April 19, 2017

Major Mobility Investment Program & P3 UpdateState Transportation Board – Committee of the Whole

Joe Carpenter, P.E., Division Director of P3

Division of P3 Overview

• Aligning resources for P3 and Design-Build delivery

• Focusing on major mobility projects

• Working to deliver major projects quickly

Design-Build Program

Benefits:

• Accelerated construction

• Earlier open to traffic

• Construction and design innovation

• More price certainty

I-75 South Metro Express Lanes

Public-Private Partnerships

All benefits of Design-Build plus:

• Brings financial partnerships

• Maximizes use of available funding

• Provides ability to provide more mobility solutions earlier

The I-75 Northwest Corridor Express Lanes project is an example of a

Public-Private Partnership

Statewide Projects

Current P3 projects:• Northwest Corridor

• 285/400 Interchange

Existing DB projects:• I-85 Express Lanes

extension

11 new MMIP projects

53 statewide bridge replacement projects

Innovative Delivery Successes

I-285/SR 400 Interchange

Freight Weigh in Motion ProjectsI-75 South Metro Express LanesSR 47 at Little River

Bridge ReplacementI-75 – Northwest Corridor Express Lanes

I-85 Express Lanes Extension

Major Mobility Investment Program Update11 Major Projects Now Underway

Delivering the Promise of the TFAAddressing Congestion Through Innovative Major Mobility Investments

Source: http://www.GAroads.org

11 Major Mobility Improvement Projects

3 Major

Interchange

Projects

4 Major Express

Lanes Projects

3 Major Highway

Widening

Projects

1 Commercial

Vehicle Lanes

Project

MMIP Program

11 major mobility projects in construction in 10 years

• $11 billion program

• Improve passenger and freight movement

• Use Innovative Delivery to accelerate solutions

MMIP Project TimelinePre-let activities:

• Preliminary engineering

• Environmental

• Design

• Right-of-way

• Procurement

Post-let activities:

• Final design

• Right-of-way

• Construction

MMIP Tier 1: I-85 Widening

• SRTA partnership for multi-year contracting

• New general purpose lanes

• Expand from 2-3 lanes

• Construction letting fall 2017

• Completion 2021

I-85 Widening Project Location

Tier 1: I-16/I-95 Interchange & WideningSavannah Area

• SRTA partnership for multi-year contracting

• Widen I-16 from 4-6 lanes from I-95 to I-516

• Improve interchange

• Construction letting summer 2018

• Completion 2022

Progress in DeliveryExpanding Resources and Partnerships for Successful Delivery

MMIP Program Delivery Model

Consultant Opportunities

Growing the Industry

Small business and DBE engagement

Program Management Consultant Team• 29 subconsultants and vendors

• 17 Disadvantaged Business Enterprise firms

• 4 firms under new contract since March:• Gude Management – Project Controls

• BTG Consulting – DBE Development/Outreach

• INTUEOR – Program Management

• Long Engineering – Subsurface Utility Engineering

• On track toward 20% goal

Mentorship programs

Program Contacts and Information

Joe Carpenter, P.E.

Division Director of P3

Darryl VanMeter, P.E.

Assistant P3 Division Director/State Innovative Delivery Administrator

Program Information and Contract Opportunities

www.dot.ga.gov/PS/Innovative

Recommended