Domino.Doc Project Overview Project Rollout/Schedule Preview Eastman Kodak Health Imaging Doug Smith

Preview:

Citation preview

Domino.Doc Project Overview

Project Rollout/Schedule Preview

Eastman Kodak Health Imaging

Doug Smith

Project Goals

Corporate Deployment of Lotus Domino for DHF/21CFR11 Submissions

Phase One - Migration of Design History Files to Louts Notes

Phase Two – define next component to be rolled out, electronic signature

General Description

Identify the desired forms and workflow for sites.

Create migration path for existing DHF database.

Training and User Documentation

FOR MORE INFO...

Contact: Jeff B.

Core Technology Used

Identify new technology being used– Why existing system needs upgrade

Quality Standards supported– Connect to Quality Section Number

Other technology options evaluated– Microsoft Content Server

Team/Resources

Assumptions about resources allocated to this project:– 4 Allendale R&D resources – 1 Dallas R&D resources– 4 Regional site liaisons– Technical support & outside services

FOR MORE INFO...

Contact: Doug S.

Procedures

Highlight any procedural differences from regular projects of this type

Discuss how user training and documentation is provided

First and Second level technical support tiers

FOR MORE INFO...

Contact: Rolando S.

High Level Milestones

Review high-level milestones:

FOR MORE INFO...

Visit the Project Database on Notes

Current Status

Gate zero scheduled 3/18/03 ( firm )– Platform development proceeding– Site requirements not defined– CRD not yet started

Projecting about 1w late at Gate 0/LCA due to CRD.

FOR MORE INFO...

Contact: Doug S.

Project Metrics Collection Plan

There are standard project metrics for all EK projects as described in the SOP 1F2236 that will be collected: Software Development Cost and Effort Software Project Schedule Progress Software Product Quality Software Product Functionality Software Product Performance goals

FOR MORE INFO...

Contact: Jeff B.

Related Documents

Marketing plan waived in PDPBudget - small budget model appliesStaffing plan contained in PDPWAIS Development Process with

RUP phased rollout

FOR MORE INFO...

Contact: Tim L.

Cost and Time Summary

Direct Labor costs: $142,140.62Capital costs not in this scheduleProject Duration: 126 daysFinal delivery date: 5/22/03Feature count: TBD

Contact: Doug S.

FOR MORE INFO...

Rollout Schedule-Overview

• All development/testing is for Gate 1/LCA

• Gate 2/3 is documentation/PR.

Gate 0 - Planning Phase

Team is formed, gate 0 work 63% complete and on schedule for 3/11/03 gate zero.

Collection of site requirements is on schedule.

Gate Zero – Platform Definition

Platform definition due 3/5/03 Running in parallel with site requirements.

Gate Zero – Process Documents

Back loaded from 3/18/03 G0 date Runs in parallel with site requirements.

Gate One – Rapid Prototyping

Engineering prototype due by 3/25 Gate two documents planned back from 5/30. Developers allocated at only 60%

Gate One – Documents

Documents due 5/9 for 5/13 G1 Substantially all development/test complete

Gate Two – Documents

Documents only, combine G2 and G3 ? No development planned/test complete

Rollout Schedule-Gate Three

No development, just documentation Duration fixed primarily by resource constraints Schedule can be improved with TKM support

Rollout Schedule-Phases

Gate targets at the top for visibility Major start dates shown below

ID Task Name Duration Start Finish

0 HI DHF System Project Schedule 148 days? 12/11/02 7/4/031 Gate Dates 86 days 3/6/03 7/4/03

2 Gate 0 Target 0 days 3/6/03 3/6/03

3 Gate 1 Target 0 days 4/7/03 4/7/03

4 Gate 2 Target 0 days 5/12/03 5/12/03

5 Gate 3 Target 0 days 7/4/03 7/4/03

6 Quality Planning Phase 62 days? 12/11/02 3/6/03

40 Requirements/Design Phase 22 days? 3/7/03 4/7/03

64 Construct/Test Phase 26 days 4/7/03 5/12/03

86 Use Phase 39 days 5/13/03 7/4/03

Project Reporting Structure

Weekly schedule update on Fridays Weekly in-process task list to Jeff Schedule distributed within R&D team. Post schedule changes as responses to

the schedule itself in the Project Database.

Conclusions

Assumes all non-project activity does not exceed 40% - OK

Detail on the site rollout in Program Plan but not schedule

Assumes no scope creep G2+ since no development is scheduled

Closing