View
909
Download
0
Category
Tags:
Preview:
DESCRIPTION
Presentation that demonstrates how spindle probes improve Overall Equipment Effectiveness
Citation preview
On-Machine Probing effects on OEEAMTS 2008
Moise CummingsTechSolve, Inc.
OMP AMTS 2008 2
Benét Laboratories
“Research was sponsored by the U.S. Army Benet Laboratories and was accomplished under Cooperative Agreement Number W15QKN-06-2-0100. The views and conclusions contained in this document are those of the authors and should not be interpreted as representing the official policies, either expressed or implied, of U.S. Army Benet Laboratories or the U.S. Government. The U.S. Government is authorized to reproduce and distribute reprints for Government purposes notwithstanding any copyright notation heron.”
OMP AMTS 2008 3
Smart Machine Technology Thrust Areas
On-MachineOn-MachineProbingProbing
Intelligent Intelligent MachiningMachiningNetworkNetwork
Health & Health & MaintenanceMaintenance
Machine Tool Machine Tool MetrologyMetrology
Intelligent Intelligent PlanningPlanning
Tool Condition Tool Condition MonitoringMonitoring
OMP AMTS 2008 4
Definition of On-Machine Probing
American Machinist magazine 2008 survey of benchmark companies
Perceptions of On-Machine Probing
What is OEE (Overall Equipment Effectiveness)?– Definition of OEE– Calculating OEE– Six big losses in a plant– Obstacles to OEE
OEE and On-Machine Probing– Test performed at TechSolve– Success Stories
Conclusions
Outline
OMP AMTS 2008 5
On-Machine ProbingAn inspection process within a machine tool that requires minimal use of peripheral inspection equipment or additional operators
– Data is used to make process adjustments to minimize non-conforming parts
Benefits to Industry Work offset verification Detects maladjusted fixtures Collects SPC data
Reduced material handling On-machine rework In-process correction
On-Machine Probing
U-TOL
L-TOL
UCL
LCL
OMP AMTS 2008 6
2008 Machine Shop Benchmark Survey Analysis
From the July 2008 issue of American Machinist– “This year, there was a noticeable increase in the uses of in-process
measurement, coordinate measuring machines, barfeeders and prefixturing of workpieces, especially for shops in the benchmark shop categories.”
Increasing the overall equipment effectiveness (OEE) is one of the hallmarks of the machine shops in the benchmark categories
OMP AMTS 2008 7
Industrial Perceptions
Probing diverts time from machining and increases cycle time– Instead of focusing on cycle time, we should evaluate overall
equipment effectiveness (OEE)
Probing routines are difficult to write and use– State-of-the-art software makes writing routines easier and more user-
friendly– Once written, routines can be used on repeat parts
The probe is only as accurate as the machine itself
OMP AMTS 2008 8
What is OEE?
Best practice way to monitor and improve the effectiveness of a manufacturing process
Organizes any productivity losses into three components to provide a gage for process improvement
– Availability, Performance, and Quality
OMP AMTS 2008 9
How is OEE calculated?
OEE = Availability X Performance X Quality
Availability = Operating Time / Planned Production Time
Performance = Ideal Cycle Time / (Operating time / Total Pieces)
Quality = Good Piece / Total Pieces
World-class performance OEE = 85%
The OEE percentage by itself may not provide the right answer– You must scrutinize its components
OMP AMTS 2008 10
Six Big Losses
OEE takes into account issues like:– Machine breakdowns– Setup time– Line restraint– Reduced speeds– Start-up rejects– Production rejects
On-machine probing addresses three of the six big losses in OEE
– Is the sum of those losses worth a probing cycle?
OMP AMTS 2008 11
Obstacles to OEE
Availability – Any event that effects planned production– Changeover, setup, break downs, material shortages
Performance – Any event that causes the process to run at less than optimal speed
– Machine wear, operator inefficiency, mis-feeds
Quality – Parts that are not produced to specification and require rework
– Start-up scrap, production scrap
Q: What are the roadblocks to world class OEE?A: Scrutinize the individual components.
OMP AMTS 2008 12
Current State of Manufacturing
Start-up scrap: One of the biggest losses to a production environment comes from the setup procedure. This may be because the setup process is very dependent on the skill of the operator. There is also a chance that the wrong rough stock can be loaded.
Production scrap: Another major loss to a production environment comes from the production process itself (such as tool wear and features “drifting” out of tolerance).
Time loss: Time is lost in production due to waiting in (off-line) inspection queues and conventional setup procedure.
OMP AMTS 2008 13
Benefits of On-Machine Probing
Precise Setup: With on-machine probing, setups can be locatedexactly to the rough stock to avoid air cuts or buried cutters in a roughing process.
Process verification: Features can be inspected during the production process and reported back to the operator. This
will reduce time at the CMM and allow for more uptime at the CNC.
Time savings: Routines can be written that will allow setup to be performed in a fraction of the time of conventional (manual) setup procedures. Local work coordinate systems can also be used to eliminate positional accuracy of the machine for a high-tolerance, local set of features, such as bolt hole patterns.
OMP AMTS 2008 14
For the sake of discussion, all of the comparisons will be done in reference to the SMPI demonstration part
SMPI Demo Part
OMP AMTS 2008 15
Process StepsPre-Technology
Time in minutesTasks Why & Benefit Post-Technology
Time in minutes
20.0 Set G54 Establish work coordinates 2.0
4.0 Validate rough stock Inspect for correct stock 2.0
4.0 Laser inspection face mill Accurate tool length - TCM 1.5
10.0 Face mill surface Optimized tool path - IM 5.0
4.0 Laser inspection end mill Accurate tool length - TCM 1.25
21.0 Roughing two pockets Optimized tool path - IM 10.5
8.0 Finishing two pockets Optimized tool path - IM 5.5
8.5 Set G55 & G56 Set local work coordinates 1.0
4.0 Laser inspection drill Accurate tool length -TCM 0.5
4.0 Drill holes in G55 & G56 Optimized tool path - IM 2.5
19.0 End mill roughing two bores Optimized tool path - IM 9.5
3.0 Laser inspection measure tool Accurate tool wear - TCM 1.25
1.0 Finish 50 mm holes Improved accuracy of holes - IM 1.0
varies Final inspection On-machine probing vs. CMM 3.0
106.5 minutes 43.5 minutes
Probing steps in blue
OMP AMTS 2008 16
Setup Time Reduction and Quality
To minimize linear inaccuracy, on-machine probing can establish a local WCS on localized datum
– This is more significant on longer parts with features that may be clustered in different sections of the workpiece
Setting a local work coordinate system showed a 50% average improvement in the true position
Time Savings: Conventional Method = 8.5 min OMP = 1.0 min = 7.5 minutes
True position improvement of 50% and more than 7 minutes saved
OMP AMTS 2008 17
Setup Time Reduction and Quality
A reduction in time at the CMM and an improved part quality means that there is and increase in the overall equipment effectiveness (OEE) of the plant.
Unknown Distance
G55 G56
Success Stories
Successes from actual customers of TechSolve that have adopted the use of spindle probes
OMP AMTS 2008 19
Effect on Availability
One component of OEE is the lost of efficiency due to machine availability
The availability is defined as:– Availability = Operating Time / Planned Production Time
Availability: Less trips to the CMM and less setups means that the customer is utilizing their machine tool to make more parts
– To achieve this the uncertainty of the process has to be addressed
OMP AMTS 2008 20
Effect on Availability
Scenario: A company manufactures complex aircraft components during a three shift (24 hour) operation. The components must be inspected to a traceable standard before they can be signed-off. The queue at the CMM and the inspection process is one hour. The CNC must idle while the inspection is taking place or risk making scrap parts.
Solution: After tuning the machine and performing repeatability studies on the machine, the CNC can inspect the parts with a high level of certainty per ASME B5.54. The shop is able to move from lot inspections to first and last article inspection while sampling CTQ features on the CNC.
The availability of the machine increases by 12%, which adds to the OEE due to the increase operating time.
– Availability = Operating Time / Planned Production Time
OMP AMTS 2008 21
Effect on Quality & Availability
Problem: A customer has to machine a cast aluminum housing. The housing has two production locating pins that are used as datums that span 24 inches apart. Between those datums are a series of machine features, among those features are four bored holes surrounded by bolt hole patterns that have to maintain true positions of 0.040”.
Solution: The client is able to use a spindle probe to establish a local work coordinate system within the bore diameter. By using that local work coordinate system as the origin of the bolt hole pattern, the process is able to easily hold a true position of 0.001” (previously 0.040”) to the main bore without breaking the setup or making multiple trips to the CMM.
OMP AMTS 2008 22
Effect on Quality and Availability
Quality: The customer realized a 60% increase in the part quality from the use of the spindle probe
Availability: Less trips to the CMM and less setups meant that the customer is utilizing their machine tool to make more parts
OMP AMTS 2008 23
Effect on Quality
Problem: A manufacturer has an issue with bottlenecks at the inspection area due to the volume of work being produced on the CNC machining area.
Goal: To utilize on-machine probing to go from ongoing inspection to first article inspection, which would reduce the inspection time by 80%. This would lead to an increase in production due to less time spent waiting for inspection.
Cell #1 Cell #2 Cell #3
Inspection
OMP AMTS 2008 24
Effect on Quality
Solution: The biggest concerns from the quality department was being able to
– Produce parts that were statistically within control for sampling– Have a method in place to make sure that the machine tool was qualified
1. The machine tool was first qualified and tuned to reduce metrology errors
2. Repeatability studies were performed per the ASME B5.54 standards to ensure the quality of the probe itself
3. The CNC machine was “foot-printed” using a diamond-circle-square test and the part was collaborated using a traceable CMM
OMP AMTS 2008 25
Effect on Quality
Result: With a machine that is qualified, repeatable, and traceable the customer can now inspect parts on the machine within a relative certainty
This will result in an a single daily inspection on the CMM and ongoing inspection key features on the machine
This increase in part quality and throughput will have a direct impact on the plant’s OEE because of the reduction in the three of the six big losses:
– Start-up scrap– Production scrap– Waiting for the CMM’s approval throughout the day
OMP AMTS 2008 26
Conclusion
Spindle probes are meant to increase the productivity and the effectiveness of a process
Probing offsets the time and cost of scrap and downtime that is currently in the machining process
Reduction in scrap and reduced time spent performing offline inspections will increase the overall equipment effectiveness (OEE) of the process