Gower Facility PlansDecember 18, 2012

Gower Middle Improvements

• 3 Science Classrooms—Grades 6, 7, & 8

• New Gym, Locker Rooms, Weight/Fitness Room

• Industrial Technology, Family & Consumer Sciences, and Art

• Lighting and Ceiling Tiles Updates

• Cafeteria Remodeled

• Athletic Fields

• Classroom Casework (cabinets and shelving)

• Entrance Vestibules at East and West Doors

• Improved Parking and Traffic Flow

Gower Middle: 2013 - 2014

Gower Middle Athletic Fields

Entrances

Gymnasium

Locker Rooms

Weight/Fitness Room

Science Classrooms

Industrial Technology

Industrial Technology

Family & Consumer Science

Family & Consumer Science

Art Classroom

Art Classroom

Gower West Improvement

• 2 Early Childhood Classrooms

• Removal of Asbestos Tile in East Classrooms

• Replacement of Flooring in East Classrooms

• Pavement Replaced on West Playground

• Fencing Added to West Playground

• Art Room Storage and Shelving

• Lighting and Ceiling Tile as Needed

Gower West 2013- 2014

Early Childhood Classroom

Early Childhood Classroom

Timeline

• January 14 Bid Invitations Published

• February 19 Bid Approval

• March 1 Excavation for GM Gym and Addition Begins

• March 25 Asbestos Abatement at GM

• June 3 Interior Work at GW & GM Begins

• September 1 Substantial Completion at GW & GM