View
218
Download
2
Category
Tags:
Preview:
Citation preview
22/26/2009
Run Support & Other Ongoing WorkRun Technical Support (mechanical, electrical
and gas systems As needed always takes priority
RPC Factory Support (continuing)(see slides later)
Prep for 2009 ShutdownDesign PC1 East maintenance support fixtures design 3/31, fabrication 5/31NCC prototype design support (on-going med. priority)
VTX fabrication tooling design (on-going med. priority)
VTX installation design (on-going med. priority) FVTX design/eng’g support (no support requested
yet)MMS Scaffolding Design design 2/27, ordering/fabrication 5/1New Beampipe supports (back logged)
RPC3 North installation PrepInstallation plan (including installation site prep
plan) 3/6 RPC Quarterly Review 3/12 & 3/13Installation fixture design 4/3Installation fixture fabrication 6/26
Maintenance & Overhead TasksProcedure Review/Updates (ongoing)Rack Room, AH, Trailer, Mixing House, etc. (ongoing)
’09 Technical Support
32/26/2009
Next Maintenance Access Day – March 4
Maintenance/Troubleshooting Task List:
TEC ES2 LV Troubleshooting RPC Grounding Issues (IR & Tunnel Access)
MuTRigger FEE Issues?
HBD Issues?
Other Issues?
52/26/2009
PC1 East Broken Wire Repair
Repairs to be performed during ’09 Shutdown
New Column SupportsUnder railway extensions
New Railway extensionswill allow DC to be pulled out ~ 3 feet more
Access to PC1 is adequate to remove and replace module
62/26/2009
PC1 East Repair Fixturing Design
Repairs to be performed during ’09 Shutdown
New Column SupportsUnder railway extensions
New Railway extensionswill allow DC to be pulled out ~ 3 feet more
Access to PC1 is adequate to remove and replace module
72/26/2009
RPC Factory Support
RPC Factory Change in Scope
Remaining Action Items:
Review the mechanical design of the burn-in assembly and the dolly system to be used in moving the ½ octant units. Design In Progress, Review to follow
Update the RPC high voltage and gas procedures if necessary (Giannotti, Pisani Jan 30, 2009) In progress
Add individual output valves to the burn-in unit gas schematics (Pisani, Jan 30, 2009) In progress
Get a permit for the R134 added consumption (Pisani, Van Essendelft, Jan 30, 2009) In Progress
Review the flammable compressed gas system piping ( Gaffney, Pisani Jan 30, 2009)To Be Scheduled
82/26/2009
RPC Factory Support Tasks:
• Complete the Dark Current Test Stand (2/27)
• Order materials for Burn-in Test Stand (2/20)
• Complete design of Tilting Transport Table (2/13) Done Review needed
• Order materials for the Tilting Transport Table (2/20)
• Order additional shelf units for gap, module and RPCstructural component storage (2/20)
• Design and order environmental control system for Burn-In Test Stand (2/27)
• Assemble gap & module storage with humidity control existing shelves (2/27), full complement of shelves (3/13)
• Extend N2 supply to storage shelves (not required)
• Assemble structural component storage existing shelves (2/27), full complement of shelves (3/13)
• Assemble tilting transport table 3/6
• Assemble burn-in test stand (bike rack) 3/27
• Extend gas, electric and safety systems to Burn-In Test Stand (4/3)
92/26/2009
RPC Factory
Module and Gap Storage with humidity Control
Burn-in test stand (bicycle rack)
Tilt Table for Assembly and Handling ½-octants and later station one octants
Detail parts storage for Module and ½ octant structural parts
Dark Current Test Stand
10
2/26/2009
RPC Factory
Dark Current Test Stand under construction
Also working on:
- a burn-in test stand for ½ octants
- additional storage for gaps modules and structural detail parts
- transport table/cart
12
2/26/2009
New Beampipe
PHENIX
SCD
Brush-Wellma
nCAP
Still Waiting for new CAP
We expect quotes for transition and spool sections shortly
13
2/26/2009
Gas Pad Upgrade & Ar Dewar
Additional Pad area for storage of empty gasbottles
New Liquid Argon Dewar to meet current and future demand
General location as shown, footprint (size) TBD
14
2/26/2009
• Roof leak in utility bathroom at northwest corner behind tech offices.
• Roof leak over door between rack room and assembly hall.
• Trailer bathroom slop sink (for Custodians).
• Heat wrap tape for trailer bathroom toilet drains to prevent freeze/clogging in winter.
• New duct heater (This item is in progress and should be completed soon)
• Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.)
2009 Building Maintenance Issues
15
2/26/2009
Shutdown ’09 Major tasks (expect 5 month shutdown):
• 2009 shutdown Begins April 10, or July 1, 2009or July 15 or ?????
• End run, remove wall, MuID collars down, EC to AH (3 weeks)
• Install Station 1 South scaffolding (1 week)
• Install Station 2/3 scaffolding (2 weeks)
• PC1 East repair (4 weeks)
• Install stations 1, 2 and 3 south MuTrigger FEE’s (12 weeks)
• MuTr decapacitations: station 3 south (3 weeks)
• RPC Station 3 North (12 weeks)
• Add Ar Dewar and expand gas pad to add storage (12 weeks)
• Prep for future upgrades/existing equipment maintenance & Repair (as necessary)
Shutdown ’09
16
2/26/2009
Safety, Security, etc.1. PHENIX Annual Safety Review Remaining Action Items:
• Settle the CM magnet ladder railings (Lynch, Pearson Phillips Feb 4, 2009) Don and Dave to resolve
• Update the documented work procedures. (Lynch) Ongoing• Add HSSD to the 1008 Assembly Hall (Phillips/ Levesque Mar 1, 2009) This is a C-A issue.
2. EMS/OSH Audit
• Joe Montalto and Dick Savage had a walk thru this week and discussed our operations with Paul and Me
• We can expect an audit this June, but our feedback is that we look good
• CAD ATS system prompts us (PHENIX) for input but does not allow us into the system. CAD is working on it.
3. ODH1 issues – please let me know of any issues with the escape packs and ODH monitors.
4. BNL Occupational injuries
• YTD: DART 10, Recordable 15, First Aid 15. Targets: DART 6, Recordable 16, First Aid: N/A
• Staff Services: slipped on ice, broken hip Recordable & DART
• Physics Dept.: preparing crate, caught foot, slipped, cut wrist, stitches Recordable & DART
• Laboratory Protection Office: slipped on ice, missed work First aid, Recordable & DART
• NSLS User fell into equipment during assembly, cut lip, stitches (Non BNL, info only)
Recommended