Aconex Reference Guide Australia & New Zealand
Citation preview
PROJECT : ROYAL NORTH SHORE HOSPITAL –CSB
Reference Guide
Royal North Shore - CSB – PW-AD-0001 – Rev 01 2
REVISION STATUS
Document Title: Aconex Reference Guide
Prepared By: Brookfield Multiplex Constructions
Reviewed By: Aconex
Approved By: Brookfield Multiplex Constructions
Revision: 01
Document Status: For Information
Date of Issue: 19/02/2013
Document No: PW-AD-0001
Document Custodian: Tasso Condous
NOTE
This is a live document.
It will require periodic updates to reflect the progress of the project, new participants and newly agreed procedures.
Initial authorship by Brookfield Multiplex Constructions& Aconex
Royal North Shore - CSB – PW-AD-0001 – Rev 01 3
TABLE OF CONTENTS 1.0 INTRODUCTION 4
1.1 Aconex 4 1.2 Getting Started with Aconex 4
2.0 ABOUT THIS DOCUMENT 6 2.1 Purpose 6 2.2 How to Use 6 2.3 Custodianship 6
3.0 PROJECT INFORMATION 7 3.1 Project Details 7 3.2 The Project Team 8
4.0 CONTROLLED DOCUMENTS 10 4.1 Core Document Fields 11 4.2 Document Numbering Convention 12 4.3 Revision Convention 13 4.4 Title Convention 13 4.5 Document Types & File Formats 14 4.6 Disciplines 15 4.7 Status 16 4.8 Other Document Field Values 16 4.9 Document Distribution 18
5.0 PROJECT MAIL 19 5.1 Project Mail Protocols 19 5.2 Project Mail Numbering Convention 19 5.3 Project Mail Type 20 5.4 Project Mail Attributes 21 5.5 Time Constrained Project Mail 21 5.6 Subject Line Conventions 21 5.7 Project Mail Approval 21
6.0 APPENDIX A - PROJECT PROCEDURES 22 6.1 Design Document Review 22 6.2 Shop Drawing Issue and Review 23 6.3 Sample / Technical Data Issue and Review 24 6.4 Sample Approval Stamp 25 6.5 Disruption/ Shutdown Application 29
7.0 APPENDIX B – DOCUMENT NUMBERING CONVENTION 30 7.1 Consultant Specification & Schedule Numbering Convention 30 7.2 Shop Drawing Numbering Convention 31 7.3 Document Review Stamp 32
CONFIDENTIALITY AND INTELLECTUAL PROPERTY STATEMENT
This document contains confidential information and uses an Aconex proprietary template. This document must not be used or disclosed for any purpose other than in connection with the implementation or use of the Aconex system (“the Purpose”). .
The intellectual property in this template (and any modification, enhancement, derivation or reproduction of it) is owned by Aconex and licensed solely for the Purpose and the license of the original or modified document can be terminated by Aconex at any time at
its absolute discretion. The Aconex name, logos and URLs are the property and/or marks of Aconex.
Any modification, enhancement, derivation or reproduction of this document must contain this “Confidentiality and Intellectual Property Statement” and any other confidentiality and any other similar markings or legends contained herein.
Any questions based on the confidentiality or ownership of this document should be directed to legal@aconex.com
Royal North Shore - CSB – PW-AD-0001 – Rev 01 4
1.0 INTRODUCTION
1.1 Aconex Aconex have been engaged on the Royal North Shore Hospital – Clinical Services Building by Brookfield Multiplex Constructions as the online collaboration system for this project.
1.1.1 Aconex Overview Aconex provides a fully integrated project information management tool including:
An automated document register Fully tracked correspondence management Detailed reporting facilities Process and document approval workflows Approvals, preferences and other company administrative tools
Note: Each organization owns their data and can only see what has been created by them or sent to them. The data is stored on redundant servers hosted in secure world-class centres. Project archives are available at any time to any company using Aconex on a project. Project Archives must be requested from Aconex and charges apply.
1.2 Getting Started with Aconex To access Aconex, you require an internet connection, the latest internet browser installed on your computer and to enroll in the Aconex training offered to all project participants. Aconex does not require you to install any licensed software to access the system. The Aconex Client Operations team will be available to guide the entire project team through Aconex implementation and support all project members throughout the project life.
1.2.1 Internet Access Aconex recommends the use of broadband internet to optimize the Aconex experience, in particular where downloading and uploading of large files is required. Broadband varies in download and upload speeds or bandwidth capacity. The optimal broadband bandwidth capacity for your organization will depend on the number of users and network configurations of your IT systems. Please check with your local IT Manager or Internet Service Provider (ISP) to confirm the details of your Organizations broadband capacity.
1.2.2 Internet Browser Aconex recommends using the latest version of Internet Explorer or Mozilla Firefox as your internet browser. The latest internet browsers are available free to download from www.microsoft.com/ie or www.mozilla.com . Please check with your local IT Manager to confirm the version of your internet browser.
1.2.3 Implementation Process The implementation process will be facilitated by Aconex. The process will require participation and input from key project stakeholders to assist in defining the appropriate system configuration for the project.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 5
1.2.4 Organization Registration New organizations to the Aconex system need to register:
1. Go to the Aconex website, Contact tab, Register your organization (http://www.aconex.com) 2. Choose the region where the project is based – Australia/NZ 3. Complete the Organization Registration form, ensuring all mandatory fields are completed (*) 4. Click the Submit button
Aconex will advise the organization administration (nominated at the time of registering) when the organization is registered.
1.2.5 New User Accounts It is the responsibility of the Organization Administrator to set up user accounts for those employees who require access to the Aconex system. Once registered, a new user can be invited to the project by another project member issuing correspondence through the mail module.
1.2.6 Training and Ongoing Support Training and Ongoing Support is available to all project participants throughout the project life. To arrange training sessions please email training-anz@aconex.com or contact Aconex on 1300 ACONEX (226 639) 24/7 helpdesk support is available for all members globally. A list of Global Helpdesk numbers and office locations can be found on www.aconex.com
Royal North Shore - CSB – PW-AD-0001 – Rev 01 6
2.0 ABOUT THIS DOCUMENT
2.1 Purpose The purpose of this document is to assist with the implementation process and record the agreed system configurations, protocols and procedures associated with the use of Aconex on the project.
2.2 How to Use This document is specific to the Aconex collaboration system and shall be read in conjunction with but not limited to all other project specific manuals, plans or procedures applicable to the project. In general this document is to be used in the following but not limited to the following scenarios:
Existing and new project participants that wish to familiarize themselves with what system configurations have been defined for their organization.
Existing and new project participants that wish to refer to project procedures that have been mapped to Aconex.
Org Admins and Project Admins that are required to perform the initial configuration or make amendments to the project setup.
Aconex will also use this document in training situations and when performing periodic health checks.
2.3 Custodianship This document is a live document. It is expected that project information requirements will change over the course of the project lifecycle as the project and participants change. This document will be required to be updated to reflect changes to system settings, processes, project participants and procedures. The ongoing management of this document will reside with the nominated custodian who is Tino Ucchino from Brookfield Multiplex Constructions and will be supported by the local Aconex Client Operations team. All proposed changes/amendments to details or procedures detailed in this document must be submitted to the nominated custodian for approval prior to implementation.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 7
3.0 PROJECT INFORMATION
3.1 Project Details The following table details the information as it appears within the Aconex system. TABLE 1 – PROJECT DETAILS
Project Details
Project Name* Royal North Shore Hospital – Clinical Services Building
Project Short Name* RNSH - CSB
Phone Number 02 93222400
Fax Number 02 80786014
Project Start Date* April 2013
Estimated Completion Date* August 2014
Project Value
Project Type
Project Address
Project Address 1* Westbourne Street
City/Suburb* St Leonards
Postcode* 2065
County/State New South Wales
Country* Australia
Project Description
(*) Mandatory field required for project setup.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 8
3.2 The Project Team 3.2.1 Project Key Contacts The following table lists the contact details of the key contacts for each organization and the relevant Aconex project information. Project participants are to contact their respective key contact for all matters relating to the use of Aconex. TABLE 2 – PROJECT KEY CONTACTS
Key Contact Information Aconex Project Information
Organization Name Role Title Contact Details
Org
Prefix
Project
Role
AC KC PA
Health Infrastructure
Client
HI CL
APP Corporation Mark Dawbney Project Manager APP PM Brookfield Multiplex Constructions
Brendan Sweeny
Project Manager BMPX HC
Brookfield Multiplex Constructions
TBA Project Manager BMPX HC
Brookfield Multiplex Constructions
Tino Ucchino Design Manager BMPX HC
Brookfield Multiplex Constructions
TBC Document Control
BMPX HC
Code Project Role Code Aconex Role
CL Health Infrastructure AC Aconex Client
PM APP KC Key Contact
HC Brookfield Multiplex PA Project Admin
CN Consultant
SC Subcontractor
Royal North Shore - CSB – PW-AD-0001 – Rev 01 9
3.2.2 Communications Flow Diagram The expected flow of communication on the Project is detailed in the figure below.
Client Health Infrastrusture
Major Contractor Brookfield Multiplex
Project Manager APP
Novated Consultants
Subcontractors
Contractual Project Mail
General Project Mail
User Groups
Royal North Shore - CSB – PW-AD-0001 – Rev 01 10
4.0 CONTROLLED DOCUMENTS This section details the fields and values associated with managing project documents using Aconex. All project participants when registering documents must apply the appropriate document tags defined by for the project. The ‘document tags’ are the key information or metadata fields that are used to identify the document such as Number, Title, Date Created. As a minimum Aconex requires all registered documents to be tagged with mandatory fields (denoted by red asterisks).
FIGURE 1 – PROJECT DOCUMENT REGISTRATION FORM
Royal North Shore - CSB – PW-AD-0001 – Rev 01 11
4.1 Core Document Fields The following table details the core Document Fields applicable to the project. When registering a document, the following fields are to be completed if required. TABLE 3 – CORE DOCUMENT FIELDS
Field Label Field Type Description of Use/Application Reference Required Search Field
Document No*#
Document Number
For tagging a document with the unique number required by the applicable document numbering convention.
Section 4.2 Y Y
Revision*# Text For tagging a document with a revision reference (applicable project convention) when it is updated. Table 4 Y Y
Title Text For tagging a document with the applicable title description associated with the document. Y Y
Type*# List (Single Select)
For tagging a document to classify it with an appropriate document type. Table 5 Y Y
Status*# List (Single Select)
For tagging a document with the appropriate status reference that is relevant to the document lifecycle.
Table 7 Y Y
Discipline List (Single Select)
For tagging a document with an appropriate discipline classification. Table 6 Y Y
Attribute List (Multi Select)
For tagging a document with one or more values of information to assist with categorization. Table 8
Y
Confidential# Check Box For defining who can have exclusive access to the registered document.
N
File# File For attaching the electronic file relevant to the registered document.
N
Print Size*# Text For detailing the print size requirements to assist users when printing the document. N N
Date Modified*#+
Date System defined field. The date is the absolute date when the document changes in the register either via uploading or on receipt of a transmittal.
Auto Y
Author Text For tagging a document with details of the author. By default, the organization name is entered.
Y Y
For additional fields to tag your documents please discuss with your Project Administrator or Aconex Client Operations Representative. (*) – System mandatory field and cannot be disabled (i.e. they must be used). (#) – Field label cannot be renamed. (+) – Field with specific function controlled automatically by Aconex system.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 12
4.2 Document Numbering Convention All documents registered in Aconex are required to have a unique number assigned (i.e. no duplicate numbers can be registered). The Aconex document number field is flexible and can support a variety of numbering conventions commonly adopted on projects. The document number field supports text, numbers and other characters permitted by the Microsoft Windows operating system.
4.2.1 Document Numbering All documents produced on this project must be numbered in accordance with the number convention defined below. Please refer to the relevant reference tables for codes applicable to the numbering parts.
Attribute 1 – Project Code
Organisation Code
Discipline Code Unique
Number*
CSB - ARUP - ST 1001
Table 6 – Document Disciplines
Table 6 – Document Disciplines
Appendix for number range
FIGURE 2- DOCUMENT NUMBER STRING *The Number part can either be a simple sequential number or it can match the originator’s own file or document number. The ‘Building’ and ‘Discipline’ prefix the number to ensure uniqueness.
4.2.2 Multiple File formats (e.g. CAD files) Aconex does not support multiple file formats attached to an individual document number when registered on Aconex. Where more than one file extension with the same document number is required, it should be registered as a new document number with a ‘file format’ abbreviation appended to the end of the document number. For example, when there is a requirement to register both the PDF and DWG version of a CAD file. In order to differentiate between the two documents, include a file format or other suffix (e.g. CAD):
Project Code Organisation Code
Discipline Code
Unique
Number*
File Format
CSB - ARUP - ST - 1001 CAD
Table 8- Attribute 1 Organisation Code Table 9
Table 6 – Document Disciplines
Appendix for number
range
FIGURE 3- DOCUMENT NUMBER STRING WITH FILE FORMAT SUFFIX Please note that the suffix is only required where the same file in two formats need to be registered. It can be omitted if only a single format of the file is being registered. Whilst native files are required for coordination at certain stages/phases of the project the agreed project document distribution format is PDF.
4.2.3 File Name Recognition Files named and saved in local/network drives in accordance with the project document numbering convention are able to capitalize on the file name recognition feature in Aconex. The figure below provides examples of appropriate file names and how the elements of the file name will be imported into Aconex as the document number and revision.
File Format Examples of Computer file name Registered Number on Aconex Rev
PDF (Default) CSB-ARUP-ST-1001(B).pdf MF-A-1001 B
AutoCAD DWG
CSB-ARUP-ST-1001-CAD_B.dwg MF-A-1001-DWG B
FIGURE 4 – MULTIPLE FILE FORMAT & FILE NAME RECOGNITION EXAMPLE
Royal North Shore - CSB – PW-AD-0001 – Rev 01 13
4.3 Revision Convention Document revisions should be sequential and should not change unless the project moves to the next phase. Members registering or superseding documents are to update the revision in accordance with the convention described for each status lifecycle. The document revision practices adopted on the project are detailed in the following table. TABLE 4 – REVISION CONVENTION
Revision Convention
Applicable Document Status
Numeric Draft
Numeric For Information
Numeric For Review
Numeric For Tender
Alpha For Construction
Alpha As-Built
4.4 Title Convention The Document Title is important and all team members must use coherent titles when registering documents. This field is an important element in searching for and retrieval of historical information within the database. The following are guidelines on good practice use of the title field:
DO make the title the same as the hardcopy
Titles should typically be very specific, e.g.”Building A – Ground Floor Reflected Ceiling Layout” or “Design Team Meeting Minutes”.
DON’T duplicate document titles
DON’T use vague titles like: Drawing 1, Drawing 2, Drawing 3 etc.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 14
4.5 Document Types & File Formats The following tables detail the Document Types available for use on the project relevant to their organizations role on the project. When registering a document, select most suitable type from the drop down list. If a document type does not exist on Aconex and is required by your organization, submit a request to the Aconex Client. An “X” indicates that the role has the ability to register the specific document type. TABLE 5 – DOCUMENT TYPES
Document
Type
Suggested Documents
PM HC CN
Brief Project briefs
Drawing Drawings including but not limited to floor plans, site plans, roof plans, elevations, sections, details and layouts
Manual Manuals including but not limited to Operating and Maintenance manuals
Report Reports including but not limited to Daily, Weekly, Flash, Monthly, PCG, Cost reports
Sample Samples including brochures and supplier information
Schedule Schedules including Window Schedules, Door Schedules, Finishes Schedules and Hardware schedules
Shop Drawing Shop drawings
Specification Specifications
Technical Data Technical data sheets
Contract For Contracts between any parties relevant to the project
Photograph For all photographic records and images.
Disruption/Shutdown Application
For HC/MGF to issue Disruption/Shutdown Applications. Refer to section 6.4
Royal North Shore - CSB – PW-AD-0001 – Rev 01 15
4.6 Disciplines The disciplines in use for this project are detailed in the following table. When registering a document, select the discipline most suitable from the drop down list. If a discipline does not exist on Aconex and is required by your organization, submit a request to the Aconex Client. TABLE 6 – DOCUMENT DISCIPLINES
Discipline Code* Application/Use
Acoustic AC For all Acoustic design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules and contracts
Administration AD For all documentation associated with Administration including but not limited to reports, plans, forms, procedures, schedules and contracts
Architectural AR For all Architectural design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules and contracts
Civil CV For all Civil design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules and contracts
Electrical EL For all Electrical design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
Environment EN For all Environmental documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules and contracts
Facade FA For all Facade design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
Fire FS For all Fire design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculationsand contracts
Geotechnical GE For all documentation associated with Geotechnical including but not limited to reports, plans, forms, procedures, schedules and contracts
Hydraulic HY For all Hydraulic design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
Interior Design ID For all Interior Clinical Design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules and contracts
Landscape LA For all Landscape design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals and contracts
Lifts/Escalators L For all Lift/Escalator design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
Mechanical ME For all Mechanical design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
Structural ST For all Structural design documentation including but not limited to sketches, reports, drawings, specifications, plans, schedules, manuals, datasheets, calculations and contracts
*Used in document numbering (see section 4.2).
Royal North Shore - CSB – PW-AD-0001 – Rev 01 16
4.7 Status The following table details the document status available for use on the project relevant to their organizations role on the project. When registering a document, select most suitable type from the drop down list. If a document status does not exist on Aconex and is required by your organization, submit a request to the Aconex Client. An “X” indicates that the role has the ability to assign the specific status to a document. TABLE 7 – DOCUMENT STATUS
Document Status Use/Explanation PM HC CN SC
Reviewed For documents which have been reviewed in accordance with project review procedures
Reviewed Subject to Comments
For documents which have been reviewed in accordance with project procedures. These have been reviewed in principle with some comments
As-Built For documents which reflect ‘as-constructed’ or ‘as-built’ information
For Approval For documents to be issued for approval
For Coordination For documents to be issued for coordination
For Construction For documents which are for construction purposes
For Information For documents to be issued for information only
For Tender For documents which are used for tendering or pricing purposes
Rejected For documents which have been reviewed in accordance with project procedures and have been rejected
4.8 Other Document Field Values All documents must be tagged with the appropriate metadata/information. This section details the metadata in use on this project.
4.8.1 Primary Attribute (Building) The primary attributes applicable to this project are detailed in the following table. TABLE 8 – PRIMARY ATTRIBUTE (BUILDING)
Primary Attribute Description Code*
Royal North Shore Hospital - CSB CSB
+*Used in document numbering (see section 4.2).
4.8.2 Organisation Code The organisation code applicable for the project for upload TABLE 9 – ORGANISATION CODE
ORGANISATION Code* DISCIPLINE
Arup Arup Principal Design Consultant, Civil and Structural Engineers, Facade Engineer
Building Studio Architects
BSA Base Building Architect (Shell and Core Package 2)
Woods Bagot WB Clinical Planning Architect (Package 3)
WSP Group WSP Mechanical, Medical Gases, Pneumatic Tubes and Vertical Transportation
Royal North Shore - CSB – PW-AD-0001 – Rev 01 17
ORGANISATION Code* DISCIPLINE
NDY NDY Electrical, Security and ICT
Warren Smith and Partners
WS+P Hydraulic and Fire
Aecom AE Fire and Acoustic Engineer
Davis Langdon DLA BCA Compliance
Morris Goding MGAC Accessibility
*Used in document numbering (see section 4.2).
Royal North Shore - CSB – PW-AD-0001 – Rev 01 18
4.9 Document Distribution This section details information related to the distribution of documents.
4.9.1 Transmittal – Reason for Issue The applicable ‘Reason for Issue’ for transmittals on the project are detailed in the following table. TABLE 9 – REASON FOR ISSUE
Reason for Issue Definition of Use
Issued for Approval Issuing documents which require approval from authorised project participants
Issued for Construction Documents which are to be used for construction purposes
Issued for Coordination Documents which require coordination
Issued for Information Documents which are to be used for information purposes.
Issued for Review Documents which require review by another project participant
Issued for Tender Documents which are to be used for tendering purposes
Royal North Shore - CSB – PW-AD-0001 – Rev 01 19
5.0 PROJECT MAIL The mail module is for communication only. It should not be used for sending drawings, specifications, shop drawings, schedules or other documents that should be distributed within the Documents module in Aconex.
5.1 Project Mail Protocols All project specific communication on this project must be sent via Aconex. Other means of correspondence such as email and fax will not be accepted by Brookfield Multiplex unless approval is given by Brookfield Multiplex, in exceptional circumstances only. Please ensure the following practices are always adhered to when using the project mail module:
1. Avoid correspondence overload by refraining from a scattergun approach. Address “To” and “CC” correspondence to relevant recipients only.
2. Insert a clear and concise subject title with key searchable words (easier to find later)
3. If the correspondence requires a response (and only when a response is essential), you must;
Select the “Response Required” option (assists with exception reporting) Nominate who you anticipate the response from (address “To” and then “CC” others) Insert a reasonable “respond by” date
4. When responding, ensure that you select the “Reply” option so that questions and responses are linked. In
doing so the mail system will acknowledge at both ends that you have responded.
5.2 Project Mail Numbering Convention All Project Mail generated in Aconex is automatically assigned with the next available number associated with the selected project mail type.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 20
5.3 Project Mail Type The authorized Project Mail types which an Organization may initiate are detailed in the following table. For additional Project Mail types please seek approval from the Aconex Client. An “X” indicates that the role has the ability to create and send the specific project mail type. TABLE 10 – PROJECT MAIL TYPES
Project Mail Type Use CL PM HC CN SC
Client Advice For the Client to respond to requests or queries
PM Instruction For the PM to provide instruction in response to requests or queries
Contractors Advice For the HC to issue specific instruction or direction in response to requests or queries raised
Consultant Advice For the Consultants to provide advice in response to requests or queries
Contract Communication
For HC to communication with the PM
Defect For the issuing of defect reports
Design Advice For HC to issue design advice to consultants
Extension of Time For the request of extension of time
Incoming Email For HC to register external mail
Incoming Fax For HC to register incoming faxes
Non Conformance Report
For HC to issue non conformance reports relating to Quality, Environment and OH&S
Notice of Delay For HC to issue a notice of delay
Request For Information
For HC to raise design queries with Consultants and Subcontractor to raise construction queries
Site Instruction For HC to issue instructions to a Subcontractor
Site Inspection Report For the issue of site inspection reports
Subcontractors Advice For Subcontractors to correspond to HC
Internal Memorandum For general communications between project participants from your organization
Meeting Minutes For issuing meeting minutes
Royal North Shore - CSB – PW-AD-0001 – Rev 01 21
5.4 Project Mail Attributes The following tables detail the attributes applicable to the project. All project mail must be tagged with the following attributes, as appropriate to the project mail.
5.4.1 Attribute 1 The attribute 1 values in use on the project are detailed in the following table. TABLE 11 – PROJECT MAIL –ATTRIBUTE 1
Attribute 1 Description
Administration
Design
Environmental
Industrial Relations
Performance
Quality
Safety
5.5 Time Constrained Project Mail Project mail which have time constraints (e.g. RFIs) can be managed by using ‘response required’ and setting a ‘due date’ when creating project mail. It is recommended where time constraints apply the project team should define the applicable types and agree on the timeframe to respond.
5.6 Subject Line Conventions It is vitally important that all team members use coherent titles when preparing Project Mail and Transmittals. The Subject Line field is an important element in Searching for & Retrieval of historical information within the project database. Please avoid the following vague Subject Lines:
"Query"
"Re: Drawings"
"Clash" etc.
Please use meaningful subject lines to facilitate efficient Project Mail retrieval and reporting in Aconex.
5.7 Project Mail Approval Aconex allows organizations to implement mail approval to prevent unauthorized distribution of selected project mail types to other organizations. This feature allows the nominated approvers to view the mail before it is issued externally. Mail approval is configured by each organization on the project. Please contact your Aconex Client Operations Representative to assist with setting up this function.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 22
6.0 APPENDIX A - PROJECT PROCEDURES
6.1 Design Document Review
APP (PM)
Royal North Shore - CSB – PW-AD-0001 – Rev 01 23
6.2 Shop Drawing Issue and Review
Shop Drawing Review – Procedure Workflow
Consultants (CON) Lead Consultant (LC)Brookfield Multiplex (HC)Subcontractor (SC)
Prepare documents, upload and register
Transmit to HC Review shop drawings
Drawings OK?
Initiate shop drawing approval workflow using
relevant workflow template
Download, print, review, mark-up and sign as
required.
Action document approval task in Aconex
Review comments and transmit commented
drawings to SC
Yes
Revise and resubmit No
Upload commented drawings, and replace
within workflow
Action document approval task in Aconex
Upload commented drawings, and replace
within workflow
Download, print, review, mark-up and sign as
required.
Action commented drawings, revise and
supersede documents
Yes
No
Approved?
Royal North Shore - CSB – PW-AD-0001 – Rev 01 24
6.3 Sample / Technical Data Issue and Review
Transmit to CL for approval
Sample / Technical Data Review – Procedure Workflow
Consultants (CON) Client (CL)Brookfield Multiplex (HC)Subcontractor (SC)
Prepare physical samples, upload, register and
transmit
Complete sample approval form, labels and delivers physical sample to HC
Review samples
Samples OK?
Transmit to CON for approval
Review and sign-off samples and attend site office (where required)
to view physical samples.
OK to issue to CL?
Review and sign-off samples and attend site office (where required)
to view physical samples.
HC scans or takes photo of approved sample and supersedes on Aconex
Yes
Yes
Revise and resubmit No
NoReview and advise SC
Sample complete Transmit to SC
APP (PM)
Royal North Shore - CSB – PW-AD-0001 – Rev 01 25
6.4 Sample Approval Stamp
SAMPLE DETAILS APPROVALS
SAMPLE NO CSB-HY-S0001 REV 2 Brookfield Multiplex Constructions
sign
print date
DATE SUBMITTED 3
Fitzpatrick
sign
SUBCONTRACTOR 4 print date
SAMPLE TITLE 5
ECHO
sign
DESCRIPTION 6 print date
MANUFACTURER 7 insert as req’d sign
MODEL NO 8 FINISH 9 print date
LOCATION USED 10 insert as req’d sign
SAMPLE TYPE 11 PHYSICAL PHOTO/CATALOGUE
print date
ASSOCIATED SAMPLES 12 insert as req’d sign
print date
Each Section has been numbered for your information
1. The numbering convention is as follows. CSB is equivalent of Clinical Services Building. HY is equivalent to the discipline, and S0001 stands for Sample 1 of a possible 9999 samples. 2. Revisions are to be changed when superseded for each submission if initial submission was not approved 3. Date sample was issued to Brookfield Multiplex Constructions 4. Company name submitting sample 5. Sample name. eg. D5 Type Light Fitting – When registering in Aconex this is to be the “Title” 6. Brief description of sample – eg. “5W LED Recessed Downlight with Warm White Bulb” 7. Name of manufacturer of submitted sample 8. Model number of sample - This information can only be given if the actual sample has a reference by the manufacturer 9. Finish, Colour or Coating of sample to be identified – eg. Brushed Aluminium/White 10. Specify location/area where sample is to be used – eg. Birthing Rooms 11. Identify whether sample is being submitted as physical, or as photo + technical specifications – Refer to BMPX 12. This section must be completed if the sample relates to or is a part of other samples which has been submitted (Eg Cistern with Toilet) 13. Notes/Comments – Generally to be used by reviewers. Should be completed if there is any additional information required or that should be included. 14. Technical Data – Technical Data associated with the sample, which would also include testing certificates etc. are to be included – scan and insert 15. Attach photos of sample (suppliers product shot or other) which identifies the important aspects of the sample. (Ensure ‘example’ text is removed). 16. Sample Stickers – Must also be completed to be attached to physical sample. Sample no., Title & Description must also be completed exactly the same as what is on the sample form.
NOTE: All documents must be registered on Aconex so that they can be Transmitted, tracked & referred to for future references. When registering document you must refer to the Aconex Reference Guide which you should have access to in your document register by selecting Documents & then search, this guide is very useful to all and treated as
the Project Bible. Ensure that registered samples on Aconex are a single, clear PDF file. Ensure that an editable Word version is also issued for updating. If you are unsure of any sections of this guide please call Site Document Controller.
NOTES/COMMENTS NOTE BY
13
TO BE COMPLETED BY REVIEWERS ONLY
Royal North Shore - CSB – PW-AD-0001 – Rev 01 26
14
Royal North Shore - CSB – PW-AD-0001 – Rev 01 27
PHOTOS 15
Royal North Shore - CSB – PW-AD-0001 – Rev 01 28
PHYSICAL SAMPLE SIGNOFF
PHYSICAL SAMPLE SIGNOFF
SAMPLE NO(&REV) 16
SAMPLE NO(&REV) 16
TITLE
TITLE
DESCRIPTION
DESCRIPTION
Brookfield Multiplex Constructions
sign Brookfield Multiplex Constructions
sign
print date
print date
Woods Bagot
sign
WS+P
sign
print date
print date
Health Infrastructure
sign
Health Infrastructure
sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
NO
TES
NO
TES
PHYSICAL SAMPLE SIGNOFF
PHYSICAL SAMPLE SIGNOFF
SAMPLE NO(&REV) 16
SAMPLE NO(&REV) 16
TITLE
TITLE
DESCRIPTION
DESCRIPTION
Brookfield Multiplex Constructions
sign Brookfield Multiplex Constructions
sign
print date
print date
WSP
sign
Building Studio Architects
sign
print date
print date
Health Infrastructure
sign
Health Infrastructure
sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
insert as req’d sign insert as req’d sign
print date
print date
NO
TES
NO
TES
Royal North Shore - CSB – PW-AD-0001 – Rev 01 29
6.5 Disruption/ Shutdown Application To be developed in conjunction with Health Infrastructure , APP and Inforeshore.
Royal North Shore - CSB – PW-AD-0001 – Rev 01 30
7.0 APPENDIX B – DOCUMENT NUMBERING CONVENTION
7.1 Consultant Specification & Schedule Numbering Convention
Discipline Discipline Prefix
From To Application / Use
Architectural AR 0100 0149 For architectural
Structural ST 0150 0199 For structural
Mechanical ME 0200 0249 For mechanical
Electrical EL 0250 0299 For electrical
Hydraulic HY 0300 0349 For hydraulic
Fire FS 0350 0399 For fire protection
Façade FA 0400 0449 For façade
Landscape LA 0550 0599 For landscape
Survey SU 0600 0649 For survey / site investigation
Lifts L 0650 0699 For lifts
Security SE 0700 0749 For security
BCA BCA 0760 0769 For BCA
Environmental EN 0770 0779 For Environmental - ESD
Specialist Lighting SP 0770 0789 For Specialist Lighting
Public Art PA 0800 0809 For Public Art
Way finding WF 0810 0819 Signage Way-finding
0820 0829 Spare
0830 0839 Spare
Royal North Shore - CSB – PW-AD-0001 – Rev 01 31
7.2 Shop Drawing Numbering Convention
Discipline Discipline Prefix From To Application/Use
Architectural AS 1000 1099 For Doors/ PMDF
AS 1100 1199 For Windows
AS 1200 1299 For Kitchen
AS 1300 1499 For Cupboards / Robes
AS 1500 1599 For Seating Systems
AS 1600 1699 For Wet Areas
AS 1700 1799 For Stairs / Handrails
AS 1800 1899 For Carpet / Tiles / Timber
AS 1900 1999 For Lift Car Fitout
AS 2000 2199 For Louvres
Structural SS 200 2199 For Post Tensioning
SS 2200 2299 For Precast
SS 2300 2699 For Structural Steel
SS 2700 2899 For Formwork
Mechanical MS 3000 3499 For Mechanical
Mechanical/Electrical MES 3499 3999 For Mechanical Switchboard
Electrical ES 4000 4499 For Electrical
SES 4500 4699 For Security
ES 4700 4799 For Hearing Loop
Hydraulic HS 5000 5499 For Hydraulic
HS 5500 5599 For Hydraulic Equipment
Fire FS 6000 6499 For Fire
FS 6500 6699 For Fire shop
FS 6700 6799 For Fire curtain
Lift/Escalators LS 7000 7499 For Lifts/Escalators
Façade FAS 8000 8299 For Curtain Wall
FAS 8300 8399 For Windows
FAS 8400 8499 For Balustrades
FAS 8500 8599 For Glazing
FAS 8600 8699 For Stone Cladding
FAS 8700 8799 For Metal Cladding
Signage SIS 9300 9399 For Signage
Landscape LAS 9400 9499 For Landscape
Public Art PA 9900 9999 For Public Art
Royal North Shore - CSB – PW-AD-0001 – Rev 01 32
7.3 Document Review Stamp All documents must be tagged with the document review stamp. This should be displayed in the title block of all drawings.
DOCUMENT REVIEW Brookfield Multiplex Constructions Pty Ltd
□ A - Acceptable for Construction.
□ B - Acceptable for Construction subject to comments. Correct and Resubmit
□ C - Unacceptable for Construction. Correct and Resubmit for Review
□ D – Drawing on Hold
Reviewed …………………………………………….. Date ………………………... These documents have been reviewed for conformity with design intent. Acceptance does not mean approval of dimensions, sizes or weights nor does it relieve the Subcontractor and/or the Consultant from responsibility for errors, omissions or compliance with his obligations and/or requirements of the Contract and/or Subcontract.
Recommended