FREMONT UNIFIED S C H O O L D I S T R I C T

Lila Bringhurst Elementary School

Construction Update

as prepared by fB2 Solutions

Board of Education Meeting

October 24, 2018

2

Home of the Blazers

3

Project Statistics

• Number of Buildings - 4

• Total Square Footage – 99,000 sq ft

• Number of Classrooms - 45

• Enrollment Capacity – 1100

• Project Budget - $54,525,492

• Projected Completion

Date – March 7, 2019

• Status of Park –Construction underway

as of October 8, 2018.

Park expected to be

completed in April 2019

4

Project Information

• First new school for the FUSD in 25 years

• Innovative architectural design that compliments surrounding subdivision activity

• Joint Use Park serves students each weekday, community nights, weekends and holidays

• Construction started 9/11/17

• 18 rain days allowed to date

• All building skeletons erected and finishes underway

• Project well under budget – Less than .05% in change orders to date

• Hybrid project under the State Facilities Program – App filed with the State Allocation

Board; Project waiting for funding allocation, anticipated no sooner than 2022

5

Site Layout

6

Elevation View – Buildings B &C