FYs 2015 & 2016 Overall Work Program Page 22
FYs2015-2016_(FINAL).docx – June 20, 2014
Farrington Highway Realignment Feasibility Study
WE Number 202.04-15 Time Period July 1 2014 – June 30, 2016
Agency OahuMPO Phone Number (808) 587-2015
Coordinator Brian Gibson Fax Number (808) 587-2018
Position Executive Director Email Address Brian.gibson@oahumpo.org
Objectives:
To determine the social, environmental, technical, and economic impacts, costs, and benefits of
realigning Farrington Highway mauka of Makaha Beach Park
To make a recommendation as to the feasibility of realigning the roadway based on a technical
evaluation
Project Description:
The Makaha Beach Park Master Plan was completed in 1998 for the City & County of Honolulu Department
of Parks and Recreation. A concept that was illustrated in that plan was a realignment of Farrington
Highway mauka of Makaha Beach Park. The plan noted that a draft detailed project report and
Environmental Impact Statement was prepared for the U.S. Army Corps of Engineers in November 1985;
and the preferred proposal was to realign Farrington Highway on the mauka side of the proposed project
site. The stated benefits of this realignment were: 1) increased recreational use, 2) expansion of the beach,
3) additional parking, 4) elimination of highway repairs due to beach erosion and storm waves, and 5)
insured access in and out of the west end of the island of Oahu. The realignment of Farrington Highway is
included in the current Oahu Regional Transportation Plan as a long-range project. However, the 1998
master plan only presented the idea as a concept; it is unclear if the Hawaii Department of Transportation
was ever involved in the development of the concept; and the 1985 Draft EIS is now almost 30 years old.
This project will re-examine the realignment concept and estimate the potential impacts, costs, benefits,
and feasibility of realigning Farrington Highway.
The consultant will work under the direction of a multi-jurisdictional project working group, which will be
formed and supported by OahuMPO.
Per Federal regulation (23 CFR 450.320), any congestion impacts will be analyzed using OahuMPO’s
congestion management process. Additionally, the study must be consistent with 23 CFR 450.318 –
Transportation planning studies and project development. Regional performance measures, if available,
should also be used in the evaluation of alternatives. Though this study is not intended to be an
environmental document, MAP-21 Section 1310 encourages the integration of planning and environmental
review to the extent possible. (Also see 23 CFR Appendix A to part 450).
Work Products/Outcomes:
An updated estimate of the potential impacts, costs, and benefits of realigning Farrington Highway
mauka of Makaha Beach Park
A recommendation or set of recommendations based on technical analysis and evaluation
regarding next steps.
Project Justification:
The realignment of Farrington Highway is supported by some portion of the public; and it is identified in the
Oahu Regional Transportation Plan 2035 as a long-range project. However, there is no recent analysis or
information as to the impacts, costs, benefits, or feasibility of realigning Farrington Highway.
FYs 2015 & 2016 Overall Work Program Page 23
FYs2015-2016_(FINAL).docx – June 20, 2014
Previous or Ongoing Work Related to Proposed Planning Study or Project:
1998 Makaha Beach Park Master Plan
1985 U.S. Army Corp of Engineers Environmental Impact Statement
Oahu Regional Transportation Plan 2035, which lists the realignment of Farrington Highway as a
long-range project
Staff Labor Commitment to the Work Element
Staff Labor To Be Used as Match Staff Labor to be Reimbursed
Task # Position/Agency
STAFF LABOR FUNDING SOURCES
Total Hrs $/Hr*
Additive Non-
Federal
Federal
0.00% FHWA
1 - 3 Planner/OahuMPO 425 $59.93 N/A $5,094 $20,378 $25,472
STAFF LABOR SUB-TOTAL EXPENDITURES $5,094 $20,378 $25,472
*Dollar figure products may not be precise due to rounding of average hourly rates
Work Element Tasks & Budget
Task # Staff Labor Commitment
Estimated
Completion
Date
FUNDING SOURCES
Total
Non-
Federal
Federal
FHWA
1 Write RFP; select consultant; complete
contracting process 1/2015 $703 $2,810 $3,513
2 Form and support project working group 6/2016 $2,876 $11,505 $14,381
3 Manage consultant 6/2016 $1,515 $6,063 $7,578
STAFF LABOR SUB-TOTAL EXPENDITURES $5,094 $20,378 $25,472
Task # Consultant Services
5 Plan and execute public input plan 6/2016 $10,000 $40,000 $50,000
6 Gather existing conditions information
(including review of existing pertinent studies) 6/2015 $8,000 $32,000 $40,000
7 Develop and analyze alternatives 8/2015 $10,000 $40,000 $50,000
8 Develop evaluation criteria 8/2015 $8,000 $32,000 $40,000
9 Evaluate alternatives 1/2016 $24,000 $96,000 $120,000
10 Develop recommendations 4/2016 $6,000 $24,000 $30,000
11 Write draft and final reports 6/2016 $10,000 $40,000 $50,000
CONTRACT SERVICE SUB-TOTAL EXPENDITURES $76,000 $304,000 $380,000
Other Costs (e.g., software, travel, equipment, etc.)
25 copies of draft report $500 $2,000 $2,500
25 copies of final report $500 $2,000 $2,500
OTHER COSTS SUB-TOTAL EXPENDITURES $1,000 $4,000 $5,000
TOTAL WORK ELEMENT COST $82,094 $328,378 $410,472
Prepared by: Brian Gibson Date: February 20, 2014
Approved by: Brian Gibson Date: February 20, 2014
Recommended