J u n e 19 , 2 01 3

Albany Medical Center Cogeneration Plant

• • •Massachusetts Energy Efficiency Partnership

130531

Let Cogen Power Your Future!

We specialize in:• Providing Comprehensive

Cogeneration Services

• Cogeneration Feasibility Studies

• Development of CHP Project Budgets

• Design-Build/EPC Turnkey Power Solutions

• Engaging Third-Party Financing

• Offering Plant Operations Services to Customers

Projects include:• BurrstoneenergyCenterMiCrogrid,utiCa,ny

• gusCenergyBioMassPlant,roMe,ny

• st.JosePh’shosPitalCogenPlant,syraCuse,ny

• avilaretireMentCenter,alBany,ny

• alBanyMediCalCenterCogenerationPlant,alBany,ny

About Cogen Power Technologies

130531

About Albany Medical Center

• Albany Medical Center Hospital

- 651-bed

- level-itraumaCenter• Albany Medical College

- MdProgram-567students

- graduatestudies-227students• Capital District Psychiatric Center

Northeastern NY’s only academic health sciences center

130531

Expansion

Phase I • New $360 Million,

350,000 SF Patient Pavilion expansion

- 20operatingroomsuites

- 60Med/surgicalBeds

- 56neonataliCuBeds

- 30adultiCuBeds

Phase II• Future 150,000 SF

expansion plannedEstimatEd

annual stEam usagE

(mlbs)

EstimatEd annual stEam

Cost ($)

Est. annual ElECtriCal

Consumption (kWh)

Est. annual ElECtriCal

Cost pEr kWh ($)

annual pEak ElECtriC

dEmand (kW)

total Est. ElECtriCal

dEmand Cost ($)

Existing Campus 185,403 $2,781,039 52,103,740 $5,731,411 9,257 $805,504phasE i addition 22,618 $339,268 8,838,713 $972,258 1,103 $113,506phasE ii addition 9,694 $145,416 3,788,019 $416,682 473 $48,217

total 217,715 $3,265,723 64,730,472 $7,120,351 10,833 $966,277

EstimatEd annual stEam Cost

$3.3 M

EstimatEd annual ElECtriC Cost

$8.1 M

EstimatEd total Costs for nEW Campus

$11.4M

130531

Feasibility Study

Identified objectives• Flexibility in how energy needs – electric and steam - are met

• Firmer control over costs and budgets

• Reduced carbon footprint

• Opportunities for further expansion in the long term

Total Estimated Plant Cost $24,000,000M

Estimated Annual Savings $2,790,044

Simple Payback 9years

Internal Rate of return 10%

NYSERDA GRANT (CHP Incentive) $2,000,000

RecommendationPrime Mover

• Mercury 50 Gas Turbine Generator

130531

Project Site

• Dense urban location

• Hilly site

• Surrounded by delivery truck driveway

• No laydown area

• Existing daycare center

• Steam pipes, running from the boiler plant to the hospital, crossing overhead on concrete piers

• Must phase work around active uses

130531

Construction

• Construction began while daycare was still in use

• Built into the side of the hill, the plant was constructed one half at a time

• First, a tunnel for new steam lines was dug into the hill

130531

• Once the lines were connected, the old lines were dismantled, and the foundation and the new building were constructed in phases over the tunnel

• New two-story 23,000 SF facility

• Structural steel frame

• Brick-colored precast insulated panels (sound deadening, R-value, and ease of assembly)

• Building was completed under schedule and under budget

Construction

130531

Project Overview• New 25,000 SF Building

• $23 Million Contract Value

• $500,000 in Value Engineering Reductions

• 8 year Simple Payback

• Generating Electrical Power & Steam

• Natural Gas Fired

• Operations in Unison with Utility

• Automated Load Shed System

• Broke Ground - March 2011

• Operational - March 2013

Albany Medical Center Cogeneration PlantAlbAny, ny

130531

First Floor Plan

130531

Technology

• 4.6MW Solar Mercury 50 Gas Turbine (Expandable to 9.2 MW)

• Rentech HRSG - 60,000 lbs/hr of Steam (Expandable to 75,000 lbs/hr) Diverter Damper

• 2 - 530 ton York Absorption Chillers (Expandable to 2,500 tons)

• Industrial Steam Condensate Tank & D/A (De-aerator) Tank

• Rockwell Load Management System

• JJ Crewe Gas Compressor

• 750 kw Caterpillar Black Start Generator

• Designed for Expansion for: - 2nd Mercury 50 Turbine - 2nd HRSG - 13,000 lbs/hr - Steam Absorption Chillers - 1500 tons

130531

Turbine

Solar Mercury 50 - 4.6 MW• 10 Stage Axial Compressor

• 2 Stage Recuperated Turbine

• Recuperation - Low NOx (Nitrogen Oxide)

130531

HRSG (Heat Recovery Steam Generator)

Rentech Boiler Systems • 13,000 lbs/hr of Steam - Unfired

• 60,000 lbs/hr of Steam - Fired

• Diverter Damper

• Peabody - Coen Burner

• Steam produced in HRSG delivered to hospital steam header

130531

Gas Compressor

JJ Crewe• 1000 scfm at 225 psi

• 60,000 lbs/hr of Steam - Fired

• Aerzen screw compressor

• Slide valve/recycle valve capacity control

130531

Chillers

York YK• (2) 530 Tons

• R134-A Refrigerant

• Full Load .587 kw/ton NPLV = .362 kw/ton

• VFD

130531

Controls

Rovisis SCADA System• Distributed PLC Control

- Allen Bradley - Monitor Only

• BOP Controls & Chiller Plant - Johnson Metasys

130531

Black Start Generator

Caterpillar• 750 kw

• Diesel

• Synch to 480v Bus and Turbine

130531

Load Management System

Rockwell• Control the import of real and reactive

power from the utility by controlling the turbine output

• Automatically calculates the number of breakers (12 controlled) that need to be shed to maintain the turbine (with a response time of 78 msec or less) upon loss of the utility.

• Provide manually initiated, automatic synchronization across both utility breakers and/or tie breaker

• Allow operators to remotely trip both utility breakers, tie breaker, or 12 feeder breakers

130531

Electrical Interconnection

• Identified milestone schedule early in project

• Worked with National Grid to finalize schedule

• Held coordination meetings every 2 to 4 weeks

• Existing services (2) were @ 34.5 kV

• Uncovered coordination issue with hospital breakers

• Completed all necessary design and obtained National Grid authorization to synchronize 14 months after first coordination meeting

130531

Environmental Benefits

Gas Hog!

3,478 Cars

REDUCES EMISSIONS OF CARBON DIOxIDE (CO2) BY 20,000 TONS PER YEAR

Taking 3,478 Cars off the RoadEqUAL TO:

130531

Challenges

1. Construction site

- a.Borderednumerousresidentialhomes

- b.Borderedtheonlydeliverytruckentrance

- c.existingsteamlines

- d.daycarelocatedonconstructionsite

- e.Coordinationwiththe$360Mexpansionprojectongoingatsametime

2. Electrical Infrastructure

- a.as-Builddwgsnot100%accurate

- b.existinghospitalbreakerswerenotcoordinatedwithutilitybreakersettings

- c.oneoftwo15MWmain34.5kvto13.2kvtransformershadfailed“C”phasewinding

solution=ChP/Cogeneration- d.temporaryreplacementwasonly5MWanddelayed“synchronization”by6months

- e.the15MWreplacementhadasixmonthleadtime3. Hospital Steam Load

- a.turbine/hrsgsteamproduction&existingboilerhouse

- b.excessivecyclingofhrsgductburner4. Hospital Staff Training

- a.trainingprovidedduringprojectconstructionandprojectcommissioning

- b.KeyhospitalFacilitydirectorleftonemonthprior toPlantturnover

- c.hospitalstaffstillacclimatingtohavingPrimePoweronsite

- d.Followuptrainingtobeprovidedat6monthmark

130531