College of Lake County Sustainable Master Plan...

Preview:

Citation preview

College of Lake CountySustainable Master Plan Update

January 27, 2015

Classroom Mock Ups

Completed Fall, 2014

Old Roadway

New Roadway

Atrium RenovationBefore

Atrium RenovationAfter

Atrium

Autobody

Before

Autobody Completed

Paintbooths

Classrooms

Mezzanine

Open House

Café

CORE AND CAFÉ CONSTRUCTION AREA

NEW BOOKSTORE

STUDENT ACTIVITIES

A162 LECTURE HALL TO REMAIN

NEW CAFÉ AND 

KITCHEN

Revised Layout

Revised Layout

A162 LECTURE HALL TO REMAIN

MULTI‐PURPOSE SPACE

STUDENT ACTIVITIES

NEW CORE AREA

Café and Student Activities

Front Door

Café and Student Activities

Café and Student Activities

Café and Student Activities First FloorLooking toward Sun Pivot Circle Entrance

Student Development

Phase ThreeJun 2016 – Dec 2016

Phase FourDec 2016 – Aug 2017

Phase TwoDec 2015 – Jun 2016

Phase OneJun 2015 – Jul 2016

June 15 Dec 15 June 16 Dec 16 June 17 Dec 17

A & B Remodeling Migration Plan

Geothermal Field

Future ExpansionFuture 

Expansion

Distribution PipingJune‐August 2015

Bore FieldMarch‐ August 2015

Phase IGeothermal Pumps in 

basement of new cafeteriaDecember 2015

Southlake Chemistry Lab Addition

Construction March-December, 2015

Science Building

TempTraffic 

Disruption

LakeshoreSchematic Design February 2015Construction Start November 2016

Recommended