A Case-based Approach toBusiness Process Monitoring
S. Montani1, G. Leonardi1
1 Dipartimento di Informatica, University of Piemonte Orientale, Alessandria, Italy
Business Process Management
BP: collection of related activities which produce a service or a product
BPM: defining, executing, monitoring and optimizing BPs
BP Optimization: flexibly change and adapt BP: Expected situations (new laws, reengineering) Unanticipated exceptions (emergencies) BP not correctly applied
Business Process Monitoring
Agile Workflow Technology: solution for process adaptation and overriding: Modifications of process schema (by process engineers) Ad-hoc changes of process instances (by end users)
Business Process Monitoring: highlighting and organizing non-compliances Allows verification of process conformance Suggests long-term changes to deal with non-compliances
Case-basedBusiness Process Monitoring
Analysis based on retrieval of traces similar to the current one Trace: Sequence of actions occoured in a process instance
Suggestions on how to modify the default process schema: Analysing most similar examples of changes in retrieved traces Inspecting clusters obtained on the base of trace similarity
To perform analysis: Case definition Similarity measure
Case Structure
Case: a trace of execution of a given process schema Process schema: general schema definition suggesting what has to be
done Trace: sequence of actions actually performed by the working team
Actions ordered by execution time, and stored with additional information: the timestamp of the event, the performer or originator of the event (i.e., the person/resource
executing or initiating the action), data elements recorded with the event (e.g., the dosage of a drug)
ID action start end actor1. A1 1-1-08 10:30 1-1-08 10:35 Robert2. A2 1-1-08 10:30 1-1-08 12:00 Frank3. A1 2-1-08 12:00 3-1-08 00:30 Louise4. A4 2-1-08 16:00 2-1-08 17:03 Carla5. A5 2-1-08 23:45 3-1-08 04:55 Joseph6. ………
Similarity Measure
Edit Distance: given two traces T1, and T2, ED (T1, T2) = number of operation needed to obtain T1 = T2
Edit operations on traces: Substitute one action with a different one Insert a new action Delete an action
Each edit operation has cost set to 1
Trace T1: A1, A2, A1, A4, A5Trace T2: A1, A1, A3, A5
To obtain T1 = T2:
- Delete A2 in trace T1- Substitute A4 with A3 in trace T1 (or sub. A3 with A4 in T2)
ED(T1, T2) = 2
Taxonomy of Actions
In our case, the cost of a substitution is not always 1: The cost is a value ϵ [0, 1] The cost is domain dependent
Actions are grouped in a taxonomy derived from domain knowledge
Distance of actions (A1, A2) proportional to distance in the taxonomy
All Actions
Emergency Hospitalization
Diagnostic Therapies Diagnostic Therapies
C.A.T. Evaluation N.M.R. Rehabilitation
Taxonomical Distance
Let α and β be two actions in taxonomy T; Let γ be the common ancestor of α and β; Taxonomical distance between α and β:
N1 = n. arcs in the path between α and γ; N2 = n. arcs in the path between β and γ; N3 = n. arcs between γ and the root of T
All Actions
Emergency Hospitalization
Diagnostic Therapies Diagnostic Therapies
C.A.T. Evaluation N.M.R. Rehabilitation
dt(C.A.T., N.M.R) = (3 + 3) / (3 + 3 + 2*0) = 1N1 = 3; N2 = 3; N3 = 0
α β
γAll Actions
Emergency Hospitalization
Diagnostic Therapies Diagnostic Therapies
C.A.T. Evaluation N.M.R. Rehabilitation
dt(C.A.T., Evaluation) = (1 + 1) / (1 + 1+ 2*2) = 0.33N1 = 1; N2 = 1; N3 = 2
α β
γ
Action Weight
Also the cost of an insertion or deletion (indirection) is domain dependent: Some indirections can cause important effects (high weight value); other indirections cause minor impact (low weight value).
Let α be an action, its weight wα is defined as: wα ϵ [0, 1[ if α generates an indirection
wα = 1 otherwhise
Trace Edit Distance
Let P, Q be two traces of actions; let α and β be two actions ϵ taxonomy T. Trace Edit Distance d(P, Q) is defined as:
Where: (e1, ... , ek) transforms P into Q, and: C(ei) = dt(α, β) if ei is the substitution of α with β
C(ei) = 1*wα if ei is the insertion (or deletion) of α in P (from Q)
Trace Edit Distance: case 1
B and B’ are comparable: dt(B, B’) ≤ τ: B and B’ considered aligned Next actions are checked (C and C’)
Trace Edit Distance: case 2
B and B’ are not comparable: dt(B, B’) ≥ τ, and A and A’ not comparable:
B is substituted with B’ Dt(B, B’) is added to d(P, Q)
Trace Edit Distance: case 3
B and B’ are not comparable: dt(B, B’) ≥ τ, and A and A’ comparable, and B and C’ comparable:
B aligned with C’; B’ considered as indirection
1*wB’ is added to d(P, Q)
Trace Edit Distance: case 4
B and B’ are not comparable: dt(B, B’) ≥ τ, and A and A’ comparable, and C and C’ comparable:
B is substituted with B’ Dt(B, B’) is added to d(P, Q)
Application Example:The Stroke Domain
Stroke: loss of brain function due to ischemia or blood hemorrage Medical emergency, potentially leading to permanent damage or to
death Number 2 cause of death worldwide (soon becoming number 1)
Stroke patient management in 4 phases: Emergency management; Hospitalization; Discharge; Follow-up.
A “correct” Patient Management
Emergency management: Symptoms recognition; C.A.T
Hospitalization in neurological ward/stroke unit Diagnosis: Neurological evaluation + E.C.G. + other diagnostic
investigations (i.e. chest X.R.) Therapy: antiaggregants; physical rehabilitation
Discharge – Follow-up: no data available
Retrieval Example:Query Case Description
Atypical situation:
Emergency: Stroke diagnosed directly after C.A.T., without need of further
investigations antiaggregant therapy started immediately
Hospitalization: Patient condition probably unstable, therefore further investigations:
additional tests and a further anticoagulant therapy. Physical rehabilitation NOT started
Retrieval Example:Case Retrieved
Query Case Most Similar Case
Indirection: diagnosis and therapy started in Hospitalization
Indirections: less investigations have been performed
Anticoagulant and antiaggregants are comparable: very close in the taxonomy since very similar effect
Query case: #103101 in the trace DB Trace DB composed by more than 300 traces
K-Nearest Neighbor retrieval using: K = 20
Trace Similarity Distance
Retrieval time: 1.2 seconds on an Intel Core2 Duo T9400 – 4Gb ram
No physical rehabilitation even in the retrieved trace – atypical situation captured
Conclusion andFuture Work
CBR-based BP Monitoring: Cases are traces of execution Trace Edit Distance
Helps in adapting BP on the basis of deviations in past traces of the same BP
Clustering to identify the most frequent changes to the BP schema Implemented (single linkage clustering), but not fully validated
Integration in the Process Mining tool ProM (W. van der Aalst) Extension of Trace Edit Distance considering temporal delays
Recommended