H2020-RISE-2016 Coordinators day

Reporting & Payment

Frederico MIRANDA

Project Officer LIFE

frederico.miranda@ec.europa.eu

2 March 2017

Progress report: Deliverable Month 12 & 36*

By deadline set in GA Annex I

Periodic report: Month 24 & End of Project

60 days from end of period

Final report: End of Project

60 days from end of project

Deliverables: Continuous Reporting

By deadline set in GA Annex I

Researcher Declarations: Continuous Reporting

Within 20 days from start of secondment

Reporting Deadlines

Continuous Reporting

7 tabs

Summary for Publications

Deliverables

Milestones

Publications

Dissemination

Patents (IPR)

SME Impact

Gender

Researchers (Declarations)

Continuous Reporting Access

Continuous Reporting

MP

Publishable Summary

Deliverables

Template for Progress Report

Milestones

Publications

All publications must mention the EU funding (sentence in GA Art. 29.4)

OpenAIRE: https://www.openaire.eu/

Dissemination

Communications must mention the EU funding (sentence in GA Art. 38.1.2)

Patents

All patents must mention the EU funding

(sentence in GA Art. 27.3)

SME Impact & Gender

Researcher Declarations

Splits correctly encoded

Library of RDs: shows duplicate entries

Researcher Declarations

Researcher Information

Secondments Information

Periodic Reporting

Same tabs as Continuous Reporting Module +3 extra

Critical Risks

Technical Report Part B

(Word Template)

Financial Statements

Periodic Report Access

Critical Risks

Technical Report Part B

Part B Sections 1. Explanation of the work carried out by the beneficiaries

and Overview of the progress

2. Update of the plan for exploitation and dissemination of results (if applicable)

3. Update of the data management plan (if applicable)

4. Follow-up of recommendations and comments from previous review(s) (if applicable)

5. Deviations from Annex 1 and Annex 2 (if applicable)

Not applicable to you RISE project (do not complete):

1.4. Access provisions to Research Infrastructures (Research Infrastructures programme only)

5.2 Use of resources (not applicable to MSCA projects)

5.2.1 Unforeseen subcontracting (not applicable to MSCA projects)

5.2.2 Unforeseen use of in kind contribution from third party against payment or free of charges (not applicable to MSCA projects)

Tech Report Part B Not Applicable

Financial Statements

Eligible Costs

Minimum 1 Month / secondment

Maximum 12 Months / staff member

1 M = day x of Month Y to day x-1 of Month Y+1

Less than 1 month = pro-rata of 30 days

Examples:

1 January – 31 January = 1 month

12 February – 11 March = 1 month

12 February – 10 March = 27 days (not eligible)

15 June – 17 August = 2 months + 3 days

Calculation of costs

Additional Information Participant Portal

Completion of Technical Report https://webgate.ec.europa.eu/fpfis/wikis/pages/viewpage.action?pageId=107942610

How to complete financial statement for RISE projects https://webgate.ec.europa.eu/fpfis/wikis/display/ECResearchGMS/How+to+complete+your+financial+statement+-+MSCA-RISE

The reporting process in general https://webgate.ec.europa.eu/fpfis/wikis/display/ECResearchGMS/Reporting+process+-+general

Calculation of secondments duration for RDs https://webgate.ec.europa.eu/fpfis/wikis/display/ECResearchGMS/Completing+the+Researcher+Declaration+Tab+for+MSCA-RISE

Final Report

Only in the last Period

In addition of Periodic Report

Final Technical Report

Final Financial Report