartohaveperformedwelltodatealthoughinonecornerofthe1907/1910buildingthepatternofcrackinginthebrickworkwallsuggeststheremayhavebeensomedifferentialsettlementofthefoundation.Atpresentlittleisknownabouttheformofthefoundations,thoughgiventhepoorgroundconditionsillustratedonthelocalgeologymapsandboreholesobtainedfromtheBritishGeologicalSocietyitseemslikelythefoundationsaresupportedontimberpiles.

1.6 Astheicemakingprocesshasdevelopedthroughouttheworkinglifeofthesebuildingstherehasbeenaneedforsomealterationstothestructurethoughthesedonotappeartohavebeenofmajorstructuralsignificance.

2.0

Int

rodu

ctio

n

2 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

2.0Introduction2.1 AlanBaxter&AssociatesLLP(ABA)havebeeninstructed

byNorthEastLincolnshireCouncil(NELC)toleadateamofconsultantstocarryoutanappraisaloftheexistingstructure,allinaccordancewiththesubmissiontoNELCdated26.06.09,theApproachandMethodologysubmittedon30.07.09anddiscussionswithNELCon17.09.09,14.01.10and27.01.10.

2.2 Theothersintheteamofconsultantsare:

RichardGriffithsArchitects(RGA)andKMCS(QuantitySurveyors)

2.3 Thefollowingreportisasummaryofourappraisalandcomprisesthreemainelements:

(i) Structuretothebuilding ByABA

(ii) Fabricofthebuilding ByRGA

(iii) CostEstimateofproposedworks ByKMCS

Itisbasedonourdesktopresearch,togetherwithwhatweareabletoseefromourvisitstothebuildingon17/09/09and14/01/10andtheoutputfromworkshopsheldatABA’sofficeswiththeconsultantteam,andwiththeclient.

2.4 AccesstothebuildinghaskindlybeenprovidedbyAssociatedBritishPorts(ABP)thoughinternallyaccessisseverelyrestrictedduetotheunsafenatureofthefloorstructuresinmanyplaces.

View from Gorton Street

3

3.0

His

tory

of t

he b

uild

ing

and

the

Site

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

3.0History of the building and the Site3.1 TheIceFactorycomprisesoftwomainbuildingsseparatedby

arailwayline(nolongerinuseandcoveredover).Themainbuildingtothesouthoftheoldrailwaywasbuiltin1900/1901byTheGrimsbyIceCompanyandwasthelargestofalltheicefactoriesinthetown.

3.2 TheFactorywasextendedin1907/1910withtheconstructionofthebuildingtothenorthoftheoldrailwayline.

3.3 In1930/1933theFactorywasmodernisedwiththeoldsteamdrivenplantreplacedwithelectricitydrivenplant.Thisapparentlyaffectedthemachineryanditsfittingsmorethanitsfabric.Aspartofthisworktheoriginalboilerhousechimneywasdemolishedthoughitsbaseremains.

3.4 Intheearly1950stheoriginalFactorywasextendedtoincorporateanewcompressorroom,togetherwithotheralterationstotheicestores.

3.5 TheIceFactoryclosedin1990andhasnotbeeninusesince.

3.6 ThebuildingswerelistedgradeII*on12September1990.AcopyofthelistingisenclosedinAppendixA.

View from Fish Dock Road Aerial view

3.0

His

tory

of t

he b

uild

ing

and

the

Site

4 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

1905Recent aerial photo

TheIceFactory

5

4.0

Geo

logy

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

4.0Geology4.1 Thegeologymapofthisareashowsthemajorityofthedock

builton‘landslip’overAlluviumoversandsandgravels.

Geology map

TheIceFactory

4.0

Geo

logy

6 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

4.2 BoreholesobtainedfromtheBritishGeologicalSocietyshowthesitetobeunderlainbymadegroundoversoftsilt,peatandclaywithsomethinlayersofsand,overchalkwhichisfoundaround80ft(24mm)belowgroundlevel.

4.3 NodetailsofthefoundationstotheIceFactoryhavebeenobtained,butitisdocumentedthattheGrimsbyDockTowerbuiltin1851isfoundedontimberpilesprobablydrivenintotheclay.ItseemslikelythattheIceFactoryisalsosupportedontimberpiles.

4.4 Boreholesfrom1925showedadepthtogroundwaterofaround15ft(4.57m),whereasin1950thedepthisshownas21ft(6.4m)andfrom1981adepthofaround10ft(3m)isrecorded.

BGIS Borehole Ref TA21/64A or Ref TA21SE/21A from the Ice Factory engine house

BGIS Borehole location plan

TheIceFactory

7

5.0

For

m o

f Exi

stin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

5.0Form of Existing Structure5.1 Thesebuildingscompriseoffairlyconventionallate19thearly

20thCenturyindustrialstructuresformingsuchspacesasaboilerhouse,compressorrooms,switchroomsandofficese.g.areas(i),(iv),(v)and(ix),alltheretosupporttheprincipalpartsofthebuildingwheretheicewasmanufacturedorstored,ieareas(ii),(iii),(vi)andvii).Intheseice-makingareasthestructureformspartofthemachineryusedtomaketheice,andalsosupportsthecasing/envelopetothemachines,ietheroofandwalls.

Key planWatertankonroof

5.0

For

m o

f Exi

stin

g St

ruct

ure

8 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Nexttothisspaceisthe1950sextensioncomprisingofaswitchroomwithanofficeatfirstfloorlevel,andthenanotherdoublestoreyheightcondenserroom.Thepitchedroofovertheofficeappearstobeoftimberceilingjoistsandrafterssupportedonsteelbeams,andthefirstfloorcomprisesofafillerjoistfloorslabspanningbetweensteelbeams.Thenewcondenserroomroofappearstobeofin-situreinforcedconcreteslabspanningbetweensteelbeams.Thesteelbeamsaresupportedonsteelcolumnsbuiltintothebrickworksidewalls.

Alargewatertankissuspendedabovetheroofoftheoriginalcondenserroomonasteelframewhichspansbetweentheloadbearingwallsatrooflevel.

(i) CompressorHouse,SwitchRoomandOffice:

Theoriginalcompressorhousecomprisesatallsinglestoreyspacearound9metreshigh,withsolidloadbearingbrickwallssupportingsteelroofbeamsandaconcretefillerandsteeljoistflatroof.Thelongerspanningroofbeamsareproppedoff3steelcolumnstowardsonesideoftheroom.Thesecolumnsalsosupportderrickcranesforservicingthecompressorsintheroom.

Thegroundfloorisofsolid,probablyreinforcedconcreteconstructionwithnumerousservicestrenches/pitsincorporatedintotheslab.Itislikelythattheveryheavycondenserplantisfixeddowntothickreinforcedconcreteplinthsaspartoftheslab.

Services trench in ground floor

Typical section through Compressor Room

Water tank on roof

Compressor Room roof

1950s Compressor Room

Original Compressor Room

GableendtoTankRoom

Fillerjoistroofslab

Travellingpulleybeam

RCslabwithpitsandservicetrenches

Derrickcrane

Steelbeam

Steelcolumn

CompressorSection

9

5.0

For

m o

f Exi

stin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

(ii) TankRooms:

Thisisthemainpartoftheoriginal1900buildingandcomprisesoftwofloorsoficemakingmachineryoverasemi-basementundercroft,allcontainedwithinanexternalloadbearingbrickwork,andinternalsteelframedstructure.

Accessisseverelylimitedforsafetyreasonswithnoaccessavailabletotheundercroft.

Thestructuretothetwobaybuildingcomprisessteelrooftrussessupportingtimberpurlins,timberboardsandslates,spanningbetweenpiersinthebrickworksidewallsandarowofsteelcolumnsonthelineofthecentralvalley.

Thereisasmallbrickworktowerattheeastendofthetankroomswhichappearstobesupported,inpartoffthesteelframe.

Some equipment remains in Tank Room Internal column support to travelling crane brackets1st floor Tank Room

Typical section through 1900/1901 Tank Rooms

Rooftruss

CIBrackets

Undercroft

Travellingcranebeam

Travellingcranebeam

1stFloor

UpperGroundFloor

5.0

For

m o

f Exi

stin

g St

ruct

ure

10 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Thetwofloorsoficemakingequipmentaresupportedoffagrillageofsteelbeamsspanningbetweenthesidewalls,thecentralrowofsteelcolumns,andtwofurtherrowsofcolumnsineachbayofthebuildingintheundercroft.

Travellingcranesspanclearacrosseachbayaboveboththetwofloorsoficemakingequipment,supportedoffcastironbracketsattachedtothepiersinthebrickworksidewallsandthecentralrowofsteelcolumns.Thecastironbracketsonthepiersarefixedthroughthebrickworktoexternalplates.

External plates to crane beam brackets

Bracket support to travelling crane beam

View of 1907/1910 Tank Room roof

Roof over Ice Store Original Boiler House

(iii) IceStore:

Thispartofthebuildingcomprisesofathreestoreyexternalloadbearingbrickworkwallsupportingaflatroofofsteelbeamswithprobablyafillerjoistslab.Ithasalsobeenconvertedforicemakingandsocontainstravellingcranesandicemakingequipmentontheuppertwostoreys.Thesemibasement/undercroftiscurrentlyastoreroomfulloffridges/freezersandwasnotaccessible.

(iv) FlakeIcePlant(PreviouslyBoilerHouse):

Thissinglestoreystructurehasloadbearingbrickworkwallssupportingasteeltrussedroofwithtimberpurlins,boardsandslates.

Originallytheboilerhousehadatallbrickchimneyinthenorthernmostcorner,butthiswasremovedaspartofthemodernisationinthe1930s.Itappearsasifthebasetothischimneyremains.

11

5.0

For

m o

f Exi

stin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

(v) CondenserRoom/Stores:

Theseareasofthebuildingaregenerallyoftwostoreyswithabasement/undercroft.Accesswasnotpossibletothebasement.Thefloorandroofstructuresappeartobeoffillerjoistconstructionsupportedonsteelbeamssprungbetweenloadbearingbrickwalls.

(vi) TankRooms:

Thisisthemajorpartofthe1907/1910extensionandisofsimilarconstructiontotheoriginaltankroomstructurein5.2(ii)above.

Thebuildingprovidedtwostoreysoficemakingequipmentsupportedbysteelgrillagesatboththefirstfloorandgroundfloorlevels.Travellingcranebeamstothefirstfloorandthegroundfloorarebothsupportedononesidebycastironbracketsinthepierstothesolidloadbearingbrickwallandontheotherbybracketsontosteelcolumns.

Thelowerlevelsteelgrillageissupporteddirectlyoffthereinforcedconcretegroundfloor.Thefloorisformedinsuchawayastoprovidethreetrenchesthefulllengthofthebuilding.

Thereisasmallbrickworktoweratthenorthendofthetankroomwhichappears,atleastinpart,tobesupportoffsteelbeams.

1st floor 1907/1910 Tank Room Ground floor steel grillage Ground floor brench and foundations to brick pier

Typical section 1907/1910 Tank Room and Ice Store

Timbertrusses

Travellingcrane

Travellingcrane

1stfloor

SteelgrillageontopofRCtrenches

Steelbeam

Steelcolumn

IceStore TankRoom

5.0

For

m o

f Exi

stin

g St

ruct

ure

12 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

5.2 Thereisasmallpedestrianbridgebetweenthe1900/1901andthe1907/1910buildingscomprisingofsteelbeamsspanningbetweentheexternalwallsofeachbuildingwithatimberboardeddeck.

5.3 Theseareunusualbuildingswithsomeverylargeopenspacessuchasthestoreinthe1907/1910buildingwhichhasloadbearingbrickworkwallsofaround10mhigh.

Theoverallstabilityofthebuildingsappearstorelyonthestiffnessoftheboardedroofstructureandthefloorstructurestoactashorizontaldiaphragmstyingtogetherthewalls.

Thegroundfloorappearstobetimberboardedoversteelbeamspossiblyoveranundercroft,butsafeaccessherewasnotpossible.

(viii) LoadingBay:

Thisareawasnotaccessiblebutitlooksasiftheflatroofstructureispossiblyofsteelfillerjoistconstructiononsteelbeamssprungbetweensolidloadbearingbrickworkwalls.

(ix) Office:

Atthewestendofthetankroomthereistwofloorsofofficeswhichappeartosimplybeanextensionofthetankroomstructurewithsomepartitionsandfalseceilingsaddedtocreatethespace.

Theroofcomprisessteeltrussesspanningacrossthewidthofthebuildingfromtheexternalloadbearingbrickworkwalltotheinternalcolumns.

(vii) IceStorageArea:

ThisisineffectasideextensiontotheTankRooms(vi)aboveformingasingleverytallstoreyheightspaceofover10m.

Theroofstructurecomprisestimbertrussessupportingtimberpurlins,rafters,boardsandslates,spanningbetweensteelvalleybeamssupportedoverslendersteelcolumns.

Base of internal columns between Tank Room and Ice Strore Bridge between buildings

Ice Store roof Roof over end of Tank Room by Offices Bridge between buildings

13

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

6.0Obvious Defects in the Existing Structure6.1 Thefourcriticalissuesinassessingtheoverallconditionofan

existingstructureare:

(i) TheQualityofOriginalDesignandConstruction.

(ii) ThePerformanceofitsFoundations/thequalityofthegroundonwhichtheyarebuilt.

(iii) PreviousAlterations.

(iv) Howwellithasbeenmaintained.

6.2 TheQualityofOriginalDesignandConstruction:

Fromwhatwecanseetheoriginaldesignandconstructionwasgenerallyofanaboveaveragequalityforindustrialbuildingsofthisage,thoughtheprocessoficemakingwithlotsofwaterthroughoutthebuildingandtheabrasivenatureoftheicemakingprocesscreatedafairlyaggressiveenvironmentforboththeexposedsteelstructure,andthosesteelelementsbuiltintotheexternalwallsandroof.

Surface corrosion and impact damage to steel beams

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

14 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

6.3 ThePerformanceofitsFoundations:

TheBGISboreholesindicatethatthewholeofthedockisunderlainbyasignificantdeptofsoftmaterialincludingpeat,withthefirstlayerofreasonablesoilcapableofsupportingheavystructuressuchastheIceFactorybeingtheboulderclayataround10mdepth.ItthereforeseemslikelythatthefoundationstotheIcefactoryareondriventimberpiles.

Therearemanycracksintheloadbearingbrickworkwallsthoughthesegenerallyseemtoberelatedtoproblemsassociatedwiththecorrosionofsteelworkbuiltintothewalls,thermalmovementsoftheuninsulatedroofsandnotobviouslytodowithmovementofthefoundations.

Theoneareawherethecracksinthewallsmayberelatedtodifferentialsettlementofthefoundationsisthenorthwesternendofthe1907/1910buildingwherethereisacrackalmostfullheightofthewalls,andappearstobewideratthetopthanatthebottom.ThisisinthecorneroftheIceStore.

Generallytheexistingfoundationsappeartohaveperformedreasonablywelltodate.

6.4 PreviousAlterations:

AswithanyindustrialbuildinghousingaprocessovermanyyearstherepeatedupdatingoftheprocessgenerallyinvolvessomealterationtothestructureandthisisthecasehereintheIceFactory.Overall,however,thesealterationsdonotappeartohavesignificantlyaffectedtheexistingstructure.

6.5 MaintenanceoftheStructure:

Fromthestateofthebuildingsitisclearthattheyhavenotreceivedanymaintenanceformanyyearsprobablyfromwaybefore1990whenthebuildingswerelastinuse.Largeareasoftheroofcoveringshavebeenremoved,orhavecollapsedandarenowinsuchapoorstate,thatrainwateriscascadingtoptobottomthroughthebuildings.

This,togetherwiththeaggressiveenvironmentgeneratedbythewaterbaseduseofthebuilding,hasledtosomeextensiveandsignificantdegradationofthestructure.

Themostobviousfactorinthedegradationoftheinternalstructureovertimeisnaturallytheprolongedexposureofthetimberandsteelstructuretowaterasaresultoftheicemakingproduction,leadingtocorrosionofthesteelworkandwetrotinthetimberstructure.Severalsteelbeamshavealsosufferedfromrepeatedcollisionswithotherheavymetalitems.Thiswas

Cracked brickwork in Ice Store Cracked brickwork in Compressor Room

Cracks in parapet walls Roof to 1900/1901 Tank Room

Physical and corrosion damage to steelwork

15

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

visibleinbeamsoverlargeopeningsintheexternalwalls,andalsointernallywherethemovementoflargesteelitems(egcansfortheicemaking)clearlyresultedinalotofphysicalclasheswithsomeofthestructure.

6.6 ExternalWalls:

6.6.1 Drawingsnumbers1568/01/15and16showelevationsoftheexternalbrickworkwallsmarkedupwithourobservationsontheobviousstructuraldefectsegapproximatelocationofcracksandtheirlikelycause.

Basedonwhatwecouldsee,thecracksinthebrickworkweregenerallyasaresultofcorrosionofsteelworkbuilt

Impact damage to brickwork around opening in wall

Spalled concrete as a result of corroded reinforcement

Crack in parapet to roof over Ice Store

Cracked concrete where reinforcement is corroding

Roof beam and filler joist roof by 1900/1901 Ice Store

RC frame around windows in 1950s extension

intotheexternalwalls,togetherwithsomethermalexpansionoftheuninsulatedflatroofsandlocallysomeimpactdamage.

6.6.2 RefertotheArchitect’sdrawingsfornon-structuralissuessuchasminorcracks,weatheringetc.

6.6.3 Thereinforcedconcretewindowframeinthe1950sofficeandcondenserroomsisinapoorconditionwithspallingoftheconcreteinseveralareasasaresultofprolongedrainwaterpenetrationoftheconcretecausingthereinforcementtocorrode,expandandpushofftheconcrete.

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

16 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

6.7.5 Alloftheotherflatroofsappeartobeoffillerjoistconstructionandinseveralareastheconcretecovertothebottomofthesteeljoistshasspalledexposingcorrodedsteelwork.Thisisevidentinthecompressorroom,icestoreandcondenserroomroofsintheoriginalbuilding.Wesuspectthisisalsothecaseintheroofstotheloadingbayinthe1907/1910extension.

6.7.3 Thetimberstructuretotheshallowpitchedroofovertheofficeinthe1950sextensionislikelytobeinaverypoorconditionandsomeofthesupportingsteelbeamsalsoappeartobesignificantlycorroded.

6.7.4 Wenotedsomespallingofconcretelocallyinsomeareasoftheundersideofthereinforcedconcreterooftothecompressorroominthe1950sextensionsuggestingrainwaterhasbeenpenetratingtherooffinishesandtheslabformanyyears.Itislikelythattherewillbeotherareaswherethereinforcementiscorrodedespeciallyinthetopoftheslab.

6.7 RoofStructures:

6.7.1 Generallythetimberboardingandpurlinstothepitchedroofstotheoriginaltankroomsandboilerhouseappeartobeinapoorstateasaresultofprolongedrainwaterpenetration.Thesteeltrusses,however,seemtobeinareasonableconditionthoughitwouldbeprudenttoexpecttofindsomelocalproblemstodowithcorrosionespeciallyalongthevalleyguttertotheoriginalbuilding.

6.7.2 Thetimbertrussestotheicestoreinthe1907/1910buildingarelikelytohavebeenmuchmoreaffectedbyrainwaterpenetrationthanthesteeltrussesandsowewouldexpecttofindsomeextensivewetandperhapsdryrotespeciallyintheendsofthetrussesalongthevalleyguttersandaroundtheedgeofthebuildingundertheparapetgutter.

Roof to 1950s Office

Severely corroded steel joist in flat roof

Roof over Ice Store

Original Compressor Room

Roof to original Tank Rooms

1950s Compressor Room

17

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

6.8 InternalStructure:

6.8.1 CompressorRooms(i)

Rainwaterpenetrationovermanyyearshasledtosomesignificantcorrosionofthesteelbeamstothefirstfloorintheoffice.Thesteeljoiststothefillerjoistfloorarealsolikelytobeaffected.

Elsewhereinthecompressorroomstheinternalsteelstructuregenerallyappearstosufferfromsomesurfacecorrosiononly,whichisnotofmajorstructuralsignificance.

Theconcretegroundfloorinallofthisareacontainsnumerousservicestrenches,plinthsandrecesses.Sometrencheshavesteelcovers,andsomearepartiallyfilledwithwater.

6.8.2 TankRooms1900/1901(ii):

Thesteelstructureabovefirstfloorlevelgenerallyappearstobeinapoorconditionasaresultoftheprolongedrainwaterpenetrationthroughthebuilding.Atthislevelthemostobviousdefectissurfacecorrosionofthesteelworkandthisvariesconsiderablywithonlylocalareasthatappeartobesignificant.

Whilstverylimitedaccesswaspossibleacrossthisareaofthebuilding,itappearsthatatfirstfloorlevel(ietheuppericemakinglevel),theeffectoftherainwaterandtheaggressiveenvironmentduringtheicemakingprocesshasleftthetimberboardedfloorinaverypoorstateandboththeextentandseverityofcorrosionofthesteelframedstructureismuchmoreseriousthanabove.

Attheuppergroundfloorlevel(iethelowericemakinglevel)theconditionofthestructureappearstobeevenmoredeterioratedthanatfirstfloorlevel.

Noaccesswaspossibletotheundercroft,asitwasmostlyfilledwithwater,butfromwhatcouldbeseenfromtheentrance,thesteelworkatthislevelisinanextremelypoorstate.Onlyafewbeamsandcolumnswerevisibleandthesewereseverelycorrodedanddelaminatingtosuchanextentthatinplacestheflangeandpartsofthewebofthebeamsandcolumnsweremissing.

Itislikelythatthefloortotheundercroftisalsoinaverypoorstate.

First floor to 1950s Office Services trench in Compressor Room ground floor

First floor Tank Room

Severely corroded steel column in Tank Room undercroft

Severely delaminating steel beam in Tank Room undercroft

6.0

Obv

ious

Def

ects

in th

e Ex

istin

g St

ruct

ure

18 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Thesteelcolumnssupportingtheroofandfirstfloorhaveheavilygussetedbaseswheretheyarefixedtothetopofthegroundslab,whichisthickenedateachcolumnpositionandmustalsobethefoundationtothecolumn.Thesteelworkcolumniscoveredinsurfacecorrosion,butattheirbasethecolumnandgussetplatesareseverelycorrodedanddelaminatinginplaces.

6.8.6 Store(vii):

Thetimbergroundfloorinthisareaisinanextremelypoorconditionwithextensiverottenandcollapsedareasofthefloorstructure.

6.8.7 LoadingBay(viii):

Noaccesspossibletothisarea.

6.8.8 Office(ix):

Localareasofthetimberboardedfirstfloorandthesteelbeamsupportshavesufferedasaresultoftheirprolongedwetstateandinplacesthetimberisclosetocollapse.Thereisextensivesurfacecorrosioninthesteelbeams.

6.8.9 Noaccesswaspossibletolookatthesteelframesupportingthelargewatertankoverthecondenserroom.Itseemsverylikelythatthissteelworkisinapoorconditionespeciallywhereitisbuiltintothebrickworkwalls.

6.8.5 TankRoom(1907/1910)(vi):

Thetimberandsteelframedstructuresupportingthefirstfloorhassufferedfromrainwaterpenetrationandtheaggressiveconditionswithintheicemakingenvironmentinasimilarthoughseeminglynotasseverelyasintheoriginaltankrooms6.8.2above.

Thesteelgrillageatgroundfloorlevelissufferingfromextensivesurfacecorrosioninplaces,inparticularatthesupportsoffthereinforcedconcretegroundfloor.Itislikelythesewillbeareasofseverecorrosionanddelaminationofthesteelwork.

ThegroundfloorcontainsthreetrencheswhichwereabouthalffullofwaterduringourvisitinJanuary.Wesuspectthereinforcedconcreteisnotinagoodcondition.

6.8.3 IceStore(iii):

Thesteelstructurehereappearedtobesufferingmuchlessfromrainwaterpenetrationthanin6.8.2above,thoughitislikelythattherewillbesomebeamswhichareseverelycorroded.

6.8.4 OldBoilerHouseandCondenserRoom(iv)and(v):

Thegroundfloorslabsintheseareasappeartobeofreinforcedconcreteandcontainssomeplantbases/plinthsandtrencheswithabasementunderthewestern-mostarea.Theextentofthisbasementisnotknownasitwasnotaccessiblethoughitseemslikelytobeonlyunderthissmallwestern-mostspace.

Corrosion to bottom of Columns in 1907/1910 Tank Room

U/s first floor to Tank Room 1907/1910

Gurretted bases to Columns in 1907/1910 Tank Room

First floor to Ice Store 1900/1901

Ground floor to Tank Room 1907/1910

19

7.0

Pro

posa

ls fo

r R

emed

ial W

orks

to th

e Ex

istin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

7.0Proposals for Remedial Works to the Existing Structure7.1 Ourexperienceofbuildingsofthisageshowsthatinorderfor

themtocopewithchangesovertime,andtocontinuetobeuseable,thentypicallytheyneedanoverhaulevery25yearsorso,withmajoroverhaulsevery50yearsorso.Itisalsoveryimportantthataspartoftheseoverhauls,allthedefectsinthestructurenotcoveredbythenormalmaintenanceofabuildingaredealtwith.Goodbuildingsofthisagecangenerallybekeptgoingalmostindefinitelyifproperlymaintained.

HereattheIceFactoryitseemsthatitshistoricaldevelopmentfollowedalongthistypicalpathforawhile,ie:

• Built1990/1901and1907/1910

• Firstmajoroverhaul1930s

• Secondoverhaul1950s

butthenwiththefishingindustryindeclineitlooksasifthenexttwooverhaulsaround1975andcertainlyin2000didnothappen.

Forthegeneralconditionofthestructureitlooksasiffew,ifany,ofthedefectsinthestructurehavebeenaddressedinthissecondhalfofitslife.

TheaggressiveconditionsgeneratedintheIceFactorymeantthatthebuildingwouldhaveneededmuchmoremaintenancethanotherbuildingsofitsage.

Itisclearthatthebuildinghasnothadanymaintenancecarriedoutformanyyearsandisnowdeterioratingatarapidlyacceleratingrate.

Lifecycle between major services/overhauls for typical traditionally built building

Lifecycle between major services/overhauls for the Ice Factory

Rate of Deterioration

7.0

Pro

posa

ls fo

r R

emed

ial W

orks

to th

e Ex

istin

g St

ruct

ure

20 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Thelongerspanpitchedroofsovertheoldboilerhouse,andthetankrooms(1900/1901and1907/1910)generallyappeartobeinalittlebetterconditionthantheothers.Intheseareasthetimberboardinglookstobeinapoorstateinplaces,butelsewhereitmaybepossibletore-usetheboards.Similarly,someofthetimberpurlinslookasiftheywillneedreplacingandotherslookasiftheycanberetained.

Wesuggestthat:

2. Alltheroofcoveringsareremoved(seealsoArchitects’report).

3. Alltimberboardingisremovedandseparatedintothatwhichcanbere-used(say30%)andthatwhichcannot.Theboardschosenforre-usewillneedtobedry,and/ordriedinacontrolledenvironment.

4. Thetimberpurlinsareremoved,andseparatedtothosethatcanbere-used(say50%)andthosewhichcannot.

5. Thesteeltrussescanthenbethoroughlywirebrushedtoremoveallsurfacecorrosionandrepainted.

6. Thenewandretainedpurlinsandboardscanthenbefixedinposition.

7.2.2 RoofStructure:

Whilstsomedetailedinvestigationwillbeappropriateinduecourse,itseemsatthisstagethattheflatroofedareashaveallsufferedfromextensiverainwaterpenetrationoversuchalongperiodoftimethatitseemsverylikelythattheywillallneedtobereplaced,ontopoftheexistingsteelbeams.Thisappliestoallthesteelfillerjoistroofsandthe1950sreinforcedconcreteroofoverthenewcompressorroom.

Wesuggestthewayforwardhereisforthereplacementworkstocommencewithastagedremovaloftherooffinishesandthentheconcretetoexposethesteelfillerjoistsandreinforcement.Theconditionofthejoistsandreinforcementcanbeassessedastheyareexposedandiffoundtobeinabetterconditiontothatcurrentlyexpectedthenitmaybepossibletoretainsomeofthesteeljoistsandmaybepatchrepairther.c.slab.Atthisstage,however,itwouldbeprudenttoallowforitalltobereplaced.

Theconditionofthepitchedroofstructuresvariesconsiderably.Thesmallpitchedroofovertheoriginal1900/1901office,andthemultipitchedroofoverthestoreinthe1907/1910buildingappeartobeintheworstcondition.Atthisstagewesuggestanallowanceismadeforreplacingtheroofstructureovertheofficecompletely.Overthestoreitlookslikelythatthesteelvalleybeamswillneedsomeremedialworkespeciallywheretheyarebuiltintothewallsandthetimbertrussesarelikelytoneedrepairs/loadrebuildingattheirendswheretheyaresupportedoffthevalleybeams.Allboardingandpurlinsarelikelytoneedreplacement.

7.2 Thefollowingsectionoutlinestheapproximatescopeofremedialworksrequiredtotheexistingstructuretoaddresstheobviousproblemsdescribedearlier.

7.2.1 ExternalWalls:

Allthecracksinthebrickworkneedtobemadegoodbycarefullycuttingoutthecrackedbricksandstitchinginnewbrickwork.Wherethecracksextendfullwidththroughthebrickwork,thisneedstobedonefrombothsides(insideandoutside).

Wherethecracksaretheresultofcorrodedsteelworkthecauseofthecracking,ietheexpansionofthesteelworkasitcorrodesanddelaminates,alsoneedstobeaddressed.Thisinvolvescarefullyremovingthebrickworkaroundtheembeddedsteelwork(egbeamend),introducingtemporarysupportstothesteelworkwhereneeded,sothatthesteelworkcanbethoroughlywirebrushedtoremovealllooserust,cleaned,andthenpaintedwithtwocoatsofbituminouspaint,priortomakinggoodthebrickworkaroundthesteelasabove.Insomelocationsthesteelworkmaybefoundtoalsoneedsomerepairandsoacontingencyshouldbeallowedtocoverthistoo.

Wheresteelbeamsarebuiltintotheexternalwalloveropeningssuchastotheloadingbay(viii),allowforthefirstthreecoursesofbrickworkoverthebeamtobecarefullycutouttoallowthebeamtobetreatedandthenreplaced.

Refertodrawingnumbers1568/01/07to08whichillustratesthelikelyapproximateextentofbrickworkrepairsatthisstagerelatedtostructuralremedialworks.RefertotheArchitects’drawingsforallotherworkstotheexternalwalls.

Roof over Ice Store 1900/1901Cracks in brickwork where steel beam is severely corroded

21

7.0

Pro

posa

ls fo

r R

emed

ial W

orks

to th

e Ex

istin

g St

ruct

ure

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

7.2.3 InternalStructure:

Withtheenvelopeofthebuildingsmadegoodtheinternalstructurewillneedtimetodryouttodeterminetheextentofremedialworks,thoughtoachievethisstateandtotacklesomeoftheobviousdefectswesuggestthefollowingapproach:

(ii) Clearoutallthedebrisetc.

(iii) Removeallrotten/damagedtimberboarding.

(iv) Pumpoutallthewaterfromthetrenchesandundercrofts.

(v) Wheresteelcolumnshavebecomesignificantlyaffectedbycorrosion/delaminationtheseshouldeitherbereplaced,orperhapsencasedinreinforcedconcretetomaintaintheirstructuralfunction.Thisappliestosomeifnotallofthecolumnsintheundercroftbeneaththeoriginal1990/1901tankrooms.

(vi) Thebuildingsthenneedtobewellventilatedtoallowthemtodryout.Thisneedstobedoneinacontrolledandmaintainedwaysothatitisnotonlyeffectivebutalsoavoidsfurtherproblemsbeinggeneratedsuchasdryrotmanifestingitselfinthetimberstructure.

7.3 ContractorsSiteSetUp

AspartoftheseworkstherewillbeasubstantialcostinvolvedintheContactorestablishinghissetuponsiteincludingallthetemporaryworksnecessaryforsafeaccessinordertoclearoutallthedebrisandcarryouttheremedialworks.Thiswillincludeaccessdecksandstairsaswellasprotectivedecksforsafeaccess.

8.0

Pro

pose

d Al

tera

tions

to th

e St

ruct

ure

22 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Dependingontheproposednewusesitmaybepossibletoreplace(eitherallorinpart)theexistingveryheavydutyfloorstructuresinthetankroomswithseveralnewlighterweightfloorstructures.

Intheareaswheretherearenointernalupperfloors,e.g.originalcondenserroom,boilerhouseandthe1907/1910store,itislikelythattheexistingstructure(wallsandcolumns)couldbeusedtosupportoneormaybetwonewfloors.

RefertotypicalsectionC.

8.0Proposed Alterations to the Structure8.1 Atthisstagetherearenospecificalterationsproposedand

NELChaverequestedsomegeneralcommentsonthefeasibilityofcarryingoutalterationsandaddinginnewfloorswithintheexistingbuilding,allbasedontheunderstandingwehaveoftheexistingstructure,describedabove.

Thefollowinggeneralcommentsassumethatallthedefectsintheexistingstructureareaddressedpriortocarryingoutanyalterations.

8.2 Roof:

Theflatroofedareascanprobablybeusedtosupportsomenewlightweightplant.Shouldtheexistingwatertankovertheoriginalcompressorroomberemovedthenthatareaoftheroofshouldbeabletocopewiththeadditionofnewplant/accommodationofasimilarmasstothewatertank.

8.3 Walls:

Thebrickworkwallsaregenerallyrobustandhavebeenusedtosupportveryheavyimposedloadsaspartoftheicemakingprocess.Itseemslikelywiththeicemakingprocessremoved,thattheycouldbeusedtosupportsomesignificantnewimposedloadsfromadditionalfloors.

Itlooksfeasibletobeabletoremovethetravellingcranebeamsandtheirfixingbracketswithoutsignificantlyaffectingtheintegrityofthebrickworkpiers/walls.

8.4 Floors:

Currentlyitseemslikelythatthefloorsinthemaintankroomsdocontributetotheoverallstabilityofthebuildingandthebrickpiers.

Wherethemainfloorbeamsareconnectedtotheexistingbrickworkwithexternalfixingplatesitmakessensetoretainthesefloorstructuresaspartofanynewscheme,thoughinprincipleitwouldbepossibletoremovethemandreplacethemwithnewfloorstructures.

Timbertrusses

Travellingcrane

Travellingcrane

1stfloor

SteelgrillageontopofRCtrenches

Steelbeam

Steelcolumn

IceStore TankRoom

Section C

Potentialnewfloorsbuiltoffexistingstructure

23

9.0

Nex

t Sta

ge

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

9.4 Itneedstoberecognisedthatthescopeofremedialworksin(iii)aboveisaimedataddressingtheobviousdefectsinthestructure,itisthenatureofbuildingsthatsomedefectsarehiddenandmayonlybecomeobviouseitherduringtheworksonsite,orindeedlaterinthelifeofthebuilding.

Allremedialworksshouldbedesignedtosympatheticallyrepairorimprovetheexistingstructure,thoughagainitshouldberecognisedthattheseworkscannotbecomparedtonewconstruction,andareaimedatextendingtheusefullifeofthebuildingwhichisindeterminate,andreliesonhowwellitiscaredforinthefuture.Itwouldbeusefultodevelopasimplemonitoringregimeaspartofthedetailedproposalstoassistwiththeassessmentofthesuccessoftheproposalsandasacheckonfuturemovementsofthestructure.

9.5 Aspartofthenextstageoftheworkswerecommendaconservationassessmentismadeofthebuildingsandtheircontentstoassistinthepreparationoftheproposals.

9.3 AsdiscussedwithNELCthisreporthasconsideredthelikelyscopeofremedialworksrequiredtoaddressalltheissuesraisedintheNELCScopeofWork.

AnestimatedcostoftheseworkshavebeenpreparedbyKMCS.

Twofurthercostestimateshavebeenprepared:

i. forworksofalesserscalethanabovejusttoaddressrainwaterpenetrationofthebuilding.

ii. Simplytoenclosethebuildinginasheetedscaffoldtotryandkeeptherainwaterout.

Inverygeneraltermsthelikelyeffectofthethreealternativescostedare:

i. Scaffoldonly:Thiswillslowdowntherateofescalationofthedegradationofthestructure,butshouldbeconsideredasatemporarymeasureonlybeforeproceedingwithmoresubstantialworks.

ii. LesserScaleofWorks:Thiswilladdressthemostobviousdefectsinthestructureandprovideabreathingspacebeforecarryingouttherestoftheworksin(iii)below.

iii. NELCFullScopeofWorks:Thisshouldpreparethebuildinggenerallyforconversionorrefurbishmentonceausehasbeenfound.

9.0Next Stage9.1 Thisreportisaimedatprovidingaveryoutlinescopeofworks

anda‘ballpark’costestimateofthelikelyremedialworksneededtotheexistingbuilding.

9.2 Inordertopreparemoredetailedproposalsforthepurposesofobtainingtendersfortheworkthenwesuggestanenablingcontractisbuiltintotheprogramme.Thisenablingcontractwouldincludesomephysicalopeningupworkstoassistindeterminingtheseverityofdegradationofthestructureandbetterdefinetheextentofremedialworks.Itcouldalsobeusedtocarryouttrialrepairsforagreementwithinterestedparties(e.g.EnglishHeritage)priortocommencingthemainworks.

Theseinvestigationworkswouldinclude:-

• Breakingoutareasoftheflatroofedstructuretorevealtheseverityofcorrosionoftheembeddedsteeljoistsand/orreinforcement.

• RemovalofareasoftherottentimberfloorsintheTankRoomsandIceStorestohelpclarifytheseverityofcorrosionofthesteelstructure.

• Trialpitstoexposethefoundationsandcheckwhetherthebuildingissupportedofftimberpiles,andwhetherthepilesextendabovethecurrentgroundwaterlevel.

• Providingsafeaccesstopreviouslyinaccessibleareasofthebuildings.

• PumpingoutofwaterfromtheundercroftandServiceTrenches.

10.0

Ex

istin

g Fa

bric

24 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

10.0Existing Fabric, by Richard Griffiths Architects (RGA)

25

10.0

Ex

istin

g Fa

bric

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

10.0

Ex

istin

g Fa

bric

26 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

27

10.0

Ex

istin

g Fa

bric

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

10.0

Ex

istin

g Fa

bric

28 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

29

10.0

Ex

istin

g Fa

bric

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

10.0

Ex

istin

g Fa

bric

30 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

31

10.0

Ex

istin

g Fa

bric

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

11.0

C

ost E

stim

ate

32 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

11.0Cost Estimate, by KMCS

33

11.0

C

ost E

stim

ate

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

11.0

C

ost E

stim

ate

34 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

35

11.0

C

ost E

stim

ate

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

11.0

C

ost E

stim

ate

36 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

37

11.0

C

ost E

stim

ate

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

39

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appendices

Appe

ndic

es

40 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Appendix AInformation Received

41

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

42 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Appendix BDrawings by ABA

43

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

44 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

45

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

46 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

47

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

48 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

49

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

50 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

51

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

52 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

53

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

54 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

55

Appe

ndic

es

Ice Factory, Grimsby Appraisal of Existing Structure / February 2010Alan Baxter

Appe

ndic

es

56 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Appe

ndic

es

58 Ice Factory, Grimsby Appraisal of Existing Structure / February 2010 Alan Baxter

Appendix CDrawings by RGA

PreparedbyDavidJohncox,withsectionsfromRichardGriffithsArchitectsbyJohnWoodcock,andfromKCMSbyColinHayward.ReviewedbyMichaelCoombsIssuedFebruary2010

T:\1568\1568-001\DTPData\IndesignDocs\1568-01-GrimsbyIceFactoryAppraisalofExistingStructure.indd

ThisreportisthecopyrightofAlanBaxter&AssociatesLLPandisforthesoleuseoftheperson/organisationtowhomitisaddressed.ItmaynotbeusedorreferredtoinwholeorinpartbyanyoneelsewithouttheexpressagreementofAlanBaxter&AssociatesLLP.AlanBaxter&AssociatesLLPdonotacceptliabilityforanylossordamagearisingfromanyunauthoriseduseofthisreport.

AlanBaxter&AssociatesLLPisaLimitedLiabilityPartnershipregisteredinEngland,numberOC328839.Registeredoffice75CowcrossStreet,London,EC1M6EL.©AlanBaxter&AssociatesLLP2009

Alan Baxter

75 Cowcross Street London EC1M 6ELtel 020 7250 1555fax 020 7250 3022email aba@alanbaxter.co.uk

Recommended