High-Speed Transportation Opportunities · 2019-09-13 · Hyperloop Regional Rail Guaranteed...

Preview:

Citation preview

1

High-SpeedTransportation Opportunities

Greater Dallas Planning Council

September 12, 2019

Kevin Feldt

North Central Texas Council of Governments

2

High Speed RailHigh-Speed Rail Recommendations

3

High Speed RailDFW High-Speed Rail Projects

Fort Worth to Laredo High-Speed Transportation Study

NCTCOG

Dallas to HoustonHigh-Speed Rail ProjectTexas Central Railway (TCR)

DFW High-SpeedTransportation Connection Study

NCTCOG

4 February 11, 2018

We Are Here

5

Dallas to Houston

Dallas

Houston

Bryan/College Station/Huntsville

FRA Preferred Alignment

Potential Stations

6

Current TCR Activity Highlights

•Building the Project Every Day

•Working with Design/Build Partner

• Preparing for Construction Activity

• Petition for Rulemaking Granted by FRA• Rule of Particular Applicability

• Final Rule Expected in 2020

• Environmental Impact Statement• Record of Decision Expected 1Q 2020

Source: Texas Central Railway

7

Other Activities

•Perkins + Will Study for Dallas

• Lot E Feasibility

• No Fatal Flaw

Source: Lockwood, Andrews and Newnam

8

Dallas Station

Source: Texas Central Railway

Lot E

9

Fort Worth to Laredo

10

Fort Worth to Laredo

• Generally Parallels IH 35• Fort Worth

• Waco

• Temple

• Killeen

• Austin

• San Antonio

• Laredo*

• Investigate High-Speed Transportation (HST) Options• Corridors• Technology• Modes of Travel

*In Laredo, the end point/station location will be studied as to not

preclude extending an alignment to Monterrey, Mexico

11

Project Background

2017

Previous StudyTOPRS ROD and FEIS

Tier 1 NEPA Study

Future

Future StudyFurther Corridor

EvaluationTier 2 NEPA Study

2019 2020

Current StudyBridge – Previous to Future

12

Project Purpose

Fort Worth

Waco

Austin

San Antonio

Laredo

Killeen-Temple

• “Bridge” to Tier 2 Environmental Study

• Investigate High-Speed Transportation (HST) Options• Corridors

• Technology

• Modes of Travel

13

TOPRS Tier 1 Corridor Analysis

14

Technologies/Modes Analyzed

MaglevHigh-Speed &Higher-Speed Trains

Hyperloop

Guaranteed TransitRegional Rail

15

City Pairs Analyzed

Fort Worth Laredo

Study Corridor

Fort Worth – Laredo: All Stops

Fort Worth – Austin – San Antonio – Laredo

Fort Worth – Austin – Laredo

Fort Worth – Laredo

Fort Worth Waco Killeen-Temple Austin San Antonio

Laredo

Fort Worth Waco Killeen-Temple Austin San Antonio

Laredo

Fort Worth Austin San Antonio

Laredo

Fort Worth Austin Laredo

16

Project Schedule

March April May June July August

September October November December JanuaryAugust

Review Technology & Design Criteria

Review Previous StudiesCorridor Development

Corridor Development Final Report

Stakeholder Coordination

17

Fort Worth to Dallas

18

Fort Worth to Dallas High-SpeedTransportation Study• Previous Efforts

• TxDOT• DFW Core Express Service

• NCTCOG• Station Area Studies• Corridor Analysis

• New Project Next Steps• Complete Agreements with FRA and FTA• Complete Scope of Work• Publish RFP – October?• Hire Consultant• Notice to Proceed – February?

Source: Hua Yang

19

DFW Core Express Service Alternatives Analysis

Downtown Dallas

Downtown Fort Worth

Arlington

Grand Prairie

Irving

19

20

Potential Arlington Station and Alignment Options

21

Potential Fort Worth Station and Alignment Options

22

Alignment Corridors Analyzed by NCTCOG

22

Proposed Texas Central HSRAlignment Corridors Analyzed

23

New Project Scope of Work

• Public & Agency Involvement

• Alternative Development

• Alternative Screening

• Conceptual Engineering

Phase 1 – Alternative Development

• NEPA Documentation & Record of Decision

• Preliminary Engineering

• Financial & Project Management Plans

Phase 2 – Engineering & Environmental

Includes a technology forum

Includes alignments & technology

Pre

-NEP

AN

EPA

24

Technology

Source: AECOM

Source: AECOM

25

Two Primary Technologies

Characteristic High-Speed Rail Hyperloop

Top Speed ~220 mph ~700 mph

Headway 30 minutes 2 minutes

Station Spacing 250 miles 250 miles

Person Capacity 2,400/hour/direction1 16,000/hour/direction2

Operation Scheduled Service On Demand

Access Multiple Stops Point to Point

Cost ~$60m/mile ???

Freight No Yes

Notes: 1 Estimate based on NCTCOG calculations combining stated headway and train set capacity from TCR2 Estimate from Virgin Hyperloop One

26

What is Hyperloop?

•New Mode of Transportation• Moving Passengers and Freight

• Near-Vacuum Tube

• Electric Propulsion

•Autonomous Pod Levitates Above the Track

•Glides Over Long Distances

Passenger pod

Cargo pod

Source: Virgin Hyperloop One

27

Virgin Hyperloop One (VHO)

•VHO One of Several Firms

• Several Meetings With Staff

•Hyperloop On The Hill Event

•Nevada Test Track

•Passenger Pod Tour

•Certification Center• Research and Development

Source: Kevin Feldt

28

Nevada Test Track

Source: Kevin Feldt

29

Passenger Pod Tour

Source: Kevin Feldt

Source: NCTCOG

30

VHO Certification Center Phasing and Timing

Phase Timing Length of Track

A 18 months1.5 km (straight)

(0.9 mi)

B 9 months3 to 5 km

(1.9 to 3.1 mi)

C 9 Months 0

D 9 Months6 to 8 km

(3.7 to 5.0 mi)

31

Hyperloop Design Parameters

✓Need For Service/Access Road Along The Guideway

✓Vacuum Buildings Every 5 Miles

X Design Elements

X Maximum Vertical Grade

X Minimum Horizontal Curve

32

747 In-flight Turn Radius

Calculate the radius of the turn using this formula, slightly

modified from Wikipedia to give nmi instead of feet:

Which gives us:

So the turn itself would be about 15 nautical miles wide(≈ 91,000 feet) not accounting for wind.

Source: Wikipedia

Radius of turn in nautical miles = velocity2

68579 x tan(bank)

7.51 nmi = 4902

68579 x tan(25°)

33

Typical Section DRAFT

* Horizontal and vertical clearances allow for the area needed to construct, operate and maintain the guideway and supporting facilities.** Minimum vertical clearance over roadways is 5 m or 16.5 ft. Vertical clearance of 5.6 m or 18.5 ft would be required over interstate highways and other roadway corridors designated for freight. Vertical clearance over passenger or freight railroads would be 7 m or 23 ft.

5 m16.4 ft

Tube

4 m13.1 ft

4 m13.1 ft

13 m42.7 ft

4 m13.1 ft

Vertical Clearance*

5 m16.4 ft

Tube

10 to 10.6 m32.9 to 34.9 ft

Vertical Clearance

Over Roadway**5 to 5.6 m

16.5 to 18.5 ft

Horizontal Clearance*

Horizontal Clearance*

34

Typical Section DRAFT

* Horizontal and vertical clearances allow for the area needed to construct, operate and maintain the guideway and supporting facilities.** Minimum vertical clearance over roadways is 5 m or 16.5 ft. Vertical clearance of 5.6 m or 18.5 ft would be required over interstate highways and other roadway corridors designated for freight. Vertical clearance over passenger or freight railroads would be 7 m or 23 ft.

5 m16.4 ft

Tube 4 m

13.1 ft4 m

13.1 ft

Horizontal Clearance*

19 m62.3 ft

4 m13.1 ft

Vertical Clearance*

5 m16.4 ft

Tube

9 m29.5 ft

Horizontal Clearance*

5 m16.4 ft

Tube

1 m3.3 ft

Vertical Clearance

Over Roadway**5 to 5.6 m

16.5 to 18.5 ft

35

Typical Section DRAFT* Horizontal and vertical clearances allow for the area needed to construct, operate and maintain the guideway and supporting facilities.** Minimum vertical clearance over roadways is 5 m or 16.5 ft. Vertical clearance of 5.6 m or 18.5 ft would be required over interstate highways and other roadway corridors designated for freight. Vertical clearance over passenger or freight railroads would be 7 m or 23 ft.

5 m16.4 ft

Tube

4 m13.1 ft

4 m13.1 ft

26.5 m = 87 ft

4 m13.1 ft

Vertical Clearance*

5 m16.4 ft

Tube

10 to 10.6 m32.9 to 34.9 ft

Vertical Clearance

Over Roadway**5 to 5.6 m

16.5 to 18.5 ft

Horizontal Clearance*

Horizontal Clearance*

8.5 m28 ft

AV/Roadway

5 m16.4 ft

Tube

36

Potential Certification Track Alignments

37

Certification Center• Working with Dallas Regional Chamber• Anticipate RFP Published in November

• Will be Interactive (No “Cone of Silence”)• Three Focus Areas

• Land • Regulatory• Funding

• Involvement • Universities• Trade Groups• Transportation Industry

• Planners• Engineers• Contractors

• Finance and Funding Key Components

38

Contact

Kevin FeldtProgram Managerkfeldt@nctcog.org

(817) 704-2529

Recommended