‹#› 1 5 March 2015 BENIMBL.COM Part 2: How to Migrate to SAP Netweaver BW on HANA NIMBL & Decision First Webinar Series

Webinar - Definitive Guide to SAP BW on HANA Migrations

  • Upload
    nimbl

  • View
    108

  • Download
    5

Embed Size (px)

Citation preview

‹#›1

5 March 2015BENIMBL.COM

Part 2: How to Migrate to SAP Netweaver BW on HANANIMBL & Decision First Webinar Series

‹#›2

Recap: why run bw on hana?

Promotes self-service reporting and analyticso Improved User Experience for exploration with Lumira, WebIntelligence,

Explorer, Design Studioo Explore and drill from high level to granular detail with enormous data

volumes Simplify the modeling process Increase the agility of the enterprise data warehouse Reduce the complexity of the EDW landscape

o Reports can be run directly off the DSOo Activation of data loads into DSOs comprise 80% of the load time

‹#›33

NIMBL Curriculum vitae

2009 14x

1Year Founded

Supporting both the Fortune 500 and Midmarket

Growth since inception

SAP Specialized – No other ERP

5280Headquartered in the Mile-High City –Denver, Colorado

174+Amazing Customers… and counting!!

100+

7+

Consultants strong

Average years of SAP Expertise per consultant

15+ Market Verticals Supported

98%Client

Satisfaction

‹#›44

our differentiators

We are passionate about SAP Technology and continue to be recognized for our bleeding-edge technical expertise.

North America’s SAP Technologists1

We present SAP education rich presentations across the globe including @ SAPPHIRE, dCode, and SAPInsider.

Sap ecosystem thought leaders4

Published authors and frequent speakers on HANA migrations for BW, ERP & CRM on HANA

Netweaver on HANA EXPERTS2

Based in Denver, our SAP Application Management Services provide 24x7x365 SLA based remote consulting.

denver-based sap ams services5

Our SolMan expertise spans the entire SAP ALM Solution Manager wheel including Technical + Application.

Solution manager specialists3

We are an SAP MCaaS, VAR, and Services Partner. We are an HP Software VAR and Services Partner.

Sap + hp strategic partners6

‹#›55

Our Services

Enhanced and consistent SAP User Experience across Computer, Tablet, and Smartphone.

Fiori Denver-based SAP delivery for Break/Fix Enhancement, and Project.

SAP AMSHarness the power of SAP HANA with the SAP Business Suite on HANA.

hana

Empower your workforce and business via SAP mobilization.

MobilityEnd-to-end SAP and HP Testing services across HP ALM, UFT, LoadRunner, and StormRunner.

SAP + HP testingRun IT like a Factory thru Solution Manager’s ITIL ALM Product Suite.

Solution Manager

Classic Basis, TDMS, LVM, EHP, Netweaver, and landscape consulting.

ADMIN + INFRASTRUCTURE

Comprehensive SAP risk mitigation via Audit, toolset, or pure consulting services.

securityDelivery from idea thru hypercare whether laser-focused or complete project.

projects

Connect systems via PI, PO, WebServices, 3rd party Middleware, etc. via seamless connectivity.

integration

Maximize your SAP investment with SAP’s latest and greatest functionality via EHP application.

Enhancement pack

Easily replicate data whenever you want from source to target system (Prod > QA, Prod > Training)!

tdms

‹#›6

Project scope Migration options Timeline Change management challenges

agenda

‹#›7

What components do we have installed?o Add-ons, BI Content

POS-DM, BPC, Integrated planning o Integration with other systems – SAP & NON-SAP

Does our current release support HANA as a DB today?o Netweaver 7.30 SP08+

If we have to upgrade, where do we go?o HANA SP09o Netweaver 7.4o Unicode?

What does the HANA landscape look like?

Scoping Questions

‹#›8

Define interoperability between current systems and target versions

Available on service marketplace & within Solution manager

Simulate multiple components & add-ons

Upgrade dependency analyzer

Source: https://websmp210.sap-ag.de/~sapidb/011000358700000779282010E.pdf

‹#›9

http://service.sap.com/UDA

Accessing UDA

‹#›10

Significant new functionality delivered with SP09o Too much to listo Read more > https://blogs.saphana.com/2014/10/21/what-is-new-in-sap-hana-sps-09/

Simplified administration Multi-tenant database containers Data tiering Better scale-out support

Why implement the latest HANA version?

‹#›11

Fiori (HTML5) based Any browser anywhere Relevant information

displayed on dashboard Same information as seen

in hana studio

Simplified Administration

‹#›12

Multi tenant database containers One database software version Simplifies landscape Central resource management Separates data, user management SAP Note 1661202 - Support for

multiple applications on SAP HANA

Multi-tenant what?

“…MDC system it is supported (for example) to run SAP ERP and SAP BW on the same production SAP HANA system, each one it's own tenant DB. However, it is not supported to run SAP ERP and SAP BW on the same tenant DB due to white list restrictions.”

SAP ERPNetweaver 7.31

AS-ABAP

SAP BWNetweaver 7.4

AS-ABAP

HAN.System.DB

HAN.DB ERP HAN.DB BW

SAP HANA

‹#›13

Released q4 2014 Hot data = in memory Cold data = disk based data store

Data tiering for BW

SAP BW 7.4, GA Q4 2014 Different than BW NLS Licensed option

‹#›14

Scale up Single node Add resources to grow Easier to manage HANA leverages latest CPU

architectures Supports High availability SAP Recommended

Scale up or scale out?

Scale out Three node minimum (per sap) Complex data management

o What data is where?o Duplicate master data

tables on each node Increased data center

expense

Source: SAP HANA SP09 Scalability

‹#›15

See your bill of materials for exact component nameo Ask your SAP account executive

SAP runtime license for SAP Netweaver BWo Not memory basedo Can be used for BW onlyo No direct access to HANA DB tools (Smart data access, SLT, etc.)o Can be used with multi-tenant database containers

SAP HANA Enterprise editiono Can be used as enterprise data warehouseo Non SAP & SAP datao BW and non BW

What are we licensed for?

‹#›16

1729988 - SAP NetWeaver BW powered by SAP HANA - Checklist Tool 1736976 - Sizing Report for BW on HANA

Upgrade Preparation & Sizing

‹#›17

Execute anytime Download SAP Note

1736976 See attached guide Conservative

estimates

SAP HANA Sizing

‹#›18

SAP Note 1667731 - Rapid database migration of SAP BW to SAP HANA

Common tasks good for any BW system

Includes archive & deletion tasks

Cleaning up BW

‹#›19

Upgrade & HANA Migration with Software Update Manager (SUM) o Leverage Database migration option (DMO)o Include support package or major releaseo Upgrade from NW 7.0+ to NW 7.4 on HANA

HANA Migration with Software provisioning Managero No Upgrade or change in SIDo Primary host is switchedo Traditional OS/DB Migration

JAVA stack must be split with either option

Migration options

‹#›20

Database Migration option Included with SL Toolset

o Service.sap.com/sltoolset Source database remains Fast fall back

What is the DMO?

Source: SAP First Guidance - Using the DMO Option to Migrate BW on HANA

‹#›21

DB Type Minimum for DMO to 731

(BW)

Minimum for DMO to 740

DB2 9 10

DB4 V7R1 V7R1

DB6 64 Bit 9.1(*) 9.1(*)

MaxDB 64 Bit 7.8,7.9(**) 7.8,7.9(**)

MSS 2008, 2012 2008, 2012

Oracle 10.2 10.2

Sybase 15.7 15.7

Supported source database platforms

Source: SAP Note 1600929 SAP BW powered by SAP HANA DB: Information

‹#›22

Timeline: hana migration

System Copy PRD > SBX

Upgrade SBX

Capture Procedures

SPAU/SPDD Activities

Modify Transport Path (QA>PRD

Development Freeze

Upgrade DEV

Build Cutover Plan

Prepare PRD upgrade

Upgrade QA

Approve Regression Test Results

Validate Solution Manager Connectivity

Execute SAP Going Live Check

Week 1-4 Week 4-6 Week 6-8 Week 8-10 Week 10-12

BW Regression Test

Manually re-apply Production Support changes

Hypercare

‘Go’ ‘No-Go’ Decision

Weekend upgrade PRD BW

Week 1-4 Week 4-6 Week 6-8 Week 8-10 Week 10-12

Best practice project

‹#›23

NIMBL delivers sap rds Rapid database migration of sap netweaver bw to

sap hana Standardized, template-ized, processes and

procedures Clearly defined deliverables, timelines, roles and

responsibilities Based on experiences and best practices from sap

and sap customers http://service.sap.com/rds > Database &

Technology > Database Migration

rapid deployment solution (rds)

BW Functional Upgrade*

BW Authorization Migration*

BW Data Volume Optimization*

BW Technical Upgrade

Unicode Conversion

BW Database Migration

Installation of SAP HANA

RDS Scope Options

Additional Service Offerings

‹#›24

Go live in 12 weeks

Implementation

Testing

Key User training

User acceptance testing

Switch to production

Start RunDeploy

Expectations

Project management

Kick-off workshop participation

Scoping workshop

Preparing technical infrastructure

End-user training

Hand over of solution

Onsite and remote support

Results

2 3

Mutually-approved options selected

Working SAP system

Successful rollout and adoption

Configuration documentation

Superior support to ensure smooth functioning

Note: This slide represents a typical deployment. Exact details may differ according to solution.

1

‹#›25

Proven process & templates

Note: This slide represents a typical deployment. Exact details may differ according to solution.

Start RunDeploy2 31

Scoping Questionnaire

Configuration Guide Kickoff Workshop Project Schedule

Support Portal

‹#›26

Approach: bw upgrade to 7.4 with dmo option

System copy production to refresh Sandbox Conduct regression testing in SaNDBOX Will require connection to ERP (Source) Systems Does not disrupt production support

BW 7.xDevelopment

BW 7.xQA

BW 7.xProduction

BW 7.4Sandbox

Capture upgrade procedures & timing

Sandbox Landscape

Transport Path

Production Support Landscape

System Copy & Upgrade to

7.4 With DMO

1

‹#›27

Approach: bw upgrade to 7.4 with dmo option

Rebuild sandbox as production support system Execute upgrade in Stage corrections and prerequisite changes in transports in DEV

prior to upgrade

BW 7.4Development

BW 7.xQA

BW 7.xProduction

Upgrade to 7.4With DMOTo HANA

BW 7.XSUPPORT

Support Landscape

Temp Transport Path During Project

Becomes developmentsystem temporarily during project

Execute upgrade procedures

Refreshed fromProduction

2

‹#›28

Approach: bw upgrade to 7.4 with dmo option

Upgrade QA – retrofit production support to DEV Light regression –primary regression test was already completed Stage corrections and prerequisite changes in transports in DEV

prior to upgrade

BW 7.4Development

BW 7.4QA

BW 7.XProduction

Upgrade to 7.4With DMOTo HANA

BW 7.XSUPPORT

Support Landscape

Temp Transport Path During Project

Execute upgrade procedures

Refreshed fromProduction

3Transport Path

‹#›29

Approach: bw upgrade to 7.4 with dmo option

Upgrade Production System using DMO Include SPAU/SPDD and changes in queue from Dev Support system exists in case of rollback

BW 7.4Development

BW 7.4QA

BW 7.4Production

Upgrade to 7.4With DMOTo HANA

BW 7.XSUPPORT

Support Landscape

Execute upgrade procedures

Refreshed fromProduction

4Transport Path

‹#›30

Two primary options existo Manual coordination and implementation of changes

Dual maintenance Manual replay of tasks in two systems

o Solution Manager Change Request Management w/ retrofit Enables cross version transports Tracks & manages all changes for production support Ensures two landscapes stay in sync

change Management

‹#›31

Determining the to-be landscape –scale up or scale out Convincing internal resources to leverage latest versions Limiting scope to migration

o then Optimizing bw post upgrade Internal resource knowledge transfer

o Highly recommend HA200 class for Basiso Recommend bw362 for bw developers

challenges

‹#›32

2015 HANA courses & certification > http://scn.sap.com/docs/DOC-61609 Rapid database migration BW on HANA > https://websmp107.sap-

ag.de/~form/sapnet?_SHORTKEY=00200797470000103359 What’s new in HANA SP09 >https://blogs.saphana.com/2014/10/21/what-is-new-in-

sap-hana-sps-09/ SAP Enterprise support OS/DB migration CHECK Migration to SAP netweaver BW on SAP HANA – Best Practices

More information

‹#›33

http://sapinsiderevents.wispubs.com/2015/Las-Vegas/BI-HANA-Admin/HANA/TracksOver 16 combined sessions between NIMBL & Decision first technologies!

Comes see us next week @ HANA 2015

‹#›34

ConnectMichael Pytel

[email protected] 720.936.5481 michaelpytel