FHWA INVEST And the Harbor Bridge Project
FHWA’s Sustainable Highways Initiative
2
“The Sustainable Highways
Initiative supports programs and
activities conducted across the
Federal Highway Administration
to facilitate balanced
decisionmaking among
environmental, economic, and
social values—the triple bottom
line of sustainability.”
–U.S. DOT FHWA
Source: www.sustainablehighways.org
What is INVEST?
3
Voluntary, web-based tool
designed to help transportation
agencies integrate sustainability
into programs and projects
Three modules designed to
evaluate the full lifecycle of
transportation programming:
– Systems Planning
– Project Development
– Operations and Maintenance Source: www.sustainablehighways.org
Infrastructure Voluntary Evaluation Sustainability Tool (INVEST)
INVEST Modules
4
Three modules for evaluating full lifecycle of transportation services.
Evaluates an agency’s
system-wide transportation
planning and programming
efforts such as:
Statewide Long Range
Transportation Plans
Metropolitan
Transportation Plans
Unified Planning Work
Program
Applicable to all phases of
project development:
Early planning
Alternatives analysis
Environmental
documentation
Preliminary and final
design
Construction
Applicable to an agency’s
internal and system
operations
Criteria related to asset
management and
maintenance activities
Systems Planning Project Development Operations & Maintenance
Nationwide Implementation of INVEST
5
Source: www.sustainablehighways.org
Harbor Bridge Project Location
6
Harbor Bridge Project
7
Existing Harbor Bridge
Rendering of Future Harbor Bridge
INVEST and the Harbor Bridge Project Timeline
8
July 2014 – Harbor Bridge Project
developer teams attend INVEST
Workshop in Corpus Christi, TX
August 2014 – INVEST Project
Development pre-scoring workshop
August - October 2014 –RFP and
Technical Provisions updated for
consistency with INVEST criteria
October 2014 – Final RFP issued
April 2015 - Conditional award of
Harbor Bridge to Flatiron/Dragados JV
INVEST Pre-scoring Workshop
9
Source: www.sustainablehighways.org
10
Harbor Bridge Project Examples from Pre-scoring Workshop
Invest Criteria Points
Available
Scoring Notes Achievable
Score
PD-02 Lifecycle Cost
Analyses
1 to 3 Can get at least 1 point for Life Cycle Cost
Analysis (LCCA) of bridges. An additional
point for LCCA of stormwater is achievable.
2
PD-07 Habitat
Restoration
1 to 3 Can get 1 point for efforts to minimize
wetland impacts (adding cross-culverts as
part of permit). An additional 2 points are
achievable through implementation of a
“restoration plan.”
3
PD-13 Freight
Mobility
1 to 7 Can get 2 points for overpass clearance
improvements for shipping. An additional 4
points are achievable by implementation of a
no-idling policy and signage and provision of
new dedicated truck delivery parking area.
4
PD-23 Reduced
Energy Emissions in
Pavement Materials
3 Can get 3 points. TxDOT uses warm mix
asphalt
3
INVEST and Harbor Bridge Sustainability Plan Requirements for the Proposal
Describe the proposer’s approach and commitment to sustainable design,
construction, operational, and maintenance practices;
Describe how a “Platinum” rating will be achieved for the INVEST Project
Development module;
Describe how a minimum of a “Silver” rating will be achieved for the INVEST
Operations and Maintenance module; and
Describe how the following sustainability categories will be addressed:
Energy and Energy Efficiency; Community and Environmental Justice; Green
Building; Waste Reduction and Recycling; Green Project Administration;
Materials and Resources; Construction Practices; and Education and
Demonstration of Energy Efficiency.
11
Next Steps
12
Commitments incorporated into contract
Monitor commitments included in sustainability plan
during construction
– Flatiron/Dragados JV committed to achieving “Platinum” INVEST
rankings for Project Development and Operations & Maintenance
Post development scoring of Harbor Bridge Project
– Attainment of “Platinum” INVEST ranking for Project Development
– Attain minimum of “Platinum” INVEST ranking for Operations &
Maintenance
Sustainability Plan – Energy Efficiency Demonstration Projects
13
All lighting fixtures LED
Solar powered path lighting with solar brick pavers and solar markers on
shared use path
Energy-generating wind sculpture
ROADWAY LIGHTING SOLAR FEATURES ON SHARED USE PATH
14
COMMUNITY PLAZA WITH ENERGY GENERATING WIND SCULPTURE
Sustainability Plan – Energy Efficiency Demonstration Projects
15
Sustainability Plan – Additional elements
Use of high strength, low permeability concrete mix
Waste reduction and recycling
– Benches at belvedere and landscaped areas made from recycled
materials
– Re-use of sign structures on new alignment
– Re-use of concrete from interchange bridges as crushed stone in
landscape
Train construction personnel about project’s sustainability intiatives
Utilize termporary and permanent best management practices (BMPs)
Minimize and mitigate impacts to minority and low-income communities
Minimize air quality degradation during construction
Use of native plants in landscaping
16
Main span cable-stayed bridge
1,655 feet long
Harbor Bridge Project
Harbor Bridge Project
17
Rendering of Future Harbor Bridge
Harbor Bridge Project
18
Rendering of Future Harbor Bridge
Harbor Bridge Project
19
Rendering of Future Harbor Bridge
“Our Sustainability Plan is focused on
establishing, implementing, and
maintaining sustainability initiatives
that will benefit the immediate and
long-term interests of the
Corpus Christi community.”
-Flatiron/Dragodos JV
20
Questions?